0. Flow Assurance

download 0. Flow Assurance

of 80

description

FA

Transcript of 0. Flow Assurance

  • DP Conference MTS Symposium

    Flow Assurance

    Elijah KemptonTommy Golczynski

    Marine Technology SocietySeptember 30, 2004

    OwnerText BoxReturn to session directory

  • Session Outline

    Flow Assurance OverviewKey Flow Assurance Issues

    WaxHydratesSlugging

    Deepwater Impacts on Flow AssuranceEmerging Technologies

    Design ConsiderationsBlack Oil SystemsGas Condensate Systems

  • Flow Assurance Overview

  • What is Flow Assurance? Analysis of the entire production system to ensure that

    the produced fluids continue to flow throughout the life of the field.

    Optimization of the design and operating procedures to cost effectively prevent or mitigate slugging, surge volumes, wax deposition, gelling, hydrates, asphaltenes, etc.

  • Key Flow Assurance Issues

    Wax (Paraffin) What is it?A solid hydrocarbon which precipitates from a produced fluidForms when the fluid temperature drops below the Wax Appearance Temperature (WAT)Melts at elevated temperatures (20F+ above the WAT)Rate of deposition can be predicted for pigging frequency

  • Key Flow Assurance Issues

    WaxSince 1996, there have been 51 major occurrences that the MMS had to be involved in

    All were paraffin-relatedMeans of remediation

    PiggingContinuous inhibition (150-250 ppm for Gulf of Mexico)Reduced wax deposition rate by 60-90%

    Industry TechnologyModeling is overly-conservative (6X pigging frequency)

  • Key Flow Assurance Issues

    Above WAT Wax Crystals (WAT)

    Seabed Temp. (40F)

    Example WAT Measurement

  • Key Flow Assurance Issues

    Factors effecting wax deposition rate

    Wax Appearance Temperature, WAT

    Production Fluid Temperature

    Flowline U-value

    Fluid PropertiesViscosityN-Paraffin Content

  • Key Flow Assurance Issues

    Wax Deposition Insulation Impact

  • Key Flow Assurance Issues

    Hydrate What is it?An Ice-like solid that forms when:

    Sufficient water is presentHydrate former (i.e., methane) is presentRight combination of Pressure and Temperature (High Pressure / Low Temperature

    Molecular Structure of

    Hydrate Crystal

  • Key Flow Assurance Issues

    HydratesPrimary cause for insulated flowlinesDeepwater operations

    Increased operating pressureCold ambient temperatures

    Means of remediationCrude oil displacement (looped flowlines)DepressurizationCoiled tubingContinuous Inhibition (Prevention Only)Methanol/MEGLDHI

  • 01000

    2000

    3000

    4000

    5000

    6000

    7000

    8000

    9000

    10000

    40 45 50 55 60 65 70 75 80 85

    Temperature, F

    P

    r

    e

    s

    s

    u

    r

    e

    ,

    p

    s

    i

    a

    Pure Water

    Sea Water

    Produced Water

    Key Flow Assurance Issues

    Hydrates Base Information

    Hydrates NoHydrates

  • 0.300

    0.325

    0.350

    0.375

    0.400

    0.425

    0.450

    0.475

    0.500

    0.525

    0.550

    0.575

    0.600

    50 75 100 125 150 175 200 225 250 275 300

    Shut-in Pressure, bara

    M

    e

    t

    h

    a

    n

    o

    l

    D

    o

    s

    a

    g

    e

    ,

    B

    B

    L

    M

    e

    O

    H

    /

    B

    B

    L

    W

    a

    t

    e

    r

    761 GOR 1100 GOR

    1700 GOR 2500 GOR

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    1000 2000 3000 4000 5000 6000 7000 8000 9000 10000

    Flowrate, B/d

    M

    e

    t

    h

    a

    n

    o

    l

    R

    a

    t

    e

    ,

    g

    p

    m

    5% Water Cut

    10% Water Cut

    20% Water Cut

    25% Water Cut

    30% Water Cut

    40% Water Cut

    50% Water Cut

    25 GPM

    Key Flow Assurance Issues

    Hydrates Base Information

  • Key Flow Assurance Issues

    Slugging What is it?Periods of Low Flow Followed by Periods of High FlowOccurs in Multiphase Flowlines at Low Gas Velocities

