0 - TRTF-um.ba l k.1110.eng.docx)
Transcript of 0 - TRTF-um.ba l k.1110.eng.docx)
��������� � � �
����������� ������������
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
� �
�
�
��
�
� � � � � �
����������������
�
���� �������������
�
Contents
Introduction Technical Drawings 1 Construction Materials Concrete 9 Isolation 11 Formwork Protective Oil 11 Formwork Separator Oil 11 Crane 12 Lifting Equipments Assembly Device 13 Lifting Triangle 13 Tools and Consumables For Tunnel Formwork Crew 14 For Rebar Crew 15 For Concreting Crew 15 Before Arrival of MESA-Supervisor 16
Assembly Preperation for Assembly Assembly Area 17 Crew for Assembly 18 Assembly of Tunnel Formwork Set Connection of Deck Panels 19 Connection of Lifting Beam 20 Connection of Inside Panels 21 Connection of Inclined Props 22 Connection of Inside and Deck Panels 23 Connection of Wheeled Prop and Wheeled Prop Support 24 Connection of Back Panel 25 Upholding the Tunnel Formwork Set 26 Assembly of Stop-ends 27 Assembly of Boxouts 28 Assembly of Outside Wallform Set Connection of Working Platform and Guardrails 29 Connection of Panel Supports and Ladder 30 Connection of Outside Wallforms 31 Upholding the Outside Wallform Set 32
Operation Preperation for Operation Before Starting the Operation 33 Crew for Operation 33 Alignment of Tunnel Formworks 33 Preperation of Foundation 35 Cleaning and Oiling of Formworks 38 Marking the Boxouts and Stopends 38 Daily Cycle Time Schedule 39 Striking 41 Formwork Setting 52 Concreting 68 Non-Standard Applications 72
�������
TRTF-Classic Tunnel Form System �������������� �������������������������������������www.mesaimalat.com.tr�
General Remarks Safety Remarks
• This “User Manual” contains information about MESA-Formwork & Scaffolding systems. It describes setting up, utilisation, correction, maintenance and loading data of these products and systems, by helping to the site as a ‘Method Statement’.
• MESA products could only be used according to the Instruction or User Manuals, any Technical Details given in Documents provided by MESA.
• Due to avoid unwanted results such as accidents and damage to health or material damages, Owners and Users of MESA products or Systems should comply the directions given by the documents and data explained above.
• In the cases which require different deviations from these manuals, Owner or User of MESA products or systems must check the evidence of the technical solutions or supplementary instruction methods and procure revised static or dynamic calculations to MESA.
• Although these User Manual have to be read before installation or any usage; in order to provide all requirements of safety on site, user should take necessary precautions according to the international safety regulations and local safety rules.
• Schematic illustrations on this manual give only basic rules to be applied during assembly, erection and dismantling, therefore it not complete from the safety point of view.
• User should inspect and check the products and systems before use. Materials not having suitable conditions such as damaging and weakening due to rust, corrosion or wear, should be removed and reported to MESA immediately.
• Since combination of any material and component originated from other manufacturers with MESA products may be dangerous for health and property, they must not be combined with MESA products. In such a case, customer should contact with MESA.
• Only the skilled persons educated according to official documents of MESA are authorised to assemble, erect and dismantle of MESA products and systems.
• Users working with MESA products and systems should read, understand and accept the information included in this manual. Otherwise, they should be trained by the customer according to MESA documentation.�
• During all set up procedure, loads must be safely transferred. • During all construction phases, all components and units must be safely stabilised. • According to the formwork system choosen, admissible fresh concrete pressure must not be exceeded. Such a case will cause to formwork overload and more deflection both on formwork and concrete, even breakage and overload on tie-rods. Maximum working load of tie-rods used must be checked. • Person who works on the system in all phases (i.e. setting up, erection, concreting, dismantling and disassembly etc.) should be assure to have enough and safe workplace. • The formwork removal must be done after the concrete has reached sufficient strength. • Formwork removal must be done by using lever arms or other tools provided together with the formwork system but not the crane or any other devices which will cause unwanted results. • In order to keep the scaffolding, platform, formwork or other parts stable and safe, user should check the conditions where the procedure occurs during the formwork removal procedure.
• Any small parts used in the system should be fixed in their place to avoid loosing or falling freely. • All connecting parts must be used properly to provide correct functioning of them. Selecting of wrong part could cause leakage of the relevant products under loading. • All connections must be checked periodically. Especially bolt and nut connections and pin connections should be controlled.
• Enough number of Fire Extinguishers and any other necessary items against danger of fire should be kept available where the formwork and scaffolding systems need.
�
�������
TRTF-Classic Tunnel Form System �������������� �������������������������������������www.mesaimalat.com.tr�
� Instruction or User Manuals must be used while Formwork assemblies, accessory attachements and concrete casting. � It is not allowed to use hummer, sledgehummer, cranka and vs that cause physical demage on Formworks, and also applications of extra welding, cutting and drilling without permission of authorities. � It is not allowed to exceed the Max Concrete Pressure described in Technical or User Manuals. � Formwork should be used between + 40 °C and – 30 °C. � Formworks should be cleaned after each application to remove the concrete residues and active faces should be lubricated with suitable concrete/metal seperation oil. � After 250 applications, maintenance should be done at site. � This maintenance covers the flatning of active surface, repainting, welding and rust control. � After 500 applications, maintenance should be done at work shop where the necessary equipments exist. � During the storage period, all active surfaces should be lubricated with suitable oil to prevent rusting. � Stock area should be closed area; if it is not possible, formworks and accessories should be stocked in open areas by covering them with water resistant materials. � Maitenance procedure should be repeated for each 250 usages after first 500 usages are exceeded. ��
� Electrical power supply and connections must be suitable as written in the ınstruction or User Manuals given by MESA.
Operational Conditions
Warranty Period�
� Limited Warranty for two (2) years is promissed by Mesa �malat San.ve Tic. A.�. for Steel Face Formworks and Slab Formworks unless the Operational Conditions described above are violated. � This warranty covers defects of steel material, welding and painting. � For Hydraulic Cylinders and Hydraulic Power Units, the limited warranty period is one (1) year.
Service Life
� Steel Face Formworks and Slab Formworks, produced by Mesa �MALAT San.ve Tic.A.�., is good for 500 concrete castings unless The Operational Conditions described below are violated.
• This Booklet is the complementary of “Technical Manual” prepared for MESA-TRTF Classic Tunnel Formwork System and all information written on these two booklets should be considered together. • Users who will work with MESA-TRTF Classic Tunnel Formwork System and all types of MESA Platform and Scaffolding Systems should be educated and informed by skilled MESA personel.
• MESA will issue a “OPERATION CERTIFICATE” to persons that have undergone required training.
• If a person who do not have this “OPERATION CERTIFICATE”, he/she could not use MESA-TRTF Classic Tunnel Formwork System and all types of MESA Platform and Scaffolding Systems.
�������
TRTF-Classic Tunnel Form System �������������� �������������������������������������www.mesaimalat.com.tr�
Information
Important Note
Sight-Check
Warning
Symbols Used�
� Mesa Imalat reserves the right to make technical changes in the interests of progress.
© Copyright by MESA Imalat San. ve Tic A.S.-Ankara-Turkey
��� ����� � Technical Drawings
TRTF – Classic Tunnel Form System 1
�������������� ����� �����������������������www.mesaimalat.com.tr�
Formwork Layouts
TECHNICAL DRAWINGS�
o Setting Plan of Tunnel Formworks
o Assembly Codes and Tie-Rod Positions
o Setting Plan of Kicker Forms
o Setting Plan of Slab and Wall Stopends
o Setting Plan of Lifting Beams
o Setting Plan of Slab Boxouts
o Setting Plan of Platforms
o Assembly Charts of Tunnel Formworks
Setting Plan of Tunnel Formworks
Formwork Layouts prepared by MESA includes the following information ;
B C D E F G H I J
2
3
4
56
7
2
3
4
56
7
B C D E F G H I J
KN1=11
50
KN1=1150
Tunnel Number
Stripping Direction
Formwork Dimensions
Slab Stopend
Wall Stopend
Back Panel
Outside Wallform
��� ����� � Technical Drawings
TRTF – Classic Tunnel Form System 2
�������������� ����� �����������������������www.mesaimalat.com.tr�
Assembly Codes and Tie-rod Positions�
Assembly Code of Deck Panel
Assembly Code of Back Panel
Assembly Code of Inside Panel
Position of Tie-Rod and Cone
Assembly Code of Outside Panel
Detail A
Detail A
��� ����� � Technical Drawings
TRTF – Classic Tunnel Form System 3
�������������� ����� �����������������������www.mesaimalat.com.tr�
Setting Plan of Kicker Forms�
AUAUAU AU
Assembly Code of Straight Kicker Form
Assembly Code of Inner Kicker Form�
Assembly Code of Corner Kicker Form�
Detail A
Detail A
��� ����� � Technical Drawings
TRTF – Classic Tunnel Form System 4
�������������� ����� �����������������������www.mesaimalat.com.tr�
Setting Plan of Slab and Wall Stopends�
PB
PB
PB
PB
PB
PB
PB
PB
PB
PB
PB
PB
PB
PB
PB
PB
PB
PB
PB
Assembly Code of Wall Stop-end
Assembly Code of Slab Stop-end
Detail A
Detail A
��� ����� � Technical Drawings
TRTF – Classic Tunnel Form System 5
�������������� ����� �����������������������www.mesaimalat.com.tr�
Setting Plan of Lifting Beams�
Assembly Code of Lifting Beam
Rough Position of Lifting Beam
Detail A
Detail A
��� ����� � Technical Drawings
TRTF – Classic Tunnel Form System 6
�������������� ����� �����������������������www.mesaimalat.com.tr�
Setting Plan of Slab Boxouts�
Wall Boxout
Position of Wall Boxout
Slab Boxout
Detail A
Detail A
��� ����� � Technical Drawings
TRTF – Classic Tunnel Form System 7
�������������� ����� �����������������������www.mesaimalat.com.tr�
S2 S2
1A1A
F2
1C1C
DT2L
DT
1
1B
F1
1B1B
1C
E
Z
FREL
2
3
4
56
7
B C D E F G H I J
+3.14 KOTU DÖ�EMES� +3.14 KOTU DÖ�EMES�
1
1 1
FL
F1
1B
1C
ER
1A 1A
F2
1
1
1
1
11
B C D E F G H I J
2
3
4
56
7
DT2R
DT
1
1
1
E
Z
1
S2
DT2L
1B
E
Z
1
1
1
Setting Plan of Platforms�
Assembly Code of Landing Platform
Assembly Code of Gable-end Frame
Assembly Code of Stripping Platform
Detail A
Detail A
��� ����� � Technical Drawings
TRTF – Classic Tunnel Form System 8
�������������� ����� �����������������������www.mesaimalat.com.tr�
28
19505093
444
28
R6
Y4
Y4
TB
TB
1950
2583
565 571 543 5502064 2107 2152 2192
1719 1745 1773 1799
TUNNEL
ASSEMBLY CODE of LIFTING BEAM
ASSEMBLY CODE of WHEELED PROP SUPPORT
ASSEMBLY CODE of INCLINED PROP
TUNNEL LENGHT (mm)TUNNEL WIDTH (mm)
MESA �MALAT SANAY�� VE T�CARET A�.Atatürk mah.Kayı cad.No:92/A,Yenikent 06378 ANKARA / TÜRK�YE
Tel : +90.312.277 33 00(pbx) - Fax : +90.312.277 37 00 (pbx)[email protected] www.mesaimalat.com-
SLAB AND WALL STOPEND
WITHWALL STOPEND
WITHSLAB STOPEND
WITHWALL STOPEND
WITHOUT
TUNNEL WEIGHT (kg)
TO VERTICAL PANEL (mm)
TO END OF TUNNEL (mm)
POSITION of LIFTING HOLECENTER OF GRAVITYTUNNEL NO :
Assembly Charts of Tunnel Formworks
Weight
Position of Lifting Hole
Tunnel Dimensions
Assembly Code of Main Connectors�
Tunnel Number
Assembly Code of Deck Panel
Assembly Code of Back Panel�
Assembly Code of Inside Panel�
��� ����� � Construction Materials
TRTF – Classic Tunnel Form System 9
�������������� ����� �����������������������www.mesaimalat.com.tr�
As described in the booklet “TRTF-
Technical Manual”, hydrostatic pressure of
concrete applied on Panels should not be
greater then 63 kN/m2.
