© JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager...

12
© JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1

Transcript of © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager...

Page 1: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

SWERN

JANET South West

Procurement & Transition

Neil ShewryProject Manager

JANET(UK)

1

Page 2: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

Procurement• Prequalification Questionnaire• Competitive Dialogue• Call for Final Tenders• Preferred & Reserve Supplier• Contract Signed• What we’ve Bought

2

Transition• Rollout of the New Network• Migration of Connections

Page 3: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

Prequalification Questionnaire (PQQ)

• Input: 11 suppliers

3

Page 4: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

Prequalification Questionnaire (PQQ)

• Output: 5 suppliers

4

Competitive Dialogue

Page 5: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

Competitive Dialogue

• Input: 5 Suppliers

Technical DialogueLegal Dialogue

Over 30 hours of meetings!

• Output: Call for Final Tenders (CFT)

5

Evaluation & Selection

Page 6: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

Evaluation & Selection

• Preferred Supplier

• Reserve Supplier

• Final Contract Negotiation

6

Contract Signed?

Page 7: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

What We’ve Bought

7

Page 8: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

What We’ve Bought

8

Page 9: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

What We’ve Bought

9

Page 10: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

Rollout of the New Network

• Contract signature by 30 September 2011• Similar topology to existing SWERN network• Audit & survey all PoPs• New circuits delivered by end February 2012

– Retain a few existing circuits

• Re-use some existing equipment– Purchase spares for ease of transition

10

Page 11: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

Migration of Connections

• Provisional plan in place• 2 phase approach

– 1. Core– 2. Access

• Estimated 6-8 week window– Dependent on circuit delivery

11

Page 12: © JANET(UK) 2011 SWERN JANET South West Procurement & Transition Neil Shewry Project Manager JANET(UK) 1.

© JANET(UK) 2011

Questions?

12