«Commodity»
Proposed Commodity Strategy
«Date»
Version 0.0
PLEASE NOTE: This document has been included as an example. The format & contents of your final commodity strategy may vary as per the internal governance, processes and procedures within your organisation.
2
Version control
Version # Updated By Date Updated Change Details
3
Page/Slide Number
Foreword
Executive Summary
Stakeholder Engagement
Commodity Charter
Current Situation:
- Commodity Profile
- Supply Market Analysis
Proposed Strategy:
- Strategic Objectives
- Sustainability
- Supplier and Contract Management
- Principal Options
- Proposed Approach
- Selection Criteria
- Award Criteria
- Deployment
- Risk analysis
- Communication Plan
- Implementation Plan
Appendices
Contents
Key Contacts:
«Name»
«Title»
Tel:
Email: __________________
«Name»
«Title»
Tel:
Email: __________________«Name»
«Title»
Tel:
Email:
4
ForewordPurpose
This document describes the commodity strategy for procuring «Commodity» .
The information within this document will be shared and developed with key stakeholders. It contains certain sensitive commercial information and should not be shared beyond this environment. In particular this document should not be shared with suppliers as it discussed several sourcing strategy options and makes recommendations for implementation.
Approval
Approval of this document will come through the established governance route.
Notes
The data contained in this document is based on data provided from several sources. These include:
«i.e. data extracted from the Scottish Procurement Information Hub (formally known as Spikes Cavell Observatory) »;
«i.e. market information provided by «source»»; and
«i.e. product and spend data provided by several of the major incumbent «commodity» providers»
The document takes into account information gathered during «timeframe», including that obtained from participants in the cross-sector User Intelligence Group held during this time.
5
Executive SummaryKey Findings
• Total spend is over £«value»:«i.e. breakdown of spend by organisation»
• Products purchased make up «No.» key sub-categories:«i.e. breakdown of spend by sub-categories»;
• More than x-number of suppliers are currently used to provide these products:«i.e. breakdown by supplier»;
Benchmarking and Opportunities, Options Considered
• Scope and Dependencies«i.e. Department (s), Organisation (s) or sector( s) interested in proposed outcomes;
• Options XXXXXXXXXXXXXXXXXXXXXXX;
«i.e. xxxxxxxxxxxxxxxx;
Recommendations and Key Actions
• After comprehensive consultation with stakeholders:«i.e. To go to market on a national, cross-sector basis breakdown by supplier»;
-«i.e. Award new contract/s by «date», with a phased implementation effective from «date»;
Benefits, Justification and projected savings«i.e. cashable/non-cashable savings»;«i.e. return on investment»;
Key Risks and Resource Implications«i.e. Insufficient access to accurate and current spend data and current contract data»;«i.e. Insufficient stakeholder engagement and demonstrable commitment to required resource».
The initial insights, options considered and recommended outcomes are based on careful consideration of the total addressable spend, cashable and non-cashable benefits.
6
Project Timeline per initiative
Source: Spikes Cavell
«Commodity» Aug- Oct 2007
Nov-Jan 2007/2008
Feb-Apr 2008 May-Jul 2008 Aug- Oct 2008
Sourcing consolidated contracts
Data Gathering & Strategy
Product level data gathering & analysis
Development of lotting and contract strategy
Stakeholder workshops/presentations
Confirmation of strategy & approach
Formal customer sign-up
Development of specification & SLA
Development & refinement of core list
Sourcing consolidated contracts
OJEU Notice Issued
Pre-qualification of suppliers
Tender preparation & management
eAuction
Final selection & validation
Formal contract award
Implementation & Mobilisation
Mobilisation
First customers go live
Mobilisation of additional customers
Supplier & contract management Estimated contract awards: May 08.
Key: In process Planned Not agreed
E x a
m p
l e
E x a
m p
l e
An estimated project plan for the implementation of each feasible option should be included.
7
UIG Membership
Name Location Dept. Role Tel.
Add Commodity Name hereCapture details of UIG members.
8
Stakeholder EngagementEarly engagement of key stakeholders will help to ensure the following benefits:
The closer alignment of strategy and specification with requirements of users; The identification of leading practices already implemented at local level; The ability to demonstrate increased buy-in to strategy, enhancing leverage in the supply market; and The improved take up of contracts once awarded.
