Pearl GTL Project
LINDE ENGINEERING
Contractor Project No : 5887 Shell Project No: HP-3000-QAT
Project Document Number: T- 4.234.070 Project Rev.: C Page 2 of 17
Purchase Order Number: 2MH127
N/A Tag/Item Number(s):
ASU Unit(s):
Z PCWBS:
-
QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION
G C 28.01.08 Ready For Construction SB UA MC/ZG RFC
MC F B 27.11.07 Company Comments Incorporated IU UA/IO CCI
IO E A 07.11.07 Company Comments Incorporated MC ZG CCI
IO MC ZG D O 10.09.07 Issued For Company Comments ICC
IO MC ZG C O 16.09.07 Issued For Company Comments ICC
IO MC ZG B 19.07.07 Issued For Review IFR
MC A 19.07.07 Issued For Internal Review IO ZG IIR Approved
By GAMA Project
Rev Rev. Date Description Prepared
By Checked
By Status
No. No. ORIGINATOR
Document Title:
LINDEGINEERING AG
METHOD STATEMENT FOR CONSTRUCTION OF TEMPORARY ROADS
Document No.
GAM MTS CIV GTL 004 G LOC470
Contractor
Gama Qatar Co. W. L. L. Org.
Code Doc. Type
Disc. Code
Geogr. Area
Seq. No
Rev. No Vendor Code
Project Document Number: T-4.234.070 Rev No: C
-
Doc. Title : GAM-MTS-CIV-GTL-004 Rev. G Method Statement for Temporary Roads
Date : 27.01.2008
T-4.234.070 Rev. C Page 4 of 17
QQQ AAA TTT AAA RRR
TABLE OF CONTENTS
1. PURPOSE_____________________________________________________________________5 2. SCOPE________________________________________________________________________5 3. HSSE _________________________________________________________________________5 4. REFERENCES _________________________________________________________________6 5. DEFINITIONS __________________________________________________________________6 6. EQUIPMENT___________________________________________________________________7 7. MANPOWER __________________________________________________________________7 8. RESPONSIBILITY ______________________________________________________________8
8.1. SITE MANAGER__________________________________________________________________8 8.2. CIVIL WORKS MANAGER ________________________________________________________8 8.3. QA/QC MANAGEMENT ___________________________________________________________8 8.4. HSSE MANAGER _________________________________________________________________8 8.5. SITE ENGINEER/SUPERVISOR ____________________________________________________8
9. METHOD OF EXECUTION ______________________________________________________9 9.1. PRE-COMMENCEMENT WORKS __________________________________________________9 9.2. CONSTRUCTION OF TEMPORARY ROADS________________________________________10
10. QUALITY ASSURANCE______________________________________________________11 11. ATTACHMENTS ____________________________________________________________12
11.1. JOB SAFETY ANALYSIS _______________________________________________________12 11.2. SUB-BASE MATERIAL AND COMPACTION CRITERIA ___________________________12
-
Doc. Title : GAM-MTS-CIV-GTL-004 Rev. G Method Statement for Temporary Roads
Date : 27.01.2008
T-4.234.070 Rev. C Page 5 of 17
QQQ AAA TTT AAA RRR
1. PURPOSE
The purpose of this method statement is to clarify the works to be carried out for the construction of Temporary Roads for the Pearl GTL Project Air Separation Unit Construction located inside the Ras Laffan Industrial City of the State of Qatar.
2. SCOPE
The scope of works covered in this document are the laying (fully or partial) and compaction of Sub-Base, and if required Sub-Grade, material to level for the construction of Temporary Roads in accordance with Section 3.8 of DEP 34.11.00.11-Gen. Temporary roads will coincide with Permanent Roads as much as feasible. Laying and compaction of Base Course as well as paving are beyond the scope of this document. Since the Temporary Roads will only be used as temporary access during the course of the works, Sub-Base may or may not be laid and compacted to its full height. After the design of the roads is completed, the compacted thickness will be checked and adjusted as per the final design prior to the construction of permanent roads.
