Pearl GTL Project LINDE ENGINEERING Shell Project No: HP-3000-QAT Contractor Project No: 5887 Project Document Number: T.4.318.623 Project Rev.: O Page 1 of 17 SUPPLIER/VENDOR DOCUMENTATION Purchase Order Number: 2MH127 Equipment Description: N/A Vendor/Supplier Name: GAMA QATAR CO. W. L. L. Vendor/Supplier Code: LOC470 Document Title: INSPECTION TEST PLAN FOR INSTALLATION OF AIR INTAKE FILTER Vendor/Supplier Doc Number: GAM-ITP-QAC-GTL-050 Vendor/Supplier Revision: C Tag/Item Number(s): SEE NEXT PAGE Unit: SEE NEXT PAGE PCWBS: SEE NEXT PAGE Vendor/Supplier Prepared By Initials / Signature Vendor/Supplier Checked By Initials / Signature Vendor/Supplier Approved By Initials / Signature Vend/Supp Revision Date SK EO AG 22.02.2009 Status of Submission (tick applicable box before submission) For Review/Info: X Final: Certified: As-Built: Purchaser signature below does not indicate responsibility or liability for accuracy or completeness of this document, nor does it alter any contractual terms or conditions or relieve the Supplier/Vendor of his contractual obligations. PURCHASER AREA BELOW Contractor Contract Number: PI 092 Contractor Name: LINDE Contractor Doc. No: GAMAC-0100-M-PC 1344 Contractor Rev no: 1.0 Review Code and Status Contractor Initials / Signature Date signed Code 1 No Comments. ACCEPTED. Work May Proceed. Code 2 Comments As Noted. Incorporate Comments, Revise and Resubmit. Work May Proceed. Code 3 REJECTED. Incorporate Comments, Revise and Resubmit. Work May NOT Proceed. Code 4 Not Reviewed. Work May Proceed.

Transcript of 050-ITP FOR INSTALLATION OF AIR INTAKE FILTER.pdf

  • Pearl GTL Project

    LINDE ENGINEERING

    Shell Project No: HP-3000-QAT Contractor Project No: 5887

    Project Document Number: T.4.318.623 Project Rev.: O Page 1 of 17

    SUPPLIER/VENDOR DOCUMENTATION

    Purchase Order Number: 2MH127

    Equipment Description: N/A

    Vendor/Supplier Name: GAMA QATAR CO. W. L. L. Vendor/Supplier Code:

    LOC470

    Document Title: INSPECTION TEST PLAN FOR INSTALLATION OF AIR INTAKE FILTER

    Vendor/Supplier Doc Number:

    GAM-ITP-QAC-GTL-050 Vendor/Supplier Revision: C

    Tag/Item Number(s): SEE NEXT PAGE

    Unit: SEE NEXT PAGE PCWBS: SEE NEXT PAGE

    Vendor/Supplier Prepared By Initials / Signature

    Vendor/Supplier Checked By

    Initials / Signature

    Vendor/Supplier Approved By Initials / Signature Vend/Supp

    Revision Date

    SK EO AG 22.02.2009

    Status of Submission (tick applicable box before submission)

    For Review/Info: X Final: Certified: As-Built:

    Purchaser signature below does not indicate responsibility or liability for accuracy or completeness of this document, nor does it alter any contractual terms or conditions or relieve the Supplier/Vendor of his contractual obligations.

    PURCHASER AREA BELOW

    Contractor Contract Number: PI 092 Contractor Name: LINDE

    Contractor Doc. No: GAMAC-0100-M-PC 1344 Contractor Rev no: 1.0

    Review Code and Status Contractor Initials / Signature

    Date signed

    Code 1 No Comments. ACCEPTED.

    Work May Proceed.

    Code 2 Comments As Noted. Incorporate Comments, Revise

    and Resubmit. Work May Proceed.

    Code 3 REJECTED. Incorporate Comments, Revise and

    Resubmit. Work May NOT Proceed.

