05 Strategic Mine Planning 1

download 05 Strategic Mine Planning 1

of 39

Transcript of 05 Strategic Mine Planning 1

  • 8/11/2019 05 Strategic Mine Planning 1

    1/39

    Copyright Datamine Corporate Limited1

    Strategic Mine Planning: Iron ore Case

  • 8/11/2019 05 Strategic Mine Planning 1

    2/39

    Copyright 1983-2005 Datamine Corporate Limited 2

    Hotteling

    Mining Economics

  • 8/11/2019 05 Strategic Mine Planning 1

    3/39

    Copyright 1983-2005 Datamine Corporate Limited 3

    Iron Ore Multimine Problem

    http://www.tradekey.com/kb-Iron-Ore-Fines/

    WANTED:Iron ore 58% fines Commodity: IRON ORE FINES ORIGIN: INDIA SPECIFICATIONS: Fe 58%rejection -57% Al2O3 3% rejection -2% SiO2 6%, 57 US$/ton

    http://go4worldbusiness.com/show/members/latest/inqdetails.asp?objid=130298http://go4worldbusiness.com/show/members/latest/inqdetails.asp?objid=130298
  • 8/11/2019 05 Strategic Mine Planning 1

    4/39

    Copyright 1983-2005 Datamine Corporate Limited 4

    Current Iron Ore Solution

    Single Cut-Off gradeFix by Pit, Fix in Time

    Individual Pit ShellsLerch Grossman

    Individual Independent

    Pushback Shells

    Multimine OptimizationLP using Xpac, Mine Max, Whittle MM, Comet

    Max Global NPV???

    Blending Targets just in the last process

  • 8/11/2019 05 Strategic Mine Planning 1

    5/39

    Copyright 1983-2005 Datamine Corporate Limited 5

    NPV Multimine Strength-weakness for the Iron Ore Project

    Multimine Current Solution: Constrained to main mine site

    with small satellites ore bodies. Input Pit sequence impact

    results, giving preference topushbacks of the first mine,after the second the third.

    To find the optimal pit

    sequences is necessary to playwith the pit permutations.

    1 2 3

    1 23

    12 3

    12 3

    1 23123

    71!850,478,588,567,862,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000

  • 8/11/2019 05 Strategic Mine Planning 1

    6/39

    Copyright 1983-2005 Datamine Corporate Limited 6

    Datamine SolutionULTIMATE PITLG LARGE PITMR SMALL PIT

    LP MULTIMINE PITTARGETS

    NPVSBLENDING WITH

    TARGETS

    PUSHBACKGENERATOR

    GT-CURVE

    PUSH/BENCH

    GT-CURVEPIT/BENCH

    LP MULTIMINESCHEDULETARGETS

    SCHEDULER

    STOCK PILE

    The ultimate pit will generate a pit limit. With large pits, LG will provide sufficient reserves for 40 years with a short processing time.With small pits, Maximising Resources will provide a maximum limit.

    The grade tonnage curves by bench and by pit will generate a globalreserves inventory. Studio will be used to create the grade-tonnagecurves which will become the input for JC-LP al gorithm.

    The LP algorithm will determine the optimal mix, suggesting tonnage, periods, average grades by pit and by period. The algorithm targetswill be maximized for NPV given the product specification as a set ofconstraints. As a sub-product for every constraint, t he LP algorithmwill provide shadow prices plus reduced cost for every decisionvariable. The

    A Blended Sequence will be created using the blend targets defined by pit and by period (from the LP algorithm).

    Pushbacks will be generated using the Blending Sequence plusoperational constraints: sinking rate, minimum width, contiguity andmaterial tonnage.

    Using the Pushbacks as i nput, grade-tonnage curves by bench and by pushback will be generated. These curves will be a representation ofthe operational reserve inventory.

    Using the Pushback grade-tonnage curves the LP algorithm willgenerate more operational optimization results. The results willinclude targets by pushback and by year.

    Using the LP targets, which list tonnages, blends, pushbacks and

    periods, a final schedule will be generated using the Scheduler in NPVS. This will be used in future designing stages, includingstockpile optimization.