3. HSSE
All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan Industrial City and international standards/codes, and Company and Contractor requirements and instructions. All personnel will go through Gama, Linde and Company Safety Induction courses as well as other trainings as identified by their supervisor. Please see Document Number GTL-GM-001-A-5635 for details. A Job Safety Analysis (JSA) specific for this work including a Risk Assessment, is prepared as per Gama procedure GTL-GM-001-A-5626 and is attached herein. Such JSA addresses the hazards associated with each task within the scope of this Method Statement and introduces the controls that will be implemented to reduce the associated risks to acceptable levels. The JSA will be used by the Site Supervisor as the basis of his TSTI / TSTO and his Toolbox Talks. All personnel will have PPE required for their specific tasks in addition to the minimum PPE (coveralls, safety goggles, safety shoes, high-visibility vests, gloves) at site at all times as required.
-
Doc. Title : GAM-MTS-CIV-GTL-004 Rev. G Method Statement for Temporary Roads
Date : 27.01.2008
T-4.234.070 Rev. C Page 6 of 17
QQQ AAA TTT AAA RRR
4. REFERENCES
Qatar Construction Standard T.4-095.955 Project HSSE Program Overall T.4-095.303 Project HSSE Construction Plan T.4-129.849 Permit to Work Procedure T-13.376.490 Project Specific Specification for Site Preparation
DEP 34.11.00.11 Site Preparation and Earthworks including Tank Foundations and Tank Farms
DEP 34.13.20.31 Roads Paving, Surfacing, Slope Protection and Fencing
T-13.376.352 Amendments and/or Supplements to Site Preparation and Earthworks including Tank Foundations and Tank Farms
T-4.234.144 QC Docs for Site Preparation and Earthworks T-4.234.074 Method Statement for Backfilling Works
Other relevant documents of RLIC, the Company and the Contractor will also be followed when applicable.
5. DEFINITIONS Company : QSGTL and/or its PMC (JK) Contractor : Linde Engineering AG Subcontractor or Gama : Gama Qatar Co. W.L.L. QCP : Quality Control Procedure QCR : Quality Control Record ITP : Inspection and Test Plan QA/QC : Quality Assurance / Quality Control RLIC or RLC : Ras Laffan Industrial City
-
Doc. Title : GAM-MTS-CIV-GTL-004 Rev. G Method Statement for Temporary Roads
Date : 27.01.2008
T-4.234.070 Rev. C Page 7 of 17
QQQ AAA TTT AAA RRR
6. EQUIPMENT
All equipment shall be inspected and approved by the Contractor and/or Company before attempting work on site and have valid certificates. A register of all machinery & equipment will be maintained and held available for inspection. Equipment will be visually checked prior to each major work and validity of inspection status will be verified. The equipment to be used for the execution of the works is summarized below. The below listed equipment will be used whenever and wherever required during the course of the works. Additional equipment may also be used if deemed necessary.
Survey equipment Dozers Excavators Motor Graders Wheel Loaders
Vibratory Rollers Dump trucks Water Bowser Jackhammers
7. MANPOWER
All personnel shall have been inducted and trained before attempting work on site and have valid certificates as required.
Site Engineer Foreman Survey Team (surveyor, survey helper) Operators
Drivers Helper Banksmen HSSE personnel
-
Doc. Title : GAM-MTS-CIV-GTL-004 Rev. G Method Statement for Temporary Roads
Date : 27.01.2008
T-4.234.070 Rev. C Page 8 of 17
QQQ AAA TTT AAA RRR
8. RESPONSIBILITY
8.1. SITE MANAGER
The Site Manager will provide inputs to the project execution plan to ensure that proper strategies & philosophies are implemented.
8.2. CIVIL WORKS MANAGER
The Civil Works manager is responsible for the overall management of the project construction team to ensure that safe and effective operations are conducted and properly documented.
8.3. QA/QC MANAGEMENT
QA/QC Department shall ensure quality compliance during all phases of the construction.
8.4. HSSE MANAGER
Responsible for the safety control works for all construction sites under the jurisdiction of his department, he will advise the execution teams regarding various kinds of safety policies, plans, etc. He will also be adviser and approver for the JSA.
