0. Flow Assurance
-
Upload
arief-ihsan -
Category
Documents
-
view
107 -
download
8
description
Transcript of 0. Flow Assurance
-
DP Conference MTS Symposium
Flow Assurance
Elijah KemptonTommy Golczynski
Marine Technology SocietySeptember 30, 2004
OwnerText BoxReturn to session directory
-
Session Outline
Flow Assurance OverviewKey Flow Assurance Issues
WaxHydratesSlugging
Deepwater Impacts on Flow AssuranceEmerging Technologies
Design ConsiderationsBlack Oil SystemsGas Condensate Systems
-
Flow Assurance Overview
-
What is Flow Assurance? Analysis of the entire production system to ensure that
the produced fluids continue to flow throughout the life of the field.
Optimization of the design and operating procedures to cost effectively prevent or mitigate slugging, surge volumes, wax deposition, gelling, hydrates, asphaltenes, etc.
-
Key Flow Assurance Issues
Wax (Paraffin) What is it?A solid hydrocarbon which precipitates from a produced fluidForms when the fluid temperature drops below the Wax Appearance Temperature (WAT)Melts at elevated temperatures (20F+ above the WAT)Rate of deposition can be predicted for pigging frequency
-
Key Flow Assurance Issues
WaxSince 1996, there have been 51 major occurrences that the MMS had to be involved in
All were paraffin-relatedMeans of remediation
PiggingContinuous inhibition (150-250 ppm for Gulf of Mexico)Reduced wax deposition rate by 60-90%
Industry TechnologyModeling is overly-conservative (6X pigging frequency)
-
Key Flow Assurance Issues
Above WAT Wax Crystals (WAT)
Seabed Temp. (40F)
Example WAT Measurement
-
Key Flow Assurance Issues
Factors effecting wax deposition rate
Wax Appearance Temperature, WAT
Production Fluid Temperature
Flowline U-value
Fluid PropertiesViscosityN-Paraffin Content
-
Key Flow Assurance Issues
Wax Deposition Insulation Impact
-
Key Flow Assurance Issues
Hydrate What is it?An Ice-like solid that forms when:
Sufficient water is presentHydrate former (i.e., methane) is presentRight combination of Pressure and Temperature (High Pressure / Low Temperature
Molecular Structure of
Hydrate Crystal
-
Key Flow Assurance Issues
HydratesPrimary cause for insulated flowlinesDeepwater operations
Increased operating pressureCold ambient temperatures
Means of remediationCrude oil displacement (looped flowlines)DepressurizationCoiled tubingContinuous Inhibition (Prevention Only)Methanol/MEGLDHI
-
01000
2000
3000
4000
5000
6000
7000
8000
9000
10000
40 45 50 55 60 65 70 75 80 85
Temperature, F
P
r
e
s
s
u
r
e
,
p
s
i
a
Pure Water
Sea Water
Produced Water
Key Flow Assurance Issues
Hydrates Base Information
Hydrates NoHydrates
-
0.300
0.325
0.350
0.375
0.400
0.425
0.450
0.475
0.500
0.525
0.550
0.575
0.600
50 75 100 125 150 175 200 225 250 275 300
Shut-in Pressure, bara
M
e
t
h
a
n
o
l
D
o
s
a
g
e
,
B
B
L
M
e
O
H
/
B
B
L
W
a
t
e
r
761 GOR 1100 GOR
1700 GOR 2500 GOR
0
5
10
15
20
25
30
35
40
45
50
1000 2000 3000 4000 5000 6000 7000 8000 9000 10000
Flowrate, B/d
M
e
t
h
a
n
o
l
R
a
t
e
,
g
p
m
5% Water Cut
10% Water Cut
20% Water Cut
25% Water Cut
30% Water Cut
40% Water Cut
50% Water Cut
25 GPM
Key Flow Assurance Issues
Hydrates Base Information
-
Key Flow Assurance Issues
Slugging What is it?Periods of Low Flow Followed by Periods of High FlowOccurs in Multiphase Flowlines at Low Gas Velocities
-
Key Flow Assurance Issues
SluggingCauses
Low fluid velocityBigger Better
Seabed bathymetry (downsloping)Riser typeLazy-S is a slug generator
Means of preventionIncrease flowrateSeparator pressureGas lift Difficult with
Catenary Risers
Lower Temperatures