Concrete�
CONSTRUCTION MATERIALS�
For earthquake zones, concrete and rebar
required for construction are as follows;
o Concrete : 0.34 – 0.45 m3/m2 in plan
o Rebar : 27 – 35 kg/m2 in plan
t� ; total time for end of setting of concrete
(= 5 h)
γγγγc ; density of fresh concrete (25 kN / m3)
σσσσhk,max ; max.pressure of fresh concrete (kN/m2)
v ; the rate of concrete placing (m/h)
hs ; the height of hydrostatic pressure (m)
K 1 ; consistency factor
The table shows the rate of
concrete placing for TRTF–
Classic Tunnel Formwork
System, according to the
maximum allowable
hydrostatic pressure (63
kN/m2) ;
Rate of Placing of Concrete
Concrete Consumption
Fresh Concrete Pressure for � hk,max = 63 kN/m2
� hk,max (kN/m2) v (m/h)
F1 Solid (5 � v + 21) � K 1 � 25 8.40
F2 Semi-solid (10 � v + 19) � K 1 � 25 4.40
F3 Rigid (14 � v + 18) � K 1 � 25 3.21
F4 Plastic (17 � v + 17) � K 1 � 25 2.71
F5 Soft (30 � v + 25) � K 1 � 30 1.27
F6 Fluid (38 � v + 25) � K 1 � 30 1.00
SVB Self-Compacting (33 � v + 25) � K 1 � 30 1.15
Class of Consistency
��� ����� � Construction Materials
TRTF – Classic Tunnel Form System 10
�������������� ����� �����������������������www.mesaimalat.com.tr�
Heating capacitiesof LPG-Heater and Radiant Burner are 15,000
and 28,500 kcal/hour respectively. �
Take 1 set of LPG-Heater � 30 m3 and 1 set of Radiant Burner � 60 m3.
For heating a 100 m3 room; 100 / 30 = 3.3 � 4 LPG-Heaters or 100 / 60 = 1.7 � 2 Radiant-Burners are required.�
��������������� ����������������������� �������
Refer to technical features of other types of Heaters or Burners
given by their own Manufacturers.�
�
Heating of the Concrete
As a rule;
The temperature should not be
greater than 80°C.
Economically, heating the full tunnel
space between 50°C and 70°C will be
sufficient.
The rate of increase in temperature
should not exceed 20 °C per hour. Otherwise,
rapid water-loss before the concrete setting
could be possible.
Water-loss reduces the concrete
strength (10% water loss cause 40% concrete
strength loss).
To avoid a rapid loss of water by
evaporation during the heating of the
concrete, the slab covered with an
appropriate insulation sheet.
As shown in the graph;
0% content of water refers to 100% of
strength of concrete that means of no loss on
the strength.
����
���
��
���
�����
�� �������� �������������
������ ���
� �� ���������
��� ����� � Construction Materials
TRTF – Classic Tunnel Form System 11
�������������� ����� �����������������������www.mesaimalat.com.tr�
By adding 20% crude oil to grease as a diluting agent, it
could be used as protective material for short period of
time under 3 months.
Protection period of the selected oil should be at least; 6-9 months (for outdoor) 12-18 months (for indoor)
Approximately 1 litre of separation oil could be used on
25-40 m2 of formwork area according to the oil type
choosen.
In considerably low temperatures, double layer sandwich type Tunnel Curtain should be used. In that case, the top of the slab is also need to be insulated with proper covering materials. �
Formwork Protective Oil
Formwork Separator Oil
Formwork protective oil should be rust
preventive and should possess good water
displacement property.
Product codes of oils frequently preferred
for protection of the concrete surfaces of panels
are as follows;
Castrol Rustilo DWX 32
Mobilarma 798
Table gives the optimum characteristics of a formwork
protective oil (example is extracted from Castrol Rustilo DWX 32).
Formwork separation oil should provide
easy release of the formwork from the concrete,
long formwork life, decreasing on air-bubbles on
the concrete surface. Concrete surface should be
clean and smooth.
Product codes of oils frequently preferred
for separation of the concrete surfaces from panels
are as follows;
YKS-Yapol
SIKA-Separol S3
����� ������������
����� ����
������ ������� ������
����!�"���� 40°��#���#�#
��$� �%����&�' ()���#�����
���#�*!� �����%����&�' )���#� ���
���#��������%����&�' ���� #�#�
���� �*�#������+��%���,�-����$�������' ���#���
.����.���*���%�.*/�01��2' �2(�!����%����&�'
����� /���������
����� 3���4����5� �����6���
������ ������ ������
"7�$��� (12
����!�"���� �$�,�°�
Table gives the optimum characteristics of a formwork
separation oil (example is extracted from YKS-Yapol).
Isolation
Insulating material (Tunnel Curtain) covering the open ends of
the tunnel formworks are made from plastic based material having a
grade of ll00 dny.
��� ����� � Construction Materials
TRTF – Classic Tunnel Form System 12
�������������� ����� �����������������������www.mesaimalat.com.tr�
Generally, a Tower Crane whose loading capacity is about 2,000 kg. at 45-50 metres of jib-length would be sufficient.
�
Location of the crane should allow to lifting and stripping operations of tunnel formworks and other equipments partaking on the construction area.
Max.Wind Speed for safe operating conditions should be taken as 40 km/h.
Refer to the operating conditions for cranes given by its manufacturer.
�
Crane
Since TRTF-Classic Tunnel Formwork System is
crane dependent, determination of type and capacity of
the crane is very important.
During assembly and operation, tunnel
formworks, outside wallforms, stripping and landing
platforms, gable end frames, kicker forms, stopends and
boxouts are lifted and transferred by crane.
Crane Type
During the assembly, the crane
must be on service for 2-4 hours per day.
Daily time schedule of the crane should
be determined in order to plan and
organize the assembly precedure.
Crane could be mobile or telescopic type or a
tower crane. In order to determine the crane type, below
parameters are taken into consideration;
o Site plan
Positions of the buildings to be constructed by
tunnel formwork system will affect the type of the
crane.
o Site conditions
Geographic condition of the whole area is an
important factor directing the determination of
type of crane.
o Type of the buildings
Size and shape of the building in plan directly
determine the type and capacitiy of the crane as
well as the height or the number of levels.
o Climatic and meteorological conditions
Comperatively low or high temperature, wind,
rain and snow will affect the capacity and type of
the crane to be selected also.
Time Schedule
Crane Capacity
The heaviest of the load at the farthest location
will determine the required capacity.
In order to identify the critical load;
o Set the Position of the crane on tunnel formwork
layout
o Draw the range of the crane
o Evaluate the weight of tunnel formwork at the
farthest location
����� ����� ������� ������
� ����� ����!�
"� ����#������
� ����� ����!�
����� ��#��������� ����� ����� $�����
#�%����� ���
��� ����� � Lifting Equipments
TRTF – Classic Tunnel Form System 13
�������������� ����� �����������������������www.mesaimalat.com.tr�
Assembly Device cannot be used for lifting and carrying the Tunnel Formwork.
Allowable working load to be applied on the Assembly Device is 1,000 kg.
�
Max. Load = 1,000 kg.
�����������
Max. Allowable Load = 4,000 kg. Before each lifting operation, ensure that the Wing Nut of the Lifting Triangle is fastened tightly. Ensure that the Tunnel Formworks are not pulled onto the Stripping Platform by using the Lifting Triangle. Avoid to apply only vertical forces to the Bearing Rod but not horizontal forces. Weekly check the Bearing Rod against any damage or fracture on the surface.�
LIFTING EQUIPMENTS�
Assembly Device
Lifting Triangle
This apparatus is supplied only to protect
the usage of Lifting Triangle out of purpose.
Such usage is generally realised during
the assembling of Tunnel Formworks.
����������������� Tunnel Formworks are set up onto their
positions by this apparatus so that it is installed at
the hook of the crane.
Maximum allowable load applied on the
Lifting Triangle is 4,000 kg. and maximum service
life of Lifting Triangle is 250 times.
Clean the Bearing Rod by using thinner or
diesel oil with a brush weekly.
It will be not allowed to crash or swing the
Tunnels during lifting operation.
All feedbacks about the Lifting Triangle
could be done by using the Serial Number written
on the product.
