STATUS REPORT OF AS ON 09.02.13
“A”-BLOCK STATUS
1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub Cellar Slab(-2)-
Completed.
STATUS REPORT OF AS ON 09.02.13
“B”-BLOCK STATUS
1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub Cellar Slab(-2)-
Completed5. Cellar Slab(-
1)Shuttering work in progress for 1 &2 flats.
STATUS REPORT OF AS ON 09.02.13
“C”-BLOCK STATUS
1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub Cellar – for flat
No:01 completed for flat No:02 today completed.
STATUS REPORT OF AS ON 09.02.13
“D”-BLOCK STATUS
1. PCC-Completed2. FOOTINGS-Completed3. G. Slab-Completed4. Sub Cellar-Completed5. Cellar Slab Column
work in progress for flat 1 & 2.
STATUS REPORT OF AS ON 09.02.13
“E”-BLOCK STATUS
1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub. Cellar- 40%-
Completed
STATUS REPORT OF AS ON 09.02.13
“TOTAL SITE” STATUS
1. All Blocks PCC-Completed
2. All Block Footings-Completed
3. All locks G. Slab-Completed
4. Total Site Sub Cellar- 88%-Completed