  • Key Flow Assurance Issues

    SluggingCauses

    Low fluid velocityBigger Better

    Seabed bathymetry (downsloping)Riser typeLazy-S is a slug generator

    Means of preventionIncrease flowrateSeparator pressureGas lift Difficult with

    Catenary Risers

    Lower Temperatures

    Relative Inexpensive

    Erosion Concerns

    Proven Technology

    DisadvantagesAdvantages

    Gas LiftOverview

  • Key Flow Assurance Issues

    Slugging Gas Lift Impacts

    0

    10000

    20000

    30000

    40000

    50000

    60000

    3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0

    Time (hours)

    L

    i

    q

    u

    i

    d

    O

    u

    t

    l

    e

    t

    F

    l

    o

    w

    r

    a

    t

    e

    (

    B

    /

    d

    )

    0 MMSCFD Gas Lift

    0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    40000

    3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0

    Time (hours)

    L

    i

    q

    u

    i

    d

    O

    u

    t

    l

    e

    t

    F

    l

    o

    w

    r

    a

    t

    e

    (

    B

    /

    d

    )

    5 MMSCFD Gas Lift

    0

    5000

    10000

    15000

    20000

    25000

    3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0

    Time (hours)

    L

    i

    q

    u

    i

    d

    O

    u

    t

    l

    e

    t

    F

    l

    o

    w

    r

    a

    t

    e

    (

    B

    /

    d

    )

    10 MMSCFD Gas Lift

    -150

    -100

    -50

    0

    50

    100

    150

    3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0

    Time (hours)

    L

    i

    q

    u

    i

    d

    A

    c

    c

    u

    m

    u

    l

    a

    t

    i

    o

    n

    A

    b

    o

    v

    e

    N

    o

    r

    m

    a

    l

    (

    b

    b

    l

    )

    0 MMSCFD Gas Lift

    5 MMSCFD Gas Lift

    10 MMSCFD Gas LiftSurge Volume

  • Key Flow Assurance Issues

    Other IssuesAsphaltenes

    ScaleCorrosion

    Emulsions

    Pour Point

    Liquids Management

    Cooldown Times

    Flare Capacity

    C-Factors

    ErosionDepressurization

    Surge Volume

    Pigging

    Chemical Inventory

    Sand

  • Deepwater Impacts on Flow Assurance

    Hydrate Formation/Wax DepositionLeads to:

    Insulation / dual flowlinesDry oil flushingActive heatingChemicalsRevamped operating strategies

    Lack of pressure / need for boostingDeepwater + high water cut + long tiebacks

    Riser base gas liftMultiphase pumpingSubsea separation

  • Potential Energy Losses

    Gas does work in moving fluids

    Function of water depth

    Expansion Cooling (Joule-Thomson Effect)

    Exacerbated at large pressure differentials

    RISER DOMINATES DEEPWATER SYSTEMS

    Insulation may not be the answer!

    Deepwater: Temperature Losses

  • 95

    100

    105

    110

    115

    120

    125

    0 1 2 3 4 5 6 7 8

    FLOWLINE

    RISER BASE

    TOPSIDES

    RISER

    WELLHEAD

    Distance (miles)

    T

    e

    m

    p

    e

    r

    a

    t

    u

    r

    e

    (

    F

    )

    Deepwater: Temperature Losses

    Joule-ThomsonCooling

    46%

    Surroundings(U-Value)

    6%

    Potential Energy(Work)

    48%

  • 16.59.215

    16.62.96

    16.61.23

    RiserFlowline

    Temperature Drop (F)Flowline Length(miles)

    Deepwater: Temperature Losses

  • Heat transfer coefficient (U-value) dictates steady state temperatures Q (heat loss) = UAT U-Value , Q T

    Thermal mass (, Cp) impacts transient performance Measure of heat storage

    Prolongs cooldown times

    Prolongs warm-up times

    Deepwater: Temperature Losses

  • Te

    m

    p

    e

    r

    a

    t

    u

    r

    e

    (

    F

    )

    Time(hours)

    40

    50

    60

    70

    80

    90

    100

    110

    0 5 10 15 20 25 30 35 40

    HIGH (Gelled Fluid #2 Water Base)

