Estimation Perspectives (v5) 1 2005 by Richard D. Stutzke Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International COCOMO and Software Cost Modeling Forum Los Angeles, 25-28 October 2005 [email protected]
  • date post

    19-Dec-2015
  • Category

    Documents

  • view

    216
  • download

    0

Transcript of 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke...

Page 1: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 1 2005 by Richard D. Stutzke

Estimation Perspectives

Richard D. Stutzke (SAIC)

25 October 2005

Presented at the 20th International COCOMO and Software Cost Modeling Forum

Los Angeles, 25-28 October 2005

 [email protected]

Page 2: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 2 2005 by Richard D. Stutzke

Topics

• Measurement and Estimation

• Product Size

• Project Cost and Schedule

• Product Performance

• Product Quality

• Process Performance

• Summary

Page 3: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 3 2005 by Richard D. Stutzke

Reasons to Estimate and Measure• Product Size, Performance, and Quality

- Evaluate feasibility of requirements - Analyze alternate product designs- Determine the required capacity and speed of hardware components- Evaluate product performance (accuracy, speed, reliability, availability)- Quantify resources needed to develop, deploy, and support a product- Identify and assess technical risks- Provide technical baselines for tracking and controlling

• Project Effort, Cost and Schedule- Determine project feasibility in terms of cost and time- Identify and assess project risks- Negotiate achievable commitments- Prepare realistic plans and budgets- Evaluate business value (cost versus benefit) - Provide cost and schedule baselines for tracking and controlling

• Process Capability and Performance- Predict resource consumption and efficiency- Establish norms for expected performance- Identify opportunities for improvement

Page 4: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 4 2005 by Richard D. Stutzke

Estimation Uncertainty Typically Decreases with Time

0.0

1.0

2.0

3.0

4.0

5.0

0.0 0.2 0.4 0.6 0.8 1.0

Elapsed Time

Uncertainty (multiple of

estimated value)

Upper 80% Bound

Lower 80% Bound

Zero Error Line

Page 5: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 5 2005 by Richard D. Stutzke

Total Estimation Life CycleDefine Project

(Products, Process)

Identify and Evaluate Risks

Estimate Cost and Schedule

Compare Planned and Actual Values

Improve Process

Calibrate

Re-estimate Cost and Schedule

Organization’s Historical DataOrganization’s Historical Data

Loop 1

Loop 2

Work Breakdown Structure

Close Out Report

Revised Inputs

Enhancements

Budget and Schedule

BEFORE

DURING

AFTER

BEFORE

DURING

AFTER

Project EstimateProject EstimateProject

PlanProject

Plan

Status & Estimate To Complete

Status & Estimate To Complete

Project ActualsProject Actuals

Documented Estimation Models

Documented Estimation Models

Updated Procedures & Checklists

Updated Procedures & Checklists

Perform Planned Activities

Measure

Perform Planned Activities

Measure

Environmental & Business FactorsEnvironmental & Business Factors

RequirementsRequirements

Staff Skill and Availability

Changes in Requirements,

Design, and Environment

Changes in Requirements,

Design, and Environment

Page 6: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 6 2005 by Richard D. Stutzke

Ways to Improve Estimation Accuracy

Before starting the project- Understand product requirements and architecture- Choose a suitable production process and supporting tools- Use a mix of estimating techniques, models, and historical data- Produce the estimate in a disciplined way

During the project- Collect actual measurements (costs, performance, progress)- Watch for violations of the estimating assumptions- Watch for changes in key factors (software size, turnover)- Update the estimate with the latest information

After the project- Collect final measurements- Analyze data and lessons learned- Capture the new information (calibrate models, update checklists)- Improve the estimating process (procedures, new tools, training)

Page 7: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 7 2005 by Richard D. Stutzke

Quantities of Interest Products and Services Delivered

- Size or amount (created, modified, purchased)- Performance (capacity, accuracy, speed, response time)- Quality (conformance to requirements, dependability)- Price and total ownership cost

Project- Effort (activities) - Staff (number, skill and experience, turnover) - Time (phases, schedule milestones)- Effort (direct and indirect)- Costs (labor and non-labor) - Computer resources used for development and test

Process - Effectiveness- Efficiency- Flexibility

Page 8: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 8 2005 by Richard D. Stutzke

Common Challenges

• Identifying the key factors that affect the quantity of interest

• Defining precise measures– Operational definitions– Affordable– Appropriate scale ([Stevens, 1948], [Zuse, 1997]

• Quantifying the influence of the key factors (valid models)• The “object” evolves during development

– “Object” can be the product, project, or process– The final object is not the one initially conceived

Page 9: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 9 2005 by Richard D. Stutzke

Product Size

Page 10: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 10 2005 by Richard D. Stutzke

Labor Dominates Software Project Cost

• The concept:Effort [phrs] = Size [SLOC] / Productivity [SLOC/phr]*

• The challenges– Choice and definition of the size measure

– Defining productivity

– Identifying all the pieces

*Productivity (product size) / (resources expended)

Page 11: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 11 2005 by Richard D. Stutzke

Physical Architecture for a Monitoring Application

Front EndSensors Mainframe Display

Device Drivers

Polling Logic

Comm. Mgt.

Executive (Control Logic)

Algorithms

- Data Validation

- Data Smoothing

- Trend Analysis

Data Management

Comm. Mgt.

Report Generator

GUI Services

Comm. Mgt.

Display Gen.

GUI Services

Page 12: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 12 2005 by Richard D. Stutzke

Software Architecture for a Monitoring Application

Control

- Executive

- Polling Logic(?)

- Self-test

- Data Archiving

System Services

- Communications Mgt.