Relative Inexpensive
Erosion Concerns
Proven Technology
DisadvantagesAdvantages
Gas LiftOverview
-
Key Flow Assurance Issues
Slugging Gas Lift Impacts
0
10000
20000
30000
40000
50000
60000
3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
Time (hours)
L
i
q
u
i
d
O
u
t
l
e
t
F
l
o
w
r
a
t
e
(
B
/
d
)
0 MMSCFD Gas Lift
0
5000
10000
15000
20000
25000
30000
35000
40000
3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
Time (hours)
L
i
q
u
i
d
O
u
t
l
e
t
F
l
o
w
r
a
t
e
(
B
/
d
)
5 MMSCFD Gas Lift
0
5000
10000
15000
20000
25000
3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
Time (hours)
L
i
q
u
i
d
O
u
t
l
e
t
F
l
o
w
r
a
t
e
(
B
/
d
)
10 MMSCFD Gas Lift
-150
-100
-50
0
50
100
150
3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
Time (hours)
L
i
q
u
i
d
A
c
c
u
m
u
l
a
t
i
o
n
A
b
o
v
e
N
o
r
m
a
l
(
b
b
l
)
0 MMSCFD Gas Lift
5 MMSCFD Gas Lift
10 MMSCFD Gas LiftSurge Volume
-
Key Flow Assurance Issues
Other IssuesAsphaltenes
ScaleCorrosion
Emulsions
Pour Point
Liquids Management
Cooldown Times
Flare Capacity
C-Factors
ErosionDepressurization
Surge Volume
Pigging
Chemical Inventory
Sand
-
Deepwater Impacts on Flow Assurance
Hydrate Formation/Wax DepositionLeads to:
Insulation / dual flowlinesDry oil flushingActive heatingChemicalsRevamped operating strategies
Lack of pressure / need for boostingDeepwater + high water cut + long tiebacks
Riser base gas liftMultiphase pumpingSubsea separation
-
Potential Energy Losses
Gas does work in moving fluids
Function of water depth
Expansion Cooling (Joule-Thomson Effect)
Exacerbated at large pressure differentials
RISER DOMINATES DEEPWATER SYSTEMS
Insulation may not be the answer!
Deepwater: Temperature Losses
-
95
100
105
110
115
120
125
0 1 2 3 4 5 6 7 8
FLOWLINE
RISER BASE
TOPSIDES
RISER
WELLHEAD
Distance (miles)
T
e
m
p
e
r
a
t
u
r
e
(
F
)
Deepwater: Temperature Losses
Joule-ThomsonCooling
46%
Surroundings(U-Value)
6%
Potential Energy(Work)
48%
-
16.59.215
16.62.96
16.61.23
RiserFlowline
Temperature Drop (F)Flowline Length(miles)
Deepwater: Temperature Losses
-
Heat transfer coefficient (U-value) dictates steady state temperatures Q (heat loss) = UAT U-Value , Q T
Thermal mass (, Cp) impacts transient performance Measure of heat storage
Prolongs cooldown times
Prolongs warm-up times
Deepwater: Temperature Losses
-
Te
m
p
e
r
a
t
u
r
e
(
F
)
Time(hours)
40
50
60
70
80
90
100
110
0 5 10 15 20 25 30 35 40
HIGH (Gelled Fluid #2 Water Base)
MEDIUM (Gelled Fluid #1 Oil Base)
LOW (Nitrogen)
Transient Temperature Loss
-
Pr
e
s
s
u
r
e
(
p
s
i
a
)
0
500
1000
1500
2000
2500
0 1 2 3 4 5 6 7 8
Distance (miles)
FLOWLINERISER BASE
RISER
WELLHEAD
TOPSIDES
Deepwater: Pressure Losses
-
176440515
17912386
18121433
RiserFlowline
Pressure Drop (psia)Flowline Length(miles)
Deepwater: Pressure Losses
-
Dry trees preferred for accessibility
Dry trees more difficult for flow assurance
Typically cannot depressurize
Short cooldown times (2-8 hours)
Fewer insulation/heating options than subsea
Limited chemical (MeOH/MEG) deliverability
Wax deposition more difficult to remediate
Deepwater:Dry Trees vs. Subsea Tieback
-
Dry Tree Analysis: Cooldown ComparisonProduction Fluid Temperature
40
45
50
55
60
65
70
75
80
85
90
95
100
0 1 2 3 4 5 6 7 8 9 10 11 12
Time (Hours)
T
e
m
p
e
r
a
t
u
r
e
(
F
)
Solid - Conduction
Liquid - Conduction+Convection
Gas - Conduction+Convection+Radiation
HYDRATE FORMATION TEMPERATURE
Dry Tree:Conduction / Convection / Radiation
-
Concentric Non-Concentric
Heat Transfer: Q = kAT / L(Conduction Only)
Accommodate Auxiliary Lines?
