04 30 011 - Defense Technical Information Centerdtic.mil/dtic/tr/fulltext/u2/a221063.pdf · LMI...

97
OCOP 0 NESTIMATING USACE CIVIL WORKS NPROJECT COSTS Report AR801 R2 MAI January 1989 William B. Moore Eric M. Small Prepared pursuant to Department of Defense Contract %tDA9O3-85-C-0139 The views expressed here are those of the Logistics Management Institute at the time of issue but not necessarily those of the Department of Defense Permission to quo te or reproduce any part must - except tor Government purposes - be obtained tr,,i the Logistics Management Institute. LOGISTICS \IANAGEMENT INSTITUTE 6400 Goldsboro Road Bethesda, Maryland 20817-5886 .0 04 30 011

Transcript of 04 30 011 - Defense Technical Information Centerdtic.mil/dtic/tr/fulltext/u2/a221063.pdf · LMI...

OCOP

0

NESTIMATING USACE CIVIL WORKSNPROJECT COSTS

Report AR801 R2

MAI

January 1989

William B. MooreEric M. Small

Prepared pursuant to Department of Defense Contract %tDA9O3-85-C-0139The views expressed here are those of the Logistics Management Institute atthe time of issue but not necessarily those of the Department of DefensePermission to quo te or reproduce any part must - except tor Governmentpurposes - be obtained tr,,i the Logistics Management Institute.

LOGISTICS \IANAGEMENT INSTITUTE6400 Goldsboro Road

Bethesda, Maryland 20817-5886

.0 04 30 011

UNCLASSIFIED

SECLRITY CLASSIFICATION OF THIS PAGE

REPORT DOCUMENTATION PAGE

1 a. REPORT SECURITY CLASSIFICATION I b RESTRICTIVE MARKINGSUnclassified

2a. SECURITY CLASSIFICATION AUTHORITY 3. DISTRIBUTION /AVAILABILITY OF REPORT"A" Approved for public release; distribution unlimited.

2b DECLASSIFICATION t DOWNGRADING SCHEDULE

4 PERFORMING ORGANIZATION REPORT NUMBER(S) S. MONITORING ORGANIZATION REPORT NUMBER(S)LMI-AR801 R2

6a NAME OF PERFORMING ORGANIZATION 6b OFFICE SYMBOL 7a NAME OF MONITORING ORGANIZATION

Logistics Management Institute (If applicable)

6c. ADDRESS (City, State, and ZIP Code) 7b ADDRESS (City, State and ZlP Code)

6400 Goldsboro RoadBethesda. Maryland 20817-5886

8a. NAME OF FUNDING/SPONSORING 8b.OFFICE SYMBOL 9. PROCUREMENT INSTRUMENT IDENTIFICATION NUMBERORGANIZATION (if applicable) MDA903-85-C-0139U.S. Army Corps of Engineers USACE

8c. ADDRESS (City, State, and ZIP Code) 10. SOURCE OF FUNDING NUMBERSPROGRAM PROJECT TASK WORK UNITELEMENT NO NO NO ACCESSION NO

11 TITLE (Include Security Classification)

Estimating USACE Civil Works Project Costs

12 PERSONAL AUTHOR(S)William B. Moore. Eric M. Small

13a TYPE OF REPORT 13b TIME COVERED 14 DATE OF REPORT (Year, Month, Day) 15 PAGE COUNTFinal FROM _ TO_ 'January 1989 88

16 SUPPLEMENTARY NOTATION

17 COSATi CODES 18 SUBJECT TERMS (Continue on reverse if necessary and identify by block number)

FIELD GROUP SUB-GROUP Design, engineering, construction management services. military construction I ILCON). costestimating, cost control.

19 ABSTRACT (Continue on reverse if necessary and identify by block number)

The U.S. Army Corps of Engineers (USACEI provided $7 billion worth of design, engineering, design and engineering management. andconstruction management services for the military construction (MILCON) and tue civil works programs in FY99. Since (ost control is a major part it

USACE's management responsibilities, their customers expect strict control of authorized funds and adherence to established budgets. This expectationhas been heightened by the decreased MILCON budgets of recent years and by legislative initiatives such as the Water Resource Development Act of1986.

In this report, we present the results of our statistical analysis ,'a thousand civil works projects and propose equations for estimating engineeringand construction management costs for various types of projects.

20 DISTRIBUTION / AVAILABILITY OF ABSTRACT 21 ABSTRACT SECURITY CLASSIFICATIONrnUNCLASSIFIEDiUNLIMITED []SAME AS RPT E DTIC USERS

22a NAME OF RESPONSIBLE INDIVIDUAL 22b TELEPHONE (Include Area Code) 22c OFFICE SYMBOL

DO FORM 1473, 84 MAR 83APReditionmaybo . ,.; xh .. SECURITY CLASSiFICA'ION OF -,,S a,

All other editions are obsolete (NDI.AS.IF' El)

LMI

Executive Summary

ESTIMATING USACE CIVIL WORKS PROJECT COSTS

The United States Army Corps of Engineers (USACE) provides engineering

and construction management services for a $1 billion annual civil works program.

In 1974, USACE analyzed the historic cost of providing these services and devcloped

curves that could be used to estimate the engineering and construction management

costs for certain categories of civil works projects. These curves are used by USACEmanagers to monitor costs and to assess t.-,e reasonableness of cost estimates.

Our analysis showed that the nature of civil works projects have changed since

the 1974 study. These cost curves used by USACE are dated. Changes in procedures

and construction techniques mean that the old equations may no longer be valid. We

found that a greater precision in cost estimating could be attained by increasing the

categories of projects examined from five to seventeen. We developed cost estimating

equations for these seventeen categories of projects and have incorporated them into

a civil works cost estimating model.

We recommend that the Director of Engineering and Construction use this

model to estimate engineering and construction management costs once a project has

been developed and to monitor these costs during project execution. This model

should be made available to USACE divisions and districts and should become part

of an overall USACE cost management strategy. We believe the model can be an

effective tool for enhancing USACE cost performance.

-2rJR8OI2,.N "

i - i ]i ii A R801112,'.,. .N 19

, _- I

CONTENTS

Page

Executive Sum m ary ............................................ iii

List of T ables .................................................. vii

Chapter 1. Introduction ........................................ i-1

Chapter 2. Results of Analysis and Recommendations ............. 2-1

Description of Regression Analysis ........................ 2-1Data and Sample Size Issues .............................. 2-1Summ ary of Results ..................................... 2-2General Interpretation of Results ......................... 2-2Recommendations Regarding Use of Results ............... 2-6Civil Works Cost Estimating Model ....................... 2-6

Appendix A. Civil Works Data Call ............................. A-1 - A-16

Appendix B. Descriptive Statistics for Collected Data ............. B-1 - B-13

Appendix C. Civil Works Cost Curves ........................... C-1 - C-54

TABLES

Page

1-1. USACE Civil Works Project Categories .................... 1-2

1-2. D istrict Response ........................................ 1-4

1-3. Distribution of Projects by Category ....................... 1-5

2-1. Summary of USACE Cost Regressions forSpecific Project Categories ............................. 2-3

2-2. Summary of USACE Cost Regressions for AllCivil W orks Projects ................................... 2-5

CHAPTER 1

INTRODUCTION

The United States Army Corps of Engineers (USACE) provides engineering

and construction management services for a $1 billion annual civil works program.

In 1974, USACE analyzed the historic cost of providing these services and developed

curves that could be used to estimate the engineering and construction managemeat

costs for five categories of civil works projects. This analysis produced a series of

curves that related USACE direct engineering and design (E&D), supervision and

inspection (S&I),l technical indirect, and general administrative overhead (G&A)

costs to the constructioi. cost of a project. The curves were based on civil works

projects that had been completed in the 10-year period before 1974.

These cost curves are used by USACE civil works project managers to monitor

costs and to assess the reasonableness of cost estimates for USACE civil works

projects. Over the years, the cost curves have proved to be effective management

tools. However, today, these cost curves are dated. Changes in procedures and new

construction techniques have raised questions about their validity. Additionally,

the original curves were limited to channel, flood protection, floodwalls and

drainage, dredging, and lock and dam projects and did not distinguish between new

construction, maintenance, or rehabilitation work. New curves are needed that are

based on data from more recent projects and from an expanded list of project

categories.

