04 PES Power Outlook 20100629 Santos

download 04 PES Power Outlook 20100629 Santos

of 39

Transcript of 04 PES Power Outlook 20100629 Santos

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    1/39

    PHILIPPINE POWER SITUATIONER:

    WILL OUR BROWNOUTS BE SHORT-LIVED OR LONG-LASTING?THE POWER OUTLOOK

    A forum on the Impending Power Crisis

    Victor B. Santos Jr.

    June 29, 2010

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    2/39

    ROTATING BROWNOUTS

    FAST-TRACK CONSTRUCTIONUrgency + Few Players = High Price

    HIGH ELECTRICITY PRICE

    THE

    VICIOUS

    CYCLE OF

    POWER

    CRISIS

    CONSUMER OUTRAGE

    POLITICAL SUPPRESSION OF

    PRICES/UNSTABLE

    REGULATORY ENVIRONMENT

    NOT ENOUGH POWER

    PLANTS BUILT

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    3/39

    DISCUSSION OUTLINE

    1. POWER SUPPLY AND DEMAND:

    WHY ARE WE HAVING BROWNOUTS?

    2. POWER RATES IN THE PHILIPPINES:

    ARE THE PRICES REFLECTIVE OF THEIR TRUE COST?

    3. TAKE-AWAYS AND NEXT STEPS:

    WHAT CAN WE DO TODAY TO PREPARE FOR TOMORROW?

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    4/39

    LATEST DOE FORECAST EXPECTS THE POWER SHORTAGE IN LUZON

    TO HAPPEN STILL IN 2011-2012

    2009 2010 2011 2012 2013 2014Committed 686.00 686.00

    Existing Capacity 10,030.00 10,030.00 9,425.00 9,425.00 9,425.00 9,425.00

    Required Reserve Margin 8,682.00 8,971.00 9,356.00 9,790.00 10,253.00 10,748.00

    Peak Demand 7,036.00 7,270.00 7,582.00 7,934.00 8,309.00 8,710.00

    LUZON GRID

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    12,000

    2009 2010 2011 2012 2013 2014

    Luzon Power Supply-Demand Forecast

    Committed Existing Capacity Required Reserve Margin Peak Demand

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    5/39

    AVERAGE DEPENDABLE

    CAPACITY IN 2009MARCH 1 CAPACITY

    Wind 33.00 -

    Oil Based 1,528.13 1,453.60

    Hydro 1,750.61 668.00

    Natural Gas 2,458.04 1,025.00

    Coal 2,634.00 2,315.00

    Geothermal 410.00 435.00

    -

    1,000.00

    2,000.00

    3,000.00

    4,000.00

    5,000.00

    6,000.00

    7,000.00

    8,000.00

    9,000.00

    10,000.00

    IN THE 1ST HALF OF 2010, THERE WERE NUMEROUS DAYS WHEN THE

    LUZON GRID WENT ON RED ALERT AND ROTATING BROWNOUTS.

    CAUSED BY A CONFLUENCE OF UNFORTUNATE EVENTS:

    DEFICIENT POWERPLANT CAPACITY

    MW REASON

    PLANNED 1,700 MW

    STA RITA 1

    STA RITA 3500

    75,000 EOH

    SCHEDULED

    MAINTENANCE

    ILIJAN 1,200

    MALAMPAYA

    SCHEDULEDMAINTENANCE

    UNPLANNED 1,973 MW

    HYDRO POWER

    MAGAT

    SAN ROQUE

    ANGAT

    HEDCOR

    BAKUNCASECNAN

    BINGA

    SUB-TOTAL

    310

    250

    158

    73

    72150

    50

    1,063

    LACK OF WATEREL NIO

    MASINLOC 1 310 BOILER TUBE LEAK

    SUAL 1 600 BOILER TUBE LEAK

    TOTAL 3,673 MW

    8,813 MW 5,897 MWTOTAL

    753 MWDEFICIT

    PEAK DEMAND: 6,650 MW

    Source: Wholesale Electricity Spot Market Daily Market Updates

    MARCH 01

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    6/39

    -

    500

    1,000

    1,500

    2,000

    2,500

    2009 2010 2011 2012 2013 2014

    Visayas Power Supply-Demand Forecast

    Committed Existing Capacity Required Reserve Margin Peak Demand

    IN VISAYAS, LATEST DOE FORECAST NOW REFLECTS ACTUAL

    SHORTAGE

    2009 2010 2011 2012 2013 2014

    Committed 160.00 638.00 638.00 638.00 638.00

    Existing Capacity 1,505.00 1,505.00 1 ,457.00 1,457.00 1,457.00 1,457.00

    Required Reserve Margin 1,642.00 1,764.00 1,787.00 1,834.00 1,906.00 1,979.00

    Peak Demand 1,331.00 1,430.00 1,448.00 1,486.00 1,545.00 1,603.00

    VISAYAS GRID

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    7/39

    DEPENDABLE CAPACITY MARCH 1 CAPACITYOil Based 539.12 410.78

    Hydro 11.51 6.90

    Coal 140.23 102.75

    Geothermal 906.25 684

    0

    200

    400

    600

    800

    1,000

    1,200

    1,400

    1,600

    1,800 128 MW

    DEFICIT

    PEAK DEMAND: 1, 332MW

    AVE DEP CAP 2009

    WITH NO NEW CAPACITIES COMING IN, THIS SUPPLY SHORTAGE

    HAS ACTUALLY PLAGUED THE VISAYAS GRID FOR THE PAST 2 YEARS

    - SUPPLY DEFICIENCY OF ~128 MW

    VISAYAS GRID

    1,597 MWTOTAL 1,204 MW

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    8/39

    THE ENTRY OF NEW COAL CAPACITY WILL PROVIDE SUFFICIENT BUFFER

    OVER THE NEXT TWO YEARS

    Dep CapAve Dep Cap

    2009

    Dep Cap 1H

    2010

    Dep Cap 2H

    2010

    Dep Cap 1H

    2011

    Biomass 0 0 0 0 18

    Oil Based 539.12 410.78 410.78 410.78 410.78

    Hydro 11.51 6.90 6.90 6.90 6.90

    Coal 140.23 102.75 266.75 348.75 630.75

    Geothermal 906.25 683.80 683.80 683.80 683.80

    0

    200

    400

    600

    800

    1,000

    1,200

    1,400

    1,6001,800

    2,000

    1,597 MWTOTAL 1,204 MW 1,368 MW 1,450 MW 1,750 MW

    3%RESERVE

    MARGIN

    31%RESERVE

    MARGIN

    9%RESERVE

    MARGIN

    PEAK DEMAND: 1,332 MW

    CEDC 1

    82MW

    (MAR.10)

    CEDC 2

    82MW

    (MAY10)

    PEDC

    82MW

    (Oct10)

    CEDC 3

    (Dec10)

    KEPCO-

    SALCON

    200MW

    (JAN.11)

    PEDC

    82MW(JAN 11)