8.5. SITE ENGINEER/SUPERVISOR
The site engineer/supervisor will perform the necessary studies and calculations and will supervise procedures. He will ensure that the work is being carried out effectively in accordance with the established Method Statements and JSA.
-
Doc. Title : GAM-MTS-CIV-GTL-004 Rev. G Method Statement for Temporary Roads
Date : 27.01.2008
T-4.234.070 Rev. C Page 9 of 17
QQQ AAA TTT AAA RRR
9. METHOD OF EXECUTION
The sequence of the works can be summarised as follows: Temporary will be done as per the procedure to be followed for concrete road and later converted to permanent road.
9.1. PRE-COMMENCEMENT WORKS
Before each activity the following must be taken into account. Work Permit
Company and Contractor requirements for Work Permits will be followed. All required permits will be obtained prior to the execution of the work. Traffic Management Plan
Works shall not interrupt any kind of vehicle traffic on any emergency access road. If to ensure smooth execution of the lifting works in an area a need for a temporary closure has been deemed necessary a road impact notice will be provided. However, no such diversion shall take place without prior written consent of the Contractor or the Company. Other requirement of RLIC, the Company or the Contractor regarding Traffic Management and Land Road Transportation will be followed. SECURING OF AREA OF INTEREST
A soft barrier will be erected on the outside of the area to be worked. Warning signs and lighting will be posted as required and where needed. The barricades and signs will be kept on site till the completion of the works. Although no night works are foreseen, proper lighting in line with Company and Contractor procedures will be provided for night works, if required. LOCATION OF UNDERGROUND STRUCTURES
Prior to the commencement of the works, a survey for the existing underground structures and facilities will be performed, if deemed necessary by the Contractor and/or the Company. The survey generally consists of three steps, one of which is the visual survey of the area done at the preparation stage. This will be followed by a survey with cable detectors and then a manual excavation of areas if it is deemed critical to relocate underground structures and cables.
MATERIAL The material to be used for the temporary roads will conform to the requirements for Type B material as required by Linde (please see attached specification for details) which will be compacted to 95% as per the Method Statement for Backfilling Works (T-4.234.074). Only material deemed suitable and approved by the Contractor and/or the Company will be used. Sampling and Testing will be carried out as per the QC Documents for Site Preparation and Earthworks (T-4.234.144) and Method Statement for backfilling Works (T-4.234.074).
-
Doc. Title : GAM-MTS-CIV-GTL-004 Rev. G Method Statement for Temporary Roads
Date : 27.01.2008
T-4.234.070 Rev. C Page 10 of 17
QQQ AAA TTT AAA RRR
Should any of the tested batches prove not compliant with the specifications, that batch will not be used and will be sent back to the quarry. Water used for compaction will be clean .The water will be tested for chemical analysis as per 10.6 of T-13-375-490. once a day/ source change. The tests will be performed by a 3rd party laboratory and/or under the supervision of a 3rd Party specialist, if required by the Company and/or the Contractor. TRIALS
Prior to the commencement of actual works, a trial will be carried out on a 15-m strip of the actual works to verify the efficiency of the compaction method. The location for such trial will be decided on site; however, it should be chosen such that, the section will form a part of the actual works, if successful.
9.2. CONSTRUCTION OF TEMPORARY ROADS
Temporary Roads will be constructed in accordance with DEP 34.11.00.11-Gen Section 3.8. The construction of the temporary roads can be summarized as laying the sub-base of permanent roads and compacting properly. The actual construction works consists basically of the following steps:
REMOVAL OF SOIL After the Surveying works and marking of the area, the soil overlaying the rock will be stripped using a Dozer or an Excavator until up to 250-mm depth. EXCAVATION OF ROCK
Normally, rock will not be excavated unless necessary for the laying and compaction of the sub-base material. However, if needed, it will be carried out as per Method Statement for Excavation (T-4.234.069).150 mm depth will be stripped and compacted with Type-B material. LAYING OF SUB-GRADE AND/OR SUB-BASE MATERIAL
Although not foreseen, it may be required to lay sub-grade material underneath the Sub-Base. Should this be the case, Sub-Grade will be laid and compacted as per Roads Paving, Surfacing, Slope Protection and Fencing (DEP 34.13.20.31) and its Amendments and/or Supplements (T-13.376.352). The approved Type B sub-base material will be laid with a Grader in layers not exceeding 300-mm in loose depth (to achieve 250-mm compacted depth) and will be soaked with water. Dozers will be used to bring the material close to the Optimum Moisture Content for better compaction.