Our initial analysis indicated that civil works projects could be divided into

17 distinct categories (see Table 1-1). The categories were established after

considering the type of work - new construction, maintenance, or rehabilitation -

coupled with the functional purpose of the project. Table A-2 in Appendix A maps

civil works fund types into the 17 project categories.

ISupervision and inspection costs are the direct costs associated with the constructionmanagement of a project. They are a subset of the supervision and administration costs which alsoinclude indirect costs.

1 1

TABLE 1-1

USACE CIVIL WORKS PROJECT CATEGORIES

Channels and harbors

Locks and dams

Beach erosion

Flood control

Flood control reservoirs

Multipurpose power

Rehabilitation: channels and harbors

Rehabilitation: locks and dams

O&M: channels and harbors

O&M: locks and dams

O&M: flood control

O&M: flood control reservoirs

O&M: multipurpose power

O&M: channel and harbor improvements

Flood control: rehabilitation

Flood control: construction

Recreation

We believe this categorization scheme provides for a homogeneous grouping of

the diverse civil works projects. These categories were the basis for the data

collection and analysis efforts.

Cost data for civil works projects can be obtained from four different USACEsources. Most cost information is maintained in the Corps of Engineers Manage-

ment Information System (COEMIS), but costs are also maintained in theAutomated Projects Reporting System (AMPRS), the Project Reporting Information

System for Management (PRISM), and manual cost records. We found that no single

source could provide all of the information for all districts and concluded that a

district data call was required.

A data call was structured and sent to all USACE districts with a civil worksmission. (See Appendix A for data definitions and a copy of the data call.) The data

call requested information on completed civil works projects. Information was eitherreported on a project basis or, in those cases where a project could be broken down

12

into a number of separate and distinct contracts, on a contract basis. When a

contract was used as the basis for reporting, districts were instructed to ensure that

planning, general design memorandum/final design memorandum (GDMIFDM), andother project-wide costs were pro-rated to contracts within the project. The districtresponses used combinations of the four potential data sources. Cost data for some

older projects were only available in manual records, while for others, automated

systems were utilized exclusively.

Although the data definitions are based upon feature/sub-feature and account-ing element level of detail, judgment is still required to categorize certain costs. This

is particularly true for allocating planning and engineering costs. We defined

engineering costs to include GDM and FDM costs as well as any other design or

engineering costs. From our statistical examination of the raw data, we believe theapportionment of planning and design costs was correct in most cases and was not a

major source of error in the analysis.

A total of 37 districts reported usable information on 974 civil works projects.

Table 1-2 shows the response by district and Table 1-3 shows the number of projects

by category.

The project data were edited for internal consistency - making certain that

the sum of the pieces equaled the totals - and for reasonableness when compared to

data from other districts. Data outliers identified by editing were confirmed with thereporting districts and corrected when necessary. The resultant data set was then

analyzed statistically to produce the new cost curves.

1 3

TABLE 1-2

DISTRICT RESPONSE

Number ofDistrict projectsPercent of total

Memphis 17 1 7%

New Orleans 9 0.9

Vicksburg 8 0 8

Kansas City 10 1 0

Omaha 67 6 9

New England 37 38

Baltimore 10 1 0New York 11 1 1

Norfolk 2 0 2

Philadelphia 81 8.3

Buffalo 127 13.0

Chicago 41 4.2

Detroit 68 7.0Rock Island 46 4,7

St. Paul 33 3 4

Alaska 14 1 4

Portland 17 1 7

Seattle 41 42Walla Walla 11 1.1

Huntington 12 1 2

Louisville 16 1 6

Nashville 8 08

Pittsburgh 9 0 9

Pacific Ocean 49 t J

Charleston 6 0 6

Jacksonville 14 1 4

Mobile 83 8.5

Savannah 6 0 6

Wilmington 18 1,8

Los Angeles 18 1 8

Sacramento 6 0 6

San Francisco 18 1 8Albuquerque 4 0 4

Fort Worth 11 1 1

Galveston 14 1 4

Little Rock 8 0 8Tulsa 24 2.5

Total n7/1 1000%

1 4

TABLE 1-3

DISTRIBUTION OF PROJECTS BY CATEGORY

Category Number of Percent of totalprojects

Channel/harbor 116 11 9%

Locks/dams 23 2.4

Beach erosion 44 4 5

Flood control 271 27 8

F/C: reservoir 54 5.5

Multipurpose power 22 2.3

Rehab: channel/harbor 9 0 9

Rehab: locks/dams 14 1.4

O&M: channel/harbor 268 27 5

O&M: locks/dams 14 1 4

O&M: flood control 8 0.8

O&M: F/C reservoir 2 0.2

O&M: M/P power 51 5.2

O&M: C/H improvement 4 0.4

F/C: rehabilitation 26 2 7

F/C: construction 22 2.3

Recreation 26 2.7

Total 974 100 0%

1 5

CHAPTER 2

RESULTS OF ANALYSIS AND RECOMMENDATIONS

DESCRIPTION OF REGRESSION ANALYSIS

Separate regression equations (with USACE project costs as a function of the

construction contract amount) were estimated for each project category for six

different USACE costs: total engineering, direct engineering and design (E&D),

technical indirect, supervision and administration (S&A), supervision and

inspection (S&), and general and admnistrative (G&A). Actual USACE costs were

used as the dependent variable instead of the cost ratios, because estimating costs,not ratios, was the purpose of this analysis. The equations were estimated with a

zero intercept (through the origin). Equations with an intercept (a fixed component)were examined initially but found to be statistically insignificant.

Since previous USACE cost curves had reflected economies of scale (lower cost

ratios for larger projects), several nonlinear models were also tested. A model which

used the square of the independent variable - a common form for reflecting

economies of scale - was rejected because the resulting cost estimates decrease asproject size increases for large projects within the relevant range. A model which

used dummy variables for large projects was rejected because the resulting cost

estimates were unstable near the project size threshold. Finally, models which used

the log or square root of the independent variable had the desirable theoretical

properties, but the square root model had consistently greater explanatory power

(adjusted R-Square) than the log models and was therefore chosen as the nonlinear

alternative.

DATA AND SAMPLE SIZE ISSUES

In order to produce internally consistent and meaningful equations. only thoseprojects with valid data for all the relevant costs were included in the regression

analysis. The resulting sample sizes were therefore smaller than those shown in

Table 1-3. Furthermore, several of the project categories in the data call produced

sample sizes too small for reliable statistical results. We combined those categorieswith small sample sizes with similar project categories to create sample sizes large

21

enough to provide reliable statistics. Consequently, the original 17 categories were

consolidated into 8 for the regression analysis.

Because of the limited data available on planning, supervision and review

(S&R), and area office overhead costs, the regression equations for these three

variables had to be estimated based on the entire data call sample. In addition,

because of the nature of S&R costs, it was more appropriate to use the architect-

engineer (AE) contract amount as the independent variable in the S&R equationrather than the construction contract amount.

SUMMARY OF RESULTS

For each of the 48 category-level regression equations, Table 2-1 displays the

estimated coefficient, the t statistic for that coefficient, the adjusted R-Square for the

equation, the model selected (the alternative - linear or nonlinear - which

produced a better fit for the six costs), and the number of projects on which the

estimates were based. Economies of scale were found (i.e., the square root model

outperformed the linear model) for four of the eight categories. The estimated

coefficients were all significant at the 99.9 percent level, and the adjusted R-Square

exceeded 0.70 for most of the equations.

Table 2-2 summarizes the results for the other three models. The adjusted

R-Squares for the planning and area office overhead equations were fairly low.

reflecting the necessary combining of different project categories and the indirect

nature of those costs, but the estimated coefficients were both highly significant and

economies of scale were found to prevail. A much stronger (and more linear)

relationship was found between S&R costs and the AE contract amount, even though

the equation was based on many different types of projects.

GENERAL INTERPRETATION OF RESULTS

The analysis confirms that USACE costs vary widely, even among similar

projects, but reasonable cost estimates can still be made based on a project's type and

size. However, the nature of the relationship between project size and USACE cost

depends upon the type of project. For four of the eight categories - Channel Harbor,

Locks/Dams, Flood Control, and Flood Control Reservoir - there are economies of

scale. For the remaining four categories, there are no significant economies of scale(i.e., the cost ratios do not depend upon project size).