A number of stakeholder workshops are planned for «time frame» : Focus on procurement managers within end user organisations Sector based approach, reflecting different operating environments and status of current arrangements
Other stakeholders (see below) to be targeted later in the year, this will include developing: a standard information pack for users; and a standard information pack/messages for suppliers
Tender &
Contract Award
It is essential that key
stakeholders, across
the organisation
and/or Public Sector,
are consulted in the
refinement and
validation of a number
of aspects of this
commodity sourcing
strategy.
Imp
act
on
su
cces
s
High
LowAdvocacy and
OwnershipSupport and
Buy-inAwareness Commitment and ActionUnderstandingUnaware
Med
Level of Engagement
9
Current Status of Commodity/Contracts
Commodity Name
Definition Source
1 - Commodity Definition
Provide details of
commodities covered
by the strategy.
10
Current Status of Commodity/Contracts
Contract Detail
Contract Scope
Expiry Date Current Pricing
2 – Current Contracts
Provide details of
existing contracts.
11
Policy detail
Reason of impact Source
3 – Relevant Policies/ Processes
Current Status of Commodity/ContractsIt is essential that key
stakeholders, across
the organisation
and/or Public Sector,
are consulted in the
refinement and
validation of a number
of aspects of this
commodity sourcing
strategy.
12
Current Situation
13
Create your Spend Analysis and add it here. This is an example of one format
Spend Analysis
Annual Spend
£0.00
£100,000.00
£200,000.00
£300,000.00
£400,000.00
£500,000.00
£600,000.00
£700,000.00
£800,000.00
£900,000.00
Organisations
Va
lue
Monmouth
Keymed
Diagmed
Cook
Conmed
Boston
14
Sustainability
The Sustainability Test
will help identify and
prioritise the
sustainable aspects
and impacts of your
requirement and
procurement .
Consideration and
actions identified
during strategy
development should
be reviewed and
monitored throughout
the life of the contract
or framework
agreement.
Area Aspects/Considerations Proposed Actions and Potential Impact
Social
Economic
Environment
15
Commodity ProfileProduct Profile
«product profile details including any relevant graphs/tables »
Commodity Tree
Commodity Characteristics Template
Examples of Templates available – See Slide Notes for
details of templates and guidance
Commodity
Sub Com 1 Sub Com 2 Sub Com 3 Sub Com 4 Sub Com 5 Sub Com 6 Sub Com 7 Sub Com 8 Sub Com 9 Sub Com 11
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Training
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Segment
Functionality
End User Requirement
s
Organisation Requiremen
ts
Future Trend
s
Constraints
Summarise key
findings.
16
Market Summary TemplateFactor Findings from research
Market definition
Market Overview
Trade Associations
Key Suppliers
Market growth
Trends and developments
Supply market trends
Summarise key
findings.
17
Supply Market AnalysisInclude any relevant graphs/tables i.e. Public sector spend £ by supplier size (%), Total Scottish market (£) by supplier size «year» (%), total employment in Scotland by supplier size «year» (%), and a synopsis of the SME market analysis”
The format of this slide is an example only. You may choose
to present different analysis tools depending on your
requirement.
SWOT Analysis
Use the Market Summary Template to populate the following:Market definition«definition»
Market size«size»
Structure«structure»
Current supply«supply»
Challenges«challenges»
Competition«competition»
Strengths Weaknesses
Opportunities Threats
Text
Text
Text
Text
Text
Text
Text
Text
Text
Text
Text
Text
POLITICAL
TECHNOLOGICAL
ECONOMIC
SOCIAL-DEMOGRAPHIC
LEGAL
ETHICAL
ENVIRONMENTAL
PEST LEEPEST LEEAnalysisAnalysis
PEST LEEPEST LEEAnalysisAnalysis
18
Supply Market AnalysisOrganisation spend as percentage of supplier turnover in ScotlandThe table below shows the annual turnover in Scotland for the top 10 suppliers in the UK and the Public Sector spend with them.The total Scottish Public Sector spend on «Commodity» is greater than any one of the suppliers’ current turnover in Scotland.
Supplier Name
Annual Turnover in
Scotland £000
Annual Turnover in UK
£000
Current Expenditure
£000
Percentage of turnover Scotland
Percentage of turnover
UK
x xx,xxx xxx,xxx xx,xxx «00»% «0.0»%
x xx,xxx xxx,xxx x,xxx «00»% «0.0»%
x xx,xxx xxx,xxx xxx «00»% «0.0»%
x xx,xxx x,xxx,xxx xxx «00»% «00»%
x xx,xxx xxx,xxx x «00»% «00»%
x xx,xxx xxx,xxx x «00»% «00»%
x xx,xxx xx,xxx x «00»% «00»%
x x,xxx xxx,xxx x,xxx «00»% «00»%
x x,xxx xxx,xxx x,xxx «00»% «00»%
x x,xxx xxx,xxx xxx «00»% «00»%
Sub-total Spend with Top 10 Suppliers xxx,xxx xx,xxx «00»%
Summarise findings and conclusions e.g. 80% of the market is with 20% of the suppliers.