    MEDIUM (Gelled Fluid #1 Oil Base)

    LOW (Nitrogen)

    Transient Temperature Loss

  • Pr

    e

    s

    s

    u

    r

    e

    (

    p

    s

    i

    a

    )

    0

    500

    1000

    1500

    2000

    2500

    0 1 2 3 4 5 6 7 8

    Distance (miles)

    FLOWLINERISER BASE

    RISER

    WELLHEAD

    TOPSIDES

    Deepwater: Pressure Losses

  • 176440515

    17912386

    18121433

    RiserFlowline

    Pressure Drop (psia)Flowline Length(miles)

    Deepwater: Pressure Losses

  • Dry trees preferred for accessibility

    Dry trees more difficult for flow assurance

    Typically cannot depressurize

    Short cooldown times (2-8 hours)

    Fewer insulation/heating options than subsea

    Limited chemical (MeOH/MEG) deliverability

    Wax deposition more difficult to remediate

    Deepwater:Dry Trees vs. Subsea Tieback

  • Dry Tree Analysis: Cooldown ComparisonProduction Fluid Temperature

    40

    45

    50

    55

    60

    65

    70

    75

    80

    85

    90

    95

    100

    0 1 2 3 4 5 6 7 8 9 10 11 12

    Time (Hours)

    T

    e

    m

    p

    e

    r

    a

    t

    u

    r

    e

    (

    F

    )

    Solid - Conduction

    Liquid - Conduction+Convection

    Gas - Conduction+Convection+Radiation

    HYDRATE FORMATION TEMPERATURE

    Dry Tree:Conduction / Convection / Radiation

  • Concentric Non-Concentric

    Heat Transfer: Q = kAT / L(Conduction Only)

    Accommodate Auxiliary Lines?

    Dry Tree:Concentric vs. Non-Concentric

  • Dry Tree:Concentric vs. Non-Concentric

  • Te

    m

    p

    e

    r

    a

    t

    u

    r

    e

    (

    F

    )

    Time (Hours)

    40

    50

    60

    70

    80

    90

    100

    0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0

    15 psia N230 psia N259 psia N2102 psia N2

    Dry Tree:Gas Properties

  • Transient issues drive deepwater design

    Cooldown / restart - Hydrates Typical deepwater practice

    Dual flowlines / crude oil displacement

    Typically cannot depressurize (oil systems)

    Consider potential for future expansion Insulation Topsides facilities

    Design for Expansion

  • 22.5 km

    10 km8 km

    8 km

    Design for Expansion

    Total Time to Displace Existing System = 22 Hours (Sequential)

    Total Time to Displace Integrated System = 45 Hours (Sequential)High Level Insulation, or Additional Topsides Facilities Required!

  • Emerging Technologies

    Passive Insulation Solutions

    Microporous Insulation

    Phase Change Materials

    Artificial Lift

    Subsea Separation (-)

    Multiphase Pumping (+)

    Gas Lift (+ / -)

  • Emerging Technologies

    Active Heating

    Hot Water Circulation

    Electrically Heated

    Electrically-heated ready

    Chemicals

    Low Dosage Hydrate Inhibitors

    Cold Flow

  • Design Considerations:Black Oil and

    Gas Condensate Systems

  • Black Oil System:Steady State Design Checklist Hydraulics

    Line sizing Dry tree vs. subsea tieback Single vs. dual flowlines Dual flowlines becoming standard for deepwater

    Pressure drop Velocity / erosion (minimum / maximum) Slugging

    Thermal Insulation requirements

    Hydrate formation Wax deposition Gel formation

  • Shutdown Planned Unplanned

    Depressurization Restart

    Warm Cold

    Fluid displacement / pigging Flowline preheating

    Black Oil System:Transient Design Checklist

  • Black Oil Systems:Steady State Design Considerations

  • Black Oil System:Steady State Hydraulics

    Pressure drop effects Physical

    Line size Tieback distance Water depth Multiphase flow:

    Head losses head gains Pipe roughness (typical values) Steel: 0.0018 Tubing: 0.0006 Flexible pipe: ID/250

