04 - PERT

download 04 - PERT

of 17

Transcript of 04 - PERT

  • 7/21/2019 04 - PERT

    1/17

    1

    P R T

    I.K. Gunarta

    Department of Industrial EngineeringITS

  • 7/21/2019 04 - PERT

    2/17

    4

    The technique is based on theassumption that an activitys duration

    follows a probability distributioninstead of being a single value.

    The probabilistic information about the

    activities is translated into probabilisticinformation about the project.

    Project Evaluation and Review Technique (PERT)

  • 7/21/2019 04 - PERT

    3/17

    5

    PERT

    Three time estimates are required to

    compute the parameters of an activitys

    duration distribution:

    pessimistic time (tp ) - the time the activity wouldtake if things did not go well

    most likely time (tm ) - the consensus best estimateof the activitys duration

    optimistic time (to ) - the time the activity wouldtake if things did go well

    . . . more

  • 7/21/2019 04 - PERT

    4/17

    6

    From these three time estimates aboutan activity, two probability distribution

    parameters are calculated: the mean(te ) and the variance (Vt ).

    te = ( to + 4tm + tp ) / 6

    Vt = [ ( tp - to ) / 6 ]2

    PERT

  • 7/21/2019 04 - PERT

    5/17

    7

    Steps in PERT Analysis

    Draw the network.

    Analyze the paths through the network

    and find the critical path. The length of the critical path is the

    mean of the project duration

    probability distribution which isassumed to be normal.

    . . . more

  • 7/21/2019 04 - PERT

    6/17

    8

    Steps in PERT Analysis

    The standard deviation of the projectduration probability distribution is

    computed by adding the variances ofthe critical activities (all of the activitiesthat make up the critical path) andtaking the square root of that sum

    Probability computations can now bemade using the normal distributiontable.

  • 7/21/2019 04 - PERT

    7/179

    Contoh

    Aktivitas A M B Te [(b a)/6]2

    A 17 29 47 30 25

    B 6 12 24 13 9C 16 19 28 20 4

    D 13 16 19 16 1

    E 2 5 14 6 4

    F 2 5 8 5 1

    Berapa probabilitas proyek selesai dalam waktu kurang dari 67 hari?

  • 7/21/2019 04 - PERT

    8/1710

    Network

    0 A

    B

    C

    D

    E

    F

    30

    30

    30

    30

    13

    43

    50

    20

    43

    16

    59

    50

    6

    56

    59

    5

    64

    6459

    59

    59

    43

    53

    4330

    5333

    300

  • 7/21/2019 04 - PERT

    9/1711

    Possible Project Duration

    Ts = 67Te = 64

  • 7/21/2019 04 - PERT

    10/1712

    Solusi

    V Path = VA + VB + VD + VF

    V Path = 25 + 9 + 1 + 1

    path = 6

    Z = (67 64)/

    = + 0.5

    P = 0.69

  • 7/21/2019 04 - PERT

    11/1713

    Immed. Optimistic Most Likely Pessimistic

    Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)

    A -- 4 6 8

    B -- 1 4.5 5C A 3 3 3D A 4 5 6E A 0.5 1 1.5F B,C 3 4 5G B,C 1 1.5 5

    H E,F 5 6 7I E,F 2 5 8J D,H 2.5 2.75 4.5K G,I 3 5 7

    PERT Example

  • 7/21/2019 04 - PERT

    12/17

    14

    PERT Example

    ACTIVITY PREDECESSOR OPTIMISTIC

    TIME

    MOST

    LIKELY

    TIME

    PESSIMISTIC

    TIME

    A - 4 6 8

    B - 1 4,5 5

    C A 3 3 3

    D A 4 5 6

    E A 0,5 1 1,5

    F B, C 3 4 5

    G B, C 1 1,5 5

    H E, F 5 6 7

    I E, F 2 5 8

    J D, H 2,5 2,75 4,5

    K G, I 3 5 7

    Probability the project will be completed within 24 days?

  • 7/21/2019 04 - PERT

    13/17

    15

    PERT Network

    A

    D

    C

    B

    F

    E

    G

    I

    H

    K

    J

    PERT Example

  • 7/21/2019 04 - PERT

    14/17

    16

    Activity Expected Time and Variance

    Activity Expected Time Variance

    A 6 4/9

    B 4 4/9C 3 0D 5 1/9E 1 1/36

    F 4 1/9G 2 4/9H 6 1/9I 5 1J 3 1/9K 5 4/9

    PERT Example

  • 7/21/2019 04 - PERT

    15/17

    17

    Earliest/Latest Times

    Activity ES EF LS LF Slack A 0 6 0 6 0 *critical

    B 0 4 5 9 5

    C 6 9 6 9 0 *D 6 11 15 20 9E 6 7 12 13 6F 9 13 9 13 0 *G 9 11 16 18 7

    H 13 19 14 20 1I 13 18 13 18 0 *J 19 22 20 23 1K 18 23 18 23 0 *

    PERT Example

  • 7/21/2019 04 - PERT

    16/17

    18

    Probability the project will be completedwithin 24 hours

    Vpath = VA + VC + VF + VI + VK= 4/9 + 0 + 1/9 + 1 + 4/9

    = 2

    path = 1.414

    z = (24 - 23)/ = (24-23)/1.414 = .71

    PERT Example

  • 7/21/2019 04 - PERT

    17/17

    19

    Probability the project will be completedwithin 24 hours

    From the Standard Normal Distributiontable:

    P(z < .71) = .5 + .2612 = .7612

    23 24

    .5000

    .2612

    PERT Example