22

(D~~~ -T w 0 1 n1 D3nW c 1 TI

0 0 e 0 ? -0 -

4 0 0 0 )

ciz z

CC))

- z2o C 0 C Cn CD-

a

In -o o) 0M o n u 0 n 0N 0

'3 Z C C D C0) 0

z .3I-a

4 - 0n 0 -D -l 0N z

ix o~~ - 0 I= Co - C

CLC

w -v

0 00 In 0 sm co - .. .r ,~116 -o M- Ln Ln cc" co 3)a

%A W CD c V

4 U) 5

~- 1.190 3)0

z*

S '- ~ ~ c- o -1 co -- 3'

CL

______ 0 _ _ _ _ _ _ _ _ _ _ _ _ __ __ _ z

2)~~~ 3 -a "-----------

30 0 14 ' Z - 00 -I I % 7

a O 0 CD 0D

o

-ad

00 0

Z CD

-j0

LA.~

0. ~ *

@8 -m I o w m o . 0 l

0 00

0 (10_ _ _

w

CC

D 0D

(x .)

wnc

I2 4

TABLE 2-2

SUMMARY OF USACE COST REGRESSIONS FOR ALL CIVIL WORKS PROJECTS

Planning costs Independent variable Construction amount

Model type Nonlinear

Sample size 246

Coefficient 46

T Statistic 10.9

Adjusted R-Square 0.32

Area office overhead costs Independent variable Construction amount

Model type Nonlinear

Sample size 172

Coefficient 22

T Statistic 7.4

Adjusted R-Square 0.24

Supervision & review costs Independent variable AE contract amount

Model type Linear

Sample size 206

Coefficient 166

T Statistic 18.0

Adjusted R-Square 0.61

The ability to accurately estimate USACE costs differs by type of project and

type of cost. For example, the Multipurpose Power equations had the highest

adjusted R-Squares and t statistics of the eight project categories, while the

Operations and Maintenance (O&M) Channel/Harbor equations had the lowest.

Similarly, the S&A equations had the highest adjusted R-Squares and t statistics of

the six different costs that were estimated at the category level, while the

technical indirect equations had the lowest. Finally, the regression coefficients show

that engineering services (as measured by total design or direct E&D costs) areconsistently more expensive than construction management services (as measured

by S&A costs).

25

RECOMMENDATIONS REGARDING USE OF RESULTS

These regression equations update the cost curves developed by USACE in the

1970s, reflecting changes in economic conditions, management policies, and

accounting practices. The ,-ew equations also cover a broader spectrum of USACE

costs (although equations have not yet been developed for planning or operations

costs), while incorporating a more detailed and more comprehensive classification of

USACE projects.

For project categories with nonlinear equations (economies of scale), the

estimated cost equals the regression coefficient times the square root of the

construction contract amount (in millions). For project categories with linear

equations (no economies of scale), the estimated cost equals the regression coefficient

times the construction contract amount (in millions).

The results can be used to help project managers estimate what the actual costs

are likely to be for specific projects, to help USACE headquarters staff estimate

resource requirements for a given customer, division, program, etc., and to help

district and division staff identify potential problem areas by comparing actual

project costs to the average cost of similar projects. However, it is important to note

that the equations are in "constant dollars," so the cost estimates are in the same

year's dollars as the construction contract amount (or the AE contract amount, in the

case of S&R costs). The estimates must therefore be adjusted - using DoD deflators

or other inflation indexes - to obtain results expressed in a different year's dollars.

Finally, attention should be paid to ongoing data collection through existing or

planned automated systems which can be used to periodically update the results

produced by this analysis or to develop cost curves or equations for USACE planning

and operations costs. The civil works data call was conducted because the project-

level data available from current USACE automated information systems were

inadequate. If these shortcomings are resolved, future analysis can be based entirely

on data from automated systems with much less effort.

CIVIL WORKS COST ESTIMATING MODEL

A microcomputer-based cost estimating model was developed to facilitate the

use of the information from the statistical analysis. This model utilizes the

equations described in the previous sections to estimate USACE costs associated

2 ;

with civil works projects and then to compare these costs with the distribution of

similar USACE projects obtained from the data call. It is an automated way to use

the results of this analysis to monitor and manage USACE civil works project costs.

A description of that model and instructions on its use are contained in the Civil

Works Cost Model Users Guide.

2 7

APPENDIX A

CIVIL WORKS DATA CALL

TABLES

Page

A- 1. Definition of Data Elements ............................. A- 13

A- 2. Project Category Mapping for USACE Civil WorksD ata C all ............................................. A - 15

B- 1. Distribution of USACE Cost Ratios for Planning ............ B- 4

B- 2. Distribution of USACE Cost Ratios for Total Engineering ... B- 5

B- 3. Distribution of USACE Cost Ratios forArchitect/Engineer (AE) Contract Costs ................. B- 6

B- 4. Distribution of USACE Cost Ratios for Supervisionand Review Costs ...................................... B- 7

B- 5. Distribution of USACE Cost Ratios for DirectEngineering and Design Costs .......................... B- 8

B- 6. Distribution of USACE Cost Ratios for TechnicalIndirect Costs ......................................... B- 9

B- 7. Distribution of USACE Cost Ratios for Supervisionand Administration Costs .............................. B- 10

B- 8. Distribution of USACE Cost Ratios for Supervisionand Inspection Costs ................................... B- 11

B- 9. Distribution of USACE Cost Ratios for Generaland Administrative Costs .............................. B- 12

B-10. Distribution of USACE Cost Ratios for AreaOffice Overhead Costs ................................. B- 13

A2

FIGURES

Page

A- 1. Data Call Form s ........................................ A- 10

C- 1. Total Engineering Costs for Channel/Harbor Projects ....... C- 4

C- 2. Direct E&D Costs for Channel/Harbor Projects ............. C- 5

C- 3. Technical Indirect Costs for Channel/Harbor Projects ....... C- 6

C- 4. Supervision & Administrative Costs forChannel/Harbor Projects ............................... C- 7

C- 5. Supervisory & Inspection Costs forChannel/Harbor Projects ............................... C- 8

C- 6. General & Administrative Costs for Channel/HarborProjects .............................................. C - 9

C- 7. Total Engineering Costs for O&M: Channel/HarborProjects, Rehab: Channel/Harbor Projects, andO&M: Channel/Harbor Improvement Projects ........... C- 10

C- 8. Direct E&D Costs for O&M: Channel/Harbor Projects,Rehab: Channel/Harbor Projects,O&M: Channnel/Harbor Improvement Projects .......... C- 11

C- 9. Technical Indirect Costs for O&M: Channel/HarborProjects, Rehab: Channel/Harbor Projects, andO&M: Channel/Harbor Improvement Projects ........... C- 12

C-10. Supervisory & Administration Costs forO&M: Channel/Harbor Projects,Rehab: Channel/Harbor Projects, andO&M: Channel/Harbor Improvement Projects ........... C- 13

C-i. Supervisory & Inspection Costs for O&M: Channel/HarborProjects, Rehab: Channel/Harbor Projects, andO&M: Channel/Harbor Improvement Projects ........... C- 14

FIGURES (Continued)

Page

C-12. General & Administrative Costs for O&M: Channel/HarborProjects, Rehab: Channel/Harbor Projects, andO&M: Channel/Harbor Improvement Projects ........... C- 15

C-13. Total Engineering Costs for Locks/Dams Projects,O&M: Locks/Dams Projects, andRehab: Locks/Dams Projects ........................... C- 16

C-14. Direct E&D Costs for Locks/Dams Projects,O&M: Locks/Dams Projects, andRehab: Locks/Dams Projects .......................... C- 17

C-15. Technical Indirect Costs for Locks/Dams Projects,O&M: Locks/Dams Projects, andRehab: Locks/Dams Projects ......................... C- 18

C-16. Supervisory & Administrative Costs for Locks/DamsProjects, O&M: Locks/Dams Projects, andRehab: Locks/Dams Projects ........................... C- 19

C-17. Supervisory & Inspection Costs for Locks/DamsProjects, O&M: Locks/Dams Projects, andRehab: Locks/Dams Projects ........................... C- 20

C-18. General & Administrative Costs for Locks/DamsProjects, O&M: Locks/Dams Projects, andRehab: Locks/Dams Projects ........................... C- 21