19
Supplier Profile Analysis
Organization and HistoryOrganization and History Strategy and Key Market Segments Strategy and Key Market Segments
Products, Service Range and Operations Products, Service Range and Operations Key Financials and Other DevelopmentsKey Financials and Other Developments
X Supplier is the global leader in the provision of Y solutions
Insert commodity specific Supplier Data. Use 1 slide for each of the top 5 suppliers.You should base the top 5 on whether you think the market is global, European, or UK only
20
Supplier Cost Drivers
Cost Element
(e.g. Material, Labour, Sub-contract, Transport, Overheads…)
% of Overall Price
(Use estimates, market, supplier and existing analysis)
Source of Data Data Confidence (Low, Medium, High)
21
Total Cost of Ownership: Considerations
Acquisition
•
•
•
•
•
•
•
•
•
•
Operation
•
•
•
•
•
•
•
•
•
•
Ownership
•
•
•
•
•
•
•
•
•
•
Disposal
•
•
•
•
•
•
•
•
•
•
22
Risk AnalysisProvide details of risks identified and assessed. Mitigation strategies should be developed where possible/appropriate
ID
Risk
Owner
Description of Risk
Probability/ Impact Result
Date of Assessment
Mitigating Actions
Next review date
1 AN OtherLack of
Stakeholder Buy-in
M/H 01/01/2010Ensure clear comms and engagement
TBC
2 AN OtherSupplier
performance failure
L/H 01/01/2010Contract Mgmt &
monitoring01/02/2010
Risk Identification & Assessment
• The following risks/issues have been identified.
• The following mitigation strategies have been developed & deployed
• xxxxxxxxx
• xxxxxxxxx
• xxxxxxxxx
23
Best Value/Opportunity Analysis
Best value analysis
Area Examples of leading practice Potential/Proposed/Approach to implementation
• Reduce consumption
• Eliminate need
• Find alternative ways of meeting needs
• Policy changes
• Benchmarking usage and consumption across comparable organisations
• «approach»
• Consolidate spend
• Common specification
• Collaboration with other public sector bodies
• A key component of this strategy is to consolidate spend across the Public Sector in Scotland.
• Improve specification
• Detailed specifications
• Lower cost specification (own brand?)
• Optimal service level
• Quantify spend volumes
• Value for Money – cost vs benefits
• «approach»
• «approach»
• Re-structure relationships
• Develop strong relationships with key suppliers
• Introduce supplier development programmes
• Review / establish service level agreements
• Introduce routine supplier monitoring and reporting
• Establish incentivised contracts
• «approach»
• «approach»
• Increase competition
• Price / performance benchmarking
• E- Auction
• Cost driver analysis
• Price harmonisation
• «approach»
• «approach»
Highlight your priorities e.g. which proposals will deliver the most significant gains.