The Bearing rod must be removed and replaced with the new one
If;
� It is bended or wrapped. � It’s screws are corroded. � The service life of 250 times is
completed.
��� ����� � Tools and Consumables
TRTF – Classic Tunnel Form System 14
�������������� ����� �����������������������www.mesaimalat.com.tr�
For Tunnel Formwork Crew�
TOOLS and CONSUMABLES�
Wlding Electrode Rutile 3.25
Steel Wire Brush
Spiral Cutter Disk
Spiral Grinder Disk
Formwork Oil
Rubber Grease
Powder Coat
TOOLS given by MESA
Socket Wrench 13 (1/2)
Socket Wrench 14 (1/2)
Socket Wrench 19 (1/2)
Socket Wrench 22 (1/2)
Socket Wrench 24 (1/2)
Socket Wrench 27 (1/2)
Hexagon Key Wrench 14
Ratchet for Jack Ø38 (31K-20")
Ratchet 1/2" w/LOCK
Ratchet Arm 5" (1/2)
2-Ended Open Jaw Spanner 19-22
2-Ended Open Jaw Spanner 22-24
2-Ended Open Jaw Spanner 27-30
Punch Ø16
Punch Ø20
Punch Ø27
Punch Ø35
Hammer (1.5 kg)
Magnetic Plumb
Chalk Line
Steel Tape (5 metre)
Metal Marker
Deck Panel Wrench
Back Panel Wrench
Punch to Remove Cones
Punch to Remove Dilatation Cones
Spatula
Lever
TOOLS to be provided by SITE
Welding Machine 400 A
Grinding Machine
Hand Drill
Club Hammer 5 kg
Ladder 200 cm.
Adze
Screw Driver
Plier
Welding Equipments (Holder,Mask and Cable)
Oiling Swab
Main tools for assembly and operation already exist in the Tool-Box supplied by MESA. Content of this Tool-Box are
listed in the section of “Complementary Equipments” on the Buuklet of “Technical Manual” given by MESA.
Additionaly, table at right shows the extra tools to be needed. These tools will be supplied by Site.
Tools
Consumables
��� ����� � Tools and Consumables
TRTF – Classic Tunnel Form System 15
�������������� ����� �����������������������www.mesaimalat.com.tr�
For Concreting Crew�
For Rebar Crew�
Miscellaneous Tools
Converet w/2-output
Needle Vibrator
Needle Vibrator
Trowel
Wheelbarrow
Hoe
Protective Glove
Rubber Glove
Protective Boiler Suit
Boiler Suit
Safety Clothes (Raincoat, Helmet vs.)
Single-Sling with Hook 100 cm. 16 mm.
Quatro-Sling with Hook 400 cm. 14 mm.
Chain Sling 12 mm.
Eye Bolt for Chain Sling 12 mm.
Extension Cord 380 V.
Extension Cord 220 V.
Miscellaneous Wall Box
Roller type Extension Cord 380-220 V
Wood Power Saw
Oxygen Cutting (Set)
Rotary Hammer Drill
LPG
Tie Wire
Concrete Cover for wall 8-14/20
Concrete Cover for slab Round
Lateral Reinforcement Lever
Iron-bending Wrench 14 mm.
Iron-bending Wrench 16 mm.
Iron-bending Wrench 18 mm.
Iron Cutter 75 cm.
Cutting Pliers 280 mm.
Wire Mesh-bending Wrench 3 mt.
Tools
Consumables
Tools
Consumables
��� ����� � Before Arrival of MESA-Supervisor
TRTF – Classic Tunnel Form System 16
�������������� ����� �����������������������www.mesaimalat.com.tr�
Check all drawings, plans and details for formwork application and ensure that they were prepared and revised according to the valid statical construction drawings.�
Maximum weight of the packages is approximately 2,500 kg.
Pallets and packages supplied by MESA should not be opened until arrival of MESA-Supervisor.
It is requested to place the request for technical assistance at least two weeks before the desired date.
The surface of the panels and other surfaces which are facing concrete are coated with a thin film of protective oil. It will be removed by using a solvent before concreting.
BEFORE ARRIVAL of MESA-SUPERVISOR�
MESA will give all necessary drawings for both
assembly and operation purposes. These are listed in the
section of “Technical Drawings” of this booklet.
Make ready the drawings of sanitary installation
and electric conduits which will be necessary during
Tunnel Formwork application. Boxouts required for these
installation will be fixed on formworks.
Drawings, Layouts and Details
Materials and Equipments
Site Conditions
In order to get the maximum benefit from the period of assistance and instruction, one must avoid time losses caused by
late preparation of necessary arguments explained below.
Check all of the materials and quantities
comparing with the documents supplied by MESA.
Debar all materials from any exterior damages
caused by climatic conditions, steal or any other
influences.
Make ready the required tools and equipments
which are necessary for assembling precedure.
Prepare the assembly area as described in the
section of “Preperation for Assembly” of this booklet.
Make ready the crane to be needed for assembly.
Clarify and prepare the assembly crew.
�������� Preperation for Assembly
TRTF – Classic Tunnel Form System 17
�������������� ����� �����������������������www.mesaimalat.com.tr�
If the foundation is ready, all of the equipments could be placed directly to their own locations where they will be used for the first time.
Assembly Area should not be out of range of the crane.
Ensure that all requirements explained in the Section of “Before Arrival of MESA-Supervisor” on this Booklet are provided.
Do not stack too many packages onto each other.
�
If the material will remain in the stack area for a relatively long period of time, it is advised that to protect the formworks from bad weather conditions.
Assembly of Gable end-frames, Stripping and Landing Platforms given wtih the Set of TRTF-Tunnel Formwork System are described in relevant Booklets given by MESA.
PREPERATION for ASSEMBLY �
Assembly Area
��������
�����������������
��� ������������!���������
�����������������
"���� �#�"����
Size of the Assembly Area should be 300 m2 at
least, leaving 2/3 of this as empty for working and the rest
for stacking the material.
The stacks should be separated from each other,
each stack containing only one type of material like
panels, platforms, accessory boxes, timber for platforms,
etc.
The assembly area should be located close to
the foundation or slab where the forms will be used for the
first time.
The ground should be relatively smooth and be
on level.
Use timber blocks between the packages in
order to avoid dents and scratches.
Figure below shows the typical assembly area.
�������� Preperation for Assembly
TRTF – Classic Tunnel Form System 18
�������������� ����� �����������������������www.mesaimalat.com.tr�
ASSEMBLY CREW
5-6 persons for assembling of - Tunnel Formworks, - Outside Wallforms - Stripping Platforms - Gable end Frames and - Landing Platforms
3-4 persons for assembling of - Timbers on Platforms - First Kicker Forms on their locations
�
All of the persons in the Assembly Crew should have been educated on necessary safety regulations.
Crew for Assembly
It is recommended that the Crew who will work
on the operation of Tunnel Formwork should work on
assembling procedure also. This will increase the
motivation and efficiency of those while working on
Tunnel Formwork operations.
In the leadership of Mesa-Supervisor, a crew
consisted of 8-10 persons totally will be sufficient for all
assembling period.
�������� Assembly of Tunnel Formwork Set
TRTF – Classic Tunnel Form System 19
�������������� ����� �����������������������www.mesaimalat.com.tr�
Assembly of Tunnel Formwork will be realised with the connection components described and listed on the Section of “Permanent Connections” on the Booklet “TRTF-Technical Manual” given by MESA.
Before starting the assembly procedure, ensure that all connectors and necessary equipments are provided.
Ensure that all safety precautions were taken properly on site.
Use Tunnel Assembly Charts given by MESA in order to check the Assembly codes of Panels and other components with the number of Tunnel which will be set off with these elements.
There must be one free hole between each U Alignment-45.
There should be M14x80 bolts&nuts at the holes on the foremost positions of both ends of the UPF profile as shown in details “a” and “b”.
Ensure that there is no any difference at junction points of two Panels.
Connections realised by using Bolt& Nut sets will require at least two washers having proper sizes.
ASSEMBLY of TUNNEL FORMWORK SET�
Locate Deck Panel on two timbers so that the
steel surface is below as shown in the figure.
Connect U Alignments-45 with M14x30 bolt&nut
to the edge from which the other Deck Panel will be
connected.
Connection of Deck Panels
Close the second Deck Panel to the first and
insert U Alignments-45 previously installed to the first
panel into the UPF profile of the second panel.
Match the holes on both panels and connect
them with M14x80 bolt&nuts through free holes on the first
panel.
Detail b Detail a
Drill the Lifting Hole of the Tunnel in accordance
with the dimensions given in the Tunnel Assembly Chart.
$�"��������%&'�
��������(���)*+,��-�
�������� Assembly of Tunnel Formwork Set
TRTF – Classic Tunnel Form System 20
�������������� ����� �����������������������www.mesaimalat.com.tr�
Ensure that Lifting hole of the Tunnel (Ø35mm) was drilled on Deck Panel properly.
�
Check the assembly code of the Lifting Beam by comparing it with the code written in Tunnel Assembly Chart.
Connection of Lifting Beam�
a
Locate the Lifting Beam on Deck Panel at the
same line of the lifting hole previously drilled.
By using M6x160 bolt&nut, install the Lifting
Beam to the Deck Panel through the Lifting Beam NPL
and Lifting Beam Socket.
�������������.���
Detail a
���������������/���
�������� Assembly of Tunnel Formwork Set
TRTF – Classic Tunnel Form System 21
�������������� ����� �����������������������www.mesaimalat.com.tr�
There must be one free hole between each U Alignment-45.
There should be M14x80 bolts&nuts at the holes on the foremost positions of both ends of the UPF profile as shown in details “a” and “b”.
Ensure that there is no any difference at junction points of two Panels.
Connection of Inside Panels�
Locate Inside Panel on two timbers so that the
steel surface is below as shown in the figure.
Close the second Inside Panel to the first and
insert U Alignments-45 previously installed to the first
panel into the UPF profile of the second panel.
Match the holes on both panels and connect
them with M14x80 bolt&nuts through free holes on the first
panel.
Connect U Alignments-45 with M14x30 bolt&nut
to the edge from which the other Inside Panel will be
connected.