C-19. Total Engineering Costs for Flood Control Projects .......... C- 22

C-20. Direct E&D Costs for Flood Control Projects ................ C- 23

C-21. Technical Indirect Costs for Flood Control Projects .......... C- 24

C-22. Supervisory & Administrative Costs for FloodControl Projects ....................................... C- 25

C-23. Supervisory & Inspcction Costs for Flood ControlP rojects .............................................. C - 26

A 4

FIGURES (Continued)

Page

C-24. General & Administrative Costs for Flood ControlProjects .............................................. C - 27

C-25. Total Engineering Costs for Flood Control ReservoirProjects and O&M: Flood Control ReservoirProjects .............................................. C - 28

C-26. Direct E&D Costs for Flood Control Reservoir Projectsand O&M: Flood Control Reservoir Projects .............. C- 29

C-27. Technical Indirect Costs for Flood Control ReservoirProjects and O&M: Flood Control Reservoir Projects ...... C- 30

C-28. Supervisory & Administrative Costs for FloodControl Reservoir Projects and O&M: Flood ControlReservoir Projects ..................................... C- 31

C-29. Supervisory & Inspection Costs for Flood ControlReservoir Projects and O&M: Flood ControlReservoir Projects ..................................... C- 32

C-30. General & Administrative Costs for Flood ControlReservoir Projects and O&M: Flood ControlReservoir Projects ..................................... C- 33

C-31. Total Engineering Costs for O&M: Flood ControlProjects, Flood Control: Rehabilitation Projects, andFlood Control: Construction Projects .................... C- 34

C-32. Direct E&D Costs for O&M: Flood Control Projects,Flood Control: Rehabilitation Projects, andFlood Control: Construction Projects .................... C- 35

C-33. Technical Indirect Costs for O&M: Flood Control Projects,Flood Control: Rehabilitation Projects, andFlood Control: Construction Projects .................... C- 36

A 5

FIGURES (Continued)

Page

C-34. Supervisory & Administrative Costs for O&M: FloodControl Projects, Flood Control: RehabilitationProjects, and Flood Control: Construction Projects C- 37

C-35. Supervisory & Inspection Costs for O&M: FloodControl Projects, Flood Control: RehabilitationProjects, and Flood Control: Construction Projects C- 38

C-36. General & Administrative Costs for O&M: FloodControl Projects, Flood Control: RehabilitationProjects, and Flood Control: Construction Projects C- 39

C-37. Total Engineering Costs for Multipurpose PowerProjects and O&M: Multurpose Power Projects ........... C- 40

C--38. Direct E&D Costs for Multipurpose Power Projectsand O&M: Multurpose Power Projects ................... C- 41

C-39. Technical Indirect Costs for Multipurpose Power Projectsand O&M: Multurpose Power Projects ................... C- 42

C-40. Supervisory & Administrative Costs for MultipurposePower Projects and O&M: Multipurpose PowerP rojects .............................................. C - 43

C-41. Supervisory & Inspection Costs for MultipurposePower Projects and O&M: Multipurpose PowerProjects ...... ......................................... C - 44

C-42. General & Administrative Costs for MultipurposePower Projects and O&M: Multipurpose PowerP rojects .............................................. C - 45

C-43. Total Engineering Costs for Beach Erosion ProjectsAnd Recreation Projects ................................ C- 46

C-44. Direct E&D Costs for Beach Erosion Projects andRecreation Projects .................................... C- 47

FIGURES (Continued)

Page

C-45. Technical Indirect Costs for Beach Erosion Projects andRecreation Projects .................................... C- 48

C-46. Supervisory & Administrative Costs for Beach ErosionProjects and Recreation Projects ........................ C- 49

C-47. Supervisory & Inspection Costs for Beach ErosionProjects and Recreation Projects ........................ C- 50

C-48. General & Administrative Costs for Beach ErosionProjects and Recreation Projects ........................ C- 51

C-49. Design Planning Costs for All Projects ..................... C- 52

C-50. Area Office Overhead Costs for All Projects ................ C- 53

C-51. Supervisory & Review Costs for All Projects ................ C- 54

\ 7

CIVIL WORKS DATA CALL

BACKGROUND

The civil works data call was initiated in April 1988 by the Director ofEngineering and Construction and the Director of Resource Management. The data

call forms and data element definitions used in this data call are shown inFigure A-i and Table A-i, respectively. The data call was necessary since no single

U.S. Army Corps of Engineers (USACE) information source could provide all theneeded data. Thus, it was necessary for USACE divisions and districts to use

combinations of available data sources - Corps of Engineers ManagementInformation System (COEMILS), Automated Projects Reporting System (AMPRS),Project Reporting Information System for Management (PRISM), and manual cost

systems - to meet the requirements of the data call.

DATA COLLECTION AND ANALYSIS

Data on nearly 1.000 civil works projects were collected from 35 districts and2 operating divisions. Those data were subjected to a series of manual and computer

edits in which blank, duplicate, or invalid projects were deleted; projects withmissing, invalid, or extreme values were identified; and the data in question werechecked and corrected where necessary. All zero entries were treated as missing

values. The resulting analysis sample contained 974 projects.

COEMIS project identification codes and civil works appropriation codes werethen used to classify the projects into 17 categories. The classification scheme (seeTable A-2) was jointly developed by LMI and USACE and provides a basis for

comparisons with military and private-sector projects.

The cost data were adjusted for inflation. Sincc data on project costs by yearwere unavailable, we assumed that total engineering, planning, architect-engineer(AE) contracting, supervision and review (S&R). engineering and design (E&D). and

design-related general and administrative (G&A) costs were incurred at the mid-point of the design phase; and that supervision and administration (S&A),

supervision and inspection (S&I), and construction-related G&A costs were incurred

\ 9

c

0

C:0

o

-1

-0 7

-3 1 ,O o l - - - - - - --- --

0

C0

~C 0

'-'0 ~~

C

Co 0

0'SC

4- 4gE

4I-

______ ________________________________________ 40

~-1~ 40

- IL

o ~.-

~ E

CC

~7~

'-Sz

2En 0- 'N ~7 5' ~Q 00 - s' ~0 "- ~

z

.\ 11

-o -,

C,

j4

c-J -~w

cc

-S Cqo Z0

aL

cm.

C 02

TABLE A-1

DEFINITION OF DATA ELEMENTS

Note: Include only contracts or portions of projects that are 100 percent physicallycompleted. A project may be split into a number of contracts and each contract can betreated as a separate project for data collection purposes.

1. EROC - Code identifying the District performing the work.

2. Project Description - The name or brief description of the project, such as that used inthe AMPRS database

3. CWIS Number - The Civil Works Identification System number.

4. COEMIS 5-Digit Project Code - The COEMIS project identification code

5. Civil 3-Digit Category, Class, and Subclass Code - The civil works appropriation code(ER 37-2-10, APP 20-1). Supply all codes if multiple codes apply to one projec-

6. Design Start Date - The General Design Memorandum (GDM) approval date.

7. Design Completion Date - The date on which design was completed.

8. Construction Start Date - The date on which construction started following notice toproceed.

9 Construction Completion Date - The date on which construction was physicallycompleted (NOT the date of financial completion).

10. Construction Contract Amount - The final dollar amount of the construction contract,including contingencies and modifications.

11. Design Costs -

a. All costs for planning to include reconnaissance and feasibility 'tudies. These arecosts included in features 501, 502, 503, and 505 (ER 37-2-10, pp 8-5a and 8-5b).

b. All design costs for GDM and Final Design Memorandum (FDM) preparation aswell as any other design costs. These are costs included in features 501, 502, 503,and 505 (ER 37-2-10, pp. 8-5a and 8-5b)

12. AE Contract Amount - The total contracted costs for contracted-out engineering anddesign effort. Feature 30.1 (ER 37-2-10, p 8-14).

13. Design Supervision and Review Costs - 'he costs for supervision and review ofcontracted-out engineering and design work. Feature 30 2 (ER 37-2-10 pp. 8-14).

14. Direct In-house Engineering and Design Costs - The costs for in-house engineering anddesign effort. Features 30.4, 30.5, and 30 6 (ER 37-2-10, pp. 8-14 and 8-1 5)

15. Technical Indirect Engineering and Design Costs - The technical indirect costs for in-house engineering and design effort. Accounting element 232 for features 30 4, 30.5,and 30 6(ER 37-2-10, pp 8-14 and 8-15).