Dry Tree:Concentric vs. Non-Concentric
-
Dry Tree:Concentric vs. Non-Concentric
-
Te
m
p
e
r
a
t
u
r
e
(
F
)
Time (Hours)
40
50
60
70
80
90
100
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
15 psia N230 psia N259 psia N2102 psia N2
Dry Tree:Gas Properties
-
Transient issues drive deepwater design
Cooldown / restart - Hydrates Typical deepwater practice
Dual flowlines / crude oil displacement
Typically cannot depressurize (oil systems)
Consider potential for future expansion Insulation Topsides facilities
Design for Expansion
-
22.5 km
10 km8 km
8 km
Design for Expansion
Total Time to Displace Existing System = 22 Hours (Sequential)
Total Time to Displace Integrated System = 45 Hours (Sequential)High Level Insulation, or Additional Topsides Facilities Required!
-
Emerging Technologies
Passive Insulation Solutions
Microporous Insulation
Phase Change Materials
Artificial Lift
Subsea Separation (-)
Multiphase Pumping (+)
Gas Lift (+ / -)
-
Emerging Technologies
Active Heating
Hot Water Circulation
Electrically Heated
Electrically-heated ready
Chemicals
Low Dosage Hydrate Inhibitors
Cold Flow
-
Design Considerations:Black Oil and
Gas Condensate Systems
-
Black Oil System:Steady State Design Checklist Hydraulics
Line sizing Dry tree vs. subsea tieback Single vs. dual flowlines Dual flowlines becoming standard for deepwater
Pressure drop Velocity / erosion (minimum / maximum) Slugging
Thermal Insulation requirements
Hydrate formation Wax deposition Gel formation
-
Shutdown Planned Unplanned
Depressurization Restart
Warm Cold
Fluid displacement / pigging Flowline preheating
Black Oil System:Transient Design Checklist
-
Black Oil Systems:Steady State Design Considerations
-
Black Oil System:Steady State Hydraulics
Pressure drop effects Physical
Line size Tieback distance Water depth Multiphase flow:
Head losses head gains Pipe roughness (typical values) Steel: 0.0018 Tubing: 0.0006 Flexible pipe: ID/250
Fluid properties Gas/oil ratio (GOR) Density Viscosity May require insulation to limit viscosity
P
r
e
s
s
u
r
e
(
p
s
i
a
)
0
500
1000
1500
2000
2500
0 1 2 3 4 5 6 7 8
Distance (miles)
-
Black Oil System: Slugging Hydrodynamic
High frequency Minimal facilities impact
Terrain High liquid / gas flowrates Topsides concern Riser fatigue concern Utilize gas lift
Hydrodynamic SluggingGas Outlet Flow
0
1
2
3
4
5
6
7
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Time (hours)
Terrain SluggingLiquid Outlet Flow
0
10000
20000
30000
40000
50000
60000
70000
80000
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Time (hours)
-
Black Oil System: Slugging Slugging issues
Sensitivity to Fluid GOR / water cut
7500 / 7512500 / 10015000 / 1500
5000 / 40017500 / 25020000 / 12517500 / 100
1300 GOR 1800 GOR760 GOR
10000 / 20026000 / 3256015000 / 13024000 / 1754015000 / 12520000 / 16020
DNF
Terrain Slugging Regime (BPD) / Surge Volume (BBL)
5000 / 30080
Water Cut (%)
-
Black Oil System: Slugging Slugging issues
Sensitivity to Trajectory: up vs. downslope
-8600
-8500
-8400
-8300
-8200
-8100
-8000
-7900
-7800
-7700
-7600
-7500
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40
Distance, miles
W
a
t
e
r
D
e
p
t
h
,
f
t
Original Route - 40 miles total length
Alternate Route #1 - 36 miles total length
Alternate Route #2 - 45 miles total length
WELLHEAD RISER BASE
0
50
100
150
200
250
300
350
400
0 1 2 3 4 5 6 7 8
Time (hours)
L
i
q
u
i
d
A
c
c
u
m
u
l
a
t
i
o
n
A
b
o
v
e
N
o
r
m
a
l
*
(
b
b
l
)
Original RouteAlternate Route #1Alternate Route #2
50 bbl Slug Catcher Capacity
>24 hour Ramp-up Required
10 hour Ramp-up Required
-
Hydrates Maintain steady state temperature
above hydrate formation region, down to reasonable flowrate
Looped flowline ~ 25% of field production (50% per flowline)
For low water-cut systems, continuous hydrate inhibition is possible
Future: continuous LDHI inhibition
Black Oil System:Steady State Thermal Design
-
Wax Maintain temperature above WAT (stock
tank), down to reasonable flowrate Looped flowline ~ 25% of field production
(50% per flowline)
Maintain viscosity at acceptable levels to reduce pressure drop