Detail a
Detail b
$�"��������%&'�
�������� Assembly of Tunnel Formwork Set
TRTF – Classic Tunnel Form System 22
�������������� ����� �����������������������www.mesaimalat.com.tr�
Ensure that the connected side of the Inclined Props are the side which has a screw and bearing boss.�
The standard adjustment of the screw should be 67 mm for standard Deck Panels.�
c
d Detail c
Detail d
Two pieces of U Alignment-89 are fitted to inner
surfaces of Mid Stiffeners of Inside Panels with 4 sets of
M14x80 bolt&nut as shown in “Detail c”.
One piece of U Alignment-109 is fitted to inner
surface of Undermost Stiffeners of Inside Panels with 2
sets of M14x30 bolt&nut as shown in “Detail d”.
$�"��������%,0�
!�������������
$������������������
$�"��������%120�
Connection of Inclined Props�
Detail a
a
67mm
Connect sufficient quantity of Inclined Props to
Inside Panels with M14x80 bolt&nut through the bearing
boss as shown in “Detail a”.
�������� Assembly of Tunnel Formwork Set
TRTF – Classic Tunnel Form System 23
�������������� ����� �����������������������www.mesaimalat.com.tr�
Use Wheeled Prop Slots on the Deck Panels to lift them.�
Use wooden wedge while hammering the Deck Panel. Otherwise, steel sheet on concrete surface would be damaged.
Ensure that the alignment is satisfied in both direction. Check the screw holes on Inside Panels and U Alignments-75 on Deck Panels are also be aligned.�
M14x80 bot&nut in connection of Inclined Prop and Deck Panel should not be tightened.
Alignment error on all junction points of Panels should not be allowed.
Connection of Inside and Deck Panels�
a
b
Detail b
Detail a Lift previously assembled
Deck Panel Set and drawn it up the
Inside Panel Set
Connect the uppermost heads
of Inclined Props to slots on Deck
Panels with M14x80 bolts&nuts as
shown in “Detail a”.
Insert U Alignments-65 which is welded at the inner face of U-
turn of Deck Panels into uppermost UPF profile of Inside Panels.
For being in alignment, hammer Deck Panels properly as
show in “Detail b”.
$�"��������%3'�
Fit the Inside Panels and Deck Panels through U-Alignments-
65 and tighten M14x50 bolts&nuts as shown in “Detail b”.
�������� Assembly of Tunnel Formwork Set
TRTF – Classic Tunnel Form System 24
�������������� ����� �����������������������www.mesaimalat.com.tr�
Ensure that; If the length of Tunnel is 2500, Wheeled Prop Support is connected to the relevant slot alone (Detail a). If the length of Tunnel is 1250, Wheeled Prop Support is connected to the relevant slot together with Inclined Prop also (Detail b).
Assembly codes and shapes of the Wheeled Prop Supports are different and they must not be confused with each other.
a
b
Detail a Detail b
L = 2500 mm
L = 1250 mm
e
Detail e
d
Detail d
Connection of Wheeled Prop and Wheeled Prop Support�
Connect Proper Wheeled Prop
Supports to the slots located on Inside
Panels with M14x80 bolt&nut as shown in
“Details a & b”.
c
Detail c
Loosely fit the Wheeled Prop to
the slots located on Deck Panels by using
M14x80 bolt&nut as shown in “Details c”.
Join the slots on Wheeled Prop
and Wheeled Prop Supports and loosely
fit the M18x150 bolt&nut as shown in
“Detail d”.
If this assembled Tunnel
Formwork Set will be located at the right
side according to the formwork layout ;
Insert Key Locks to the Key Lock Bolts
wlded on the edges of Deck Panels and
loosely fit them with M18 nuts & washers
as shown in “Detail e”.
For the Tunnel Formwork which
will be located at the left side on formwork
layout;
Insert only M18 nuts&washers to the Key
Lock Bolts welded on Deck Panels.
�������� Assembly of Tunnel Formwork Set
TRTF – Classic Tunnel Form System 25
�������������� ����� �����������������������www.mesaimalat.com.tr�
Provide the angle between Inside and Deck Panels as 90° before the installation of Back Panel.�
There must be one free hole between each U Alignment-45.
There should be M14x80 bolts&nuts at the holes on the foremost positions of both ends of the UPF profile at the corner as shown in “Corner Detail”.
Ensure that there is no any difference at junction points of three panels.
�
Installation of Back Panel Wheel to the Back Panel should be completed.
Use wooden wedge while hammering the Back Panel. Otherwise, steel sheet on concrete surface would be damaged.
Connection of Back Panel�
$�"���������%&'�
Connect U Alignments-45 with M14x30 bolt&nut
to the edges of Deck and Inside Panels from which Back
Panel will be connected as shown in “Detail a & b”
respectively. ����������$�"���������%&'��� �����������
a
b
Detail a
Detail b
Close Back Panel to Tunnel Formwork Set and
insert U Alignments-45 previously installed to Inside and
Deck Panels into the UPF profile of U-turn on Back Panel.
For being in alignment, hammer Back Panel
properly.
Corner Detail
Match the holes on all three panels and connect
them with M14x80 bolt&nuts through free holes on Back
panel.
c If this assembled Tunnel Formwork Set will be
located at the right side as in the sample shown in the
figure ;
Insert Key Locks to the Key Lock Bolts wlded on the edges
of Back Panels and loosely fit them with M18 nuts &
washers as shown in “Detail c”.
For the Tunnel Formwork which will be located at
the left side on formwork layout;
Insert only M18 nuts&washers to the Key Lock Bolts
welded on Back Panels.
Detail c
�������� Assembly of Tunnel Formwork Set
TRTF – Classic Tunnel Form System 26
�������������� ����� �����������������������www.mesaimalat.com.tr�
Check if there is any crack or bend on the Lifting Rod of Assembly Device.
�
Cracked, damaged or bended Lifting Rod must not be used in anyway.
Ensure that all connections are fitted properly.
�
For safety and security, check the stability of Tunnel Formwork and take precautions especially in windy conditions.
Upholding the Tunnel Formwork Set�
a
Detail a
As shown in “Detail a”, pass the Lifting Rod of
Assembly Device through the Lifting Hole previously drilled
on Deck Panel in dimensions given in Assembly Chart of
the Tunnel Formwork.
Screw the Lifting Nut tightly .
Lift the Tunnel Formwork by turning it so that it
will be on the wheels and wheeled props.
�����������
��������.��
Loosen the Lifting Nut and take away the
Assembly Device.
�������� Assembly of Tunnel Formwork Set
TRTF – Classic Tunnel Form System 27
�������������� ����� �����������������������www.mesaimalat.com.tr�
Marking could be done by using any of three pre-holes located on the Stop-end Slides.
�
Holes to be drilled could not overlap 50x60 tube sections on Panels.
Assembly of Stop-ends�
Detail b
Detail a
a
b
Mark the position of Wall stop-end in accordance
with the wall length in the construction drawing.
Drill Ø16mm holes at the same level of Stop-end
Slides so that the holes should be between two adjacent
50x60mm tube sections welded on the Inside Panel sheet.
Install Wall Stop-end by fitting M14x50 bolt&nut
through the hole on the Stop-end Slide and the hole on the
Inside Panel.
�������%����
�������%����
���%����������
���%����������
Samely, mark the position of Slab stop-end in
accordance with the slab length in the construction
drawing.
Drill Ø16mm holes through any of the holes
located on the Wall Stop-end Slides so that the holes
should not overlap 50x60 mm tube sections welded on the
Deck Panel sheet.
Install Slab Stop-end by fitting M14x50 bolt&nut
through the hole on the Stop-end Slide and the hole on the
Deck Panel.
�������� Assembly of Tunnel Formwork Set
TRTF – Classic Tunnel Form System 28
�������������� ����� �����������������������www.mesaimalat.com.tr�
For the first case of Formwork Setting, Boxouts are transferred with Tunnel Formworks.
Ensure that the Boxouts are stocked horizontally.
Assembly of Boxouts�
Mark the position of Wall Boxouts in accordance
with the wall length in the construction drawing.
Drill Ø20mm holes on the Vertical Panel through
the holes on the slides of Boxout so that the holes should
be between two adjacent 50x60mm tube sections welded
on the Vertical Panel sheet.
Weld a Boxout Nut in the inner surface of UPF
slide on the Boxout.
Install Boxout to the Vertical Panel by using
Boxout Bolt through the Boxout Nut welded on the Boxout
Slide.
b
Detail a
a
Detail b
�������� Assembly of Outside Wallform Set
TRTF – Classic Tunnel Form System 29
�������������� ����� �����������������������www.mesaimalat.com.tr�
ASSEMBLY of OUTSIDE WALLFORM SET�
Connection of Working Platform And Guardrails�
Make ready all necessary componets and
connectors for assembly.
Lay down the Outside Panel on two timbers so
that the steel surface is below as shown in the figure.
Connect each of Platform Support to the Panel
with one set of M14x80 bolt&nut (Detail a).
Connect each Platform Connector to the Panel
with two sets of M14x30 bolt&nut (Detail b).
Detail c
b
a
Detail a Detail b
Detail d
c
d
Install Working Platform and make connection
between it and each Platform Support with two sets of
M14x30 bolt&nut.
For Outside Panels whose length L is 2500 mm,
connect each of Platform Support to the Guardrail Post
with two sets of M14x80 bolt&nut (Detail c).
�
For Outside Panels whose length L is 1250 mm,
introduce Guardrail Connectors by connecting them to the
Working Platform with two sets of M14x30 bolt&nut. Then
connect each Guradrail Post to the Guardrail Connector
with two sets of M14x80 bolt&nut.
Make each connection between Platform
connectors and Working Platform with two sets of M14x30
bolt&nut (Detail d).
�������� Assembly of Outside Wallform Set
TRTF – Classic Tunnel Form System 30
�������������� ����� �����������������������www.mesaimalat.com.tr�
Connection of Panel Supports and Ladder�
Detail h Detail j
Detail e Detail f
e
f
h
j
Detail g
g
Install Panel Supports to the Panel and make
connection between each Support and the Panel with two
sets of M14x30 bolt&nut (Detail e) and one set of M14x80
bolt&nut (Detail f).
If the assembly contains a ladder set, then
connect the ladder to the Working Platform with two sets
of M14x30 bolt&nut (Detail g).
Ladder is fixed to the Panel with a Ladder
Connector. Installation is done by using one set of
M14x100 bolt&nut (Detail h) and one set of M14x80
bolt&nut (Detail j).