16. Construction Supervision and Administration Costs (S&A) - The costs of supervisingand administrating construction projects (including supervision and inspection costs).Feature 31 (ER 37-2-10, pp. 8-15 and 8-16)

(Continued)

\ I13

TABLE A-1

DEFINITION OF DATA ELEMENTS (Continued)

17. Construction Supervision and Inspection Costs (S&l) - The costs of supervising andinspecting construction projects (included in S&A above). Features 31 1 through 31.32inclusive (ER 37-2-10, pp 8-15).

18. General and Administrative Costs (G&A) - The total district overhead costs of theproject (for both engineering and construction), not including Area Office overhead.All accounting element 351 costs (excluding Real Estate).

19. Area Office Overhead - The Area Office overhead costs of the project (use zero if nooverhead). All accounting element 352 costs.

20. Project Location, City - The city or town at or near the project (including 5-digit zipcode if available).

21. Project Location, State - The primary state in which the project is located.

22. Total Engineering Manhours - The total engineering manhours, including both directand indirect, spent on the project. Direct hours may be taken from COEMIS, indirectfrom other sources.

23. Total Construction Manhours - The total construction manhours, including both directand indirect, spent on the project.

at the midpoint of the construction phase. We assumed that the total construction

amount was determined in the construction start year. Once the costs were assigned

to specific years, they were converted into 1987 dollars using the 20-city annual

average Engineering News Record (ENR) Construction Cost Index.

Finally, we made no adjustments for regional cost differences for four reasons:

(1) USACE salaries are not regionally adjusted, (2) regional differences in construc-

tion labor costs are minimized by the requirements of the Davis-Bacon Act, (3) con-

struction materials and equipment are frequently not purchased locally, and (4) theanalysis of cost ratios - regional USACE costs divided by regional construction

costs - rather than absolute costs reduces the effect of any regional variations.

.\ 14

TABLE A-2

PROJECT CATEGORY MAPPING FOR USACE CIVIL WORKS DATA CALL

Project category Fund types

Channels and harbors BA - 121

BB - 100,121,21X

BE - 21X

FW - 216

Locks and dams BA - 220

BB - 22X

BF - 220

Beach erosion control BA - 140

BB -410

BC - 400

BD- 140,4XX

GM - 400

Flood control BA - 151,510,511

BB- 230,516

BD- 516,517

BE- 150,151,5XX

BG -511

BJ - 517

FW- 511,516,517

Flood control reservoirs BB - 520

BC - 520

BD - 520

BE - 152,52X

BT - 520

Multipurpose power BA - 600

BF- 100,160,6XX

BK - 600

Note: Two-letter part of fund type s from COEMIS project identification code, ,3 chgit oart of furd type is fromcivil works appropriation code, and X's refer to all numners starting with olgits shown (e g. 1XX = 100 - 199)

(Continued)

\15

TABLE A-2

PROJECT CATEGORY MAPPING FOR USACE CIVIL WORKS DATA CALL (Continued)

Project category Fund types

Rehabilitation - channels and harbors BE - 300

BH-800,813

BJ - 813

Rehabilitation - locks and dams BH - 814,818

BP-814

Operations and maintenance - channels and harbors CA - 11X,211

Operations and maintenance - locks and dams CA - 12X

CB - 120

Operations and maintenance - flood control CA - 100,300,510

CB 20X,23X-29X

Operations and maintenance - flood control reservoirs CB - 21X

BH -817

BP-817

Operations and maintenance - multipurpose power BH - 818

BP- 818

CC- 210,3XX,510

CG - 300

Operations and maintenance - channel and harbor CB - 22X

improvements CD - 220

CG - 232

Flood Control - rehabilitation BH - 516,517

DC- 3XX

Flood control - construction ER - 32X

Recreation BG - 711,713,720,770

Note: Two-letter part of fund type is from COEMIS project identification code 3-digit Dart of fund type is fromcivil works appropriation code, and X's refer to all numbers starting with digits shown ie g, Ixx = 100- 199)

APPENDIX B

DESCRIPTIVE STATISTICS FOR COLLECTED DATA

DESCRIPTIVE STATISTICS FOR COLLECTED DATA

Cost ratios derived using the project costs collected from the civil works datacall are shown in Tables B-i through B-10. The definition of each ratio is noted in

each table. For each of the 10 U.S. Army Corps of Engineers (USACE) cost ratios,

the following information is displayed by project category:

* The sample size: number of valid projects reported

* The minimum value

* The 20th percentile: the value below which 20 percent of the sample projectcost ratios fell

* The 40th percentile

* The median value: the 50th percentile

* The 60th percentile

* The 80th percentile

* The maximum value.

When the sample size is very small, several of these statistics may be the same. For

example, if there is only one project in a given category, the minimum and maximumvalues will be identical (as will the intermediate percentiles).

The regression equations described in Chapter 2 provide point estimates for a

typical project within each category. However, actual project costs can differ fromthose estimates and still be reasonable. USACE managers must use their judgementin deciding what the appropriate range should be for each cost ratio and project cate-

gory. This range will depend upon the complexity of the project, factors unique to aspecific district, and the distribution of actual costs for other projects. The descrip-

tive statistics presented in this appendix can therefore be used as a valuable adjunctto the r( gression equations; they are not a substitute for those equations.

TABLE B-1

DISTRIBUT1ON OF USACE COST RATIOS FOR PLANNING

Percentiles

ProjocO category sample

Minimum 20th 40th Median I 60th 80th Maximum

Channei'iiarbo, 53 0 000 0 006 C082 0 078 0 11) 0 216 3 390

LOcks.Dams 4 0 001 0 001 0 001 0 003 0 004 0 015 0 015

3ec ~so,7 0000 0 026 0 034 0 093 c0098 0 141 0 294

''00d Cotrol 127 0 000 10 025 0 048 0 Cb8 0 093 30203 3 838

1'0OoiDcrntroi Reservoir '9 0 000 00300 0 001 0 001 0 004 0 015 0 029

iwI1ou.roose Poe, 2 0 000 0 000 0 000 0 000 0 000 0 000 0 000

-i,' chari'n , Harbor 0 ----

Reiilo X3~0iS0-

OW& Ch~ne,'H4 bc, 4 0 001 0 001 0 001 0 006 001il 0064 0 064

00&M -0csD4n1 0

O&M HIood C.,introl 0 --- .-

O&M- ~CReservoir 0 .--- -

O&M Mulipu~rose Pow~er 0

10&M C H Imp~rovement 0

C Rehabilitation 19 0 007 0 038 0 075 0 090 C '20 0 '52 -0 233

* C Crnstruction 2 0001 0 001 0 001 0 001 "002 0002 0 002

Recre.1on 2 0 03S 0 035 035 006 095 09 09,;

Note: Ratios are planning Costs divided by the Construction Contract amount

B -4

TABLE B-2

DISTRIBUTION OF USACE COST RATIOS FOR TOTAL ENGINEERING COSTS

Percentiles

Project category Sample

Minimum 20th 40th Median 60th 80th Maximum

ChannelHarbor '12 0 001 0 043 0 070 0 093 0 ! 16 0 252 4 261

LOCKIDams 23 0 026 035 0 059 0 110 0 147 0 218 0 287

Btar(, Erosion 37 0 015 044 0 082 005 113 0 165 3 172

Flood Control 240 0 005 0 072 0 138 01 0 210 0 312 1 896

Flood Control Reservoir 53 0 09 0 053 0 083 0 095 0 124 3 168 0 919

Multipurpose Power 22 0 018 0 06S 0 104 0 113 0 '22 3 166 0 253

Rehab ChannelHarbor 7 0 006 0 050 0 075 0 076 0 082 0 193 0 222

Rehab Locc.sOams '4 0012 0 055 0 066 0 019 0 084 0 119 3 154

O&M CharneliHarlor 211 0 001 0 018 0 035 0 047 0 062 ) 112 ' 264

O&M LocKsDams 13 0 027 0 028 0 028 3 029 0 030 J 033 3 272

O&M Flood Control 4 0030 0030 0031 0036 0041 0 050 0050

O&M FIC Reservor 2 0 060 0 060 0 060 0 064 0 061 0 067 0 0b7

O&M Multiourpose Powe, 48 0 023 0 028 0035 0041 0060 0 073 0 478

O&M CH Imoroement 4 0 035 0 035 0 059 J 104 0 149 ' 53? 0 537

F C Renao,l,taton 26 0 015 0088 0 228 3 268 0 383 0 610 2 515

F C Constrcton 21 0C61 C 095 0 123 2 40 0 so 1 168 0673

RecretvOn 22 0 029 0 040 1) 040 0 040 C47 0 109 1 356

Note: Ratios are total engineering costs divided by the construction contract amount

