03-4M1804 Baseline Schedule for Review

2
Activity ID Activity Name Original Duration Start Finish Culvert Rehabilitat Culvert Rehabilitation In Glenn County 62 06-Jun-14 A 22-Sep-14 Submittals Submittals 14 06-Jun-14 A 15-Jul-14 4M1804.SUB.100 WPCP Submitted 0 06-Jun-14 A 4M1804.SUB.110 WPCP Re-Submitted 0 23-Jun-14 A 4M1804.SUB.120 Safety Plan Re-Submitted 0 17-Jun-14 A 4M1804.SUB.130 Lead Compliance Plan Submittals 0 27-Jun-14* 4M1804.SUB.140 Safety Plan Approval By Caltrans 14 23-Jun-14 A 15-Jul-14 4M1804.SUB.150 Lead Compliance Plan Approval By Caltrans 10 30-Jun-14 15-Jul-14 Construction Construction 45 21-Jul-14 22-Sep-14 4M1804.100 Construction Start 0 21-Jul-14* 4M1804.110 Construction Finish 0 22-Sep-14 Location 1 Location 1 5 21-Jul-14 25-Jul-14 4M1804.LOC1.100 Remove Fence, Culvert & Marker 1 21-Jul-14 21-Jul-14 4M1804.LOC1.110 Install Marker, ESA Fence, Cleaning & Inspection Of Pipe 1 22-Jul-14 22-Jul-14 4M1804.LOC1.120 CIPPL 2 23-Jul-14 24-Jul-14 4M1804.LOC1.130 Cleaning & Inspection 1 25-Jul-14 25-Jul-14 Location 2 Location 2 5 28-Jul-14 01-Aug-14 4M1804.LOC2.100 Remove Fence, Culvert & Marker, Cleaning & Inspection 1 28-Jul-14 28-Jul-14 4M1804.LOC2.110 Remove SC Slope Protection, Install Fence Type WM & BW 1 29-Jul-14 29-Jul-14 4M1804.LOC2.120 71" X 41" Steel FES, Install Misc. Steel 1 30-Jul-14 30-Jul-14 4M1804.LOC2.130 Misc. Steel 1 31-Jul-14 31-Jul-14 4M1804.LOC2.140 Minor Concrete (Invert Paving), Install Marker 1 01-Aug-14 01-Aug-14 Location 3 Location 3 5 04-Aug-14 08-Aug-14 4M1804.LOC3.100 Remove & Install Marker, Cleaning & Inspect Of Culvert 1 04-Aug-14 04-Aug-14 4M1804.LOC3.110 Cleaning & Inspection 1 05-Aug-14 05-Aug-14 4M1804.LOC3.120 Misc Steel 2 06-Aug-14 07-Aug-14 4M1804.LOC3.130 Minor Concrete (Invert Paving), Install Marker 1 08-Aug-14 08-Aug-14 Location 4 Location 4 5 11-Aug-14 15-Aug-14 4M1804.LOC4.100 Remove Fence, Culvert & Marker 1 11-Aug-14 11-Aug-14 4M1804.LOC4.110 Ditch Excavation, Grade To Day Light, Install 18" CSP, Cleaning & Inspect Of Culvert 1 12-Aug-14 12-Aug-14 4M1804.LOC4.120 CIPPL 2 13-Aug-14 14-Aug-14 4M1804.LOC4.130 Install Marker 1 15-Aug-14 15-Aug-14 Location 5 Location 5 5 18-Aug-14 22-Aug-14 4M1804.LOC5.100 Remove Fence, Culvert & Marker 1 18-Aug-14 18-Aug-14 4M1804.LOC5.110 Ditch Excavation, Grade To Day Light, Install 18" CSP, Cleaning & Inspect Of Culvert 1 19-Aug-14 19-Aug-14 4M1804.LOC5.120 CIPPL 2 20-Aug-14 21-Aug-14 4M1804.LOC5.130 Install Marker 1 22-Aug-14 22-Aug-14 Location 6 Location 6 5 25-Aug-14 29-Aug-14 4M1804.LOC6.100 Remove & Install Marker,CIPPL, Cleaning & Inspect Of Culvert 1 25-Aug-14 25-Aug-14 4M1804.LOC6.110 CIPPL, Cleaning & Inspect Of Culvert 4 26-Aug-14 29-Aug-14 Location 7 Location 7 5 02-Sep-14 08-Sep-14 4M1804.LOC7.100 Remove Marker, Ditch Excavation, Grade To Day Light, Cleaning & Inspect Of Culvert 1 02-Sep-14 02-Sep-14 4M1804.LOC7.110 Minor Concrete Footing, Minor Concrete Structure, Install Marker 1 03-Sep-14 03-Sep-14 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 June 2014 July 2014 August 2014 September 2014 October 2014 22-Sep-14, Culvert R 15-Jul-14, Submittals WPCP Submitted WPCP Re-Submitted Safety Plan Re-Submitted Lead Compliance Plan Submittals Safety Plan Approval By Caltrans Lead Compliance Plan Approval By Caltrans 22-Sep-14, Construc Construction Start Construction Finish 25-Jul-14, Location 1 Remove Fence, Culvert & Marker Install Marker, ESA Fence, Cleaning & Inspection Of Pipe CIPPL Cleaning & Inspection 01-Aug-14, Location 2 Remove Fence, Culvert & Marker, Cleaning & Inspection Remove SC Slope Protection, Install Fence Type WM & BW 71" X 41" Steel FES, Install Misc. Steel Misc. Steel Minor Concrete (Invert Paving), Install Marker 08-Aug-14, Location 3 Remove & Install Marker, Cleaning & Inspect Of Culvert Cleaning & Inspection Misc Steel Minor Concrete (Invert Paving), Install Marker 15-Aug-14, Location 4 Remove Fence, Culvert & Marker Ditch Excavation, Grade To Day Light, Install 18" CSP, Cleaning & CIPPL Install Marker 22-Aug-14, Location 5 Remove Fence, Culvert & Marker Ditch Excavation, Grade To Day Light, Install 18" CSP, Clea CIPPL Install Marker 29-Aug-14, Location 6 Remove & Install Marker,CIPPL, Cleaning & Inspec CIPPL, Cleaning & Inspect Of Culvert 08-Sep-14, Location 7 Remove Marker, Ditch Excavation, Grade T Minor Concrete Footing, Minor Concrete 03-4M1804 - Culvert Rehabilitation In Glenn County 26-Jun-14 23:18 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 1 of 2 CPM Schedule Provided By: Pushpa Services