    Fluid properties Gas/oil ratio (GOR) Density Viscosity May require insulation to limit viscosity

    P

    r

    e

    s

    s

    u

    r

    e

    (

    p

    s

    i

    a

    )

    0

    500

    1000

    1500

    2000

    2500

    0 1 2 3 4 5 6 7 8

    Distance (miles)

  • Black Oil System: Slugging Hydrodynamic

    High frequency Minimal facilities impact

    Terrain High liquid / gas flowrates Topsides concern Riser fatigue concern Utilize gas lift

    Hydrodynamic SluggingGas Outlet Flow

    0

    1

    2

    3

    4

    5

    6

    7

    1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0

    Time (hours)

    Terrain SluggingLiquid Outlet Flow

    0

    10000

    20000

    30000

    40000

    50000

    60000

    70000

    80000

    1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0

    Time (hours)

  • Black Oil System: Slugging Slugging issues

    Sensitivity to Fluid GOR / water cut

    7500 / 7512500 / 10015000 / 1500

    5000 / 40017500 / 25020000 / 12517500 / 100

    1300 GOR 1800 GOR760 GOR

    10000 / 20026000 / 3256015000 / 13024000 / 1754015000 / 12520000 / 16020

    DNF

    Terrain Slugging Regime (BPD) / Surge Volume (BBL)

    5000 / 30080

    Water Cut (%)

  • Black Oil System: Slugging Slugging issues

    Sensitivity to Trajectory: up vs. downslope

    -8600

    -8500

    -8400

    -8300

    -8200

    -8100

    -8000

    -7900

    -7800

    -7700

    -7600

    -7500

    0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40

    Distance, miles

    W

    a

    t

    e

    r

    D

    e

    p

    t

    h

    ,

    f

    t

    Original Route - 40 miles total length

    Alternate Route #1 - 36 miles total length

    Alternate Route #2 - 45 miles total length

    WELLHEAD RISER BASE

    0

    50

    100

    150

    200

    250

    300

    350

    400

    0 1 2 3 4 5 6 7 8

    Time (hours)

    L

    i

    q

    u

    i

    d

    A

    c

    c

    u

    m

    u

    l

    a

    t

    i

    o

    n

    A

    b

    o

    v

    e

    N

    o

    r

    m

    a

    l

    *

    (

    b

    b

    l

    )

    Original RouteAlternate Route #1Alternate Route #2

    50 bbl Slug Catcher Capacity

    >24 hour Ramp-up Required

    10 hour Ramp-up Required

  • Hydrates Maintain steady state temperature

    above hydrate formation region, down to reasonable flowrate

    Looped flowline ~ 25% of field production (50% per flowline)

    For low water-cut systems, continuous hydrate inhibition is possible

    Future: continuous LDHI inhibition

    Black Oil System:Steady State Thermal Design

  • Wax Maintain temperature above WAT (stock

    tank), down to reasonable flowrate Looped flowline ~ 25% of field production

    (50% per flowline)

    Maintain viscosity at acceptable levels to reduce pressure drop

    Insulate to minimize pigging frequency Pigging frequency > residence time

    Continuous paraffin inhibition (if necessary)

    Black Oil System:Steady State Thermal Design

  • Black Oil System:Steady State Thermal Design

    Limited insulating capacity0.75 1.50Flexible

    Riser installation difficulties0.20 0.25Pipe-in-pipe

    Dependant on soil propertiesCombined with insulation

    0.50 1.00Burial

    Buoyancy issues0.50 0.75Wet (Syntactic)

    0.08 0.10

    Achievable U-value(BTU/hr-ft-F)

    Industry acceptanceMicro-porous

    Issue / ConcernInsulation Option

  • Black Oil System:Steady State Thermal Design

    Arrival TemperatureWater Cut = 0%

    20.0

    22.0

    24.0

    26.0

    28.0

    30.0

    32.0

    34.0

    36.0

    38.0

    40.0

    42.0

    44.0

    46.0

    48.0

    50.0

    7500 10000 12500 15000 17500 20000 22500 25000 27500 30000 32500 35000 37500 40000Liquid Flowrate (blpd)

    A

    r

    r

    i

    v

    a

    l

    t

    e

    m

    p

    e

    r

    a

    t

    u

    r

    e

    (

    C

    )

