04 12 12

26
TSX-V: ALR STRATEGIC LOCATION IN AN EMERGING COPPER-GOLD PORPHYRY DISTRICT April 2012

Transcript of 04 12 12

Page 1: 04 12 12

TSX-V: ALR

STRATEGIC LOCATION IN AN

EMERGING COPPER-GOLD

PORPHYRY DISTRICT

April 2012

Page 2: 04 12 12

This document contains forward-looking statements under Canadian securities legislation. Forward-looking statements include, but are not limited

to, statements with respect to the development potential and timetable of the Rosita project; the timing and amount of estimated future

development and exploration; costs of future activities; capital and operating expenditures; success of exploration activities; government regulation

of mining operations; and environmental risks. Generally, forward-looking statements can be identified by the use of forward-looking terminology

such as “plans”, “expects” or “does not expect”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates” or “does not

anticipate”, or “believes”, or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”,

“might” or “will be taken”, “occur” or “be achieved”. Forward-looking statements are based on the opinions and estimates of management as of the

date such statements are made. Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may

cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied

by such forward-looking statements, including but not limited to risks related to: timing and availability of external financing on acceptable terms;

unexpected events and delays during construction, expansion and start-up; variations in ore grade and recovery rates; receipt and revocation of

government approvals; actual results of exploration and mining activities; changes in project parameters as plans continue to be refined; future

prices of metals; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining

industry. Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from

those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There

can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those

anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. The Company does not

undertake to update any forward-looking statements except in accordance with applicable securities laws.

The technical and scientific information included herein has been reviewed and approved by Joseph Arengi, M.Sc., P.Geo , President and CEO of

the Company, and a qualified person under National Instrument 43-101 of the Canadian Securities Administrators.

Forward Looking Statements

Page 3: 04 12 12

Alder Resources

• Experienced team with proven track record

• Extensive Central American experience

• Right to acquire 65% interest in 33 km2

target-rich property with Copper- Gold-Silver

Porphyry/Skarn potential

• Excellent exploration upside at Rosita, a

past producer

Page 4: 04 12 12

The Alder Team - Management

• Joseph Arengi , M. Sc., P. Geo. – President and CEO

35 years of exploration and operational experience throughout Canada, Nicaragua, South

America and Africa. Credited with discovering 4 billion pounds of copper and 60 million

ounces of silver in Botswana.

• John Spurney – VP Exploration

Over 30 years of diversified technical and managerial experience in mineral exploration,

primarily in Latin America, the Western U.S. and Asia.

• Ryan Ptolemy – CFO

Certified General Accountant and CFA charter holder. Mr. Ptolemy is currently also CFO of

Rodinia Lithium Inc. and Belo Sun Mining Corp. and was a Toronto investment dealer.

• Josh van Deurzen – Corporate Secretary

Corporate and securities lawyer, working as a legal consultant to various public and private

companies in the resource-based sector.

Page 5: 04 12 12

The Alder Team - Board of Directors

• Don Dudek, Chairman

For 28 years, Mr. Dudek held various roles with junior and senior exploration and mining

companies. He is currently Senior VP Exploration for Avion Gold Corp.

• Rene Bharti, Director

Mr. Bharti, a Queen’s University Commerce graduate, has held roles in several public and

private companies including those in the resource and other sectors.

• Dan Bruno, Director

A Chartered Financial Analyst and MBA graduate, Mr. Bruno has over 15 years of investment

experience.

• Honourable Pierre Pettigrew, P.C., Director

Mr. Pettigrew is former Minister of Foreign Affairs and currently Executive Advisor, Deloitte &

Touche LLP. He is an advisor and board member of several publically traded companies.

• Will Randall, Director

A professional Geologist whose experience includes management roles in both mineral

exploration and production.

Page 6: 04 12 12

Share Structure and Trading

TSX-V: ALR

ALR Share Structure:

Common Shares: 72,579,085

Current share price : $0.19

Warrants: 21,982,685

Average warrant price ($/share): $0.21

Options: 7,200,000

FULLY DILUTED SHARES: 101,761,770

Insiders/Institutional Holders: 8%

Share Trading Activity:

52 week High/Low ($/share): $0.065/0.285

Market capitalization: $13,427,131

Cash Balance: $3.0M

Debt: None

Page 7: 04 12 12

Nicaragua

• Largest and safest country in Central America

• Stable, supportive and democratically elected government

• Attractive tax regime; 3% NSR, 30% Net Profits Tax

• Long mining history with 3 currently producing gold mines:

• La Libertad, El Limon Mines (B2Gold)

• Bonanza Mine (Hemco)

• Proactive promotion of mining investment (www.nicaragua-pdac.org)

Page 8: 04 12 12

Rosita Project - Location

•3,356 ha

property

•120 km to the

Puerto Cabezas

seaport

•275 km to

capital city of

Managua

Page 9: 04 12 12

NE Nicaragua – an emerging porphyry district

2.3M ozs Au

production

3.0M ozs Au production

245M lbs Cu, 160K ozs,

2.6M ozs Ag production

B2Gold/Calibre:

261.7m @ 0.78 g/t Au,

0.30% Cu

NEW PORPHYRY Cu-Au

DISTRICT

(See notes 2 and 3)

Page 10: 04 12 12

Rosita Project - History

• Past producer from two open pits – Santa Rita and R-13

• 245M lbs Copper (See Notes 1 and 2)

• 160,000 ounces Gold

• 2,610,000 ounces Silver

• Early mining focused on high grade copper with 2%

copper stockpiled

• First gold recovery during last 5 years of production

Page 11: 04 12 12

Rosita Project - Geology and Prospects

Page 12: 04 12 12

Rosita Project - Target-Rich

FOCUSED ON THREE MAIN TARGETS:

• Stockpiles and Tailings

• Mineralization Adjacent to Santa Rita and R-13 Pits

• Bambana Porphyry

Page 13: 04 12 12

Santa Rita Stockpiles – RC Drill Holes

• 55 RC holes

completed in 6

stockpiles over

320,000 m2

• Weighted ave

grades of 0.49% Cu,

0.42 g/t Au and

7.24 g/t Ag

• Resource estimate

underway

(See Alder News Release of March 1, 2012)

Page 14: 04 12 12

Tailings Assessment

• Initial sampling

to characterize

grade and

distribution

• ~490,000

square metres

• Resource

estimate to

follow if

warranted

Page 15: 04 12 12

Santa Rita – Cross Section

2 Alder News release of February 8, 2012; See Note 3

Santa Rita and R-13 Pits:

• 0.91%Cu, 1.00 g/t Au and 16.63 g/t

Ag/12.0m in vertical RC2

• 2.95%Cu, 0.34 g/t Au, 35.31 g/t

Ag/18.3m in ddh below Santa Rita2

• 0.98%Cu/79.9m in ddh below R-13

Page 16: 04 12 12

Santa Rita – Cross Section

(See Note 3)

Continuity in host rock

Stacked lenses

Good grades and widths

Page 17: 04 12 12

Santa Rita- Longitudinal Section

(See Note 3)

Open

Op

en

Open

Page 18: 04 12 12

Santa Rita/ R-13 Potential

1 Tonnages and grades are historical and

non-compliant; (See Note 2)

1.2M tonnes @ 0.83% Cu1 1.1M tonnes @ 1.42% Cu1

Page 19: 04 12 12

Bambana - Cu-Au-Ag Porphyry

(See Note 3)

Page 20: 04 12 12

Rosita Project - 2012 Exploration Objectives

• Complete 8,000m of core drilling by Q4

• IP Geophysical Survey in Q1 and Q2

• Initial Resource for stockpile material Q2

• Preliminary Metallurgical Study of stockpiles in Q2

Page 21: 04 12 12

Rosita Project - Exploration Timeline

Milestone Qtr 1/12 Qtr 2/12 Qtr 3/12 Qtr 4/12

Trenching

IP Geophysics

RC Drilling Stockpiles

Initial Resource Estimate - Stockpiles

Diamond Drilling – Santa Rita/R-13 (5,000m)

Diamond Drilling – Bambana/Other (3,000m)

Resource Estimate – In Situ

Page 22: 04 12 12

Summary

• Aggressive exploration program underway on high quality

targets

• Initial Results Highly Encouraging

• Highly experienced team with Central America focus

• Significant Porphyry discovery by B2Gold/Calibre 8 km from

Rosita

Page 23: 04 12 12

Notes to Text

• Note 1: See references in Alder Technical Report referred to in News Release of January 9, 2012 and filed on

SEDAR.

• Note 2: All of the historical mineral resource estimates and production totals quoted herein are based upon

historical data and reports obtained and prepared by previous operators and consultants (Arengi, 2003;

Hendrickson, 1995; Rivera, 1977; Rosario, 1974; Sims, 1998) and the quoted mineral resource estimates/mineral

inventory were prepared prior to the introduction of National Instrument 43-101. These historic resource

estimates/mineral inventory are considered to be relevant to the evaluation of the Rosita D concession. A Qualified

Person has not completed the work necessary to independently verify the classification of the historic mineral

resource estimates. Alder is not treating the mineral resource estimates as National Instrument 43-101 compliant

defined resources verified by a Qualified Person. The historical estimates should not be relied upon.

• Note 3: Alder has not yet verified the historic drill results reported herein and does not intend to use this

information for purposes other than planning and prioritizing exploration targets.

Page 24: 04 12 12

Addendum

Page 25: 04 12 12

Santa Rita Pit And Stockpiles

Page 26: 04 12 12

Bambana Porphyry Cu

BB10-001 (88.5m) - 0.60% Cu, 14.1 g/t Ag/2.0m