Insulate to minimize pigging frequency Pigging frequency > residence time
Continuous paraffin inhibition (if necessary)
Black Oil System:Steady State Thermal Design
-
Black Oil System:Steady State Thermal Design
Limited insulating capacity0.75 1.50Flexible
Riser installation difficulties0.20 0.25Pipe-in-pipe
Dependant on soil propertiesCombined with insulation
0.50 1.00Burial
Buoyancy issues0.50 0.75Wet (Syntactic)
0.08 0.10
Achievable U-value(BTU/hr-ft-F)
Industry acceptanceMicro-porous
Issue / ConcernInsulation Option
-
Black Oil System:Steady State Thermal Design
Arrival TemperatureWater Cut = 0%
20.0
22.0
24.0
26.0
28.0
30.0
32.0
34.0
36.0
38.0
40.0
42.0
44.0
46.0
48.0
50.0
7500 10000 12500 15000 17500 20000 22500 25000 27500 30000 32500 35000 37500 40000Liquid Flowrate (blpd)
A
r
r
i
v
a
l
t
e
m
p
e
r
a
t
u
r
e
(
C
)
0.5 W/m.K1.0 W/m.K2 W/m.K3.0 W/m.Kno heat loss
0.50 BTU/ft hr F
0.30 BTU/ft hr F
0.20 BTU/ft hr F
0.09 BTU/ft hr F
Adiabatic (0 BTU/ft hr F)
-
Black Oil Systems:Cooldown Design Considerations
-
Shutdown statistics Typical shutdown durations
89% shutdowns < 10 hours 94% shutdowns < 12 hours 99.9% shutdowns < 24 hours
Typical shutdown causes
Black Oil System: Cooldown
PumpsScaleCorrosionSandParaffinHydratesAsphaltenesSeparationOther
-
Planned shutdown Procedure Inject hydrate inhibitor for one residence time
(minimum) At high water cuts, may need to reduce flowrate to
effectively treat system
Inject hydrate inhibitor into subsea equipment Particular attention to horizontal components Self-draining manifold / jumpers Treat upper portion of wellbore
SCSSV vs. top ~50 ft
Shut-in system
Black Oil System: Cooldown
-
Unplanned shutdown Procedure Determine minimum cooldown times
No-Touch Time ~2-4 hours / no action taken subsea
Light Touch Time ~2-4 hours / treat critical components Time is a function of chemical injection philosophy / number of wells
Preservation Time Time required to depressurize or displace flowlines with non-hydrate
forming fluid
Black Oil System: Cooldown
Time=0 Time=8Time=4
No-Touch Light Touch Preservation
-
Insulation selection Cooldown time determined
by: U-Value Thermal mass (, Cp)
Measure of heat storage
Line size impacts Bigger = More
Thermal Mass
Gas / liquid interface typically controlling point
Gas = low thermal mass Highest pressure Coldest temperature
Black Oil System: Cooldown
40
50
60
70
80
90
100
110
120
130
140
150
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36
Time (hours)
T
e
m
p
e
r
a
t
u
r
e
(
F
)
Pipe-in-Pipe (0.20 BTU/hr-ft-F)
Wet Insulation (0.75 BTU/hr-ft-F)
Flexible Pipe (1.00 BTU/hr-ft-F)
HYDRATE FORMATION (PURE WATER)
-
Black Oil System: Cooldown
30
40
50
60
70
80
90
100
110
120
130
140
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Distance (miles)
T
e
m
p
e
r
a
t
u
r
e
(
F
)
0 hours (Steady State)
1 hours
2 hours
4 hours
6 hours
8 hours
10 hours
12 hours
18 hours
24 hours
RESERVOIRWELLHEAD
FLOWLINE
RISER
-
Black Oil System: Cooldown
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
6000
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Distance (miles)
P
r
e
s
s
u
r
e
(
p
s
i
a
)
0 hours (Steady State)
24 hours
RESERVOIR
WELLHEAD
FLOWLINE
RISER
-
Black Oil System: Cooldown
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Distance (miles)
L
i
q
u
i
d
H
o
l
d
u
p
(
-
)
0 hours (Steady State)
24 hours
RESERVOIRWELLHEAD
FLOWLINE
RISER
-
Black Oil System: Cooldown
-30
-20
-10
0
10
20
30
40
50
60
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Distance (miles)
H
y
d
r
a
t
e
P
r
o
p
e
n
s
i
t
y
,
T
-
T
h
y
d
(
F
)
0 hours (Steady State)
1 hours
2 hours
4 hours
6 hours
8 hours
10 hours
12 hours
18 hours
24 hours
RESERVOIR
WELLHEAD
FLOWLINE
RISER
-
Is there adequate chemical injection to treat subsea components within cooldown time? Wellbore Trees Jumpers Manifolds
What is the subsea valve closure philosophy? Packed: More liquid / higher pressures Un-packed: Less liquid / lower pressures
Does insulation provide sufficient cooldown time? No-touch Light-touch Preservation
Is gel formation a possibility? If yes, system design philosophy changes
Is SCSSV set deep enough to avoid hydrates?
