06465758
-
Upload
felipemonteroe -
Category
Documents
-
view
1 -
download
0
description
Transcript of 06465758
![Page 1: 06465758](https://reader035.fdocuments.us/reader035/viewer/2022080913/563db9d4550346aa9aa0576e/html5/thumbnails/1.jpg)
1
Abstract--The implementation of Reliability Centered
Maintenance (RCM) method can assist in achieving cost
effectiveness, and allow a greater understanding of the risk level that organizations presently manage. This systematic method
identifies the most applicable and effective maintenance plan to
avoid each failure mode of the equipment. The work presented
here describes how the RCM methodology can be applied to a digital protective relay installed in a primary distribution
substation. RCM can estimate failure before it occurs with
predictive testing and inspection tools, as well as organize maintenance plans according to the impacts of protective relay
failure on system reliability.
Keywords--Reliability Centered Maintenance (RCM),
Reliability, Distribution Power System, Periodic Preventive
Maintenance.
I. INTRODUCTION
ISTRIBUTION power system operators are increasingly
required to supply customers with high quality and
continuous service. The protection scheme’s responsibility is
to quickly clear faults and limit any damage to distribution
power equipment [2]. It keeps the power system stable by
isolating only the components that are under fault, whilst
leaving as much of the network as possible still in operation.
The technology utilized in protection schemes must be reliable
throughout their life span. Reliability can be improved by an
adequate maintenance plan. A maintenance plan should ensure
high reliability of protection scheme with minimized cost.
Nowadays, digital protective relays are used in protection,
supervision and control of electrical equipment. These
Intelligent Electronic Devices can manage several functions of
protection and automation, measurements of currents and
voltages with great accuracy. Normally, the distribution
operators have implemented a periodic preventive
maintenance practice in these digital protective relays, which
is essential in preventing any unusual performance of the
system where these protection relays operate.
H. Tavares is with FE/UP (Faculty of Engineering, University of Porto),
Porto, Portugal (e-mail: [email protected]).
H. Leite is with INESC TEC and FE/UP (Faculty of Engineering,
University of Porto), Porto, Portugal (e-mail: [email protected]).
A. Pinto, P. Vidal and J. Santos are with the Portuguese Network
Operator, EDP Distribuição - Energia S.A., Porto, Portugal (e-mail:
[email protected], [email protected] and [email protected]).
The authors would like to acknowledge the cooperation of the Laboratory
of Systems Protection at DEEC/FEUP (University of Porto).
In general, preventive maintenance programs are
established according to different criteria, depending on the
Utility or even on the Maintenance Department to which the
protective relay belongs to. These options are based on
manufacturer’s recommendations, analysis of fault statistics,
the relative importance of the equipment protected, and
maintenance experience. Utilities try with periodic preventive
maintenance to decrease failures rates of protection schemes.
However, its periodicity of the maintenance plan leads to high
costs. For the sake of cost management, a maintenance plan
must ensure that the maintenance is at the right time and with
the right activity [6]. Thus, RCM methodology identifies
functions, functional failures, failure modes, their effects and
also consequences of the failures for each component in its
operating context. This approach recognizes that the value of
every technical maintenance activity and provides rules to
decide the most adequate maintenance task to avoid each
failure mode [3].
The work here presented suggests a plan of maintenance
based on RCM methodology for a digital protective relay
installed in a distribution substation protecting a medium
voltage cable.
II. RCM METHODOLOGY AND CHALLENGES TO IMPLEMENT ON
A DIGITAL PROTECTIVE RELAY
The RCM process entails answering seven questions about
the protective relay [3]. They are:
1. What are the functions and associated performance
standards of the relay in its present operating context?
2. In what way does it fail to fulfill its functions?
3. What causes each functional failure?
4. What happens when each failure occurs?
5. In what way does each failure matter?
6. What can be done to predict or prevent each failure?
7. What should be done if a suitable proactive task cannot
be found?
By answering the first five questions, it is possible to obtain
detail information about the protective relay in its operating
context and identify the dominant causes of failures. Question
six and seven determine the maintenance procedure for each
failure mode of the relay [5].