Optimise Total Supply Chain Costs
Reduce / EliminateTransactions
Total Cost Management
Reduce Total Life cycle / Ownership Costs
CostCash
QualityService
InnovationSustainability
Optimise Total Supply Chain Costs
Reduce / EliminateTransactions
Total Cost Management
Reduce Total Life cycle / Ownership Costs
CostCash
QualityService
InnovationSustainability
24
Best Value Analysis (Cont’d.)Best value analysis
Area Example of leading practice Potential/Proposed/Approach taken in this strategy
• Re-structure supply base
• Tender requirements for all spend
• Supplier consolidation
• «approach»
• «approach»
• Reduce / eliminate transactions
• Rationalise suppliers
• Rationalise requirements
• Low value ordering systems (e.g. GPC)
• e-Procurement Scotland / other systems
• Consolidate invoices
• «approach»
• «approach»
• «approach»
• «approach»
• Reduce total life cost / cost of ownership
• Re-engineer processes
• Outsourcing
• Reduce inspection/checking
• Reduce stock holding
• Reduce/consolidate deliveries
• Reduce maverick spend
• «approach»
• «approach»
• Optimise Total Supply Chain Costs
• Design / development
• Integrate logistics
• Frameworks to reduce for lengthy tender processes
• «approach»
• Corporate Social Responsibility
• Focus on demonstrably sustainable (or reduced impact) products, services and solutions
• «approach»
Optimise Total Supply Chain Costs
Reduce / EliminateTransactions
Total Cost Management
Reduce Total Life cycle / Ownership Costs
CostCash
QualityService
InnovationSustainability
Optimise Total Supply Chain Costs
Reduce / EliminateTransactions
Total Cost Management
Reduce Total Life cycle / Ownership Costs
CostCash
QualityService
InnovationSustainability
25
Proposed Strategy
26
Strategic ObjectivesObjectives
Implementation of this category strategy is intended to address «No.» key objectives:
• «i.e. To leverage the £«00»+ million, spent annually, to realise improvements in the value for money obtained in the sourcing of «Commodity» including reductions in product prices, enhancements to product quality and improvements in service levels, where appropriate»;
• «i.e. To increase the take up of leading processes and practices across the sector, including increases in the efficiency of key transactional processes including order, delivery and payment»;
• «i.e. To release valuable ‘local’ and sector procurement resources to enable them to allow them address other areas of spend, increasing the range and depth of third-party expenditure influenced by procurement across the public sector»; and
• «i.e. To reduce the negative environmental and social impact of the use of «Commodity».
In striving to achieve these objectives, the strategy will also seek to consider its impact on:
•«i.e. Incumbent and potential SME suppliers»;
•«i.e. The long term competition in the provision of «Commodity» to the public sector in Scotland»;
•«i.e. The need for continuity of service provision between current and proposed contracts»; and
•«i.e. The need for choice and flexibility to be retained in order to address certain, specific needs of individual end user organisations».
Each of the options considered have been tested against its impact on these objectives and considerations.
The strategy, and the key options considered, have been tested against the aims of the strategy and a number of other important considerations.
Whilst the proposed approach represents the preferred option for realising these aims a number of options were given careful consideration.
27
Principal Options Appraisal
The Authority is
committed to
managing, monitoring
and developing
supplier performance
and understanding
whether our contracts
are delivering and
meeting the needs of
our customers.
Option 1 Option 2 Option 3 Option 4Recommendation
& Justification
1
Procurement Route
Not applicable
Do nothing Use existing framework
Develop bespoke contract
Benefits & Concerns
2
OJEU Procedure
Open Restricted Competitive Dialogue
Other
Benefits & Concerns
28
Principal Options AppraisalThe Authority is
committed to
managing, monitoring
and developing
supplier performance
and understanding
whether our contracts
are delivering and
meeting the needs of
our customers.
Option 1 Option 2 Option 3 Option 4Recommendation &
Justification
3
Lots Not applicable
1 Lot Geographical Product / Service
Benefits & Concerns
4
Suppliers Per Lot
Not applicable
1 Supplier 3 – 5 Suppliers
5 + Suppliers
Benefits & Concerns
29
Proposed InitiativesKey Principles
The proposed approach to the supply market includes:
•«i.e. A single, national and cross-sector sourcing exercise to commence in «Month/year»»;•«i.e. Contract(s) to be awarded by «Date» with a phased implementation and first orders being placed from «Date»;
•«i.e. Contract(s) to cover an initial term of «Years» years with options to extend by a further «Year/s» year/s»; and
•«i.e. Public sector organisations will be expected to confirm their commitment to using the/these contract(s) during «Month/year» (regardless of their anticipated migration date)».
More detail on the specific requirements to be addressed with this/these contracts is provided in the Proposed Statement of Requirements document (which is available separate to this strategy document).
Key Advantages
•«xxxx»;•«xxxx»;
•«xxxx»;•«xxxx».
It is anticipated to deliver savings of up to £«0.0» million per annum for the public sector in Scotland
Potential Issues and Risks
•«i.e. Participation by regional SME suppliers may be limited»;•«i.e. Strategy and sourcing process will need to be carefully explained to stakeholders and suppliers».
The proposed approach is based on «xxxx».