  • 8/11/2019 05 Strategic Mine Planning 1

    7/39Copyright 1983-2005 Datamine Corporate Limited 7

    A proof-of-concept study at pilot scale to generate a multi-pit,long-term production plan for CVRD Carajs which maximizesthe Net Present Value of CVRD's operation , while:

    meeting the specification (product quality) targets;

    respecting the available infrastructure facilities; adhering to the maximum amount of waste removal;

    meeting the total material movement targets; and

    feasible according to CVRD's operating constraints.

    Industrial Application 1: CVRD Pilot Project

  • 8/11/2019 05 Strategic Mine Planning 1

    8/39Copyright 1983-2005 Datamine Corporate Limited 9

    Grade stabilization in the two key-products (SFCJ and PFCJ)considering unavoidable increase in SiO2 over time:

    CVRD Terms of Reference

    The acronym within brackets below each grade refers to thespecific variable name as defined and used by CVRD.

  • 8/11/2019 05 Strategic Mine Planning 1

    9/39Copyright 1983-2005 Datamine Corporate Limited 10

    Solution Methodology

    Multimine GlobalOptmization

    Grade-Tonnagecurves by Pit,

    Bench &Interval

    ControlVariable

    Results Table

    Multi-correlation Analysis

    Blended SequenceOptimization

    Individual PitSchedules

    Check OperationalConstraints

    Sensitivity Analysis

    Shadow Pricesand ReducedCosts Tables

    Correlation analysis using Pearson's andEuclidian Distance models to determine theextent of the correlation between key variables

    and to define the control variable(s) for the pilotproject.

    Schedule optimization and parameterization todetermine grade-tonnage curves by bench, byincremental pit and by key-variable interval,generating a global reserves inventory for all the

    pits.

    Definition of the optimal mix/blend of ore andaverage grades by pit and by period. Theresulting blended sequence is maximized forNPV in a iterative fashion, according to productspecification and operational constraints.

    Economic and operational analysis of themultimine scheduling results. Identification ofcritical constraints and parameters. Shadowprices and reduced costs analysis on key-variables and constraints to guide the operationaldecision-making process.

  • 8/11/2019 05 Strategic Mine Planning 1

    10/39Copyright 1983-2005 Datamine Corporate Limited 11

    The results of the correlation analysis indicate that all key-variables are strongly correlated, except P (in POVER and inPSFT).

    Multi-correlation Analysis

    FEOVER SIOVER ALOVER MNOVER POVER FESFT SISFT ALSFT MNSFT PSFT

    FEOVER 1.0 0.7 0.6 0.4 0.4 1.0 0.8 0.5 0.3 0.4SIOVER 0.7 1.0 0.6 0.3 0.4 0.7 0.9 0.5 0.2 0.4

    ALOVER 0.6 0.6 1.0 0.3 0.7 0.6 0.5 0.9 0.3 0.7MNOVER 0.4 0.3 0.3 1.0 0.1 0.4 0.5 0.4 0.9 0.1POVER 0.4 0.4 0.7 0.1 1.0 0.4 0.2 0.6 0.1 0.9FESFT 1.0 0.7 0.6 0.4 0.4 1.0 0 .8 0.5 0.3 0.4SISFT 0.8 0.9 0.5 0.5 0.2 0.8 1.0 0.5 0.4 0.2

    ALSFT 0.5 0.5 0.9 0.4 0.6 0.5 0.5 1.0 0.4 0.6MNSFT 0.3 0.2 0.3 0.9 0.1 0.3 0.4 0.4 1.0 0.1PSFT 0.4 0.4 0.7 0.1 0.9 0.4 0.2 0.6 0.1 1.0

    0-0.4%0.4%-0.5%0.5%-0.7%0.7%-1%

    **. Correlation is s ignificant at the 0.01 level (2-tailed).

    Correlations

  • 8/11/2019 05 Strategic Mine Planning 1

    11/39Copyright 1983-2005 Datamine Corporate Limited 12

    Euclidian distance model analysis suggest a similar behaviorbetween SiO2, Al2O3 and Mn. This means that gradestabilization of SiO2 will also control both Al2O3 and Mn.

    P has not been used as a control variable, but it has beenmeasured and recorded in all scheduling runs.