    VISAYAS GRID

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    9/39

    POWER SUPPLY SHORTAGE IN MINDANAO IS EXPECTED

    TO HAPPEN IN 2011

    2009 2010 2011 2012 2013 2014

    Committed 42.00 42.00 50.00 50.00 50.00 100.00

    Existing Capacity 1,682.00 1,682.00 1,682.00 1,682.00 1,682.00 1,682.00

    Required Reserve Margin 1,645.00 1,720.00 1,794.00 1,874.00 1,960.00 2,047.00

    Peak Demand 1,359.00 1,421.00 1,483.00 1,549.00 1,620.00 1,692.00

    -

    500

    1,000

    1,500

    2,000

    2,500

    2009 2010 2011 2012 2013 2014

    DOE Power Supply-Demand Forecast - Mindanao

    Committed Existing Capacity Required Reserve Margin Peak Demand

    MINDANAO GRID

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    10/39

    Dep Cap Actual Cap March 2010

    Oil Based 517.68 436.86

    Hydro 861.80 288.63

    Coal 210.00 210.00

    Geothermal 108.48 98.72

    0.00

    200.00

    400.00

    600.00

    800.00

    1,000.00

    1,200.00

    1,400.00

    1,600.00

    1,800.00

    HOWEVER, 1H 2010 SHORTAGES IN MINDANAO WAS A RESULT OF

    MINDANAOS DEPENDENCE ON HYDRO POWER

    1,698 MWTOTAL 1034 MW

    DEFICIENT

    POWER PLANT

    CAPACITY MW REASON

    UNPLANNED

    AGUS 1-7 538 LACK OF WATEREL NIO

    ILIGAN DIESEL 100SHUTDOWNNEEDS SPARE

    PARTS

    TOTAL 638 MW

    423MWDEFICIT

    PEAK DEMAND: 1,457 MW

    MINDANAO GRID

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    11/39

    HOW MUCH RESERVE CAPACITY DOES A GRID

    REALLY NEED?

    1. AGE AND CONDITION OF POWER PLANTS

    2. RELATIVE SIZES OF INDIVIDUAL POWER PLANT UNITS MORE

    LARGE-SIZED GENERATING UNITS REQUIRE HIGHER LEVEL OFRESERVES

    3. CONDITION/RELIABILITY OF TRANSMISSION SYSTEM

    4. GENERATION CAPACITY MIX HAVING MORE INTERMITTENTSOURCES (e.g. HYDRO AND WIND) REQUIRE HIGHER LEVEL OFRESERVES

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    12/39

    GRID CODE AND ERC-APPROVED ANCILLARYSERVICE PROCUREMENT PLAN

    TYPE OF RESERVE % of PEAK

    DEMAND

    1. Load following

    and frequencyregulation

    2.8%

    2. Spinning

    Reserve*10.4%

    3. Back-Up Service

    19.6%4. Reactive Support -

    TOTAL 32.8%

    Note: * equivalent to largest single unit

    for each grid

    DOE REQUIRED RESERVE MARGIN

    GRID % of PEAKDEMAND

    LUZON 23.4%

    VISAYAS 23.3%

    MINDANAO 21.1%

    DOE Supply-Demand Forecasts use a required

    Reserve Margin based on probabilistic method

    Loss of Load Probability (LOLP) or the

    expected number of days for a specified

    period in which peak demand is expected to

    go exceed capacity

    PRESCRIBED RESERVE MARGINS

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    13/39

    WITH NPC NO LONGER

    ALLOWED TO PUT UP ANY

    NEW POWER PLANTS, WHERE

    WILL OUR NEEDED RESERVE

    CAPACITY COME FROM?

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    14/39

    MUCH NEEDED CAPACITIES WILL COME FROM GREENFIELD

    DEVELOPMENTS AS WELL AS INCREASED AND IMPROVED CAPACITIES

    OF PRIVATIZED PLANTS

    LUZONPlant MW

    CALACA REHAB 320

    BACMAN REHAB 110

    ANGAT REHAB 28

    AMBUKLAO REHAB 70

    REHAB SUB-TOTAL 528 MWPAGBILAO EXPANSION 400

    QPPL EXPANSION 500

    SAN GABRIEL 550

    PANTABANGAN-MASIWAY EXPANSION 77

    CBK EXPANSION 360

    EXPANSION SUB-TOTAL 1,887 MW

    BURGOS WIND 116

    GN POWER 600

    TANAWON 40

    GREENFIELD SUB-TOTAL 756 MW

    LUZON TOTAL 3,171 MW

    MINDANAOPlant MW

    CONAL COAL 200

    MINDANAO III / APO 50

    GREENFIELD TOTAL 250 MW

    VISAYASPlant MW

    KEPCOSALCON CEBU COAL 200GLOBAL PANAY COAL 100

    CEBUEDC - COAL 246

    NASULO 20

    GLOBAL GREEN 18

    ASEA ONE 35

    GREENFIELD TOTAL 619 MW

    TOTAL 4,040 MW

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    15/39

    FROM NOVEMBER 2007 TO OCTOBER 2008, THE LUZON

    GRIDS AVERAGE DEPENDABLE CAPACITY WAS ~7981 MW

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    9982

    9797

    9612

    9427

    9242

    9058

    8873

    8688

    8503

    8318

    8133

    7948

    7763

    7578

    7394

    7209

    7024

    6839

    6654

    6469

    6284

    6099

    Frequency

    DEPENDABLE CAPACITY (MW)

    LUZON GRID- Nov 2007 to Oct 2008

    Frequency Cumulative %

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    16/39

    AFTER PRIVATIZATION PICKED UP MOMENTUM, AVERAGE DEPENDABLE

    CAPACITY OF THE GRID INCREASED BY ~450 MW TO 8,467 MW. THE

    INCREASE HAPPENED WITHOUT ANY NEW POWER PLANTS.