Black Oil System:Cooldown Checklist
-
Black Oil Systems:Depressurization Design
Considerations
-
Hydrate remediation strategy Reduce pressure below hydrate formation pressure at seabed
Effectiveness based on: Fluid properties
GOR Water cut
Seabed bathymetry Upslope Downslope
Deepwater issues Reduce pressure to ~200 psia at seabed Maintain pressure below hydrate conditions during restart
Black Oil System: Depressurization
Time=0 Time=8Time=4
No-Touch Light Touch Preservation:Depressurization
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
40 45 50 55 60 65 70 75 80 85
Temperature, F
P
r
e
s
s
u
r
e
,
p
s
i
a
Pure Water
Sea Water
Produced Water
Phyd ~ 200 psia
-
0500
1000
1500
2000
2500
3000
3500
4000
4500
0 1 2 3 4 5 6 7 8 9
0.0 hours0.5 hours1.0 hours
P
r
e
s
s
u
r
e
(
p
s
i
a
)
Distance (miles)
FLOWLINE
MUDLINE
BOTTOM HOLE
RISER BASE
Depressurization:Subsea Tieback
-
0500
1000
1500
2000
2500
3000
3500
4000
4500
0 2000 4000 6000 8000 10000 12000
0.0 hours
0.5 hours
1.0 hours
Distance (feet)
P
r
e
s
s
u
r
e
(
p
s
i
a
)
MUDLINE
BOTTOM HOLE
GAS/LIQUIDINTERFACE
SCSSV
Depressurization Dry Tree
-
Can you depressurize below hydrate formation conditions? If YES, can you depressurize in late-life at high water cuts? If YES, can you maintain pressure below hydrate formation conditions
during restart? Difficult for deepwater
If YES, is there a pour point concern? Depressurization increases restart pressure requirements
If NO, consider the following for hydrate prevention: Displacement (dual flowlines)
Active heating
Continuous chemical inhibition
Black Oil System:Depressurization Checklist
-
Black Oil Systems:Displacement Design
Considerations
-
During Prevention time, displace produced fluids from flowline Unable to get hydrate inhibitor to in-situ fluids
during shutdown Dual flowlines required Sufficient insulation / cooldown time Function of flowline length
Black Oil System: DisplacementHydrate Prevention - Shutdown
Time=0 Time=8Time=4
No-Touch Light Touch Preservation:Displacement
-
Black Oil System: DisplacementDischarge Pressure Required
HOLD BACKPRESSURE AT OUTLET
-
Black Oil System: DisplacementHydrate Prevention - Shutdown
Dead Oil Flushing - Year 5FPSO Pump Discharge Pressure
FPSO Arrival Pressure Controlled at 1500 psia
0
200
400
600
800
1000
1200
1400
1600
1800
0 0.5 1 1.5 2 2.5 3 3.5
Time (H)
Pig reaches base of first riser
Produced fluids move up second riser
Gas breaks through
second riser
Pig moves up second riser
-
During Prevention time, displace produced fluids from flowline Topsides design considerations
Available backpressure Circulation rate Limited by pig integrity Typically 3-5 ft/sec May be faster for straight-pipe
Storage volume Circulation passes With pig: 1 residence time Without pig: 2-3 residence times for efficient water removal
Black Oil System: DisplacementHydrate Prevention - Shutdown
-
Black Oil System: DisplacementHydrate Prevention Dry Tree
During shutdown, how quickly will fluids fall below SCSSV? Very little work done with L/D ratios >100 (deepwater riser
~10000) Field data shows oil/water separation ~ 70-80 ft/hr
Bullhead / displace with non-hydrate forming chemical to SCSSV Methanol/MEG (volume concerns) Heavy diesel (high density, by-pass produced fluids) Dead oil
Ability to bullhead a function of displacement rate
-
Is there sufficient time to accomplish displacement operation? Sufficient insulation / Cooldown time
Is the topsides facility designed to accomplish displacement operation? Pump capacity Storage capacity
Can system be restarted into crude-oil filled flowline? Displace with gas? High pour point fluids what is the restart pressure required?