    Multi-correlation Analysis

    SiO2

    Control

  • 8/11/2019 05 Strategic Mine Planning 1

    12/39Copyright 1983-2005 Datamine Corporate Limited 13

    Global Optimization and Blended ScheduleN5 N4E

    N4W

    Year 1Year 2Year 3

    Year 10

    Global optimization and blended scheduling results byincremental pit, by bench, by period and by key-variableinterval, generating an optimal schedule and the globalmineable reserves inventory for all the pits.

  • 8/11/2019 05 Strategic Mine Planning 1

    13/39Copyright 1983-2005 Datamine Corporate Limited 14

    Scheduling Results

    The table illustrates the scheduling results obtained, in thisinstance for SiO2 in the ore for Pit N5, Benches 5, 6 and 7.

    Similar results were compiled for all benches of pits N4E, N4Wand N5, for all key-variables.

    BENCH CUT PERIOD1 PERIOD2 PERIOD3 PERIOD4 PERIOD5 PERIOD6 PERIOD7 PERIOD8 PERIOD9 PERIOD10

    SIO2%

    PIT-N5 5 0.03 0 0 0 0 0 0 0 0 0 0

    PIT-N5 5 0.50 0 0 0 0 0 0 0 0 0 0PIT-N5 5 1.00 0 0 0 0 0 0 174000 0 0 0

    PIT-N5 5 1.20 0 0 0 0 0 0 296250 0 0 0

    PIT-N5 5 2.00 0 0 0 0 0 0 0 0 0 0

    PIT-N5 5 3.00 0 0 0 0 0 0 0 2589211 0 0

    PIT-N5 5 100.00 0 0 0 0 0 0 0 0 0 0

    PIT-N5 6 0.03 0 0 0 0 0 0 0 0 0 0

    PIT-N5 6 0.50 0 0 0 0 0 0 0 0 0 0

    PIT-N5 6 1.00 963023.438 0 0 0 0 0 0 0 0 0

    PIT-N5 6 1.20 0 0 0 0 0 0 1585453.13 0 0 0

    PIT-N5 6 2.00 0 2870335.16 4345745.84 0 0 0 0 0 0 0

    PIT-N5 6 3.00 0 0 0 0 0 0 4898994 0 0 0PIT-N5 6 100.00 0 0 0 0 0 0 0 0 0 0

    PIT-N5 7 0.03 0 0 0 0 0 0 0 0 0 0

    PIT-N5 7 0.50 0 0 0 0 0 0 0 0 0 0

    PIT-N5 7 1.00 1328039.13 0 0 0 0 0 0 0 0 0

    PIT-N5 7 1.20 0 0 1774921.88 0 0 0 0 0 0 0

    PIT-N5 7 2.00 0 0 0 13980915 0 0 0 0 0 0

    PIT-N5 7 3.00 0 0 0 0 0 0 0 5817006 0 0

    PIT-N5 7 100.00 0 0 0 0 0 0 0 0 0 0

    TOTAL ORE

  • 8/11/2019 05 Strategic Mine Planning 1

    14/39Copyright 1983-2005 Datamine Corporate Limited 15

    Scheduling Results: Surface Area Restrictions

    The diagram on the left shows the initial surface topography in the N4E, N4Wand N5 pits, matching the 2010 pit limits established by CVRD (diagram on theright). The pit road and area constraints provided by CVRD (to be mined out onlyafter 2010) are also marked on the diagram.

    Initial Topo Active Area Final Pit Constraints (2010)

    Area Constraints

    Pit Road

  • 8/11/2019 05 Strategic Mine Planning 1

    15/39

    Copyright 1983-2005 Datamine Corporate Limited 16

    Scheduling Results: Scheduled Pit Surfaces for 2006

    The diagram on the left shows the scheduled pit surfaces for 2006, that respectboth the area restrictions and the pit road.

    Pit Surfaces for 2006

    Area Constraints

    Pit Road

    Final Pit Constraints (2010)

  • 8/11/2019 05 Strategic Mine Planning 1

    16/39

    Copyright 1983-2005 Datamine Corporate Limited 17

    Scheduling Results: Scheduled Pit Surfaces for 2007

    The diagram on the left shows the scheduled pit surfaces for 2007, that respectboth the area restrictions and the pit road.