    Code 4 Not Reviewed. Work May Proceed.

  • Pearl GTL Project

    LINDE ENGINEERING

    Shell Project No: HP-3000-QAT Contractor Project No: 5887

    Project Document Number: T.4.318.623 Project Rev.: O Page 2 of 17

    Purchase Order Number:

    2DF955, 2DF956, 2DF957, 2DF958, 2DF959, 2DF960, 2DF961, 2DF962

    Tag/Item Number(s):

    1S-2111, 1S-2211, 1S-2311, 1S-2411 2S-2111, 2S-2211, 2S-2311, 2S-2411 1A-2114, 1A-2214, 1A-2314, 1A-2414 2A-2114, 2A-2214, 2A-2314, 2A-2414

    Unit(s): 1-2100, 1-2200, 1-2300,1-2400, 2-2100, 2-2200, 2-2300, 2-2400

    PCWBS: FA03, FB03, FC03, FD03, GA03, GB03, GC03, GD03

  • QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION

    C O 22.02.09 Issued for Company Comments SK EO AG ICC

    B 19.02.09 Issued for Review SK EO AG IFR

    A 15.01.09 Issued for Internal Review SK EO AG IIR

    GAMA Rev.

    Project Rev

    Date Description Prepared

    By Checked

    By

    Approved By

    Status

    No. No. ORIGINATOR

    LINDEGINEERING AG

    Document Title:

    INSPECTION TEST PLAN FOR INSTALLATION OF AIR INTAKE FILTER

    Contractor

    Gama Qatar Co. W. L. L.

    Document No. LOC470

    GAM ITP QAC GTL 050 C

    Org.

    Code

    Doc.

    Type

    Disc. Code

    Geogr. Area

    Seq.

    No

    Rev. No

    Vendor Code

    Project Document Number: T.4.318.623

    Rev No: O

  • QSGTL PEARL PROJECT C2 ASU Construction Works

    ITP NO: GAM-ITP-QAC-GTL-050

    ITP FOR INSTALLATION OF AIR INTAKE FILTER

    DATE: 22.02.09-REV.C

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY (TPI) / VENDOR

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test

    Frequency Reference Document Acceptance Criteria

    Responsible Party

    Verifying Documents S X C A

    T-4.318.623 REV-O Page 4

    1.0 DOCUMENTATION

    1.1 Contractor drawings, project specifications, manuals, codes

    100% - - TECHINICAL

    OFFICE - H R R

    1.2 Lifting studies (For Heavy Equipments)

    100%

    T.4.234.084 - HSSE - H R R

    2.0 EQUIPMENT

    2.1 Equipment identification and name plate verification-Receiving Inspection

    100% T-4.250.945

    Approved drawing,

    DEP 31.10.03.10; DEP 31.29.00.10

    STORE

    INCHARGE GAM-QCR-QAC-GTL-080 I S S S

    2.2 Storage, preservation and documentation (FSI)

    100% T.13.377.360E;T.4.250.932

    Approved drawing,

    DEP 31.29.00.10;DEP 70.10.70.11 T.13.377.454E;

    Vendor instruction,

    FSI GAM-QCR-QAC-GTL-069 I S S S

    2.3

    Inspection measuring and test

    equipment calibration

    100% T.4.250.915 - QCI Calibration certificate H R R

    3.0 FOUNDATION

    3.1

    Foundation complete and

    Accepted (including chipping, pocket cleaning etc.)