B-5

TABLE B-3

DISTRIBUTION OF USACE COST RATIOS FOR ARCHITECT/ENGINEER (AE) CONTRACT COSTS

Percentiles

Project category Sample

Minimum 20th 40th Median 60th 80th Maximum

ChanneiHaroor 61 0 000 0 003 0 012 0 019 0 024 0 058 0 890

La( ,Dars 22 0 001 0 004 01007 3 012 0 018 0 024 0038

Beach Erosion i1 0 004 0 005 0 012 0 023 0 025 0 030 814

FIood Control 99 0000 0 004 0 008 0 016 0 021 0066 0669

F oocControl Reservor 50 0001 0004 0007 0008 0012 002 3

129

Multiourpose Power 21 0 000 0 003 0 005 0 007 0 012 3 020 3 062

Rehab Channel/Harbor 3 0 003 0 003 0 010 0 010 0 010 1 208 0 018

Rehab LOC)CksDams '0 0 000 0 005 0 006 0 007 0 00 001S 02

O&M ChannellHarbor 44 0 000 0 002 0 007 0 010 .018 0 048 0 075

O&M LOCKhDams 1 0 003 0 003 0 003 0 003 003 0 003 3 C03

O&M Flood Control 0 -

O&M FC Reervolr 1 0 004 0 004 0 004 0 004 004 0 004 0 004

O&M MultipurDose Power 5 0004 30 0012 0014 0 14 0238 0262

O&M C H Imorovc ,ent 1 0028 0 028 0 028 0 028 0 028 0 028 2 023

F C 4ehabitation 8 0 014 0 020 0 024 0 028 0 032 0 045 0 250

F C Constru,0on 21 0 005 0 015 0024 0 026 0028 0 241 0 07

Recreation 0) 00010 027 041 062 ) 084 2 8rb

Note: Ratios are AE Contract amount divided by the cOnstruction contract amount

B 6

TABLE B-4

DISTRIBUTION OF USACE COST RATIOS FOR SUPERVISION AND REVIEW COSTS

Percentiles

Project category sampleMinimum 20th 40th Median 60th 80th Maximum

ThAn,'eIHaroor 24 3 000 J 000 0 30i 1 001 1 03 3 006 3061

-o< SDani 22 33 00 33 00 ,3 01 301 3 30' 0 004 3 0'3

3eAch Eosor, 9 3 00 3 000 3 30' 002 3 302 0 06 3 C6,

5;8o, Controi 58 3 300 3 300 0 10 2 3i

C2 0 012 3 261

-1loiodControl Fl,,er oir 44 3000 3000 0"301 2301 D3a1 0003 0012

l1'tiouroose Power '8 ) 000 3 000 0 30 , 30O 3,0 0 304 0

ehao 2hdnrel Harbor 2 3 300 ) 00 0 00 3 "0C 3300 3 30]0 3 000

Rer,-iD .ocwO.as I 3 000 3 000 0 301 32C] C3 307 3 301

O&A CianrPHaroor 3300 3 301 0 304 33G4 2 304 J 312

O&M L),CSDams 0 -

O&M Flood Control 0

O&M F C Resero.r 0 - -

O&M Multiouroose Powei 3 D300] 3 300 0 135 3 3 335 346 3'

O&M CH troroement 3302 ) 302 3 202 2 C02 3302 302 3 2

C Rehalhtatton 3 3 301 330' 0 220 01 320 3356

C ConstructiOn 20 301 3 302 0 303 ]04 04 " J05

R-3I3on 305 3305 ]- U5 3)05 j ]2I 3305

Note: Ratios are supervision and review costs divided by the construction contract amount

1-7

TABLE B-5

DISTRIBUTION OF USACE COST RATIOS FOR DIRECT ENGINEERING AND DESIGN COSTS

PirCent, I.,

Prolct category SampleMinimum 20th 40th Median 60th 80th Maximum

Channe, HarOr 104 D 001 2 024 " 041 052 0 067 ) 137 343

.c-.0 S 23 ) 020 3 027 3 045 0 48 0 056 0 i085 0 096

-each 37 0 004 ) '22 0 045 0 057 0 072 0 108 355

1ooc Contro, 231 3 000 ) 045 0 080 0 ''3 0 138 0 199 32

PIo Contrcl Resero,r 54 0 002 3 035 0 050 3365 0 089 0 126 0 185

MuitIourocse Power 22 0 0'6 0 038 0 064 0 077 C 086 0 092 .43

Rehab Channel,Haroor I 0 005 0 014 0 027 0 242 0 ,42 8 It8

Rehal) Locm.Dams 4 0 009 30033 0 040 0 63 0C 75 0 082 2

O&M CSannelHarbor '98 0 000 ) 012 1 028 0 038 -050 '25

O&M LOCK Dams ' 3238 0238 0238 ,0238 0238 0238 238

O&M FlIOI Controi 8 0018 3018 0019 3021 0024 0330 35t,

O&M FC Aeservor 2 0 036 3 036 0 036 0 050 C .64 0064 006

O&M MumtlDurDoie Power 26 0 028 0 036 0037 0 039 0 344 3 052 0 ' 1

O&M CH Inoroveent 4 0 018 0 018 0021 0066 01 3 326 .325

c C Pehali ation 26 ,0008 3 j6 0 '48 0 *9 , 80 03 16 "09

P.C Construction 21 1 028 0 044 3 052 064 0 072 0 106 41

23-,,vOn A 0 a 17 3 024 1 7024 0325 , u28 0048 j it

Note: Ratios are direct engineering and design costs civided by the construction contract amount

TABLE B-6

DISTRIBUTION OF USACE COST RATIOS FOR TECHNICAL INDIRECT COSTS

Percent ile

Project category Sample

Minimurn 20th 40th Median 60th 80th Ma.-mrn

Charnel Harbor "0 2 000 0 201 D N05 2 J09 2]1 - 8 330

1C, CA9s 19 0 003 0 "07 2 013 2 4 ,S 23 2 I13

iit rs,oi 35 0000 '204 0 007 209 . 1 3 122 2

P IOd Co'tro, 205 2 000 cog 3 020 2 026 20 2 '5 1 '399

F Icol Cotrot Rese'"or 40 3 000 2 03 3 010 0 311 012 .224 226

M1l1Di.iDOse Power 21 2 000 2 202 2 204 3 00s 2 0'2 2 C 2 252

Rehab C anneimaroor 7 ) 201 2 202 3 004 2204 22C7 2 29 2 223

RehaO c3Carns 1 2003 2 208 013 2013 20 4 .- 2- 3 3

O&M Charne, Harbor o8 '0 2 203 2 206 2 208 21 22 2 29 2 96

O&M , s. Dams 03' 031 3031 2031 2231 ]03' 223'

O&M IOO Conr01 302 212 0012 3214 216 220 2237

O&M I'C Reeror 0 024 0 024 0 024 2 224 2 024 2 224 2224

')&M VMDU'ooDSe ' er 25 0 002 0 320 2224 2224 2 C25 J 230 2 23b

r&) C 21 0 002 22 22!4 2323 232 329 2239

C Re,,t, 3 001 2 004 2 214 2224 230 '5 9 44

C r 9 012 2 ji9 2 024 2q 24 3, 2 .