30
Appendices
31
Supplier Selection CriteriaAreas to be included in Supplier Evaluation
Attributes Means of appraisal Minimum Expectations
Financial Status «xxxx» «i.e. “Secure” or better»
Conviction of Criminal Offences
«xxxx» No conflictions
Business Probity «xxxx» No occurrences
Technical and Professional Ability
«xxxx» Meets minimum standards
Health and Safety «xxxx» Must be related to the requirements of the contract
Quality Assurance «xxxx» «i.e. ISO 14001 or equivalent»
Corporate Social Responsibility
«xxxx» Must be related to the requirements of the contract
Insurance «xxxx» Availability of required policies
Transactional Efficiency «xxxx» «i.e. Use of ePS and P-Card»
Potential suppliers will be evaluated against a broad range of criteria.
The criteria listed here are to be reviewed further and provide only an indication of the range of attributes to be considered during the supplier selection process.
32
Supplier Award Criteria
Source: Spikes Cavell
Areas to be included in Supplier Evaluation
Attributes Means of appraisal Minimum Expectations
Price «xxxx»
«xxxx»
Quality «xxxx» meets required quality
Technical Merit «xxxx» meets specification
Delivery «xxxx» « i.e. Delivery date, period or period of completion »
After-Sales Service
Technical Assistance «xxxx» Can provide required service
Running Costs and effectiveness
«xxxx»
Implementation Capability «xxxx»
«xxxx»
Account Management / MI «xxxx»
Product Range «xxxx»
«xxxx»
Transactional Efficiency «xxxx» «i.e. Use of ePS and P-Card»
Environmental Characteristics
«xxxx» Must be linked to the subject matter of the contract
Potential suppliers will be evaluated against a broad range of criteria.
The criteria listed here are to be reviewed further and provide only an indication of the range of attributes to be considered during the supplier selection process.
33
Communication PlanIn addition to the work carried out by the UIG outline how the category strategy and final outcomes will be communicated to individual organisations
- << i.e. road shows>>
- << workshops>>
- << website>>
- <<XXXXX>>
Do CoEs or individual organisations need to provide information or commitment and at what stage of the strategy development or implementation?
- << i.e. intention to participate – before we go out to tender>>
- << sign an Agency Agreement – before the Framework is established>>
- << sign a Participation Agreement – after the Framework is established and prior to the first order being placed>>
- <<XXXXX>>
Timescales for critical activities
- << outline key dates>>
- <<XXXXX>>
- <<XXXXX>>
Comments….
34
Implementation PlanKey steps and requirements
• <<Outline requirements>>
• <<XXXXXXXXXXXX>>
• <<XXXXXXXXXXXX>>
Content Management requirements
• <<XXXXXXXXXXXX>>
•<<XXXXXXXXXXXX>>
Resources and structure
• <<outline>>
• <<XXXXXXXXXXXX>>
• <<XXXXXXXXXXXX>>
Timescales
• <<outline>>
• <<XXXXXXXXXXXX>>
• <<XXXXXXXXXXXX>>
Evaluation and Control
•<<outline>>
• <<XXXXXXXXXXXX>>
• <<XXXXXXXXXXXX>>
Comments….
35
Contract and Supplier ManagementOverview
Strategic Objectives
This approach to Contract & Supplier Management has been developed to;
•Drive continual improvement and benefits from existing and future contractual relationships
•Ensure that all parties to contracts were meeting their obligations
•Measure performance against KPI’s & SLA’s
•Measure behaviours such as communication, responsiveness and innovation
•Provide end users with an opportunity to provide feedback on supplier & contract performance
•Be consistently applied across all categories
Scope
The term ‘contract & supplier management’ can be broken down into the following key component parts:
•Contract Implementation and Management
•Supplier Management and Development
•Operational Management
•Contract Administration
•Supply Chain Innovation & Development
The Authority is
committed to
managing, monitoring
and developing
supplier performance
and understanding
whether our contracts
are delivering and
meeting the needs of
our customers.
36
Contract and Supplier Management
Approach
A balanced scorecard approach has been developed to manage, monitor and develop supplier performance. The scorecard has 4 core indicators and suggested sub-criteria as follows:
At this stage buyers should be aware of the requirement to consider CSM. Further development is required at the ITT stage when Management Information needs will be defined and when KPIs will be identified. The scorecard will be finalised at the contract award stage.
The Authority is
committed to
managing, monitoring
and developing
supplier performance
and understanding
whether our contracts
are delivering and
meeting the needs of
our customers.
Balanced Scorecard
Quality Service
Fit for Purpose Responsiveness
Returns Complaints
CSR Management Information
Continual Improvement/Innovation Education/Training
Delivery Cost
Lead time/delivery time Pricing stability
On time delivery against objectives Invoice accuracy
Accuracy Cost reduction initiatives
Communication