    100% T-4.250.945

    Approved drawing,

    DEP 34.19.20.31; T.13.376.358 DEP

    31.29.00.10

    QCI MC Check Record H S S S

  • QSGTL PEARL PROJECT C2 ASU Construction Works

    ITP NO: GAM-ITP-QAC-GTL-050

    ITP FOR INSTALLATION OF AIR INTAKE FILTER

    DATE: 22.02.09-REV.C

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY (TPI) / VENDOR

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test

    Frequency Reference Document Acceptance Criteria

    Responsible Party

    Verifying Documents S X C A

    T-4.318.623 REV-O Page 5

    3.2 Shims installation 100% T-4.250.945 Approved drawing,

    T.13.376.358

    DEP 31.29.00.10

    QCI

    GAM-QCR-QAC-GTL-183 I I S I

    4.0 STRUCTURAL STEEL INSTALLATION UNDER THE STRUCTURE

    4.1

    Foundation acceptance

    a) Check elevation of foundation

    b) Location of anchor bolts (if applicable)

    c) Embedded plates installation (if applicable)

    100% RFC Drawings RFC Drawings QC

    Inspector

    GAM-QCR-QAC-GTL-037

    H

    I

    R

    S

    4.2

    Verification of lifting points & support points(During transportation, Before& after lifting the structure)

    100% T.4.250.897 34.28.00-31;

    T.13.376.359E Site

    Engineer ----------- I S S I

    4.3

    Verify a) alignment b) verticality (Before bolt tightening and or welding)

    100% T.4.250.907

    Approved drawings

    34.28.00-31; T.13.376.359E

    Site Engineer

    GAM-QCR-QAC-GTL-

    038, 039

    H

    I

    S

    I

  • QSGTL PEARL PROJECT C2 ASU Construction Works

    ITP NO: GAM-ITP-QAC-GTL-050

    ITP FOR INSTALLATION OF AIR INTAKE FILTER

    DATE: 22.02.09-REV.C

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY (TPI) / VENDOR

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test

    Frequency Reference Document Acceptance Criteria

    Responsible Party

    Verifying Documents S X C A

    T-4.318.623 REV-O Page 6

    4.4

    Check bolt tightening

    a) Verification of torque

    b) Check anchor bolt tightening (if applicable)

    100% T.4.250.907

    Approved drawings

    34.28.00-31; T.13.376.359E

    Site Engineer

    GAM-QCR-QAC-GTL-041 & Red Indication Mark over bolt head

    H

    I

    S

    I

    4.5

    Painting / Coating Repair works ( if applicable)

    Refer To Painting ITP I

    W

    S

    I

    4.6

    Grouting Verification of surface preparation

    Refer To Grouting ITP (For structure only) I

    W

    S

    I

    4.7

    Final Inspection of accessories

    Ladders, stairs treads, safety cages, Gratings, Toe plates

    100% T.4.250.907

    Approved drawings

    T-13.376.377; 34.28.00-31;

    T.13.376.359E

    Site Engineer

    GAM-QCR-QAC-GTL-040

    GAM-QCR-QAC-GTL-183

    I

    I

    S

    I

    5.0 FILTER HOUSE

  • QSGTL PEARL PROJECT C2 ASU Construction Works

    ITP NO: GAM-ITP-QAC-GTL-050

    ITP FOR INSTALLATION OF AIR INTAKE FILTER

    DATE: 22.02.09-REV.C

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY (TPI) / VENDOR

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test

    Frequency Reference Document Acceptance Criteria

    Responsible Party

    Verifying Documents S X C A

    T-4.318.623 REV-O Page 7

    5.1

    Installation of weather hoods to walkway section

    a) Visual Damages (Gasket D- fog etc)

    b) Bolt tightening

    100% T-4.157.374

    T-4.250.947

    Approved drawings

    DEP 31.29.40.10;

    DEP 31.29.40.31

    QCI

    GAM-QCR-QAC-GTL- 041 GAM-QCR-QAC-GTL-183

    H I S I

    5.2

    Installation of walkway & Filter house

    100% T-4.157.374

    T-4.250.947

    Approved drawings

    DEP 31.29.40.10;

    DEP 31.29.40.31

    QCI GAM-QCR-QAC-GTL-041 GAM-QCR-QAC-GTL-183

    I S S I

    5.3

    Installation of maintenance door, C.A.S access hatch installation, hopper assembly