The maintenance plan can be either or both proactive
and/or reactive. Proactive plans are undertaken before a failure
occurs, whereas reactive plan deals with failed state which
prevents equipment from getting into a failed state. The
maintenance tasks considered in this work are the following:
Applying Reliability Centered Maintenance to a
Digital Protective Relay H. Tavares, H. Leite, A. Pinto, P. Vidal and J. Santos
D
2012 3rd IEEE PES Innovative Smart Grid Technologies Europe (ISGT Europe), Berlin
978-1-4673-2597-4/12/$31.00 ©2012 IEEE
![Page 2: 06465758](https://reader035.fdocuments.us/reader035/viewer/2022080913/563db9d4550346aa9aa0576e/html5/thumbnails/2.jpg)
2
- T1: Preventive condition-based maintenance;
- T2: Periodic preventive maintenance (overhauling
of components);
- T3: Periodic preventive maintenance (replace
components);
- T4: Corrective maintenance;
- T5: Redesign of functional modes;
- T6: Finding hidden failures;
- T7: Combination of T1, T2 and T3;
To establish the most appropriate maintenance task in order
to avoid each failure mode of the digital protective relay
decision criterion is applied to each of the failure mode of the
digital protective relay. This criterion is based on the
consequences of the digital protective relay failures, reliability
of the equipment, technical, financial resources and risk
tolerance. The Maintenance Department at the Portuguese
Distribution Network Operator (DSO) has lately
registered the causes of protective relays failures and their
respective repair costs. Therefore, this work applies the RCM
method with the currently available information, to address
functional needs of the protection relay with an adequate
maintenance plan.
III. DIGITAL PROTECTIVE RELAYS INSTALLED AND ACTUAL
MAINTENANCE POLICY
A digital relay consists of the following main parts:
processor, analogue input system, digital output system,
independent power supply, communications and user
interface. These are to be assessed as possible functional
failures.
Normally at the Maintenance Department in DSO the
protective relays are subjected to a five year planned
maintenance programme where all the functional functions are
tested and visual inspection is made.
The length of “effective age” in year of the digital
protective relays installed at the primary substation which has
not failed yet is showed in Fig. 1.
Fig. 1. The “effective age” in years of the installed digital protective relays
that never failed.
So that, 121 digital protective relays have been put under a
planned maintenance and 51 of them already had two planned
maintenance. Fig. 2 shows the number of digital protective
relays that failed versus the “effective age” of its failure. Note
that, 4 of them fail before the first five year maintenance plan
and 12 of them fail even after the planned maintenance.
Fig. 2. The number of the digital protective relays failure by their “effective
age”.
An analysis was then performed to establish a correlation
between a condition index and the relays “effective age” and
no survivor curve was identified, i.e. no relationship was
found between the relays age and the percentage of the
equipment that has failed or retired.
IV. RCM METHODOLOGY SUGGESTED
In order to find an optimal maintenance plan, it is necessary
to identify maintenance tasks in order to avoid various failure
modes from the digital protective relay. The maintenance plan
has the objective of ensuring high reliability at a minimum
cost.
Firstly, the RCM methodology identifies the “failure
modes” which are reasonable and likely cause of the digital
protective relay failure. A failure mode is any event which
causes a functional failure. Secondly, an “effect analysis” is
performed for each of those identified functional failure. A
description of the failure effects outlines what happens when a
failure mode occurs. It should include all the information
needed to support evaluating the consequences of those
failures. The effects of the failure are described in terms of
non-evidence or evidence that the failure has occurred, threat
to safety, environmental hazards, operational or non-
operational effects [7]. In this work the cost analysis were
quantified and present in Table I. It is necessary to include
when operational or non-operational failure modes occur.
TABLE I
COSTS CONSIDERED
Costs Quantified Variables
Scheduled maintenance
Staff required
Repair time (h)
Staff per hour (€/h)
Staff transportation, repair equipment, etc...
Failure repair Digital protective relay repair cost
Operational consequences Expected energy not supplied
A. The RCM Decision Process
The RCM decision worksheet is illustrated in Fig. 3, [4].
The reliability indicators of the digital protective relay failure
modes are the Mean Time between Failures (MTBF) and
Mean Time to Repair (MTTR), [8].
9
28
91
12
4855
11 7
39
12
0
20
40
60
80
100
2 3 4 5 6 7 8 9 11 13
1
2
1
6
1
3
2
1
0
1
2
3
4
5
6
7
2 3 5 6 7 8 9 11
![Page 3: 06465758](https://reader035.fdocuments.us/reader035/viewer/2022080913/563db9d4550346aa9aa0576e/html5/thumbnails/3.jpg)
3
Is a task to detect
whether the failure is
occurring or about to
occur applicable?
Is a scheduled
restoration task to
reduce the failure
rate applicable?
T1
Is a scheduled discard
task to reduce the
failure rate
applicable?
Is a failure-finding
task to detect the
failure applicable?
Could the multiple
failure affect safety or
the environment?
Is a combination of tasks
to avoid failures
aplicable?
T2
T3
T6
T5 T4
Does the failure mode
have safety
consequences?
Does the failure mode
have environmental
consequences?