�
�������� Assembly of Outside Wallform Set
TRTF – Classic Tunnel Form System 31
�������������� ����� �����������������������www.mesaimalat.com.tr�
There must be one free hole between each U Alignment-45.
There should be M14x80 bolts&nuts at the holes on the foremost positions of both ends of the UPF profile as shown in details “a” and “b”.
Ensure that there is no any difference at junction points of two Panels.
Connection of Outside WallForms�
As shown in “Detail a - �”, connect U Alignments-
45 with M14x30 bolt&nut to the edge from which the other
Outside Panel will be connected.
As shown in “Detail a - ��”, close the second
Outside Panel to the first and insert U Alignments-45
previously mounted to the first panel into the UPF profile of
the second panel.
Match the holes on both panels and connect
them with M14x80 bolt&nuts through free holes on the first
panel.
a
Detail a - � Detail a - ��
d
c b
One piece of U Alignment-51 is fitted to inner
surfaces of Uppermost Stiffeners of two Outside Panels
with 4 sets of M14x80 bolt&nut as shown in “Detail b”.
Two pieces of U Alignment-89 are fitted to inner
surfaces of Mid Stiffeners of two Outside Panels with 4
sets of M14x80 bolt&nut as shown in “Detail c”.
One piece of U Alignment-109 is fitted to inner
surface of Undermost Stiffeners of two Outside Panels
with 2 sets of M14x30 bolt&nut as shown in the “Detail d”.
$�"��������%'1�
$�"��������%,0�
$�"��������%120�
Detail b
Detail c
Detail d
�������� Assembly of Outside Wallform Set
TRTF – Classic Tunnel Form System 32
�������������� ����� �����������������������www.mesaimalat.com.tr�
The angle “�” between two ropes should not be greater than 60°.
At winddy conditions ( wind speed is geater than 72 km/h), Outside Wallform Sets must be stacked in horizontal position.
Upholding the Outside WallForm Set�
Pass the Crane Ropes (or hooks) through the
Lifting Hooks welded on the Outside Panels properly. �
��������(/�
Lift the Outside Wallform Set and locate it in
vertical position.
If the Outside Wallform Set will be stacked in
vertical position, then lower the jacks on the Panels
Supports so that the Set will be inclined.
������� � Preperation for Operation
TRTF – Classic Tunnel Form System 33
�������������� ����� �������������������������www.mesaimalat.com.tr�
OPERATION CREW
Min.12 persons for - Removing - Cleaning - Oiling - Stripping - Setting and adjustment
of Formworks and Platforms.
Min.6 persons for - Rebar Working
Min.4 persons for - Plumbing - Installation of electrical conduits
Persons in the Operation Crew should have been educated on necessary safety regulations.
Valid structural construction drawings, boxout plans, detaied drawings of plumbing and electric conduits should be ready.
o Operation Crew should be ready.��
o Tunnel Formworks, Outside Wallforms, Platforms, Stopends, Kicker Forms and Platforms should be ready for operation.
�
o Tools and consumable materials should be ready.
�
o Crane should have been placed in right way. �
o Climatic conditions should allow to operation.
WD
Crew for Operation
PREPERATION for OPERATION�
Alignment of Tunnel Formworks
For a 200 m2 of construction area in plan (which
is approximately equivalent of 650 m2 total formwork
area), crew needed for proper operation is listed below;
Before Starting the Operation
As a summary, before starting the setting up the
Tunnel Formwork, rebar working, concreting, stripping
and erection operations, It is recommended to provide the
below necessities.
90°
HT
LP HP
WD: Deck Panel Width HT : Tunnel Height HP : Wheeled Prop Height LP : Prop Length
In order to adjust the alignment of a Tunnel
Formwork;
Firstly it is necessary to provide the
perpendicularity of Deck Panel and Inside Panel. This is
obtained by adjusting either the length of Inclined Prop or
the height of Wheeled Prop or both.
Secondly, it will be needed to adjust the reverse
deflection of Deck Panels, which is described below.
������� � Preperation for Operation
TRTF – Classic Tunnel Form System 34
�������������� ����� �������������������������www.mesaimalat.com.tr�
Alignment of a Half Tunnel
90° 90°
<90°
>90° <90°
After providing the right angle between Deck and
Inside Panels, increase or decrease the length of
Wheeled Prop to obtain the verticality of Inside Panel.
If Inside Panel is in vertical position then;
o If the angle between Deck and Inside Panel is
less than 90°, then increase both the length of Inclined
Prop and the height of Wheeled Prop properly.
o If the angle is greater than 90°, then decrease
both the length of Inclined Prop and the height of
Wheeled Prop properly.
If Deck Panel is in horizontal position then;
o If the angle between Deck and Inside Panel is
less than 90°, then increase the length of Inclined Prop
only.
o If the angle is greater than 90°, then decrease
the length of Inclined Prop only.
"�����
� ���� � ������������
����� �� &���� ��
����� ��
&���� ��
��$�������
��$���������
������� �����������������
����� �� &���� ��
������� ������������ �
������ ����������� �
� ��� ����� ������ ���������� �!
'(
��%�
�������
���������
��������
�����)�������*+, ° )
)�������-.����)������� 8�+,/�
"����#��$���%����������������������
&��������� ������ ���������� �!
Symbols Used
������� � Preperation for Operation
TRTF – Classic Tunnel Form System 35
�������������� ����� �������������������������www.mesaimalat.com.tr�
Reinforcement bars embedded on the slab must be in correct positions.
Ensure the surface of the foundation is smooth and clear.
�
Ensure the distance between Kicker Forms are correct.
Overlapping of Reinforcement Bars and the centerlines drawn could not be allowed.
It is recommenended that Preperation of Foundation should be realised in the daytime.
Maximum dimensional tolerance for kicker is ±3mm.
Preperation of Foundation
Before starting the casting of first kicer, provide
the flatness of the foundation.
Offset the main centerlines
and draw chalk line.
Oil the surfaces of Kicker
Forms with suitable Formwork
Separation Oil.
Connect straight kicker forms
by M14x50 bolt&nut.
Connect corner and �nner
kicker forms by Key Locks and M14
nuts.
Place and Install Kicker
Forms as given in the Kicker Plan.
������� � Preperation for Operation
TRTF – Classic Tunnel Form System 36
�������������� ����� �������������������������www.mesaimalat.com.tr�
On the corners; cones and clamps are located on all directions.
Ensure that, construction site is ready for concreting.
�
Concrete setting period changes with the weather conditions.
In order to prevent from
closing of Kicker forms to each other,
locate Tie-Rod Cones instead of
Kicker Spacers on each 1.25 metre
length.
Locate the Kicker Clamps
near to each Cones in order to prevent
from openings of Kicker forms to each
other
Realise the concreting
procedure properly.
Measure the starting and
ending points of wall boxouts and
locate concrete stoppers to each
ends.
Clean the construction site
form concrete particles and dust.
Wait for concrete setting
about 12 hours.
Firstly remove the clamps
and then concrete stopers from the
concrete by using lever.
������� � Preperation for Operation
TRTF – Classic Tunnel Form System 37
�������������� ����� �������������������������www.mesaimalat.com.tr�
<90° 90° 90° <90°
Check whether the kicker is cracked or damaged and the required kicker height is achieved.�
Uneven level on kicker is not allowed for next operations.
If kicker dimensions are out of tolerances, Tunnel Formworks will be located on inproper positions which will cause unwanted results on all of the levels to be constructed.
Secondly remove the straight
kicker forms and then inner and corner
kicker forms from the concrete by
using lever.
Realise the rebar working of
walls properly.
Lift and transfer the kicker
forms by uisng the holder on them.
Collect all other components
(i.e. clamps, stopers, bolts and nuts
etc.) on the boxes given by MESA.
������� � Preperation for Operation
TRTF – Classic Tunnel Form System 38
�������������� ����� �������������������������www.mesaimalat.com.tr�
Refer to Lifting Triangle operational conditions described in the Section “Lifting Equipments” of this Manual.�
Provide necessary tightness on the Lifting Beam Nut to avoid from unwanted bending of the Lifting Rod.�
Positions of Wall and Slab Stopends and Boxouts are defined on relevant drawings.�
Provide the vertical alignment of Wall Stopends.�
Cleannig and Oiling of Formworks
Marking the Boxouts and Stopends
Clean the surface of the Inside Panels from
“prefabricated Formwork Protective Oil” with suitable tools.
Oil the surfaces with the oil described in the
Section “Formwork Separator Oil” of this Manual.
Pass the Lifting Rod of the Lifting Triangle
through the Lifting Hole on the Deck Pannel.
Screw the Lifting Beam Nut from under the Lifting
Beam tightly.
Measure te distance from one end of the Tunnel
Formwork Set to the place where the Wall Stopend is
fixed.
Mark the vertical level for Stopend firstly.
Secondly, choose the most suitable hole located
on the slides of the Stopend where a Ø18mm hole will be
drilled on the Inside Panel.
�n a same manner, mark and drill te connection
holes for Slab Stopends and Wall Boxouts.
������� � Daily Cycle
TRTF – Classic Tunnel Form System 39
�������������� ����� �������������������������www.mesaimalat.com.tr�
DAILY CYCLE�
Time Schedule
This time schedule is prepared for a Tunnel Formwork application which has a 450-500 m2 construction area for one
floor
o Concreting Phases for One Floor : 2
o Formwork area : 1/2 of a floor (650 m2 approx.)
o Platform area :1/1 of a floor (full set for one floor)
o Climatic Conditions :approx. 20 °C in day and approx., 5 °C at night
o Working Hours : from 06h to 18h
o Working Crew : 12 persons in theTunnel Crew
6 persons in the Rebar Crew
4 persons in the Plumbing Crew
5 persons in the Concrete Crew (might be from the Tunnel Crew)
Striking of Formwork
Removing the Curtains and the Heaters �
�(! �2! ��! �,! ��! ��! 9�#���!�����(!��! ��! �)! ��! �(!
Removing the Kicker Forms �
�
�
Striking the Wall Boxouts �
No.s of Persons
)
�
�
�
�
�
�
����$���
�
�
�
�
�
Back Propping
Lowering and Striking the Second Half Tunnel Sets
Cleaning and Oiling the Second Half Tunnel Sets
�2!