-
Doc. Title : GAM-MTS-CIV-GTL-004 Rev. G Method Statement for Temporary Roads
Date : 27.01.2008
T-4.234.070 Rev. C Page 11 of 17
QQQ AAA TTT AAA RRR
COMPACTION AND TESTING The material will then be compacted by Vibratory Rollers up to 95% of Maximum Dry Density. One Field Density Test as per ASTM D1556 or D2922 (together with Moisture Content Test as per ASTM D2216 or D3017) will be performed for each 750 m2 of compacted fill. Should any of the Field Density tests prove insufficient compaction, that section will be re-compacted, re-soaked if necessary, and re-tested until it satisfies project requirements. As an alternative, Nuclear Density Probe Testing method may be used for compaction tests. However, should this be the case, all relevant procedures and specifications regarding the operation and storage of Nuclear Devices will be followed where applicable. The tests will be done by an independent Third Party and/or under the supervision of an independent specialist. STOCKING OF SOIL
Excavated top soil and natural soil will be stored in an area within the site, which will be designated by the Contractor and approved by the Company for future use. The maximum height of stock pile will be 3.00 M with slope. This material can be used as filling or backfilling material provided that it satisfies the conditions of the project specification for the same. Bank of stockpile shall be made as per the project specifications. No work will be done and no one will be allowed into the excavation area under the part where and when heavy machinery is working topside. DISPOSAL OF EXCAVATED MATERIAL
Excess material that will not be used onsite as backfill material or for the construction of the access roads on the construction site will be loaded on to Dump Trucks by backhoe/loaders and transported to a location within RLIC designated by the Contractor and approved by the Company and RLIC as per the Method Statement for Disposal of Excavated Material (T-4.234.071) and in line with Land Road Transport requirements of the project.
10. QUALITY ASSURANCE
A Quality Assurance System shall be operated conforming to related standards and procedures. Controls and checks shall be established and documented through T-4.234.573 (ITP for Earthwork ).
-
Doc. Title : GAM-MTS-CIV-GTL-004 Rev. G Method Statement for Temporary Roads
Date : 27.01.2008
T-4.234.070 Rev. C Page 12 of 17
QQQ AAA TTT AAA RRR
11. ATTACHMENTS
11.1. JOB SAFETY ANALYSIS
11.2. SUB-BASE MATERIAL AND COMPACTION CRITERIA
-
JOB SAFETY ANALYSIS FORM
Page No:
Job being analysed: Temporary Road WorksDepartment/Section doing JSA:HSSE & Construction
JSA Members: Job Performers:
Normal Approvals: Name Signature Date General job requirements / Common Personnal Protective Equipment.JSA by:
Curtis Wallace
Job Supervisor: 1. The following Personal Protective Equipment shall be worn while disposing excavated materials: Approved coveralls, safety glasses, safety helmet, safety shoes and gloves.
Additional Approvals (Determined by Job Supervisor in correlation with QSGTL/LINDE SHES Manager).Name Signature Date
Discipline Superindent(QSGTL/LINDE)SHES Representative(QSGTL/LINDE) SHES Representative(GAMA QATAR)OTHERS(List Below): 2.Permit To Work.
Approval required for hazardous work detailed in the QSGTL/LINDE work permit procedure.Changing conditions and emergency proceduresStop work. Switch of equipment.Supervisor directs personnel to nearest and safest muster point considering wind direction. Supervisor counts all employees. Missing employees are reported to to QSGTL/LINDE SHES Dept. When all clear is given check with QSGTL/LINDE SHES before returning to work.
QSGTL/LINDE EMERGENCY TELEPHONE NO. SHES MANAGER: 680 9103QSGTL HOT LINE :
Note: 1) If any of the tasks involves biological, physical or chemical hazards, then The QSGTL/LINDE Industrial Hygienist must also approve the work. 2)Use additional sheets as necessary. 3)Details on safety (PPE,Hazard etc) and environmental requirements can be found in QSGTL/LINDE Safety and Environment Procedures.