    0.5 W/m.K1.0 W/m.K2 W/m.K3.0 W/m.Kno heat loss

    0.50 BTU/ft hr F

    0.30 BTU/ft hr F

    0.20 BTU/ft hr F

    0.09 BTU/ft hr F

    Adiabatic (0 BTU/ft hr F)

  • Black Oil Systems:Cooldown Design Considerations

  • Shutdown statistics Typical shutdown durations

    89% shutdowns < 10 hours 94% shutdowns < 12 hours 99.9% shutdowns < 24 hours

    Typical shutdown causes

    Black Oil System: Cooldown

    PumpsScaleCorrosionSandParaffinHydratesAsphaltenesSeparationOther

  • Planned shutdown Procedure Inject hydrate inhibitor for one residence time

    (minimum) At high water cuts, may need to reduce flowrate to

    effectively treat system

    Inject hydrate inhibitor into subsea equipment Particular attention to horizontal components Self-draining manifold / jumpers Treat upper portion of wellbore

    SCSSV vs. top ~50 ft

    Shut-in system

    Black Oil System: Cooldown

  • Unplanned shutdown Procedure Determine minimum cooldown times

    No-Touch Time ~2-4 hours / no action taken subsea

    Light Touch Time ~2-4 hours / treat critical components Time is a function of chemical injection philosophy / number of wells

    Preservation Time Time required to depressurize or displace flowlines with non-hydrate

    forming fluid

    Black Oil System: Cooldown

    Time=0 Time=8Time=4

    No-Touch Light Touch Preservation

  • Insulation selection Cooldown time determined

    by: U-Value Thermal mass (, Cp)

    Measure of heat storage

    Line size impacts Bigger = More

    Thermal Mass

    Gas / liquid interface typically controlling point

    Gas = low thermal mass Highest pressure Coldest temperature

    Black Oil System: Cooldown

    40

    50

    60

    70

    80

    90

    100

    110

    120

    130

    140

    150

    0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

    Time (hours)

    T

    e

    m

    p

    e

    r

    a

    t

    u

    r

    e

    (

    F

    )

    Pipe-in-Pipe (0.20 BTU/hr-ft-F)

    Wet Insulation (0.75 BTU/hr-ft-F)

    Flexible Pipe (1.00 BTU/hr-ft-F)

    HYDRATE FORMATION (PURE WATER)

  • Black Oil System: Cooldown

    30

    40

    50

    60

    70

    80

    90

    100

    110

    120

    130

    140

    0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0

    Distance (miles)

    T

    e

    m

    p

    e

    r

    a

    t

    u

    r

    e

    (

    F

    )

    0 hours (Steady State)

    1 hours

    2 hours

    4 hours

    6 hours

    8 hours

    10 hours

    12 hours

    18 hours

    24 hours

    RESERVOIRWELLHEAD

    FLOWLINE

    RISER

  • Black Oil System: Cooldown

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    5000

    5500

    6000

    0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0

    Distance (miles)

    P

    r

    e

    s

    s

    u

    r

    e

    (

    p

    s

    i

    a

    )

    0 hours (Steady State)

    24 hours

    RESERVOIR

    WELLHEAD

    FLOWLINE

    RISER

  • Black Oil System: Cooldown

    0.0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.6

    0.7

    0.8

    0.9

    1.0

    0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0

    Distance (miles)

    L

    i

    q

    u

    i

    d

    H

    o

    l

    d

    u

    p

    (

    -

    )

    0 hours (Steady State)

    24 hours

    RESERVOIRWELLHEAD

    FLOWLINE

    RISER

  • Black Oil System: Cooldown

    -30

    -20

    -10

    0

    10

    20

    30

    40

    50

    60

    0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0

    Distance (miles)

    H

    y

    d

    r

    a

    t

    e

    P

    r

    o

    p

    e

    n

    s

    i

    t

    y

    ,

    T

    -

    T

    h

    y

    d

    (

    F

    )

    0 hours (Steady State)

    1 hours

    2 hours

    4 hours

    6 hours

    8 hours

    10 hours

    12 hours

    18 hours

    24 hours

    RESERVOIR

    WELLHEAD

    FLOWLINE

    RISER

  • Is there adequate chemical injection to treat subsea components within cooldown time? Wellbore Trees Jumpers Manifolds

    What is the subsea valve closure philosophy? Packed: More liquid / higher pressures Un-packed: Less liquid / lower pressures

    Does insulation provide sufficient cooldown time? No-touch Light-touch Preservation

    Is gel formation a possibility? If yes, system design philosophy changes

    Is SCSSV set deep enough to avoid hydrates?