description

Construction Schedule

Transcript of 03-4M1804 Baseline Schedule for Review

Page 1: 03-4M1804 Baseline Schedule for Review

Activity ID Activity Name OriginalDuration

Start Finish

Culvert Rehabilitation In Glenn CountyCulvert Rehabilitation In Glenn County 62 06-Jun-14 A 22-Sep-14

SubmittalsSubmittals 14 06-Jun-14 A 15-Jul-14

4M1804.SUB.100 WPCP Submitted 0 06-Jun-14 A

4M1804.SUB.110 WPCP Re-Submitted 0 23-Jun-14 A

4M1804.SUB.120 Safety Plan Re-Submitted 0 17-Jun-14 A

4M1804.SUB.130 Lead Compliance Plan Submittals 0 27-Jun-14*

4M1804.SUB.140 Safety Plan Approval By Caltrans 14 23-Jun-14 A 15-Jul-14

4M1804.SUB.150 Lead Compliance Plan Approval By Caltrans 10 30-Jun-14 15-Jul-14

ConstructionConstruction 45 21-Jul-14 22-Sep-14

4M1804.100 Construction Start 0 21-Jul-14*

4M1804.110 Construction Finish 0 22-Sep-14

Location 1Location 1 5 21-Jul-14 25-Jul-14

4M1804.LOC1.100 Remove Fence, Culvert & Marker 1 21-Jul-14 21-Jul-14

4M1804.LOC1.110 Install Marker, ESA Fence, Cleaning & Inspection Of Pipe 1 22-Jul-14 22-Jul-14