Does the failure mode
have operational
consequences?
Will the loss of
function caused by this
failure mode on its
own become evident
to the operating crew
under normal
circunstances?
Yes
No
No
Yes
No
No
No
No
No
No
Yes
Yes
Yes
Yes
Yes
Is a task to detect
whether the failure is
occurring or about to
occur applicable?
Is a scheduled
restoration task to
avoid failures
applicable?
T1
Is a scheduled discard
task to avoid failures
applicable?
T2
T3
No
No
No
Yes
Yes
Yes
T7 T4
NoYes
Is a task to detect
whether the failure is
occurring or about to
occur applicable?
Is a scheduled
restoration task to
reduce the failure
rate applicable?
T1
Is a scheduled discard
task to reduce the
failure rate
applicable?
T2
No
No
Yes
Yes
Yes No
T3 T4
NoYes
Fig. 3. The RCM decision logic diagram.
V. APPLYING RELIABILITY CENTERED MAINTENANCE TO A
DIGITAL PROTECTIVE RELAY
As an example of all function from the digital protective
relay, Table II select seven of those functions.
TABLE II
SEVEN DIGITAL PROTECTIVE RELAY FUNCTIONS
Protective elements
1 Instantaneous overcurrent (50)
2 Instantaneous overcurrent for neutral (50N)
3 Under voltage (27)
Automation element
4 Reclosing relay (79)
5 High voltage automatic reset overload relay
Additional elements
6 Disturbance recorders
7 Events log
From Table II, three relay functions were selected (i.e. 1, 4
and 7) as an example to identify the functional failures [9].
TABLE III
EXAMPLE OF THE FUNCTIONAL FAILURES
Functions
(F) Functional Failures (FF)
1
A The protective relay does not operate when a
network fault occurs (incorrect operation)
B
The protective relay does operate when a
network fault does not occurs(unintentional
operation)
4 A Incorrect reclosing operations (acts erroneously)
B Digital output system does not work
7 A Events log or state-change event are not
recorded or stored
From the functional failure, Table IV shows the identified
failure modes from the protective relay.
TABLE IV
FAILURE MODES
F FF Failure Modes (FM)
1 A
1 Microprocessor does not perform the
protection algorithm
2 Power supply unit burned
3 Digital output system does not work, the
contacts are interlocked
4
A / D converter does not correctly convert
the analogue signals measures, so that the
protection does not operate accordingly
5 Input digital signals system damaged
4 A 1
Microprocessor does not perform the
protection algorithm
2 Digital output system does not work, the
![Page 4: 06465758](https://reader035.fdocuments.us/reader035/viewer/2022080913/563db9d4550346aa9aa0576e/html5/thumbnails/4.jpg)
contacts are interlocked during the reclosing
process
3 Input digital signals system damaged,
circuit breaker change-
7 A 1
Microprocessor does not perform the voltage
values
2 Memory damaged
Table V lists the failure effects of each failure mode.
TABLE V
FAILURE EFFECTS ANALYSIS
F FF FE Failure effects
1 A
1
-Signalling from watchdog
- Possibility of failing the protected equipment and
incrementing the collateral damage
-Increment outage durations well as the
energy non-supplied
2
-Signalling from watchdog
- Possibility of failing the protected equipment and
incrementing the collateral damage
- Increment outage duration as well as the
energy non-supplied
3
-Possibility of damaging the
-Increment the collateral damage
-Increment outage duration and
non-supplied
4
-Protective relay mal
-Increase the expected energy
customers
5
-Protective relay mal operate
-Increment outage duration and
non-supplied
4 A
1
-Signalling from watchdog
-Protective relay mal
-Increment outage duration and
non-supplied
2
- Possibility of failing the protected
cable in this example) and increment
collateral damage
-Increment outage duration and
non-supplied
3 -Protective relay mal
7 A 1 -Signalling from
2 -Signalling from
Table VI shows the failure consequence
determined from the RCM worksheet showed in Fig. 3
TABLE VI
FAILURE CONSEQUENCES & MAINTENANCE
F FF MF Failure
Consequence
1 A
1 Safety
Operational
2 Safety
Operational
3 Non-operational
4 Non-operational
5 Non-operational
4 A
1 Safety
2 Safety
3 Hidden function
7 A 1 Non-operational
2 Non-operational
A. Comments on Failure Consequences
Twenty nine different operational modes
together responsible for different functional
shows the results of the failure consequences
13.79% are hidden and 86.21% are evident functions
during the reclosing
ocess
Input digital signals system damaged,
-state wrong read
Microprocessor does not perform the voltage
values
Memory damaged
each failure mode.