    Black Oil System:Cooldown Checklist

  • Black Oil Systems:Depressurization Design

    Considerations

  • Hydrate remediation strategy Reduce pressure below hydrate formation pressure at seabed

    Effectiveness based on: Fluid properties

    GOR Water cut

    Seabed bathymetry Upslope Downslope

    Deepwater issues Reduce pressure to ~200 psia at seabed Maintain pressure below hydrate conditions during restart

    Black Oil System: Depressurization

    Time=0 Time=8Time=4

    No-Touch Light Touch Preservation:Depressurization

    0

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    8000

    9000

    10000

    40 45 50 55 60 65 70 75 80 85

    Temperature, F

    P

    r

    e

    s

    s

    u

    r

    e

    ,

    p

    s

    i

    a

    Pure Water

    Sea Water

    Produced Water

    Phyd ~ 200 psia

  • 0500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    0 1 2 3 4 5 6 7 8 9

    0.0 hours0.5 hours1.0 hours

    P

    r

    e

    s

    s

    u

    r

    e

    (

    p

    s

    i

    a

    )

    Distance (miles)

    FLOWLINE

    MUDLINE

    BOTTOM HOLE

    RISER BASE

    Depressurization:Subsea Tieback

  • 0500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    0 2000 4000 6000 8000 10000 12000

    0.0 hours

    0.5 hours

    1.0 hours

    Distance (feet)

    P

    r

    e

    s

    s

    u

    r

    e

    (

    p

    s

    i

    a

    )

    MUDLINE

    BOTTOM HOLE

    GAS/LIQUIDINTERFACE

    SCSSV

    Depressurization Dry Tree

  • Can you depressurize below hydrate formation conditions? If YES, can you depressurize in late-life at high water cuts? If YES, can you maintain pressure below hydrate formation conditions

    during restart? Difficult for deepwater

    If YES, is there a pour point concern? Depressurization increases restart pressure requirements

    If NO, consider the following for hydrate prevention: Displacement (dual flowlines)

    Active heating

    Continuous chemical inhibition

    Black Oil System:Depressurization Checklist

  • Black Oil Systems:Displacement Design

    Considerations

  • During Prevention time, displace produced fluids from flowline Unable to get hydrate inhibitor to in-situ fluids

    during shutdown Dual flowlines required Sufficient insulation / cooldown time Function of flowline length

    Black Oil System: DisplacementHydrate Prevention - Shutdown

    Time=0 Time=8Time=4

    No-Touch Light Touch Preservation:Displacement

  • Black Oil System: DisplacementDischarge Pressure Required

    HOLD BACKPRESSURE AT OUTLET

  • Black Oil System: DisplacementHydrate Prevention - Shutdown

    Dead Oil Flushing - Year 5FPSO Pump Discharge Pressure

    FPSO Arrival Pressure Controlled at 1500 psia

    0

    200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    0 0.5 1 1.5 2 2.5 3 3.5

    Time (H)

    Pig reaches base of first riser

    Produced fluids move up second riser

    Gas breaks through

    second riser

    Pig moves up second riser

  • During Prevention time, displace produced fluids from flowline Topsides design considerations

    Available backpressure Circulation rate Limited by pig integrity Typically 3-5 ft/sec May be faster for straight-pipe

    Storage volume Circulation passes With pig: 1 residence time Without pig: 2-3 residence times for efficient water removal

    Black Oil System: DisplacementHydrate Prevention - Shutdown

  • Black Oil System: DisplacementHydrate Prevention Dry Tree

    During shutdown, how quickly will fluids fall below SCSSV? Very little work done with L/D ratios >100 (deepwater riser

    ~10000) Field data shows oil/water separation ~ 70-80 ft/hr

    Bullhead / displace with non-hydrate forming chemical to SCSSV Methanol/MEG (volume concerns) Heavy diesel (high density, by-pass produced fluids) Dead oil

    Ability to bullhead a function of displacement rate

  • Is there sufficient time to accomplish displacement operation? Sufficient insulation / Cooldown time

    Is the topsides facility designed to accomplish displacement operation? Pump capacity Storage capacity

    Can system be restarted into crude-oil filled flowline? Displace with gas? High pour point fluids what is the restart pressure required?

