09 January 2016

download 09 January 2016

of 1

description

7 days plan

Transcript of 09 January 2016

  • Well / Rig: K-259HST3/AD-30

    Saturday Sunday Monday Tuesday Wednesday

    9-Jan-2016 10-Jan-2016 11-Jan-2016 12-Jan-2016 13-Jan-2016

    Activity

    R/Trip and circ., with 8 " bit clean out Cont. Logging M/U and RIH 6 1/8" C/O BHA to 6629 ft Con't RIH completionSet Packer S/L operations

    R/Trip and circ., with 8 " bit & Scrapper RIH completion Shear Seal assy Secure wellLogging POOH & Space out for TRSV Prepare jacket

    Con't RIH completion Prepare rig for skid

    QHSE Safety meeting before Tour Safety meeting before Tour Safety meeting before Tour Safety meeting before Tour Safety meeting before Tour

    Key PersonnelTo the Rig

    From the Rig

    To the Rig

    From the Rig

    To the RigCompletion engineer

    From the Rig Smith fisher man Baker logging tools & Crew

    To the Rig

    From the Rig

    Logistics

    Boats Needed

    Water (Gals) 60,000 60,000Diesel (Gals)

    Barite (ton)Cement (ton)

    Day & Date(From 00:00 Hrs To 23:59 Hrs)

    KJOTools & Material

    Service CompanyTools & Material

    ADCTools & Material

    09 Jan, 2016