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    9982

    9797

    9612

    9427

    9242

    9058

    8873

    8688

    8503

    8318

    8133

    7948

    7763

    7578

    7394

    7209

    7024

    6839

    6654

    6469

    6284

    6099

    Frequency

    DEPENDABLE CAPACITY (MW)

    LUZON GRID - Nov 2008 - Oct 2009

    Frequency Cumulative %

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    17/39

    DISCUSSION OUTLINE

    1. POWER SUPPLY AND DEMAND:

    WHY ARE WE HAVING BROWNOUTS?

    2. POWER RATES IN THE PHILIPPINES:

    ARE THE PRICES REFLECTIVE OF TRUE COST?

    3. TAKE-AWAYS AND NEXT STEPS:

    WHAT CAN WE DO TODAY TO PREPARE FOR TOMORROW?

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    18/39

    POWER IS SOLD AND PURCHASED THROUGH (1) POWER SUPPLY

    CONTRACTS AND (2) THE WHOLESALE ELECTRICITY SPOT MARKET

    POWER RATE FORMAT

    (1) BILATERAL POWER

    SUPPLY CONTRACTS

    FIXED FORMULA

    BILATERAL SETTLEMENT

    ERC-DEFINED BENCHMARK RATE (PRE OPEN ACCESS)

    (2) WESM HOURLY PRICES

    WESM BILLING AND SETTLEMENT

    PRICES ARE DETERMINED BY SUPPLY-DEMAND SITUATION

    PER HOUR

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    19/39

    BETWEEN 2004 - 2009, NPC RATES HAVE GONE UP TO AS HIGH AS

    50%, 100% AND 133%...

    -50%

    0%

    50%

    100%

    150%

    200%

    250%

    300%

    350%

    400%

    J

    - r-04

    -

    J

    l-04

    - -

    J

    -05

    r- y-0

    5

    J

    l-

    S

    -05

    -

    J

    - r-06

    -

    J

    l-06

    -v

    -06

    J

    - r- y-0

    7

    J

    l-

    S

    -07

    -

    J

    - r - -

    J

    l-08

    -v

    -08

    J

    - r - -

    J

    l-

    S

    -09

    -

    J

    -10

    r-

    GROWTH(20

    04=0)

    COMPARATIVE PRICE MOVEMENTS - NPC RATE VS. POWER INPUTS

    NPC Effective Rate-VISAYAS NPC Effective Rate-LUZON NPC Effective Rate-MINDANAO

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    20/39

    HOWEVER PRICES OF MAJOR INPUTS TO ELECTRICITY SUCH ASOIL AND COAL HAVE INCREASED BY AS HIGH AS 320% AND 349%.

    -50%

    0%

    50%

    100%

    150%

    200%

    250%

    300%

    350%

    400%

    J

    -r

    -04

    -

    Jl-0

    4 - -

    J

    -05

    r-

    y-0

    5

    Jl-

    S

    -05

    -

    J

    -r

    -06

    -

    Jl-0

    6-

    v-0

    6

    J

    -r

    -y

    -07

    Jl-

    S

    -07

    -

    J

    -r

    - -

    Jl-0

    8-

    v-0

    8

    J

    -r

    - -

    Jl-

    S

    -09

    -

    J

    -10

    r-

    GROWTH(20

    04=0)

    COMPARATIVE PRICE MOVEMENTS - NPC RATE VS. POWER INPUTS

    NPC Effective Rate-VISAYAS NPC Effective Rate-LUZON NPC Effective Rate-MINDANAO

    Diesel ($/BBL) NEX Coal ($/Ton)