Wall Reinforcement of Next Phase
Installation of Plumbing/Electrical Conduits on Wall
Removing the Slab Boxouts
Lowering and Striking the First Half Tunnel Sets
Cleaning and Oiling the First Half Tunnel Sets
Removing the Slab Stopends
Uninstallation of the Wall Boxouts
Marking the Half Tunnel levels on Kicker
Striking the Outside Wallforms
Removing Tie-Rods
Loosening the Roof Keys
STRIKING
Removing the Cones
������� ��4 �� ��� ��4 ���� ���� ��4 ��������� ��4 ��������4�/
������� � Daily Cycle
TRTF – Classic Tunnel Form System 40
�������������� ����� �������������������������www.mesaimalat.com.tr�
See details of each operations scheduled above on the following pages.
�
Time Schedules and capacity of crew explained above tables give only basic ideas to be applied during the operation, therefore it could not be used directly on site since there might be many of factors affecting the operation program.
Setting of Formwork�
Concreting Operation�
Curing
CONCRETING
Last Check before Concreting
Installation of Heaters
Closing the Tunnel Curtains
Concreting
No.s of Persons
(! 2! �! ,! ��! ��! ��! ��! �)! ��! �(! �2! 9�#���!������!
�
�
�
�
������� ��4 �� ��� ��4 ���� ���� ��4 ��������� ��4 ��������4�/
������� ��4 �� ��� ��4 ���� ���� ��4 ��������� ��4 ��������4�/
Slab Reinforcement (highest level)
Alignment of Half Tunnels
Moving the idle Gable Platforms
Moving the idle Landing Platforms
Installation of Kicker Spacers
Installation of Kicker Forms and Clamps
Tightening of Top Tie-Rods
Adjustment of Opposite Deflection
Moving the idle Stripping Platforms
Leveling the Second Half Tunnel Sets
Installation of Slab Boxouts
SETTING��! ��! �)!
�
�
)
�
(! 2! �! ,! ��!
�
�
�
Tightening of Bottom and Mid Tie-Rods
Cleaning and Oiling the Deck Panels
��!
Moving and Setting the Outside Wallforms
Slab Reinforcement (lowest level)
Installation of Plumbing/Electrical Conduits on Slab
Moving and Setting the First Half Tunnel Sets
Leveling the First Half Tunnel Sets
Installation of Tie-Rods and Cones
Carrying and Installation of Wall Boxouts
Moving and Setting the Second Half Tunnel Sets
Installation of Plumbing/Electrical Conduits on Wall
Tightening of Roof Keys
Installation of Slab Stopends
No.s of Persons
�
��! �(! �2! 9�#���!������!
�
�
�
)
�
�
�
�
�
�
�
�
�
�
�
�
������� � Daily Cycle
TRTF – Classic Tunnel Form System 41
�������������� ����� �������������������������www.mesaimalat.com.tr�
Wire-mesh usage as the reinforcement bar is recommended.
Place the rebars on the slab whose span “g” is the smallest. �
Ensure that rebars are vertical and corners are properly installed.
Striking
Wall Reinforcement of Next Phase
Prepare the rebars on the area reserved for rebar-
workering.
Place the rebars properly.
Use tower crane to carry all the required rebars to
the slab where the tunnel formworks will be used to cast
the concrete on the next phase.
�(! �2! ��! �,! ��! ��! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 42
�������������� ����� �������������������������www.mesaimalat.com.tr�
Finish all lifting and carrying operations before striking the formworks since The Lifting Triangle will be installed to the Crane Hook.�
In order not to became dangerous during the carrying of Tunnel formworks, ensure that the Curtains are not swung.
LPG tubes must be securely closed and hoses must be separated form the Heaters.
Removing the Curtains and the Heaters�
Installation of Plumbing and Electrical Conduits on Walls �
Carry and distribute required materials and
equipments to the slab properly.
Open the Tunnel Curtains and fold them properly.
Remove LPG tubes (if exist) on the Stripping
Platforms.
Start the installation of plumbing and electrical
circuits on walls properly.
�(! �2! ��! �,! ��! ��! ��! ��!
�(! �2! ��! �,! ��! ��! ��! ��!
������� �
TRTF – Classic Tunnel Form System
�������������� ����� �����������
Ensure that the Kickers arprovide necessary alignments.
Removing the Kicker Forms�
Remove Kicker Clamps
Remove Kicker Stopers
Loosen the nuts on the Roof
Keys which connect the Inner and
Corner Kicker Forms.
Remove the Kicker Forms
from the concrete by using lever.
Remove the Kicker Spacers
from the concrete by using lever.
Fill concrete to the clearance
Kicker Spacers.
Check the height of Kickers.
Collect all Spacers, Clamps and
Accessory Box.
43 ��������������www.mesaimalat.com.tr�
re smooth and .
es caused from
d Stopers on the
�(! �2! ��! �
Daily Cycle
,! ��! ��! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 44
�������������� ����� �������������������������www.mesaimalat.com.tr�
Keep the boxouts securely.
Removing the Slab Boxouts�
Removing the Slab Stopends�
If the boxout consist four parts, loosen the nuts
on the Roof Keys which connect these parts to eachother.
Remove each part from the concrete by using
lever respectively.
If the boxout consist only one
part, remove it from the concrete by
using lever.
Remove only Stopend Locks.
Collect all Locks for the next
concreting phase.
Connect the parts in order to
use the boxout in the next concreting
phase.
�(! �2! ��! �,! ��! ��! ��! ��!
�(! �2! ��! �,! ��! ��! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 45
�������������� ����� �������������������������www.mesaimalat.com.tr�
Separate the parts of Boxouts from each oher before carrying if lifting the whole set is not possible.
Do not remove the Roof Keys from Pannels. They should still be on the Pannels.
Removing the Wall Boxouts�
Loosening the Roof Keys�
Loosen and remove all Wall Boxout Bolts.
Collect all Bolts for the next concreting phase.
After stripping of Tunnel Formworks, Door
Boxouts will be drawn into the room by using lever and
they will be carry on the Stripping Platforms by manpower
in order to lift and trasfer them to the next concreting
phase.
On the Deck Pannels, by using Deck Pannel
Wrench, loosen all Roof Key Bolts located on the hook
side of them.
On the Back Pannels, by using Back Pannel
Wrench, loosen all Roof Key Bolts located on the hook
side of them.
Turn Roof Key Bolts so that two Pannels will
easily be separated from each other.
�(! �2! ��! �,! ��! ��! ��! ��!
�(! �2! ��! �,! ��! ��! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 46
�������������� ����� �������������������������www.mesaimalat.com.tr�
Refer to system section for application given by MESA to take the Jack Height “K”.
Ensure that Tie-Rods and Notched Nuts have been withdrawn towards the Half Tunnels on the connections of Wall Formwork and Half Tunnel Set.
Since 2010, Flange Nuts have been used instead of Notched Nuts.
Marking the Half Tunnel levels on Kicker�
Removing Tie-Rods�
Unscrew and remove the Wing Nuts.
From the other side, withdraw the Tie-rods and
Notched Nuts together.
Collect Tie-rod sets on the Vertical Panel
Stiffeners.
On the kickers where the Tunnel Formworks are
transferred for next concreting phase, mark the level which
is equal to the Jack Height “K” for bottom edge of Vertical
Panel.
�(! �2! ��! �,! ��! ��! ��! ��!
�(! �2! ��! �,! ��! ��! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 47
�������������� ����� �������������������������www.mesaimalat.com.tr�
Complete all lifting and carrying operations before striking the formworks since The Lifting Triangle will be installed to the Crane Hook.�
Ensure the stocking area is safe and smooth.
Angle between the Lifting Ropes “�” must not greater than 60°.�
If the Outside Wallform Set will be located vertically, it must be in inclined position as described in the Section “Assembly of Outside Wallform” in this Manual.�
Striking the Outside Wallforms�
Install the lifting rope to the Lifting Hooks welded
on the Outside Panels properly.
�
By unscrewing the bolts on the connections
between Outside Panels, separate the Outside Wallform
Sets from each other.
Ground the Outside Wallform Set properly.
Lay down the Outside Wallform Set properly.
�(! �2! ��! �,! ��! ��! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 48
�������������� ����� �������������������������www.mesaimalat.com.tr�
Refer to Lifting Triangle operational conditions described in the Section “Lifting Equipments” of this Manual.�
Ensure the surface of the Stripping Platform is so clean that it allows to drive the Half Tunnel easily.
Security Net of the Stripping Platform must be lowered.�
Since the Stripping and carrying operations of Half Tunnels are started and the Lifting Triangle is installed to the Crane Hook, ensure all other lifting operations which do not need the Crane should be completed.
Striking Operation should start with the Half Tunnel Set which was located on the place where concreting operation was started.�
Refer to the “User Manual” of Stripping Platform given by MESA.
Lowering and Striking the First Half Tunnel Sets�
Seperate Half Tunnel Sets
from each other by unscrewing the
bolts connected two Deck Panels and
two Inside Panels.
Lower the First Half Tunnel
Set located in a room by lowering the
Inside Panel Jacks until the Wheeled
Prop touches the slab.
Drive the First Half Tunnel
Set throughout the Stripping Platform
until the Lifting Hole appears.
Lifting Hole
Pass the Lifting Rod of the Lifting Triangle
through the Lifting Hole on the Deck Pannel.
Screw the Lifting Beam Nut from under the Lifting
Beam tightly.
�(! �2! ��! �,! ��! ��! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 49
�������������� ����� �������������������������www.mesaimalat.com.tr�
Longitudinal distance “L” between two adjacent props could not be greater than 1500 mm�
Make double Prop row, if the span “g” is greater than 4500mm.�
Cleaning and Oiling the First Half Tunnels�
Back Propping�
Clean the surface of the Inside Pannels from any
rust and concrete particles with spatula or suitable tools.
Oil the surfaces with the oil described in the
Section “Formwork Separator Oil” of this Manual.
Since Propping will start just after the Stripping of
the Fist Half Tunnel Formwork Set, bring necessary
quantity of Adjustable Props inside the room
Install Adjustable Props properly.
Insert wooden wedges between the Prop and the
slab both on top and at the bottom.
L
g < 4500 mm g > 4500 mm
�(! �2! ��! �,! ��! ��! ��! ��!
�(! �2! ��! �,! ��! ��! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 50
�������������� ����� �������������������������www.mesaimalat.com.tr�
Comply with the descriptions and restrictions written in the Section “Lowering and Striking the First Half Tunnel Sets” of this Manual.