    Pit Surfaces for 2007

    Area Constraints

    Pit Road

    Final Pit Constraints (2010)

  • 8/11/2019 05 Strategic Mine Planning 1

    17/39

    Copyright 1983-2005 Datamine Corporate Limited 18

    Scheduling Results: Scheduled Pit Surfaces for 2008

    The diagram on the left shows the scheduled pit surfaces for 2008, that respectboth the area restrictions and the pit road.

    Pit Surfaces for 2008

    Area Constraints

    Pit Road

    Final Pit Constraints (2010)

  • 8/11/2019 05 Strategic Mine Planning 1

    18/39

    Copyright 1983-2005 Datamine Corporate Limited 19

    Scheduling Results: Scheduled Pit Surfaces for 2009

    The diagram on the left shows the scheduled pit surfaces for 2009. The positionof the pit road has been clearly preserved eventhough extensive mining is takingplace near its location.

    Pit Surfaces for 2009

    Area Constraints

    Pit Road

    Final Pit Constraints (2010)

  • 8/11/2019 05 Strategic Mine Planning 1

    19/39

    Copyright 1983-2005 Datamine Corporate Limited 20

    Scheduling Results: Scheduled Pit Surfaces for 2010

    The diagram on the left shows the scheduled pit surfaces for 2010. The positionof the pit road has been clearly preserved eventhough extensive mining is takingplace near its location.

    Pit Surfaces for 2010

    Area Constraints

    Pit Road

    Final Pit Constraints (2010)

  • 8/11/2019 05 Strategic Mine Planning 1

    20/39

    Copyright 1983-2005 Datamine Corporate Limited 21

    Scheduling Results: Scheduled Pit Surfaces for 2011

    The diagram on the left shows the scheduled pit surfaces for 2011. The positionof the pit road has been preserved for one additional year (the constraint wasthat the pit road had to be preserved at least until 2010).

    Pit Surfaces for 2011

    Area Constraints

    Pit Road

    Final Pit Constraints (2010)

  • 8/11/2019 05 Strategic Mine Planning 1

    21/39

    Copyright 1983-2005 Datamine Corporate Limited 22

    Scheduling Results: Scheduled Pit Surfaces for 2012

    The diagram on the left shows the scheduled pit surfaces for 2012. The 2010 pitroad and area constraints do not apply any longer so mining is taking placewithin the limits of all three mines.

    Pit Surfaces for 2012

    Area Constraints

    Pit Road

    Final Pit Constraints (2010)

  • 8/11/2019 05 Strategic Mine Planning 1

    22/39

    Copyright 1983-2005 Datamine Corporate Limited 23

    Scheduling Results: Scheduled Pit Surfaces for 2013

    The diagram on the left shows the scheduled pit surfaces for 2013. The 2010 pitroad and area constraints do not apply any longer so mining is taking placewithin the limits of all three mines.

    Pit Surfaces for 2013

    Area Constraints

    Pit Road

    Final Pit Constraints (2010)

  • 8/11/2019 05 Strategic Mine Planning 1

    23/39

    Copyright 1983-2005 Datamine Corporate Limited 24

    Scheduling Results: Scheduled Pit Surfaces for 2014

    The diagram on the left shows the scheduled pit surfaces for 2014. The 2010 pitroad and area constraints do not apply any longer so mining is taking placewithin the limits of all three mines.

    Pit Surfaces for 2014

    Area Constraints

    Pit Road

    Final Pit Constraints (2010)

  • 8/11/2019 05 Strategic Mine Planning 1

    24/39

  • 8/11/2019 05 Strategic Mine Planning 1

    25/39

    Copyright 1983-2005 Datamine Corporate Limited 26

    Scheduling Results: Ore and Waste Totals

    The chart shows the yearly totals for ore and waste, as well asthe variation of the stripping ration between 2006 (period 1)and 2016 (period 10). The expected results were achievedand a more detailed consultancy project is recommended toimprove waste removal variations during and after period 6.