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    21/39

    LUZON VISAYAS MINDANAO NEW COAL

    PENDING ICERA APPLICATION 0.64 0.07 0.04

    PENDING GRAM APPLICATION 0.63 0.06 0.11

    AUTOMATIC COST ADJ - FPPCA 0.37 0.32 0.11

    AUTOMATIC COST ADJ - FxA 0.00 0.02 0.00

    FBHC 0.02 0.02 0.03

    BASIC ENERGY CHARGE 4.36 3.73 2.82 5.54

    0.00

    1.00

    2.00

    3.00

    4.00

    5.00

    6.00

    7.00

    P/kWh

    P6.01/

    kWh

    P4.21/

    kWhP3.11/

    kWh

    THE BENCHMARK NPC RATES MUST REFLECT THEIR TRUE COSTS.

    NPC TODAY STILL SELLING BELOW ITS COST.

    P5.40/kWh

    ERCS DIRECTION TO ADOPT AN AUTOMATIC COST ADJUSTMENT MECHANISM IS THE

    MORE APPROPRIATE METHODOLOGY FOR POWER RATES REFLECT TRUE COST

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    22/39

    WESM MUST HAVE CORRECT PRICE SIGNALS THAT

    INVESTORS CAN TRUST

    -6.00

    -4.00

    -2.00

    0.00

    2.00

    4.00

    6.00

    8.00

    10.0012.00

    14.00

    16.00

    18.00

    Jan

    -08

    Fe

    b-0

    8

    Mar-

    08

    Apr-

    08

    May

    -08

    Jun

    -08

    Jul-08

    Aug

    -08

    Sep

    -08

    Oct-

    08

    Nov

    -08

    Dec

    -08

    Jan

    -09

    Fe

    b-0

    9

    Mar-

    09

    Apr-

    09

    May

    -09

    Jun

    -09

    Jul-09

    Aug

    -09

    Sep

    -09

    Oct-

    09

    Nov

    -09

    Dec

    -09

    Jan

    -10

    Fe

    b-1

    0

    P/kWhWESM Weekly Average PricesJan. 1, 2008 Feb. 24, 2010

    Sual

    Outage

    Summer

    Months

    LowerDemand due

    to Typhoons

    San Jose

    Transformer

    Outage

    ERC orders

    use of NPC

    TOU

    Cold Season

    and Extended

    Holidays

    Warmer

    TemperatureIncrease in Intervals

    with Must-Run Unit

    Dispatch (80% More

    Compared to 2008)

    Malampaya and Baseload

    Plant Outages (Grid under

    Critical Capacity Levels)

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    23/39

    ACROSS-THE-BOARD SUBSIDIES ON ELECTRICITY MISALLOCATE

    RESOURCES AWAY FROM THE POOR AND TOWARDS THE RICH

    Class A

    56% of

    total kWh

    Class B

    36% oftotal kWh

    % SHARE OF NATIONWIDE

    ELECTRICITY CONSUMPTION PERINCOME CLASS

    Class C,D,E,F

    8% of total kWh

    Source: Family Income and Expenditures Survey (FIES), National Statistics Office 2006

    Class A

    2.3M Filipinos

    Class B

    10.4M Filipinos:

    Class C,D,E,F

    73.8M Filipinos

    NO. OF FILIPINOS PER

    INCOME CLASS

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    24/39

    As A Percentage Of Their Budgets, Lower Income Families

    Spend Much Less On Electricity Than Higher Income

    Households

    Source: Family Income and Expenditures Survey (FIES), National Statistics Office 2006