    100% T-4.157.374

    T-4.250.947

    Approved drawings

    DEP 31.29.40.10;

    DEP 31.29.40.31

    QCI GAM-QCR-QAC-GTL-041 GAM-QCR-QAC-GTL-183

    I I S I

    5.4 Air tightening 100% T-4.157.374

    T-4.250.947

    Approved drawings

    DEP 31.29.40.10;

    DEP 31.29.40.31

    QCI GAM-QCR-QAC-GTL-183 I I S I

    5.5 Louver Section

    a)Mechanical Check-Visual 100%

    T-4.157.374

    T-4.250.947

    Approved drawings

    T-13.376.359 E; DEP 34.28.00.31

    Site

    Engineer GAM-QCR-QAC-GTL-041 & GAM-QCR-QAC-GTL-183

    H I S I

    5.6

    Transition Duct

    a) Visual Inspection (Gasket, cleaning etc.)

    100% T-4.157.374

    T-4.250.947

    Approved drawings

    DEP 31.29.40.10;

    T-13.377.453E

    Site

    Engineer GAM-QCR-QAC-GTL-041 & GAM-QCR-QAC-GTL-183

    H I S I

  • QSGTL PEARL PROJECT C2 ASU Construction Works

    ITP NO: GAM-ITP-QAC-GTL-050

    ITP FOR INSTALLATION OF AIR INTAKE FILTER

    DATE: 22.02.09-REV.C

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY (TPI) / VENDOR

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test

    Frequency Reference Document Acceptance Criteria

    Responsible Party

    Verifying Documents S X C A

    T-4.318.623 REV-O Page 8

    5.7 Silencer Duct

    a) TACK welding -visual 100%

    T-4.157.374

    T-4.250.947

    Approved drawings

    DEP 31.29.40.10;

    T-13.377.453E

    QCI

    GAM-QCR-QAC-GTL-041 GAM-QCR-QAC-GTL-161 GAM-QCR-QAC-GTL-183

    I I S I

    5.8 Round to square Duct

    a)Visual Inspection 100%

    T-4.157.374

    T-4.250.947

    Approved drawings

    DEP 31.29.40.10;

    T-13.377.453E

    QCI GAM-QCR-QAC-GTL-041 GAM-QCR-QAC-GTL-183

    I S S I

    5.9 Hooper Fan

    100%

    T-4.157.374

    T-4.250.947

    T-13.376.359 E; DEP 34.28.00.31

    Site

    Engineer GAM-QCR-QAC-GTL-041

    GAM-QCR-QAC-GTL-183 I I S I

    5.10 Filter Element Installation 100% T-4.157.374

    T-4.250.947

    T-13.376.359 E; DEP 34.28.00.31

    Site

    Engineer GAM-QCR-QAC-GTL-183 I I S I

    5.11 Piping connection-PULS system

    Ref. Piping ITP

    6 FINAL INSPECTION

    6.1 Air tightness, Cleanliness, visual inspection

    100% T-4.157.374

    T-4.250.947

    T-13.376.359 E; DEP 34.28.00.31

    Site

    Engineer GAM-QCR-QAC-GTL-183 I I S I

    6.2 Final Linde MC inspections and documentation

    100% T-4.157.374

    T-4.250.947

    Approved drawings

    DEP 31.29.40.10;

    T-13.377.453E

    QCI Linde MC Check records H H S H

  • GAM-QCR-QAC-GTL-037 Rev. O

    C2 ASU PEARL GTL PROJECT

    RAS LAFFAN INDUSTRIAL CITY

    STRUCTURAL STEEL PRE ERECTION & INSTALLATION

    PROCESS SHEET

    Subcontract Ref.: Report No.:

    Item Description: Date:

    Item Location/ Area: ITP No.: GAM-ITP-QAC-GTL-

    Subsystem: Test Code No.:

    Ref. DWG / Docs:

    Used Measuring and test equipment ref. (if applicable):

    Check the following:

    Item

    No.