  • 8/11/2019 05 Strategic Mine Planning 1

    26/39

    Copyright 1983-2005 Datamine Corporate Limited 27

    Scheduling Results: Ore Production by Pit

    The chart shows the contribution of each pit (N4W, N4E, N5)to the total ore production from 2006 (period 1) to 2015 (period10).

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    PERIOD1 PERIOD2 PERIOD3 PERIOD4 PERIOD5 PERIOD6 PERIOD7 PERIOD8 PERIOD9 PERIOD1

    N4W

    N4E

    N5

  • 8/11/2019 05 Strategic Mine Planning 1

    27/39

    Copyright 1983-2005 Datamine Corporate Limited 29

    Scheduling Results: Key-Variable Grade Variation

    The table shows the scheduling results for the grade variationof the key-variables. The results match CVRD's stabilizationtargets for the two key-products (SFCJ and PFCJ).

  • 8/11/2019 05 Strategic Mine Planning 1

    28/39

    Copyright 1983-2005 Datamine Corporate Limited 31

    Scheduling Results: Economic Analysis

    The table shows the economic analysis of the scheduled

    production. It considers the following parameters provided byCVRD: Sale contract of 0.55 US$/Ton unit Fe Ore cost of 1.15 US$/Ton ore Processing cost of 8.8 US$/Ton Waste removal cost of 1.15 US$/Ton Interest rate of 10%.

  • 8/11/2019 05 Strategic Mine Planning 1

    29/39

    Copyright 1983-2005 Datamine Corporate Limited 32

    Sensitivity Analysis: Shadow Prices

    Allowable Allowable Shadow

    Variable Name Increase Decrease Price

    TON TON US$/TONPER1 SIOVER 563.8 3435.9 64.6PER2 SIOVER 1897.1 1258.0 13.2PER3 SIOVER 461.8 649.1 10.3PER4 SIOVER 468.8 565.1 38.6PER5 SIOVER 3276.2 4206.6 42.1PER6 SIOVER 6077.3 7020.6 47.2PER7 SIOVER 8343.1 5664.9 47.8PER8 SIOVER 5330.8 2575.7 32.7PER9 SIOVER 10576.7 1545.2 0.7

    PER10 SIOVER 4237.8 6938.5 44.5PER1 ALOVER 4329.0 1037.7 -70.7PER2 ALOVER 5198.9 2011.0 -46.2PER3 ALOVER 922.9 590.8 -48.4PER4 ALOVER 1585.2 1494.0 -58.4PER5 ALOVER 5164.4 4022.3 -65.6PER6 ALOVER 3533.1 4891.1 -71.8PER7 ALOVER 16856.9 3714.0 -63.8PER8 ALOVER 5330.5 6443.2 -65.3PER1 MNSFT 191.3 1248.3 -56.8

    PER2 MNSFT 341.1 601.3 -33.6PER3 MNSFT 5760.9 2801.5 -44.4PER4 MNSFT 1349.5 1968.6 -77.5PER5 MNSFT 5021.5 3910.9 -78.1PER6 MNSFT 4497.3 6298.6 -50.9

    Shadow prices havebeen calculated foreach key-variable ineach period.

    This indicates theallowances in mass foreach key-variablewithout deviating fromthe optimal solution.

    It also providesmanagement with ameasure of the

    economic impact ofrelaxing constraints atdifferent schedulingperiods.

  • 8/11/2019 05 Strategic Mine Planning 1

    30/39

    Copyright 1983-2005 Datamine Corporate Limited 33

    Sensitivity Analysis: Reduced Costs

    The table shows theresults of the reducedcosts analysis for SiO2in Pit N5.

    Reduced costs can beused as a decision-making tool formeasuring the impactof eventual deviationsfrom the optimumschedule allowingmanagement tochoose which cut-offinterval has lesseconomic impact in aparticular schedulingperiod.