    10,490,4612,213,568

    Class B

    Food, 45.9%Clothing, 5.1%

    Furnitures, 5%

    Educational Fees,

    12.4%

    Water, 1.1%

    Taxes, 1.0%

    Household

    operations, 4.4%

    Personal Care, 5%

    Fuel, 4%

    Electricity,

    4.3%

    Medical Care, 2.5%

    Recreational, 3.3%

    Transport and

    Comm., 7.3%

    Class A

    Transport and

    Comm., 10.4%

    Recreational, 6.3%

    Medical Care, 3.7%

    Electricity,

    4.9%

    Fuel, 4%

    Personal Care, 5%

    Household

    operations, 5.0%

    Taxes, 2.7%

    Water, 1.1%

    Educational Fees,

    15.2%

    Furnitures, 5%

    Clothing, 5.8%

    Food, 31.6%

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    25/39

    As A Percentage Of Their Budgets, Lower Income Families

    Spend Much Less On Electricity Than Higher Income

    Households

    Source: Family Income and Expenditures Survey (FIES), National Statistics Office 200613,845,948 14,320,288

    Class D

    Transport and

    Comm., 3.0%

    Recreational, 0.7%Medical Care, 1.6%

    Electricity,

    1.4%

    Fuel, 4%

    Personal Care, 5%

    Householdoperations, 5.3%

    Taxes, 0.1%

    Water, 0.4%

    Educational Fees,

    10.0%

    Furnitures, 5%

    Clothing, 2.1%Food, 61.3%

    Class C

    Food, 56.4%Clothing, 2.5%

    Furnitures, 5%

    Educational Fees,

    10.8%

    Water, 0.6%

    Taxes, 0.2%

    Householdoperations, 5.4%

    Personal Care, 5%

    Fuel, 4%

    Electricity,

    2.6%

    Medical Care, 1.8%

    Recreational, 1.7%

    Transport and

    Comm., 4.5%

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    26/39

    As A Percentage Of Their Budgets, Lower Income Families

    Spend Much Less On Electricity Than Higher Income

    Households

    Source: Family Income and Expenditures Survey (FIES), National Statistics Office 200622,357,84622,479,051

    Class F

    Transport and Comm.,

    3%

    Recreational, 0%

    Medical Care, 3%

    Electricity,

    0.5%

    Fuel, 2%

    Personal Care, 3%

    Household

    operations, 4%

    Taxes, 0%

    Water, 0%

    Educational Fees, 5%

    Clothing, 0%

    Food, 75%

    Class E

    Transport and

    Comm., 2%

    Recreational, 0%

    Medical Care, 2%

    Electricity,

    1%

    Fuel, 2%

    Personal Care, 3%

    Householdoperations, 5%

    Taxes, 0%

    Water, 0%

    Educational Fees,

    6%

    Clothing, 1%Food, 72%

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    27/39

    WHY DO WE HAVEONE OF THE HIGHEST

    POWER RATES IN ASIA

    WHEN WE SAY WEHAVE BEEN

    SUBSIDIZED BY THE

    GOVERNMENT?

    Industrial Power Rates (2006)

    6.3

    6.3

    6.0

    7.0

    14.0

    0 2 4 6 8 10 12 14 16

    Vietnam

    Malaysia

    Indonesia

    Thailand

    Philippines

    US cents/kWh

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    28/39

    Philippines ChinaMalaysiaThailand Vietnam

    RATE TO INDUSTRIAL CONSUMER (as of Dec 2006)

    COMPARATIVE GENERATION MIX OF SELECTED ASIAN COUNTRIES

    $0.14 / kWh

    $0.070 / kWh $0.058 / kWh $0.062 / kWh $0.063 / kWh

    Indigenous

    64.8%

    Imported

    35.1%

    Imported

    23.6%

    Imported

    27%

    Imported

    2.2%

    Indigenous

    76.4%

    Indigenous

    73% Indigenous

    97.7%

    Geothermal18.5% Coal26.9%

    Oil

    8.2%

    Natural Gas

    29.5%

    Hydro

    18% Natural Gas

    66.1%

    Oil

    6.4%

    Coal

    17.2%

    Hydro

    7.4%

    Hydro

    10%Coal27%

    Natural Gas

    63%

    Hydro

    14.7%

    Nuclear

    1.9%

    Natural Gas

    0.3%

    Oil

    2.5%

    Coal

    80.5%

    Source: DOE, Various energy sources (2006)