    Description QC Inspector

    Initial Date

    Pre Erection :

    1. Foundation Handing over (Civil to Mechanical).

    2. Preparation of grouting (Chipping & Cleaning).

    3. Checking for anchor bolt.

    4. Shim plate fixed as per RFC drawing & work instructions.

    Installation Process :

    1. Foundation Complete & inspected.

    2. All Structural members correctly installed.

    3. Base supports are set at correct elevation.

    4. Structures Plump & alignment in all directions.

    5. Length of bolts is correct.

    6. All washers are correctly mounted.

    7. Correct tightening for all bolts.

    8. All temporary construction materials are removed.

    9. Welding acceptable.

    The Installation of the above Steel has been Satisfactorily completed in accordance with the Drawings& Specifications. Note: This QCR form revised on 23.11.2008 as per the site requirement and QCR form # 125 shall not been used further as per (PMC commends) Transmittal # PI-092-LIN-PMC-TX-21510.

    ORGANIZATIONS NAME SIGNATURE DATE

    Accepte

    d B

    y

    THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    QSGTL OR its PMC REP.

  • GAM-QCR-QAC-GTL-038 Rev. O

    C2 ASU PEARL GTL PROJECT

    RASLAFFAN INDUSTRIAL CITY

    STEEL STRUCTURES ELEVATION REPORT

    ( BASED ON SURVEY REPORT)

    Subcontract Ref.: Report No.:

    Item Description: Inspection Date:

    Item Location / Area: Test Code No.:

    Subsystem: ITP No.:

    Ref. DWG / Documents:

    Used Measuring and test equipment ref. (if applicable):

    INSPECTIONS

    Column No Planned Level Actual Level Level/Difference Plumb

    0 Degree 90 Degree

    ORGANIZATIONS DATE NAME SIGNATURE

    Accepte

    d B

    y THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    QSGTL OR its PMC REP.

  • GAM-QCR-QAC-GTL-039 Rev. O

    C2 ASU PEARL GTL PROJECT

    RAS LAFFAN INDUSTRIAL CITY

    ALIGNMENT REPORT FOR STEEL STRUCTURE

    Subcontract Ref.: Report No.:

    Item Description: Inspection Date:

    Item Location / Area: Test Code No.:

    Subsystem: ITP No.:

    Ref. DWG / Docs:

    Used Measuring and test equipment ref. (if applicable):

    Unit No.:

    OUT OF PLUMBNESS

    ORGANIZATIONS DATE NAME SIGNATURE

    Accepte

    d B

    y THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    QSGTL OR its PMC REP.

  • GAM-QCR-QAC-GTL-040 Rev. A

    C2 ASU PEARL GTL PROJECT-RAS LAFFAN

    INDUSTRIAL CITY

    CHECK LIST OF LADDER, HANDRAIL, STAIRCASE & GRATING

    Subcontract Ref.: Report No.:

    Item Description: Inspection Date:

    Item Location / Area: Test Code No.:

    Subsystem: ITP No.:

    Ref. DWG / Documents:

    Used Measuring and test equipment ref. (if applicable):

    INSPECTIONS

    No.

    Ladders Handrail Staircases Check of Grating

    Mark No Ok/Not Ok

    Mark No Ok/Not Ok

    Mark No Ok/Not Ok

    Mark No Ok/Not Ok

    ORGANIZATIONS DATE NAME SIGNATURE

    Accepte

    d B

    y THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    QSGTL OR its PMC REP.

  • GAM-QCR-QAC-GTL-041 Rev. O

    C2 ASU PEARL GTL PROJECT

    RASLAFFAN INDUSTRIAL CITY

    BOLT TIGHTENING INSPECTION REPORT

    Subcontract Ref.: Report No.:

    Item Description: Inspection Date:

    Item Location / Area:

    Test Code No.:

    Subsystem: ITP No.:

    Ref. DWG / Docs:

    Used Measuring and test equipment ref. (if applicable):

    INSPECTIONS

    Item No/Spool No

    Mark No./Joint No Bolting Bolt Tightening (Torque Value)

    Inspectors Signature Grade Size

    ORGANIZATIONS DATE NAME SIGNATURE

    Accepte

    d B

    y THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    QSGTL OR its PMC REP.