4M1804.LOC1.120 CIPPL 2 23-Jul-14 24-Jul-14

4M1804.LOC1.130 Cleaning & Inspection 1 25-Jul-14 25-Jul-14

Location 2Location 2 5 28-Jul-14 01-Aug-14

4M1804.LOC2.100 Remove Fence, Culvert & Marker, Cleaning & Inspection 1 28-Jul-14 28-Jul-14

4M1804.LOC2.110 Remove SC Slope Protection, Install Fence Type WM & BW 1 29-Jul-14 29-Jul-14

4M1804.LOC2.120 71" X 41" Steel FES, Install Misc. Steel 1 30-Jul-14 30-Jul-14

4M1804.LOC2.130 Misc. Steel 1 31-Jul-14 31-Jul-14

4M1804.LOC2.140 Minor Concrete (Invert Paving), Install Marker 1 01-Aug-14 01-Aug-14

Location 3Location 3 5 04-Aug-14 08-Aug-14

4M1804.LOC3.100 Remove & Install Marker, Cleaning & Inspect Of Culvert 1 04-Aug-14 04-Aug-14

4M1804.LOC3.110 Cleaning & Inspection 1 05-Aug-14 05-Aug-14

4M1804.LOC3.120 Misc Steel 2 06-Aug-14 07-Aug-14

4M1804.LOC3.130 Minor Concrete (Invert Paving), Install Marker 1 08-Aug-14 08-Aug-14

Location 4Location 4 5 11-Aug-14 15-Aug-14

4M1804.LOC4.100 Remove Fence, Culvert & Marker 1 11-Aug-14 11-Aug-14

4M1804.LOC4.110 Ditch Excavation, Grade To Day Light, Install 18" CSP, Cleaning & Inspect Of Culvert 1 12-Aug-14 12-Aug-14

4M1804.LOC4.120 CIPPL 2 13-Aug-14 14-Aug-14

4M1804.LOC4.130 Install Marker 1 15-Aug-14 15-Aug-14

Location 5Location 5 5 18-Aug-14 22-Aug-14

4M1804.LOC5.100 Remove Fence, Culvert & Marker 1 18-Aug-14 18-Aug-14

4M1804.LOC5.110 Ditch Excavation, Grade To Day Light, Install 18" CSP, Cleaning & Inspect Of Culvert 1 19-Aug-14 19-Aug-14

4M1804.LOC5.120 CIPPL 2 20-Aug-14 21-Aug-14

4M1804.LOC5.130 Install Marker 1 22-Aug-14 22-Aug-14

Location 6Location 6 5 25-Aug-14 29-Aug-14

4M1804.LOC6.100 Remove & Install Marker,CIPPL, Cleaning & Inspect Of Culvert 1 25-Aug-14 25-Aug-14

4M1804.LOC6.110 CIPPL, Cleaning & Inspect Of Culvert 4 26-Aug-14 29-Aug-14

Location 7Location 7 5 02-Sep-14 08-Sep-14

4M1804.LOC7.100 Remove Marker, Ditch Excavation, Grade To Day Light, Cleaning & Inspect Of Culvert 1 02-Sep-14 02-Sep-14

4M1804.LOC7.110 Minor Concrete Footing, Minor Concrete Structure, Install Marker 1 03-Sep-14 03-Sep-14