If lifting the whole set of boxout is not possible then separate the parts of Boxout from each oher before carrying.
Lowering and Striking the Second Half Tunnel Sets�
Cleaning and Oiling the Second Half Tunnels�
Striking the Wall Boxouts�
As in the Section “Lowering and Striking the First
Half Tunnel Sets”, seperate Half Tunnel Sets from each
other and lower the First Half Tunnel Set by lowering the
Inside Panel Jacks until the Wheeled Prop touches the
slab.
Drive the First Half Tunnel Set throughout the
Stripping Platform until the Lifting Hole appears.
Clean the surface of the Inside Pannels from any
rust and concrete particles with spatula or suitable tools.
Oil the surfaces with the oil described in the
Section “Formwork Separator Oil” of this Manual.
�(! �2! ��! �,! ��! ��! ��! ��!
�(! �2! ��! �,! ��! ��! ��! ��!
�(! �2! ��! �,! ��! ��! ��! ��!
Lower the jacks under the boxouts.
Draw the boxout into the room by
using lever and carry on the Stripping
Platforms by manpower in order to lift and
trasfer them to the next concreting phase.
������� � Daily Cycle
TRTF – Classic Tunnel Form System 51
�������������� ����� �������������������������www.mesaimalat.com.tr�
The side of the Cone which has small diameter must be on the Wall Fromwork side.�
Hammer the Cones by means of the “Punch to
Remove Cone” from the side where the diameter of the
cone is small.
Withdraw the cone from the othe side of the wall.
Collect and oil the cones.
Removing the Cones��(! �2! ��! �,! ��! ��! ��! ��!
������� �
TRTF – Classic Tunnel Form System
�������������� ����� �����������
The Half Tunnel Set is rcompletely and carry to the phase.
Ensure that there is enough spTunnel Set which has a Back Set will be located behind twhich has already set.
Comply with the operation rwind limits given by the CraManufacturer.�
Check the Tunnel Number isthat of the Half Tunnel SeFormwork Layout provided by
Before starting to carry the transferring of Gable End FStripping and Landing Paltfbe completed. Refer to “User Manual”s of platforms provided by MESA
Formwork Setting
Moving and Setting the First Ha
Carry the Half Tunnel Set and
place where it will be located on the
phase.
Unscrew the Lifting Nut and re
Triangle from the Half Tunnel.
Draw up the Half tunnel Set
touches the kicker.
52 ��������������www.mesaimalat.com.tr�
ready to strip next concreting
pace for the Half k Panel if such a the Half Tunnel
rules, load and ane
s the same with et given in the y MESA.
Formworks, Frames and forms have to
those A.
alf Tunnel Sets
d leave it on the
next concreting
emove the Lifting
by lever until it
��! ,! ��!
Daily Cycle
�! ��! ��! �)! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 53
�������������� ����� �������������������������www.mesaimalat.com.tr�
Check the Level by Levelling instrument.
�
At the rebar side, if Tie-Rod collides with rebar, cut that part of rebar properly.
Ensure that Tie-Rods did not go out of the Cones.
�
The side of the Cone which has small diameter must be on the Wall Formwork side.�
Make ready all components and spare parts for connections described in “TRTF-Technical Manual”.
Leveling the First Half Tunnel Sets�
Installation of Tie-Rods and Cones�
Adjust the bottom level of the Inside Panel with
Panel Jack so that the line marked on the Kicker will be
conisided with the bottom edgee of the Panel.
If there are two or more Half Tunnel sets to be
located longitudionally, connect them with proper bolts
explained in “TRTF-Technical Manual” provided by MESA.
Pass the Tie-Rod and Wing
Nut set through the tie-rod holes on
the Inside Panels.
Install Cones through the Tie-
Rods.
��! ��! ��! �)!�! ,! ��! ��!
��! ��! ��! �)!�! ,! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 54
�������������� ����� �������������������������www.mesaimalat.com.tr�
Before carrying the First Half Tunnel Set of the adjoining room, ensure all necessary workings on this First Half Tunnel Set are completed properly.
Check if the dimensions of Boxouts is true.
�
Installation of Wall Boxouts�
Installation of Plumbing and Electrical Conduits on Wall�
Complete the plumbing connections and
installation of conduits box on the wall.
Carry the Wall Boxout as an assembly and
close to the place where it will be installed.
Draw up the Boxout by lever until it touches
the kicker.
Adjust the bottom level of the Boxout with
the Jack located at the bottom so that the connection
hole on it will coinside with the hole on the Inside
Panel.
From inside of the Half Tunnel, screw the
Boxout Bolt to connect it to the Inside Panel.
��! ��! ��! �)!�! ,! ��! ��!
��! ��! ��! �)!�! ,! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 55
�������������� ����� �������������������������www.mesaimalat.com.tr�
Ensure that there is enough space for the Half Tunnel Set which has a Back Panel if such a Set will be located behind the Half Tunnel which has already set.
Check the Tunnel Number is the same with that of the Half Tunnel Set given in the Formwork Layout provided by MESA.
Check the Level by Levelling instrument.
�
Make ready all components and spare parts for connections described in “TRTF-Technical Manual”.
Moving and Setting the Second Half Tunnel Sets�
Leveling the Second Half Tunnel Sets�
As in the Section “Moving and Setting the First
Half Tunnel Sets”, carry the Second Half Tunnel Set and
leave it on the place where it will be located on the next
concreting phase.
Pass the Tie-Rod and Wing Nut set through the
tie-rod holes on the Inside Panels.
Install Cones through the Tie-Rods.
As described in the “Leveling the First Half
Tunnel Sets”, adjust the bottom level of the Inside Panel
with Panel Jack so that the line marked on the Kicker will
be conisided with the bottom edgee of the Panel.
If there are two or more Half Tunnel sets to be
located longitudionally, connect them with proper bolts
explained in “TRTF-Technical Manual” provided by MESA.
��! ��! ��! �)!�! ,! ��! ��!
��! ��! ��! �)!�! ,! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 56
�������������� ����� �������������������������www.mesaimalat.com.tr�
Ensure that all accessories, spare parts and components are already collected on accessory boxes and they are ready to transfer.
Check the space between two Stopends. This will also provide the checking the space between two Deck Panels.
Completing the Half Tunnel Setting (Total)�
Installation of Slab Stopends�
Carry the Half Tunnel Sets starting from the first
one to the second one for each room.
Repeat precedures explained on above pages.
After finishing the lifting and carrying operations
of Half Tunnel Sets, remove the Lifting Triangle from the
hook of crane.
Install Slab Stopend Lock between two adjacent
Stopends.
��! ��! ��! �)!�! ,! ��! ��!
��! ��! ��! �)!�! ,! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 57
�������������� ����� �������������������������www.mesaimalat.com.tr�
Check the alignment of Deck Panels.
�
In some applications, Inside Panels could also be connected with each other by Roof Keys.
�
Equalize the level of Deck Panels so that the roof
Keys sould easily connect them.
Turn the Roof Key so that the sloteon it will locate
on the Key Bolt properly.
Tighten the nuts on the Key Bolts
Repeat the same procedure for Back Panels and
Outside Panels if exist.
Tightening the Roof Keys���! ��! ��! �)!�! ,! ��! ��!
������� �
TRTF – Classic Tunnel Form System
�������������� ����� �����������
The notch should be placedbetween two parts of th estiOtherwise after tightinf the will squeeze the stiffener.�
Do not use any tie-rods or ndamaged or rusty.�
Tightening of Bottom and Mid T
Cleaning and Oiling the Deck Pa
Pass the Tie-rod through the tie-
and Vertical Panels located at the other si
Screw the Notched Nut loos
touches to the stiffener.
Starting with Back Panels, screw
on the Tie-rod at the bottom tightly.
Screw the Wing Nut on the Tie-r
loosely.
Clean the surface of Deck Pann
and concrete particles with spatula or suit
Oil the surfaces with the oil
Section “Formwork Separator Oil” of this M
58 ��������������www.mesaimalat.com.tr�
d in the space iffener. Wing Nut it
nuts which are
Tie-Rods�
anels�
rod Hole on Back
ide.
sely until it just
w the Wing Nuts
rod at the middle
nels from any rust
table tools.
described in the
Manual.
��! ,! ��!
��! ,! ��!
Daily Cycle
�! ��! ��! �)! ��!
�! ��! ��! �)! ��!
������� �
TRTF – Classic Tunnel Form System
�������������� ����� �����������
Slab Reinforcement (lowest leve
Installation of Plumbing anConduits on Slab�
Clean the surface of Deck
Pannels from any rust and concrete
particles with spatula or suitable tools.
Carry slab rebars and place
them onto the Deck Panels where the
spans “g” are smaller.
Oil the surfaces with the oil
described in the Section “Formwork
Separator Oil” of this Manual.
Place the concrete covers on
Deck Panels.
Proceed the slab rebar
working for the lowest level properly.
Carry all neceesary materials
onto the Deck Panels where the spans “g
Install the electrical condui
plumbings on the slab.
59 ��������������www.mesaimalat.com.tr�
el)�
nd Electrical
and place them
” are smaller.
its and pipes,
��! ,! ��!
��! ,! ��!
Daily Cycle
�! ��! ��! �)! ��!
�! ��! ��! �)! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 60
�������������� ����� �������������������������www.mesaimalat.com.tr�
Slab is now ready for installation of boxouts and kicker forms.
�
Comply with the operation rules, load and wind limits given by the Crane Manufacturer.�
Make ready all components and spare parts for connections described in “TRTF-Technical Manual”.
Slab Reinforcement (highest level)�
Moving and Setting the Outside Wallforms�
Proceed the slab rebar working for the highest
level properly.
Carry the Outside Wallform Set and leave it on
the place where it will be located on the next concreting
phase.
Draw up the Outside Wallform Set by lever until it
touches the kicker.
Adjust the bottom level of the Outside Panel with
Panel Jack so that the line marked on the Kicker will
coniside with the bottom edgee of the Panel.
If there are two or more Outside Wallform Sets to
be located longitudionally, connect them with proper bolts
explained in “TRTF-Technical Manual” provided by MESA.
��! ��! ��! �)!�! ,! ��! ��!
��! ��! ��! �)!�! ,! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 61
�������������� ����� �������������������������www.mesaimalat.com.tr�
Make ready all components and spare parts for connections described in “TRTF-Technical Manual”.