  • PROJECT: C2 ASU PEARL GTL PROJECT, RAS LAFFAN INDUSTRIAL CITY

    EQUIP. TAG.NO.: DESCRIPTION: LOCATION:

    MANUFACTURER: DRG.NO.: RFI NO:

    MONTH

    1 2

    3 4 5 6

    7

    8

    9

    10

    11

    12

    ACTIVITY Month

    Date Checked

    Check all internal and accessories storage is acceptable

    Visual Check : Is there any damage

    Check for protective covers on all the openings

    Check all warning labels,like N2 warning plate are existent

    Actual Pressure level

    Required Pressure Level

    GAMA SIGN WITH DATE

    LINDE SIGN WITH DATE

    QSGTL or its PMC

    NOTE:

    GAM-QCR-QAC-GTL-069 Rev. O

    STORAGE, PRESERVATION AND NITROGEN PURGING REPORT

    FORM NO:

    SHT:

  • C2 ASU PEARL GTL PROJECT

    RAS LAFFAN INDUSTRIAL CITY

    GAM-QCR-QAC-GTL-080 Rev. O

    EQUIPMENT RECEIPT CHECK SHEET

    ITEM No: PO No: REQ No:

    UNIT No: MANUFACTURER :

    ITEMS TO BE CHECKED INSPECTOR

    INITIAL REMARKS

    1 Name Plate

    2 Preparation and painting

    3 Desiccant installed

    4 Moisture present

    5 Nozzle flange faces acceptable

    6 Temporary nozzle protection acceptable

    7 Internals and accessories complete and storage acceptable

    8 Purge - pressure:

    Purge monitoring date: Pressure

    Date of initial inspection:

    Name and signature of Inspector:

  • Welder

    ID

    1

    Visual

    InspectionLocation RemarksWPS No

    VISUAL INSPECTION REPORT FOR EQUIPMENT/STRUCTURAL STEEL

    Date of

    Acceptance Visual

    Inspection

    Name :

    Project Name : ASU C2 PEARL GTL PROJECT Date :

    Report No :

    SL

    No

    GAM-QCR-QAC-GTL-161 REV. O

    ProcessEquipment TypeName of Welder

    Company / PMC QCLINDE QC

    Date :

    Note: Acceptence Criteria-

    Prepared By Checked By: GAMA QATAR QC

    Signature :

  • C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY

    AIR INTAKE FILTER INSTALLATION PROCESS SHEET

    Tag No: Report No:

    Item Description: Date:

    Drawing No: Area:

    System No: Sub-System No:

    Item No

    Description

    Signature & Date

    Gama Linde QSGTL

    1. Foundation complete, Level & Accepted.

    2. Shim plates as per drawings

    3. Installation of Staircase, ladder, gratings, toe plates etc.

    3.1 Installation of Weather hood

    4 Installation of 1st , walkway and second cabins

    5 Installation of accessories (doors, CAS access hatch etc)

    5.1 Air tightening Inspection

    5.2 Louver section installation

    5.3 Transition duct installation

    6 Silencer duct installation

    6.1 Round to square duct installation

    7 Hooper fan installation

    8 Filter element installation

    9 Final Inspection (Cleanliness, air tightness, visual checks etc.)

    Remarks:

    The Installation of the above Air Intake Filter has been satisfactorily completed in accordance with the Drawings & Specifications

    ORGANIZATIONS DATE NAME SIGNATURE GAMA QATAR REP

    LINDE REP

    QSGTL REP

    GAM-QCR-QAC-GTL-183 Rev. O