1.1"ah J 001 2 2216 b, "

Note: Ratios are technical indirect Costs divided by the construCtion Contract imount

IB

TABLE B-7

DISTRIBUTION OF USACE COST RATIOS FOR SUPERVISION AND ADMINISTRATION COSTS

Percentiles

Prjet category Sample

Minimum 20th 40th Median 60th 80th Maximum

Channel Harbor 107 2 001 0 023 C40 i"55 363 C96 1 735

LOC0,.amS 23 3 026 ) 032 0 047 24ri 052 2065 J082

Beach Erosion 37 )008 0 029 0 039 3 043 053 0062 "9

FiOO Control 228 0001 0 031 0 047 2 056 2 C65 0 00 2 1

Fio l Control Reservor 54 2014 0 033 0 038 J42 C047 062 00gS

MuitiouiDose Power 22 2003 j 019 0 023 0033 2036 43 0089

Rehab Channel.Haroor 7 0 01% 0 015 0 027 ' 033 2086 0 '04 0 'bb

Rehab LOCkSCamS 14 0 019 0 034 0 047 0 253 0C67 0 097 0 '39

O&M Channe,HarbOr 215 0000 202b 2048 2257 2 Cb4 090 0 18

O&M ,,(i,0ars 13 0 r53 0 255 056 2 056 2059 0063 0 48

O&M 7-o1d Control 8 0 045 0 045 0 050 C 052 2053 056 0 057

O&M r C Reser-or 2 0056 3056 0056 2251 2257 )057 0057

O&M %luliopuroose Power 51 0 018 0 052 0 057 2258 2 20 C67 0 302

O&M CH fmorovement 4 3 049 0 049 0060 2 266 2073 '63 0 b3

C ReraOh1 a1,cn 21 )009 0 017 0 035 11 2.60 0C 1 3 'S2

P-C C;nstruct,z 21 0036 0060 , 066 2067 207' 0C6 0 '67

Rerreation 25 1020 0 0s0 0 053 2355 ? 251 058 28b

Note: Ratios are suoerv' ion and administration costs divided by the construction contract amount

I10

TABLE B-8

DISTRIBUTION OF USACE COST RATIOS FOR SUPERVISION AND INSPECTION COSTS

Percentiles

Project category Sample

Minimum 20th 40th Median 60th 80th Maximum

ChanneHa'oor Q3 2 201 3021 ' 0' 3 )-244 0 248 2 071 1 728

LO(k&Dam$ 23 2 J15 3 C22 0 033 ) 341 0 048 2065 2.282

8eacl, Eros=on 36 2 )04 2 022 0 034 2 035 0039 2 053 " 79

11ooa Contro 225 ) 201 20U3 2 037 344 0 050 2 '6 3442

FiOO4I Controi Reservo, 50 2 301 021 ) 027 032 0 037 2 045 ) 27

'Aoi1OurOce e 22 ) 009 3 017 0 020 2 025 0 031 0 038 2 ,65

Rerad COAn'- Ha-tocr 7 2 210 2 012 0 0A3 3 31 2 067 2 082 2 '62

eiaD L.:c .ODas 14 3 017 2 028 0 036 2040 0 044 2 015 2 15

O&M Ch',-, HarbOr 59 2 203 2 033 047 3 253 2 361 3 089 2 298

i2&M x 2 ,'I% '3 0045 3047 2048 2248 050 0053 3 3

O&M ;c-d ContIr, 8 2 036 2 036 2 040 2 041 2 043 2 045 3 245

O&M I C RePe,4 r 0 045 3 045 0045 2 045 2 045 0 045 2 245

O&M Muir cwoose Power 5) ) -15 3 043 2 046 2 247 2 048 2 057 2 259

O&M C H o1ro,n-t 4 3240 ) C4(I 2 248 2 256 2263 1 128 2 '28

P C Rehaotatr, 21 2 2og ) 017 3 030 2340 22 21 0 b9 2 '21

; C C ntructon 27 2033 2049 2255 225 55 5 2356 2264

Rereatlo, 25 3 )16 2 040 042 44 2 246 3 246 8

Note: Ratios are suoervision and inspection costs divided by the construction contract amount

I1 II

TABLE B-9

DISTRIBUTION OF USACE COST RATIOS FOR GENERAL AND ADMINISTRATIVE COSTS

Percentiles

Projec category Sampinle

Minimum 20th 40th Median 80th 80th Maxn.in

C"4nnel Harlbor 99 0 000 0 005 ) 014 ) 018 0 025 3 344 ) 992

,oc %Cams 23 0 006 0 010 ) 012 0 012 0 014 3 018 03 034

1each Eroson 37 ) 005 0 010 0 016 3 022 0 026 3 040 0 !47

*'ood Control 227 0 00 014 0 025 0 030 0 035 0 360 0 275

IOocjControl Reservor 53 000 D 02 3 017 0 018 0 023 0 330 0 08

"t~iourposePowe, 2' )00 0)0 J 012 3 013 0 016 ) 016 0326

Rehao rhannelHarOo ' 001 006 0 008 0 010 0 028 ) 32 049

Rehao LOCi Dams 4 0005 00 0 )0 4 0 C19 0023 )030 0034

&M Channe".rDor "9 03 0010 ) 0016 )0 8 0 022 035 253

'D&M c'Ci K"C 3 016 0 06 3017 017 008 339 0057

CO&M P 000 C Dntrol 1 3009 309 0010 0010 0011 00'1 0012

O&M 0 C 312 3 .11 0012 002 0012 )02 00J12

O&M -.AuitsourDose P"wer 5 )00 0012 3014 3015 00,? )021 0245

&mC H ,orcveee 4 0 012 0 012 0 012 0 028 0 045 0 387 0 187

C ReeO.aiht,in Z6 0003 0 012 312 0 027 003 0040 3291

*C Cst'on 21 0006 )311 014 0014 0017 025 0 "

26 00'0 0011 3011 0012 0012 0 13 0.043

Note: Ratios are general and administrative Costs divded by the construction contract amount

IB 12

TABLE B-10

DISTRIBUTION OF USACE COST RATIOS FOR AREA OFFICE OVERHEAD COSTS

Percentiles

Projet category SampleMinimum 20th 40th Median 60th 80th Maximum

Channel/Haroor 32 3 000 0000 0 00i a 001 3 002 3 004 3 0'

Lo<iisOat$ I ) 000 ) 000 3 000 0 DO0 3 00 3 coo 0 000

Beach Eroson 9 0 000 000 0 002 3 003 3004 3 008 0 040

Flooo Control 47 0 000 000 )003 3 )04 0 305 008 0 032

Flood Control Reservoir 12 0 000 000 0 000 0 200 3 000 3 000 0 004

Mulouroose Power 10 3000 0 000 2 00 3302 3 002 3005 3 0'1

Rena Char- Haroor 5 0 000 0 001 0 002 3 302 3002 2003 0 003

Re"40 -_ wsc.,s 1 0 004 0 004 0 004 3 304 3 204 3 004 ' 004

O&M Channe, H roor 51 3 000 0 003 0 006 0 307 3 007 0 012 0 057

O&M LOt'kD4irS 0 041 3041 0 041 3 041 3 041 0 041 0 041

O&M Flood Cottrol 3 .-

O&M F C Reseror 3 -

O&M Muitipuroose Pwer 3 0002 9 002 0006 0206 0006 0 016 3 0 '6

O&M CH l3rO-emn1 - -

C Rehaihiat,o, 3 0001 3001 0001 2001 3001 3001 3301

C ContrutmOn 2 0 005 3 005 005 3 021 3 0 36 036 30 3b

R.creato 3

Note: Ratios area office overhead costs divided by the construction contract amount

1,-13

APPENDIX C

CIVIL WORKS COST CURVES

APPENDIX C

CIVIL WORKS COST CURVES

This appendix contains curves which present the cost equations developed from

the regression analyses. Cost equations, regression statistics, and graphic represen-

tations are presented for each category and cost analyzed. These curves display the

characteristics of the derived cost equation - economies of scale, etc. - and can be

used to estimate costs graphically, although calculations using the provided

equations will yield more accurate results.

Users of these curves are reminded of the civil works cost estimating model

that will perform estimating calculations and compare actual cost data to historic

U.S. Army Corps of Engineers (USACE) cost experience. Further information on

this model is contained in the civil works cost estimating model user's guide.

(>3

0 D

ID

0E z

z

0 Er%a 2

c4o 4A

E. 0

c

Ln 0 0UU

20 z

00

CC0 Z

C-4-

C5 0

0 cC)

0

0

o 9-0

000

- 0 w

0A E 0

oM~'

cI L.2

0

0

C u -

0

0-

0 .

A, C-DLAJ 4A

0

00

o Li

cwu~ 0

0)o

o

c. 00

0 40 Li

C>C

z .- 0

C-6

0r0%

co

0*0

00

C-

CD 0

o %Ao %)

c n0

(? >

cr 0

C ~CL

CL

cV,

C-o

0co

00

00

0 -o

o c

cr z

s 0C ~ cc

ClC

0 0

C-8,

C,

0I

0

o 4C).