  • 8/11/2019 05 Strategic Mine Planning 1

    31/39

    Copyright 1983-2005 Datamine Corporate Limited 34

    Industrial Case 2: MBR Project

    HEM SIB RSIB CG IBLI MIAN Total

    0.92 5.93 2.39 2.16 2.71 0.62 14.73 2.93 12.63 4.48 1.94 3.47 1.55 27.01 3.18 13.13 4.66 1.30 3.07 0.77 26.11 3.70 12.28 4.36 1.35 2.87 0.45 25.01 3.33 13.49 3.91 1.15 2.90 0.51 25.29 2.12 13.50 3.87 0.76 3.85 0.40 24.51

    19.26 3.83 6.77 29.85 19.26 3.83 6.77 29.85 19.26 3.83 6.77 29.85

    19.26 3.83 6.77 29.85 20.18 4.01 5.96 30.16 20.18 4.01 5.96 30.16 20.18 4.01 5.96 30.16 20.18 4.01 5.96 30.16 20.18 4.01 5.96 30.16 20.36 3.98 6.04 30.38 20.36 3.98 6.04 30.38 20.36 3.98 6.04 30.38 20.36 3.98 6.04 30.38 20.36 3.98 6.04 30.38 20.36 3.98 6.04 30.38 20.36 3.98 6.04 30.38 20.36 3.98 6.04 30.38

    16.18 411.79 90.88 8.65 124.08 4.31

    TOTAL

  • 8/11/2019 05 Strategic Mine Planning 1

    32/39

    Copyright 1983-2005 Datamine Corporate Limited 36

    Mine Sequencing - Traditional Method with NPVS

    "helicopter mining";

    Mining takes place simultaneously along the entire the pit area:

  • 8/11/2019 05 Strategic Mine Planning 1

    33/39

    Copyright 1983-2005 Datamine Corporate Limited 38

    Mine Sequencing - Solution Methodology for MBR

    Ultimate Pit withBlending Algorithm

    (Initial Run)

    Refine Schedule with Adjustment Factor

    (% Final Pit)

    Year > 1 ?or

    Targets T ?

    GeneratePushbacks

    CreateSchedule

    CheckTargetsT

    Area Variableset

    A1+A1+A3

  • 8/11/2019 05 Strategic Mine Planning 1

    34/39

    Copyright 1983-2005 Datamine Corporate Limited 39

    PERIOD MASS

    0

    1

    2

    3

    4

    5

    6

    7

    HEM SIB RSIB CG IBLI MIANVARIABLE

    M T O

    MBR

    NPV

    0

    510

    15

    20

    25

    30

    35

    40

    45

    50

    mbr npv

    waste

    ore

    SAP GALIN

    50.891 45.913

    (*) 3Mt on Pilha Itabiritos

    MBR Mine Sequence: Results for Year 1

  • 8/11/2019 05 Strategic Mine Planning 1

    35/39

  • 8/11/2019 05 Strategic Mine Planning 1

    36/39

    Copyright 1983-2005 Datamine Corporate Limited 41

    MBR Mine Sequence: Results for Year 3

  • 8/11/2019 05 Strategic Mine Planning 1

    37/39

    Copyright 1983-2005 Datamine Corporate Limited 42

    NPVS4 enhancements for Iron Ore

    Blending Targets by Period

    OES output, Mining Sequence in Block Model

    Better Pushback Design.

    l k d

  • 8/11/2019 05 Strategic Mine Planning 1

    38/39

    Copyright 1983-2005 Datamine Corporate Limited 43

    Conclusion, Remarks and Future Opportunities

    The Multimine solution provides optimal scheduling results plus valuableinformation for management decision.

    The current Datamine capability is offered through consulting serviceswhich apply the Multimine solution methodology.

    As a future development this methodology will be incorporated into thesoftware products in the Datamine Solution Footprint.

    The approach can be applied to other opportunities in the Market

    1. Oil Sands2. Base Metals

    F O i i

  • 8/11/2019 05 Strategic Mine Planning 1

    39/39

    Future Opportunities

    Oil Sands Canada, 98 BiUS$ Investment

    Not using NPV, using Real Options Currently there is no mining scheduler software supporting RO Opportunity to be the first supplier of Consulting and Software Implementation

    using RO.

    Operational Improvement in SouthAmerica Codelcos Drill to Mill expansion requirements. Phelps Dodge SAG Mill optimization. Pelambres Increasing Work Index Problem. Antamina, Yanacocha, Goldfields, SPCC outsorcing requeriments in Mine

    Planning.