    For dry trees, is a proper fluid available for displacement?

    Black Oil System:Displacement Checklist

  • Black Oil Systems:Restart Design Considerations

  • Black Oil System: Cold Restart System pressure < hydrate formation conditions throughout

    restart? For deepwater, hydrostatic pressure in riser too high Separator pressure: may need alternate start-up vessel

    Hydrate inhibition required until arrival temperature reaches Safe Operating Temperature (SOT) Maintain hydrate inhibitor rate: Fluid completely inhibited Reduce hydrate inhibitor rate: Fluid not completely inhibited to

    shut-in conditions

    SOT is minimum topsides temperature that provides sufficient cooldown time, in the event of an interrupted restart

  • Black Oil System: Cold Restart

    Shut-in Pressure, psia

    M

    e

    t

    h

    a

    n

    o

    l

    D

    o

    s

    a

    g

    e

    ,

    B

    B

    L

    M

    e

    O

    H

    /

    B

    B

    L

    H

    2

    O

    0.30

    0.35

    0.40

    0.45

    0.50

    0.55

    0.60

    1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000

    PRODUCEDWATER

    SEA WATER

    PURE WATER

  • Black Oil System: Cold Restart

    Flowrate, BPD

    M

    e

    t

    h

    a

    n

    o

    l

    ,

    g

    p

    m

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    2000 3000 4000 5000 6000 7000 8000 9000 10000

    5% WATER

    50% WATER

    25% WATER

    75% WATER

  • Black Oil System: Cold Restart Achievable restart rates determined by:

    Shut-in conditions Fluid GOR Water cut Hydrate inhibitor

    Rule of Thumb: Greater inhibitor injection rates result in lower overall inhibitor volumes used during restart Small tiebacks: 5-10 gpm / well Large deepwater: 25+ gpm / well

    Warm-up trends: Wellbore: Very quick (

  • Black Oil System: Cold Restart

  • Black Oil System: Cold Restart

  • 1.12.95.8Micro-porous

    1.58.4> 24Buried1.13.210.6Flexible1.23.59.2Conventional1.13.06.1Pipe-in-pipe

    Max Flowrate

    10000STBPD

    5000 STBPD

    Insulation Type

    Cold Restart: Case Study3 Mile Tieback Warm-up Time

  • 7.013.0> 24Micro-porous

    > 24> 24> 24Buried12.3> 24> 24Flexible10.9> 24> 24Conventional7.214.0> 24Pipe-in-pipe

    Max Flowrate

    10000STBPD

    5000 STBPD

    Insulation Type

    Cold Restart: Case Study15 Mile Tieback Warm-up Time

  • 772798> 850Micro-porous

    > 2300> 1700> 850Buried1053> 1700> 850Flexible1074> 1700> 850Conventional781814> 850Pipe-in-pipe

    Max Flowrate

    10000STBPD

    5000 STBPD

    Insulation Type

    Cold Restart: Case Study15 Mile Tieback MeOH Volume

  • Is there sufficient hydrate inhibitor available? Delivery rates Storage volumes

    How will multiple wells be restarted? Single well at max. rate Multiple wells at reduced rate Single flowline vs. dual flowline

    What is the minimum temperature required to achieve safe conditions? Safe Operating Temperature (SOT)

    Black Oil System:Restart Checklist

  • Hydraulics Ensure Production Delivery Throughout Field Life Minimize Slugging

    Wax Deposition Minimize Wax Deposition (Insulation/Pigging/Chemicals)

    Hydrate Formation Avoid Steady State Hydrate Formation Optimize Cooldown Times (Insulation) Prevent Transient Hydrate Formation

    (Depressurization/Displacement/Chemicals) Minimize Inhibitor Consumption

    Black Oil System:Summary of Design Considerations