02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06

June 2014 July 2014 August 2014 September 2014 October 2014

22-Sep-14, Culvert R

15-Jul-14, Submittals

WPCP Submitted

WPCP Re-Submitted

Safety Plan Re-Submitted

Lead Compliance Plan Submittals

Safety Plan Approval By Caltrans

Lead Compliance Plan Approval By Caltrans

22-Sep-14, Construction

Construction Start

Construction Finish

25-Jul-14, Location 1

Remove Fence, Culvert & Marker

Install Marker, ESA Fence, Cleaning & Inspection Of Pipe

CIPPL

Cleaning & Inspection

01-Aug-14, Location 2

Remove Fence, Culvert & Marker, Cleaning & Inspection

Remove SC Slope Protection, Install Fence Type WM & BW

71" X 41" Steel FES, Install Misc. Steel

Misc. Steel

Minor Concrete (Invert Paving), Install Marker

08-Aug-14, Location 3

Remove & Install Marker, Cleaning & Inspect Of Culvert

Cleaning & Inspection

Misc Steel

Minor Concrete (Invert Paving), Install Marker

15-Aug-14, Location 4

Remove Fence, Culvert & Marker

Ditch Excavation, Grade To Day Light, Install 18" CSP, Cleaning &

CIPPL

Install Marker

22-Aug-14, Location 5

Remove Fence, Culvert & Marker

Ditch Excavation, Grade To Day Light, Install 18" CSP, Clea

CIPPL

Install Marker

29-Aug-14, Location 6

Remove & Install Marker,CIPPL, Cleaning & Inspec

CIPPL, Cleaning & Inspect Of Culvert

08-Sep-14, Location 7

Remove Marker, Ditch Excavation, Grade T

Minor Concrete Footing, Minor Concrete S

03-4M1804 - Culvert Rehabilitation In Glenn County 26-Jun-14 23:18

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

Page 1 of 2 CPM Schedule Provided By: Pushpa Services

Page 2: 03-4M1804 Baseline Schedule for Review

Activity ID Activity Name OriginalDuration

Start Finish

4M1804.LOC7.120 Misc. Steel 1 04-Sep-14 04-Sep-14

4M1804.LOC7.130 Invert Paving 1 05-Sep-14 05-Sep-14

4M1804.LOC7.140 Cleaning & Inspect Of Culvert 1 08-Sep-14 08-Sep-14

Location 8Location 8 4 09-Sep-14 12-Sep-14

4M1804.LOC8.100 Remove Culvert & Marker, 18" HDPE Corrugated, Concrete Backfill, Place HMA 1 09-Sep-14 09-Sep-14

4M1804.LOC8.110 Grade To Daylight, Roadway Excavation 1 10-Sep-14 10-Sep-14

4M1804.LOC8.120 Shoulder Backing 1 11-Sep-14 11-Sep-14

4M1804.LOC8.130 Clearing & Grubbing, Install Marker 1 12-Sep-14 12-Sep-14

Location 9Location 9 4 15-Sep-14 18-Sep-14

4M1804.LOC9.100 Remove Culvert & Marker, 18" HDPE Corrugated, Concrete Backfill, Place HMA 1 15-Sep-14 15-Sep-14

4M1804.LOC9.110 Grade To Daylight, Roadway Excavation 1 16-Sep-14 16-Sep-14

4M1804.LOC9.120 Shoulder Backing 1 17-Sep-14 17-Sep-14

4M1804.LOC9.130 Clearing & Grubbing, Install Marker 1 18-Sep-14 18-Sep-14

Punch ListPunch List 2 19-Sep-14 22-Sep-14

4M1804.PUN.100 PunchList 2 19-Sep-14 22-Sep-14

02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06

June 2014 July 2014 August 2014 September 2014 October 2014

Misc. Steel

Invert Paving

Cleaning & Inspect Of Culvert

12-Sep-14, Location 8

Remove Culvert & Marker, 18" HDP

Grade To Daylight, Roadway Excavation

Shoulder Backing

Clearing & Grubbing, Install Marker

18-Sep-14, Location 9

Remove Culvert & Marker, 1

Grade To Daylight, Roadwa

Shoulder Backing

Clearing & Grubbing, Install Marker

22-Sep-14, Punch List

PunchList

03-4M1804 - Culvert Rehabilitation In Glenn County 26-Jun-14 23:18

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

Page 2 of 2 CPM Schedule Provided By: Pushpa Services