Installation of Slab Boxouts�
Cut the rebars where the Boxouts will be placed.
Carry and install the Boxouts properly.
In order to fix the boxouts, pass the pins through
the hole on the Deck Panels.
Detail a
Detail a
Pass the Tie-rod already installed on Vertical
Panel located at the other side through the tie-rod Hole on
the Outside Panel.
Screw the Notched Nut loosely until it just
touches to the stiffener.
Screw the Wing Nut on the Tie-rod at the bottom
tightly and screw the Wing Nut on the Tie-rod at the middle
loosely.
��! ��! ��! �)!�! ,! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 62
�������������� ����� �������������������������www.mesaimalat.com.tr�
Before installation, Kicker Forms should be oiled properly.
�
Distance between the Klicker Spacers should not greater than 1250 mm.�
Observe that there are still some gaps between two adjacent Half Tunnels, because the top Tie-Rods are not tightened.�
Make ready all components and spare parts for connections described in “TRTF-Technical Manual”.
Make ready all components and spare parts for connections described in “TRTF-Technical Manual”.
Installation of Kicker Spacers�
Installation of Kicker Forms and Clamps�
Put Kicker Spacers (two sided) between two
adjacent Deck Panels so that the lugs at the bottom on
them should touch Deck and Inside Panels.
Between Outside Panels and Half Tunnels, use
Single Sided-Kicker Spacers.
��! ��! ��! �)!�! ,! ��! ��!
��! ��! ��! �)!�! ,! ��! ��!
������� �
TRTF – Classic Tunnel Form System
�������������� ����� �����������
Kicker Forms now supporSpacers and Slab Stopends.
�
Check the Kicker Spacers are wheeled props do not touch to
Tightening of Top Tie-Rods�
Pass the top Tie-rod through th
the Vertical Panel located at the other side
Screw the Notched Nut loos
touches to the stiffener.Screw the Wing N
rod loosely.
Tighten the Wing Nuts on the m
Tighten the Wing Nuts on the top Tie-rod
Transfer all Kicker Forms and Kic
to the working area.
Put Corner Kicker Forms firstly.
Connect them with the Inner K
Roof Keys.
Join the Straight Kicker Forms
Corner Kicker forms by bolts described
“Assembly of Kicker Forms” of “TRTF-T
provided by MESA.
63 ��������������www.mesaimalat.com.tr�
rted by Kicker
wll installed and o the slab.
e tie-rod Hole on
e.
sely until it just
Nut on the top Tie-
mid Tie-rod firstly.
secondly.
cker Clamps near
Kicker Forms with
s to the end of
d in the Section
Technical Manual”
��! ,! ��!
Daily Cycle
�! ��! ��! �)! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 64
�������������� ����� �������������������������www.mesaimalat.com.tr�
x
y
z
z y
x
z y
x
1 2
3
1
4 3 2
6 5
1
3 2
1 3
4 5 6
2
<90°
>90°
90°
If desired alignment is not provided or failed
somehow after assembling of Half Tunnel Set, it will be
needed to adjust the alignment similarly.
If Deck Panel is in horizontal position, then;
o Start to adjust the length of Inclined Prop from
one end of Half Tunnel Set (from no.1 to no.6 as shown in
the figure).
If Inside Panel is in vertical position, then;
o Start to adjust the length of Inclined Prop and
the height of Wheeled Prop from one end of Half Tunnel
Set (from no.1 to no.6 as shown in the figure).
If the perpendicularity of Deck and Inside Panel
is already provided, then;
o Start to adjust the height of Wheeled Prop from
one end of Half Tunnel Set (from no.1 to no.6 as shown in
the figure).
"�����
� ���� � ������������
����� �� &���� ��
����� ��
&���� ��
��$�������
��$���������
������� �����������������
����� �� &���� ��
������� ������������ �
������ ����������� �
� ��� ����� ������ ���������� �!
'(
��%�
�������
���������
��������
�����)�������*+, ° )
)�������-.����)������� 8�+,/�
"����#��$���%����������������������
&��������� ������ ���������� �!
Alignment of Half Tunnels���! ��! ��! �)!�! ,! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 65
�������������� ����� �������������������������www.mesaimalat.com.tr�
<90° <90° >90° >90°
<90° >90° 90° 90°
90° <90° <90° 90°
90° 90° <90° >90°
d
g�
Experienced results are listed above. The measure of Opposite Deflection “d” differ by the slab thickness, site conditions and experience of the Operation Crew itself.
Check the kicker level of Inside Panel Jack is in proper position.
Provide required dimension of the Inside Panel height which touches the kicker.
Ensure Inside Panels are in vertical positions and the alignment of Deck Panel give required opposite deflections.
Site is now ready to concreting procedure with well aligned Formworks and well prepared working area.
Adjustment of Opposite Deflection�
Before concreting, it is necessary to change the
setting of perpendicular angle between Deck and Inside
Panels, so that the horizonrtal alignment of slab will be
obtained without being affected by dead load of concrete
itself.
Below formulae give satisfactory opposite
deflections “d” changing with the range of span “g”.
2100mm � g � 3900 mm � d = 2 mm 3900mm < g � 5700 mm � d = 4 mm 5700mm < g � d = 8-20 mm
Before starting the concreting, be sure that the
Wheeled Prop does not touch the slab.
Adjust the length of Inclined Prop and the height
of Wheeled Prop properly in such a way that the vertical
alignment of Inside Panels are satisfied.
Figures show different cases which requires
necessary adjustments.
��! ��! ��! �)!�! ,! ��! ��!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 66
�������������� ����� �������������������������www.mesaimalat.com.tr�
Refer to the “User Manual” of the Stripping Platform provided by MESA.
Refer to the “User Manual” of the Gable End Frame provided by MESA.
Moving the Idle Stripping Platforms�
Moving Idle Gable Platforms�
Transfer the Stripping platforms which are in idle
position to the places for next concreting phase.
Transfer the Gable End Frames which are in idle
position to the places for next concreting phase.
��! ��! �)! ��! �(! �2! 9�#���!������!
��! ��! �)! ��! �(! �2! 9�#���!������!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 67
�������������� ����� �������������������������www.mesaimalat.com.tr�
Refer to the “User Manual” of the Landing Platform provided by MESA.
Moving the Idle Landing Platforms�
Transfer the Landing Platforms which are in idle
position to the upper level for next concreting phase.
Figure shows the Landing Platform which has
already reaised one level.
��! ��! �)! ��! �(! �2! 9�#���!������!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 68
�������������� ����� �������������������������www.mesaimalat.com.tr�
Comply with all safety regulations and conditions.�
Concreting
Last Check before Concreting�
Before starting the concreting procedure,
from Safety point of view;
o Check all Safety Nets of Stripping Platforms are
in vertical position.
o Check all access points between Stripping
Platforms and Gable-end Frames are securily
provided.
o Check Working Platforms on Outside Wall
Formworks provides necessary access and
safety.
o Check all timber products are in good condition.
from Technical point of view;
o Remove all unnecessary materials away from the
concreting area.
o Check all Wing Nuts are screwed tightly.
o Check all kicker form components are well
installed.
o Check all Slab and Wall stopends are fixed.
o Check the positions of boxouts are correct and
they are properly installed.
o Check the position of Concrete Distribution
Boom.
o Check the position of Concrete Pump.
��! ��! �)! ��! �(! �2! 9�#���!������!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 69
�������������� ����� �������������������������www.mesaimalat.com.tr�
Ensure that all safety requirements are provided.
Technical documents should be reviewed in the Section “Construction Materials” of this Manual.
Ensure that air leakage at the bottom is prevented.
Closing the Tunnel Curtains�
Installation of Heaters�
Carry the heaters and required componenets
near to the Tunnel Formworks.
Place them inside Tunnel Formworks and make
necessary installations.
Operate the Heaters properly.
Close all Tunnel Curtains and tie two parts.
��! ��! �)! ��! �(! �2! 9�#���!������!
��! ��! �)! ��! �(! �2! 9�#���!������!
������� �
TRTF – Classic Tunnel Form System
�������������� ����� �����������
Comply with rules and condrate of placing of concrete ethe Section “Construction Mthis Manual.�
At junction points on slabs where the concrete will be completed on the next phase; pour concrete having a width of 1/5 of the span “g”.
�
Concreting�
Starting point for pouring the
concrete will be clarified according to
the below parameters;
o Concreting should start from
the inside walls (or core
walls) to the outside walls.
o The walls which have the
largest boxout areas have the
first priority.
Continue to place the concrete w
Trowel by means of Kicker Form
and Slab Boxouts.
o Concreting should start from
Tunnel Formwork will be transfe
next concreting phase.
70 ��������������www.mesaimalat.com.tr�
ditions for the explained in Material” of
with slab.
ms, Slab Stopends
the area whose
erred firstly for the
��! ��! �)! �
Daily Cycle
�! �(! �2! 9�#���!������!
������� � Daily Cycle
TRTF – Classic Tunnel Form System 71
�������������� ����� �������������������������www.mesaimalat.com.tr�
Ensure that the hourly increase in temperature inside the room should not be greater than 20 °C.
Maximum inside temperature should be 70 °C.�
�
Take required precautions for different climatic conditions.�
�
Periodic checking of the Heaters during night against any unwanted situation and fire is strongly recommended.
Curing�
Curing could be continued all night long.
Check the fuel quantity periodically.
Provide required wetness of concrete.
��! ��! �)! ��! �(! �2! 9�#���!������!
������� � Non-standard Applications
TRTF – Classic Tunnel Form System 72
�������������� ����� �������������������������www.mesaimalat.com.tr�
In some buildings, the floor height of a basement,
ground level or any storey could be greater than the typical
floor. Then it could be necessary to pour the walls in two
phase.
Then install the Special Tunnel Raising Units to
the Half Tunnle Sets and follow the instructions provided
by MESA.
In some buildings, some of the spans colud be so
great that it could be necessary to introduce Table Forms
between two adjacent Tunnel Formwork Sets.
Then install the Special Table forms supplied by
MESA and follow the instructions.
NON-STANDARD APPLICATIONS�
Storeys with higher floor height
Rooms with greater spans than Standards
� ���
TRTF – Classic Tunnel Form System
�������������� ����� �������������������������www.mesaimalat.com.tr�
� ���
TRTF – Classic Tunnel Form System
�������������� ����� �������������������������www.mesaimalat.com.tr