0o

o o 0~ 0

L6

0 ziv, E

00

' .A

olc'U

C

ID-

w -0 0

00

LUJ

00

E LU>

c cc

X 0

0 =U

0

E22a.>

0

z 4

;z ZLz~

oQU 00

Lu

0 20cC

10In

.1'i

00a1.

I-

co0

0j

(5

c0 0

0 0

=0

oI -c 1=

~, 0

- ~ z4

= 0

0 a2LL 4z

100.S

* aa 0u.

-v, L

o >

CD.

00

4cc

co cc

LUz

0 C

Z=

0LUJZ2

Li-a

~~0 0

C-U

0 0.

4, 4

0

I.W

a00

0cc<4

00 wz

ILU

z

0

..rE

m~ >

CD 0

cn 0w- - <

0

Z cr

o

000

E u

z=

<0U Z

z 03

00

N E"

cr.

00

>

M cr

%~ A

> 0lC4

C 03

0

00

ID

0 L0

0 zWCD uzz

00

c4

0

00

o z

o- *a

U, 0

CzOz

c, 0

c U,

0, 0

0

z cC* 0 4

C~ 14

Li0cc01

o z

2A

00

S00

o T

UCL

o rZC)

.0

oo

2. 0

a E

C CD

402cz

C--5

0

0 -co 0

1-

0 c

00

U, 00 E

0-4

CC

~ 0 0

C~ 16

0L00

I-

co

4

Go 0

LU

z

~ 0c 0.D vi

S0E

00

0 I

-. M

0 t l

C0oo

0

, 0 =

0 0~0

1 4

0~0

-AJ

L

0 V40

C-17

0A00

0k'

04

0'0

4A aV;

c

oJ

E 0

0o .0'0 0 %A

EEYo -o

40c 0-

A Uj

2 02

U'

UL

InL

CU I

c 0 -0

c~ 1=

0o

00

a1.0 0

00

0o

Lfn'0 0

E

0

o 0 ;cw

08

Z. C

o o~2 w

co -o

0 I-)

0~

05 e0

C-19

Ir.

z 0CL0

u,0

Ln 0

o 0~0 I.-

so, 0

C it L

0 %Ao :, u

oo 0

UL

8l

aL.

C),

0 0 V

C-20

0

C).In CD -

CtwCDa

0000

o =8

0 E

00oo

0 0U

0 0u

> -

o Q

c E -LD 0 n

C-21

VI,

co

00

0

CD

0' 0 0

E 0m -j

o .- ~ U.

0'0 vi

0 0 0CD M

7 v

c -U

0 0 LUc 20~

40- 0-

00

'NVI

C 22.

00

00

00

v 0 0o00

- 0c

00

0E

o

Ln 0,,, E u

C ~ 0

u,

.11

ui V4

o-23

0

0D

0

a4A

00

00

0

o I-0 0

E

00

E 0fc)1

C-24

C)0

co

0

0

1:e

E0:3 L&

0 " .

00

0 i

o oro 0

cr 0

r4 -

CD25

0,

4.4.

C 25

0

c 00

ao

CL

I-

0 ,

0.-

C" z0 0

'c 0

0

" o -.0 0j

.E

0'- 0 -

0 E 00 0c c

o E 0

c U w

o 3 I-,CC

o z

'ccc

(-0I2-

CL C IoCD

C. 2 6

0

0

co

0ao

uJ

o 0

.-

0

C- z0 0

o

00

m 0

U, 0

E

LU

o-" 0

~ 0

ocoo -

CD C

fu~ 0 t

(C 27

00

o %

co0

0' 0

0

In-

0o 0

'N 0:-J

S0E 0jm

00

0

0 I-Ez

0

0 E 0

CD

o u0

~'0

0)~ -.

,- 0

'N C 0

LA.

00

co0*0

zAM

0

0

0

00

U, 0

0 1:o5

:3 C

00o z ZaE

z-

%A

Do 0

C 29

00

cc

co

LU

00

20

0

00

CD 0

o 000

0 L

0 Cc

2 2

0 ~ U,

-0 W6

C -30-

0

V,

00

0*'0

U, 0

C) 0 .-

0 I=

0 0c 0.o0 0

c 0 -LU

u zC

E --

E05

OL 0

c --301

co I-

La

CD 00 0 L

oo0 0

U,0 00E

c -'U.

E 00 LL 0.

.~0 u kA

3 0o V

0 p o~0

0 a:

C0

~- 0 0

LU'

2 I ..

0a c: 0 W

C .32W

0n

0u

00

a.

cw

0

0 0 >um 0

o 00

E 0 0C

c U 0

z

Ct

C 00 4A

C-33C

0

LU

z0

Ln zC) LU

000 CC

v) 0E Lu~

00

= C

0- 02

c -- Q-'-0

o 00 00E I I -

2 a0

-. -j

LU

o o~ LU

co %Q

c~

C)

0

314

0n

00

LI.,

00z000

0 u

0zo- w

0 0Z

o0o 0

C> 0~i, 0

o -0

~~ 000 0.

-~ 00A 0

U U.

VIo

00 ~ 0

- 1-

p - 0Do

C-35

0 0ON-

a

z

0

o

==J0 0

z'o ' ,-

0 OLo O

o 0

CD, 0o =

C2C

~0"

c uo

c 0

- 0 gOZ

020

0 36~~ 0 Z0

.0

LU,

0 0

C~ 36

z

00

z0U

00

C)-

0

0o 0

c 0j00

- 00'O

01~

I-j

0 0 ~ z0a

~~ z~

- 0

a, ca

o 00

a, L

:3 .0 0%

C 37

00

00

z0

CkF0

D Z0z

0

0 Z -

.000. 0

~ 0o ~ J~o

0-wZ

U' 0

Ez

CC

00

2 A

0~@8

'A'

c~' 0 AU

C 38

00

00

IQ-

a.

O0

C ua. ,

z

v0 O

Z,' 0

0 4

00 _

W6L&

z0

o L_

c E C)

C . .9

00

co A

C) 0C) In

0 L0

C:, 0

0 C

E CL0

0

- z

~ Id,ow

CDC

00

0

a*a

0

a.1

00

S0

0

0 0

- 0C0

0~ 0 Z

U

CDC

C 41

.1-

0

0 D

00

J~ 0~~ 0

oz

CD 0

c, 0

C -1

o I I

0

crS o 0LA'

09Lw A

0a.

F

-

0o ZD

o 9L

00

E,,

o .-

c ui00

J, 0

0t) cc

" 0 o •

I IIx

S a.

~' 0i.-) cc

Co 0

10 C000

C 4:34

0L

00

CL

00

LUIvi

0 0

oo

o 0

00

00

C < Vek

0 (v

00

o o U

CL

Sa.

0

9 L.

o.-0, 0

CL LU- a

6n oa 0

C .4

00

LU

a00

0

LU

o 0

-AJ

0

0

0

o 0

'I,

CD-0 4Acaa

C 45

0

C) LU

CD az

0 ccE4

o mU

0

~~0

z

(Lj CC

C -1

00

0~0

LU

z00

E LU00

c 00o 000

c 4Uul 0 cc

E L&

C 0V, Q

cLU

4,

CtL

CD,

caU 00 "

C~ 07

cc0

a.'%

00

a.'j

o D <

4A4

4' 0' 0E2

00

o oA

laa0'

.4 0

CDC

y 0D

C D

C~ 0 %

C' 48~

00

co

0'I

z

00

0 0U

00

S0

S <

0

00 Cz 0

C-49~

0

00

LM~

z

0

S CL

E 0U

0

0 uo0

C

0' 00E

0 0

0In L,

0 aa

*1~ 0

C.~

zo *V

0

0)

0

00

C)-

co a.0

FU

zCD <

000

S0 'a

E 0o LM

0

00

= 0 0C

o U.0

0 C a

'a

tCtI

0 V4

C-51--

c0

0

oo

0

00

0

Eo I&

E 2l

U, 0

cm 0

0 0

52 L

00

C LA

SC

00

Eo0

%a 0c E J

0, ~

4, ~ 0

o - j

-E, D

>~ 0

C 53

00

0%j

01

00

L6

I^0

0 c

o 4U

!-0

CD co

0 0l

C V

C-50