NALYSIS
Failure effects
Signalling from watchdog
the protected equipment and
the collateral damage
well as the expected
supplied
Signalling from watchdog
Possibility of failing the protected equipment and
the collateral damage
Increment outage duration as well as the expected
supplied
Possibility of damaging the protected equipment
ncrement the collateral damage
Increment outage duration and the expected energy
supplied
Protective relay mal-operate
energy non-supplied to
mers
relay mal operate
and the expected energy
supplied
Signalling from watchdog
Protective relay mal-operate
Increment outage duration and the expected energy
supplied
Possibility of failing the protected equipment (MV
and incrementing the
collateral damage
Increment outage duration and expected energy
supplied
Protective relay mal-operate
from watchdog
from watchdog
failure consequences maintenance task,
from the RCM worksheet showed in Fig. 3.
AINTENANCE TASK
Maintenance task number
T4
T4
T6
T6
T6
T4
T6
T6
T4
T4
different operational modes were identified all
functional failures. Fig. 4
shows the results of the failure consequences. Note that
evident functions.
Fig. 4. The failure consequences.
The evident functions
maintenance task, while the
plan of finding hidden failures task.
relationship between equipment age and the percentage of the
equipment population that has failed or retired
preventive maintenance may not be
apply. A finding hidden technique should be carried o
Scheduled failure-finding entails checking hidden function
regular intervals. A failure finding task on a digital protective
relay is very important for a maintenance plan as digital
protective relay are characterized for its high reliability. The
failure finding task consists o
situations of faults, allow
protective relay works when required. To determine failure
finding intervals, the failure rates of digital protective relay
functions must be known, as well as the occasions when
failures of the protected equipment
protective relays are in a failed state
determine the failure-finding intervals
used [3]:
2
MFM
TEDM
TIVEM
FFI
××
=
Where: TIVE
M is the mean time between failures
protective device in years; M
failures of the protected function in years;
time between multiple failures in years
As aforementioned, multiple
protected equipment fails and
a failed state. The failure of the protected equipment and the
protective relay happens independently.
was considered that the protected equipment is a medium
voltage underground cable with a conditional probability of
0.00613failures/year [11] and a conditional probability of
failure of digital protective relay of
As it is known the conditional probability of both
relay and protected equipment, with the help of the
Chronological Monte-Carlo technique
probability of multiple failure of 0.000026 of one year, after
placing 70680 random points
4
functions should have a corrective
, while the hidden functions should have a
finding hidden failures task. As there was no
equipment age and the percentage of the
equipment population that has failed or retired, periodic
maintenance may not be a suitable technique to
apply. A finding hidden technique should be carried out.
finding entails checking hidden functions at
A failure finding task on a digital protective
relay is very important for a maintenance plan as digital
protective relay are characterized for its high reliability. The
consists of testing and simulating different
, allows examining whether digital
protective relay works when required. To determine failure
finding intervals, the failure rates of digital protective relay
functions must be known, as well as the occasions when
the protected equipment occurs and digital
in a failed state [10]. In order to
finding intervals (FFI) expression (1) is
)1(
is the mean time between failures of the
TEDM is the mean time between
ures of the protected function in years; MF
M is the mean
failures in years;
ultiple failures occur when the
and the digital protective relay is in
failure of the protected equipment and the
independently. In this example, it
was considered that the protected equipment is a medium
derground cable with a conditional probability of
] and a conditional probability of
digital protective relay of 0.00333 failures/year [1].
As it is known the conditional probability of both protective
relay and protected equipment, with the help of the Non-
Carlo technique it was determining the
probability of multiple failure of 0.000026 of one year, after
placing 70680 random points. The estimated probability for
![Page 5: 06465758](https://reader035.fdocuments.us/reader035/viewer/2022080913/563db9d4550346aa9aa0576e/html5/thumbnails/5.jpg)
5
multiple failure is within the variance of 0.01% and 95% of
confidence interval.
VI. FINAL REMARKS & CONTRIBUTION FROM THIS WORK
This work shows the application of the RCM methodology
to a digital protective relay which protects a medium voltage
underground cable. Nineteen functions from the protective
relay are evaluated, where functional failures, effects and their
consequences are identified. With this analysis, the
maintenance staff may spot functional failures quicker and
reduce the repair time and its associated costs. With RCM
methodology it is possible to understand better the impacts of
its functional failures on the entire network.
Through signalling from the protective relay “watchdog
function”, it is possible to identify 86% of all failures. Thus
the corrective maintenance task should be applied. Based on
the available source data, when a protective relay is protecting
an underground cable at a substation, the planned maintenance
programme should be of 2.5 years for hidden failures.