    Imported

    14.0%

    Indigenous

    86.0%

    Oil

    14.0%

    Hydro

    42.0%

    Coal

    15.0%

    Natural Gas29.0%

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    29/39

    Geothermal

    Steam

    3030

    IRONICALLY IN THE PHILIPPINES, INDIGENOUS FUELS ARE THE

    MOST HEAVILY TAXED

    0.040.21

    ~0.30-0.70

    1.79

    In P/kWh

    Legend:

    Import/Excise tax on Imported Fuels

    Royalties on Indigenous Fuels

    Note: Royalties include income tax portion.Source: In-house analysis, Actual 2007 figures

    0.22

    PD 972, PD 1174:

    30% of net proceeds

    ~ 3% of gross

    PD 1442:

    60% of net proceeds

    ~ 6%-42% of gross

    PD 87:

    60% of net proceeds

    ~ 48%-56% of gross

    RA 9337, Tarrif and Customs Code:

    Excise Tax: Coal-P10/MT, Bunker-0, LNG -

    2%, Diesel-0;

    Import Duty= Coal:3%, Oil:1%

    Indigenous

    Coal

    Imported Coal Indigenous

    Natural Gas

    Imported

    Diesel

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    30/39

    3131

    Thailand Philippines Indonesia Malaysia Vietnam

    Gross Proceeds 100.00% 100.00% 100.00% 100.00% 100.00%

    Less:

    Royalty 10.00%

    Recoverable Costs 20.00% 19.39% 19.39% 19.39% 19.39%

    Net Proceeds 80.00% 80.61% 80.61% 70.61% 80.61%

    Contractor Share 40.00% 32.24% 46.51% 35.31% 26.60%

    Government Share 40.00% 48.37% 34.10% 35.31% 54.01%

    Total Government Take

    Government Share 40.00% 48.37% 34.10% 35.31% 54.01%Royalty 0.00% 0.00% 10.00% 0.00%

    Income Tax 22.32% 14.12%

    Total Govt Take 40% 48% 56% 59% 54%

    WHILE IT APPEARS THAT THE PHILIPPINE TAX TAKE ON OIL/GAS ISAMONG THE LOWEST IN SOUTHEAST ASIA

    Source: DOE

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    31/39

    3232

    ... IN INDONESIA, THAILAND, VIETNAM AND MALAYSIA,

    DOMESTICALLY USED NATURAL GAS IS NOT TAXED AND IN SOME

    CASES EVEN SUBSIDIZED

    Cost of Natural Gas

    (In P/kWh)

    Sources: 1. US Embassy in Indonesia. Gas sold to domestic market is typically priced 1/3 less than LNG sales.

    2. Unocal Thailand Fact Sheet. Royalty paid from 1981-2003 is $1.4 Billion for 5.561 Tcf of natural gas.

    3. Price of gas sold by government owned PVN to government owned EVN is $3.22/MMBtu.

    4. Petronas. Government subsidy on domestically used natural gas ~$1.72Billion per year.

    Gas rate to TNB is RM6.4/MMBtu (~$1.78/MMBtu)

    1.76

    0.540.08 - -

    1.44

    1.03

    1.271.08

    0.66

    Philippines Indonesia (1) Thailand (2) Vietnam (3) Malaysia (4)

    P/kWh

    Level of Royalties

    Philippine Government Collects 37 Billion Pesos

    From Natural Gas Royalties Yearly

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    32/39

    ACROSS-THE-BOARD REDUCTION ON ELECTRICITY RATES WILL FAVORTHE HIGHER INCOME HOUSEHOLDS

    Class A

    56% of

    total kWh

    Class B

    36% oftotal kWh

    % SHARE OF NATIONWIDE

    ELECTRICITY CONSUMPTION PERINCOME CLASS

    Class C,D,E,F

    8% of total kWh

    Source: Family Income and Expenditures Survey (FIES), National Statistics Office 2006

    Class A

    2.3M Filipinos

    Class B

    10.4M Filipinos:

    Class C,D,E,F

    73.8M Filipinos

    NO. OF FILIPINOS PER

    INCOME CLASS

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    33/39

    HIGHEST BANG-FOR-BUCK FOR GOVERNMENT FROM ROYALTYREMOVAL WILL BE ACHIEVED BY REDUCING POWER RATES FOR

    HIGH LOAD FACTOR INDUSTRIAL USERS

    Source: Com etitive Landsca e Stud , Deloitte Consultin , 2003

    STUDY OF UP PROF. DANTE CANLAS: GOVT ROYALTIES LOST VIA TARGETED REDUCTION

    OF POWER RATES TO THESE CUSTOMERS WILL BE REGAINED IN 2 YEARS TIME VIA

    INCREASED ECONOMIC ACTIVITY AND EMPLOYMENT

    Texas Instruments Intel

    Salaries45%

    Services

    5%

    Transportation

    14%

    Taxes

    6% Telecom

    1%

    Training

    1%

    Water

    1%Construction

    2%

    Electricity

    25%

    Salaries

    37%

    Electricity41%

    Waste Water

    1%

    Construction

    17%

    Taxes2%

    Transportation

    2%

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    34/39

    IF IMPLEMENTED, GENERATION RATES TO HIGH LOAD-FACTOR

    POWER USERS (TODAY, ROUGHLY ~600MW) COULD BE AS LOW AS

    2.57 P/KWH

    3.52

    0

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    4

    4.5

    5

    NPC Ecozone Rate

    P/kWh

    4.45

    2.57

    MERALCOGENERATION CHARGE

    Generation ChargeFrom Natural Gas

    Fired Power Plants

    (2700MW)

    4.36*

    Generation Charge From NaturalGas Fired Power Plants After

    Removal of Royalties

    (2700MW)

    * May 2008

    INITIALLY, ONLY PHP5 BILLION FOREGONE ROYALTY TO GOVERNMENT

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    35/39

    DISCUSSION OUTLINE

    1. POWER SUPPLY AND DEMAND:

    WHY ARE WE HAVING BROWNOUTS?

    2. POWER RATES IN THE PHILIPPINES:

    ARE THE PRICES REFLECTIVE OF TRUE COST?

    3. TAKE-AWAYS AND NEXT STEPS:

    WHAT CAN WE DO TODAY TO PREPARE FOR TOMORROW?

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    36/39

    TAKE-AWAYS AND NEXT STEPS

    1. OUR GRIDS NEED SUFFICIENT AND APPROPRIATE GENERATIONCAPACITY RESERVES TO ENSURE THAT OUR LIGHTS STAY ON

    There is significant value in securing reserves, we actually use powerwe pay for but do not use

    Amount of reserve capacity for each grid should consider theidentified various factors (age, relative sizes, condition oftransmission system and generation mix)

    2. NEEDED CAPACITY CAN BE PROVIDED BY PRIVATE SECTORPLAYERS

    Expansion and capacity improvements by the private sector onprivatized plants provide fastest solution to immediate need

    Greenfield power projects exist and can provide long-term capacityrequirements

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    37/39

    TAKE-AWAYS AND NEXT STEPS (CONT)

    3. ERC TO FOLLOW THROUGH WITH BENCHMARK RATES WHICH

    ARE REFLECTIVE OF TRUE COST AND PRESENT MARKET

    CONDITIONS

    4. CORRECT TAXATION POLICY ON INDIGENOUS ENERGY SOURCES,SPECIFICALLY NATURAL GAS

    5. IMPROVED COORDINATION AMONG THE PLAYERS DOE, NGCP,

    PEMC, ERC, GENCOs, DUs/ECs

    6. STABILITY AND CONTINUITY OF ENERGY POLICIES

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    38/39

    ROTATING BROWNOUTS

    FAST-TRACK CONSTRUCTIONUrgency + Few Players = High Price

    HIGH ELECTRICITY PRICE

    THE

    VICIOUS

    CYCLE OFPOWER

    CRISIS

    CONSUMER OUTRAGE

    POLITICAL SUPPRESSION OF

    PRICES/UNSTABLE

    REGULATORY ENVIRONMENT

    NOT ENOUGH POWER

    PLANTS BUILT

    EVERYBODY SHOULD PLAY THEIR ROLE TOBREAK THE COUNTRY OUT OF THIS CYCLE

  • 8/9/2019 04 PES Power Outlook 20100629 Santos

    39/39

    END OF PRESENTATION