NEW REVISED
QQQ AAA TTT AAA RRR
1
-
RISKRANK
1 1.1 Unauthorised entry. 1.1.1 Working area shall be barricaded and secure by watchman.
1 3 3 1.1.2 Safety sign board placed.1.1.3 Toolbox meeting.
1.2 Tire puncture 2 2 4 1.2.1 Daily checking the machine.1.3 Maintenance & Repair
inside. 2 2 41.3.1 Providing the maintenance area (not to
let any spillage).2 Material Handling. 2.1 Collision of equipment
4 3 122.1.1 Provision of sufficient banksmen for
working equipment. 1 3 3
2.1.2 Carrying out the all traffic regulations.2.1.3 Safe access shall be maintained at site
for vehicles and equipment.2.2 Injuries due to collisions. 1 4 4 2.2.1 Use of seatbelts by operators other appropriate PPE.
2.2.2 First Aid Team and nurse with clinic.2.3 Vehicle collision while
travelling. 2 3 62.3.1 Training for drivers about the traffic
regulations and speed limits.2.3.1.1 Driver competency check.
1 3 3
2.4 Rock falling down from 2 2 4 2.4.1 Dump trucks must be covered.2.4.2 Carrying out the all traffic regulations.
2.5 Speed. 2.5.1 Driver shall be trained.
3 3 9
2.5.2 Driver shall be paid for days they have worked, not for trips they have completed in attempt to prevent any rush.
1 3 3
2.5.3 Following all road and traffic regulations.
2.6 The dumptruck turn upside down.
2.6.1 Dumptrucks drivers must be ensure that their dump bodies are fully lowered before any movement.
3 3 9 2.6.2 Warning and training the driver on not be hurry. 1 3 3
2.6.3 A competent and experience supervision will be provided.
4 4.1 Heat Stress. 4.1.13 3 9 4.1.2 1 3 3
4.1.34.1.4
4.2 Back pain.
2 3 6
4.2.1 Employess shall use lifting techniques lift with legs not their backs. Get help when needed.
5.2.1.1 Cover manual handling in Daily Toolbox Talk.
1 3 3
4.2.2 Not allow to carry heavy loads or sample package.
R
JOB SAFETY ANALYSIS / RISK ASSESSMENT
ITEM
PREPARED BY REVIEWED BY- SHES MANAGER APPROVED BY-CONSTRUCTION MANAGER APPROVAL SIGNATURE/DATE
CONTROLSADDITIONAL
CONSEQUENCES
Others
2.6.1.1
2.6.1.2
SCOPE : Temporary Road Works
Initial Risk Residual RiskACTIVITY P C P C
Monitor the Heat Stress Index if exceeded greater than 50 degree Celcius then all work at elevation should stop.
5.1.1.1
HAZARD / POTENTIALCONTROLSCURRENT
Dumping will be done on a level ground surface.Do not run truck while dump box is in dumping position.
Before start the work
Driver competency check.All drivers shall have valid Qatari driving licenses, all operators shall have 3rd party certifications.
Driver competency check.All drivers shall have valid Qatari driving licenses, all operators shall have 3rd party certifications.
2.5.1.12.5.1.2
2.1.1.12.1.1.2
QQQ AAA TTT AAA RRR
2
-
Temporary roads 28.01.2008.pdfTemporary roads 28.01.2008.pdf Work Permit Traffic Management Plan SECURING OF AREA OF INTEREST LOCATION OF UNDERGROUND STRUCTURES MATERIAL TRIALS REMOVAL OF SOIL EXCAVATION OF ROCK LAYING OF SUB-GRADE AND/OR SUB-BASE MATERIAL COMPACTION AND TESTING STOCKING OF SOIL DISPOSAL OF EXCAVATED MATERIAL
JSA Temporary Road works.pdfCOVER PAGE
JSA Temporary Road works 1.pdf
Copy of GAMAC-0100-C-PC 1003_T-4.234.070_B.pdf