Nevertheless it would be necessary to analyse a larger sample
of data in order to make this study conclusive.
Applying RCM to a digital protective relay from
distribution substation, the Maintenance department from an
Electrical Utility can:
1. Obtaining the component failure rate of each digital
protective relay, which can help to establish a more
efficient maintenance plan;
2. Improving protection reliability and making ideal
decisions to improve a protection system, as the
maintenance criteria is based on the implication of
power system dependability and security.
3. Understanding better the digital protective relay
behavior in its operational context which can help
selecting the most effective maintenance activity that
would prevent each failure mode;
4. Revising the current maintenance procedures during a
digital protective relay life span and adjusting these
procedures according to the relay’s operational
performance.
VII. REFERENCES
[1] R. Kirby and R. Schwartz, "Microprocessor-based protective
relays," Industry Applications Magazine, IEEE, vol.15, no.5, pp.43-50,
September-October 2009.
[2] Juan M. Gers and Edward J. Holmes, “Protection of electricity of
distribution networks”, 2nd ed., Stevenage: Institution of Electrical
Engineers, 2004, ISBN: 0-86341-357-9, pp. 1-43.
[3] J. Moubray, “Reliability centered maintenance”, 2nd ed., Amsterdam:
Elsevier Butterworth-Heinemann, 1997, ISBN: 0-7506-3358-1, pp.18-
180.
[4] J. Moubray, "Reliability centered maintenance”, 2nd ed., Amsterdam:
Elsevier Butterworth-Heinemann, 1997, ISBN: 0-7506-3358-1, pp. 200-
201.
[5] Ting Chan, Chen-Ching Liu and Jong-Woong Choe, "Implementation of
reliability-centered maintenance for circuit breakers," Power
Engineering Society General Meeting, 2005 IEEE, pp. 684- 690.
[6] L. Bertling, R. Eriksson and R.N. Allan, "Relation between preventive
maintenance and reliability for a cost-effective distribution
system," Power Tech Proceedings, 2001 IEEE Porto, pp. 6.
[7] Zao-jie Kong and Ying-xin Meng, "Research on Probability Reliability-
Centered Maintenance model based on Requirement-Oriented
Maintenance," Industrial Engineering and Engineering Management
(IE&EM), 2011 IEEE 18Th International Conference , pp. 1155-1158.
[8] M. Fotuhi-Firuzabad, S. Afshar, D. Farrokhzad, and Jaeseok Choi,
“Reliability centered maintenance program initiation on electric
distribution networks," Transmission & Distribution Conference &
Exposition: Asia and Pacific, 2009, pp.1-4.
[9] Ding Maosheng, Wang Gang and Li Xiaohua, "Reliability analysis of
digital relay," Developments in Power System Protection, 2004, Eighth
IEE International Conference, pp. 268- 271.
[10] I.P. Siqueira, "Optimum reliability-centered maintenance task
frequencies for power system equipments," Probabilistic Methods
Applied to Power Systems, 2004 International Conference, pp. 162-167.
[11] IEEE Recommended Practice for the Design of Reliable Industrial and
Commercial Power Systems, IEEE Standard 493-1990, 1991, pp. 114.
VIII. BIOGRAPHIES
Helder Tavares was born in Vale de Cambra, Portugal, on February 3, 1989.
He received the M.Sc. degree in electrical engineering from the Faculty of
Engineering of the University of Porto (FEUP), Portugal, in 2012.
Helder Leite received his Electrical Engineering degree from University of
Porto, Portugal in 2000 and the PhD degree in Electrical Engineering from
The University of Manchester, UK, in 2004. H. Leite joined university of
Porto as a Lecturer in 2005. His research interests include Distribution
Generation Integration, Electric Power Systems and Power Systems
Protection.
Alberto Pinto received the M.Sc. degree from the Faculty of Engineering of
the University of Porto (FEUP), Porto, Portugal, in 2008, in electrical
engineering. Since 2009, he is a specialist engineer in the Operation and
Maintenance Department at EDP Distribuição-Energia S.A, the Portuguese
Distribution System Operator.
Pedro Borges Vidal received his Electrical Engineering and Computers
degree from Faculty of Engineering of the University of Porto (FEUP), in
1998 and has a master degree in business administration (MBA). Since June,
2011, he is responsible for OMPRT (Operation and Maintenance Department-
Porto) in EDP Distribuição-Energia S.A.
José Miguel Santos received his Electrical Engineering and Computers
degree from Faculty of Engineering of the University of Porto (FEUP), in
1995 and has a MBA in business administration. He is now a subdirector for
Automation and Telecontrol in EDP Distribuição- Energia S.A.