For dry trees, is a proper fluid available for displacement?
Black Oil System:Displacement Checklist
-
Black Oil Systems:Restart Design Considerations
-
Black Oil System: Cold Restart System pressure < hydrate formation conditions throughout
restart? For deepwater, hydrostatic pressure in riser too high Separator pressure: may need alternate start-up vessel
Hydrate inhibition required until arrival temperature reaches Safe Operating Temperature (SOT) Maintain hydrate inhibitor rate: Fluid completely inhibited Reduce hydrate inhibitor rate: Fluid not completely inhibited to
shut-in conditions
SOT is minimum topsides temperature that provides sufficient cooldown time, in the event of an interrupted restart
-
Black Oil System: Cold Restart
Shut-in Pressure, psia
M
e
t
h
a
n
o
l
D
o
s
a
g
e
,
B
B
L
M
e
O
H
/
B
B
L
H
2
O
0.30
0.35
0.40
0.45
0.50
0.55
0.60
1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000
PRODUCEDWATER
SEA WATER
PURE WATER
-
Black Oil System: Cold Restart
Flowrate, BPD
M
e
t
h
a
n
o
l
,
g
p
m
0
5
10
15
20
25
30
35
40
45
50
2000 3000 4000 5000 6000 7000 8000 9000 10000
5% WATER
50% WATER
25% WATER
75% WATER
-
Black Oil System: Cold Restart Achievable restart rates determined by:
Shut-in conditions Fluid GOR Water cut Hydrate inhibitor
Rule of Thumb: Greater inhibitor injection rates result in lower overall inhibitor volumes used during restart Small tiebacks: 5-10 gpm / well Large deepwater: 25+ gpm / well
Warm-up trends: Wellbore: Very quick (
-
Black Oil System: Cold Restart
-
Black Oil System: Cold Restart
-
1.12.95.8Micro-porous
1.58.4> 24Buried1.13.210.6Flexible1.23.59.2Conventional1.13.06.1Pipe-in-pipe
Max Flowrate
10000STBPD
5000 STBPD
Insulation Type
Cold Restart: Case Study3 Mile Tieback Warm-up Time
-
7.013.0> 24Micro-porous
> 24> 24> 24Buried12.3> 24> 24Flexible10.9> 24> 24Conventional7.214.0> 24Pipe-in-pipe
Max Flowrate
10000STBPD
5000 STBPD
Insulation Type
Cold Restart: Case Study15 Mile Tieback Warm-up Time
-
772798> 850Micro-porous
> 2300> 1700> 850Buried1053> 1700> 850Flexible1074> 1700> 850Conventional781814> 850Pipe-in-pipe
Max Flowrate
10000STBPD
5000 STBPD
Insulation Type
Cold Restart: Case Study15 Mile Tieback MeOH Volume
-
Is there sufficient hydrate inhibitor available? Delivery rates Storage volumes
How will multiple wells be restarted? Single well at max. rate Multiple wells at reduced rate Single flowline vs. dual flowline
What is the minimum temperature required to achieve safe conditions? Safe Operating Temperature (SOT)
Black Oil System:Restart Checklist
-
Hydraulics Ensure Production Delivery Throughout Field Life Minimize Slugging
Wax Deposition Minimize Wax Deposition (Insulation/Pigging/Chemicals)
Hydrate Formation Avoid Steady State Hydrate Formation Optimize Cooldown Times (Insulation) Prevent Transient Hydrate Formation
(Depressurization/Displacement/Chemicals) Minimize Inhibitor Consumption
Black Oil System:Summary of Design Considerations