- Math and Statistics (e.g., LSQ fitting)

- GUI Services

- Data management (RDBMS)

Report Generation

- Report Generation

- Display Generation

Data Analysis

- Data Validation(?)

- Data Smoothing

- Trend Analysis (threshold detect)

Data Acquisition

- Device Drivers

- Polling Logic(?)

- Data Validation(?)

- Units Conversion (scaling, clipping)

Software Product

*The items followed by “(?)” may be allocated different areas depending on various considerations.

Tooling

- Emulators

- Stubs

- Test Drivers

- Test Data Preparation

- Test Data Analysis

- Scripts

Page 13: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 13 2005 by Richard D. Stutzke

Productivity Is Slippery

• Common Issues– What is being counted? (new, modified, prototypes, tooling, breakage)– How is size defined? (Example: a line of source code)– What activities and phase are covered? (CM? QA? RA? I&T?)– How formal is the process? (reviews, documentation)– How skilled is the staff?– How many person-hours per person-month? (overtime, days off)

• Specific Challenges– Software (all components unique, “exceptional” functions overlooked)– Hardware (components and assemblies)– Services (installation, training)– Documents (original, copies)

Page 14: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 14 2005 by Richard D. Stutzke

Migration of Reused Code to the “Dark Side”

0

50

100

150

200

250

300

0.0 0.2 0.4 0.6 0.8 1.0

Elapsed Time (Relative Units)

EstimatedSize

(KSLOC)

Total Size (All Code)

Original Total

Modified + Unmodified

Unmodified Only

Additional New

New

Modified

Copied

Page 15: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 15 2005 by Richard D. Stutzke

Project Cost and Schedule

Page 16: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 16 2005 by Richard D. Stutzke

The Precursors of Estimation

• Customer’s needs and operational environment

• Products and services to be delivered

• Production process to be used

• Project goals and constraints

• Estimate’s purpose and constraints

• Applicable estimating techniques and tools

Page 17: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 17 2005 by Richard D. Stutzke

Project Information Flow

Production Process

Product Architecture

SOWContract

CLINs__________________

Technical Baseline

___________________________________________________

Resource Loaded Network

Cost Baseline

1.0 ____ $1.1 ____ $1.2 ____ $

2.0 ____ $

Master ScheduleAnalyzeDesignCodeTestReviewDeliver

WBS

(Work Packages)

Schedule Baseline

Earned Value Plan

BCWS $ $ $ $BCWP $ $ $ $ACWP $ $ $ $

TPM

Planning Tracking

SpecProduction

ProcessProduct

Architecture

SOWContract

CLINs__________________

Technical Baseline

___________________________________________________

Resource Loaded Network

Cost Baseline

1.0 ____ $1.1 ____ $1.2 ____ $

2.0 ____ $

Master ScheduleAnalyzeDesignCodeTestReviewDeliver

WBS

(Work Packages)

WBS

(Work Packages)

Schedule BaselineSchedule Baseline

Earned Value Plan

BCWS $ $ $ $BCWP $ $ $ $ACWP $ $ $ $

Earned Value Plan

BCWS $ $ $ $BCWP $ $ $ $ACWP $ $ $ $

TPM

Planning Tracking

SpecSpec

Actuals

Project DataEngineering DataProcurement Data

Page 18: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 18 2005 by Richard D. Stutzke

Estimating Techniques*

• Expert Judgment (Delphi or PERT)

• Analogy (“nearest neighbors”)

• Scaling (additive, multiplicative)

• Top-Down

• Bottom-Up

• Parametric Models

*See comparison in Chapter 22 of [Boehm, 1981].

Page 19: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 19 2005 by Richard D. Stutzke

Usage of Estimating Techniques Changes

0

20

40

60

80

100

Phase of the Product's Life Cycle

MethodUse (%)

Experts

Analogies

Bottom Up(Using WBS)

Extrapolationof Actual Data

Parametric Models

Conception Elaboration Construction Transition Operation

Page 20: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 20 2005 by Richard D. Stutzke

Product Performance

Page 21: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 21 2005 by Richard D. Stutzke

Reasons to Estimate Product Performance

• Evaluate feasibility of specified performance• Establish bounds on expected performance• Identify type and amount of computer resources needed

– “Capacity planning”– System sizing

• Identify significant design parameters• Provide information when cannot measure

– Product not yet built– Product is inaccessible (e.g., 24 x 7 x 52)– Measurement is too dangerous or expensive

Page 22: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 22 2005 by Richard D. Stutzke

Typical TPMs for Computer Systems

Accuracy- Correctness (corresponds to real world)- Adequate precision (resolution)

Dependability- Reliability- Availability- Probability Of Failure On Demand

Speed- Response time (GUI)- Execution time (per function, transaction, etc.)- Data transfer rates

Resource Consumption- CPU usage- Storage (memory, disk)- Transmission channel usage (I/O, LAN)- Peripherals

Page 23: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 23 2005 by Richard D. Stutzke

Resource Usage versus System Performance

Software Algorithms

Assumed Operational Profile

Actual Operational Profile

Estimated System

Performance

Hardware Costs

Mission Success

Estimated Resource Usage

Actual Resource Usage

Actual System Performance

Platform Capacity and Configuration

User Acceptance

Page 24: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 24 2005 by Richard D. Stutzke

Estimation and Measurement Challenges

Platform characteristics- Multiple processors- Memory cacheing- Configurable COTS components (e.g., buffer size)- “Hidden” factors (operating system’s scheduler)- Internal workload (other concurrent processes)

External environment and workload- Number of users- External stimuli (probabilistic events, multiple scenarios)

Algorithms- Use of loops, iteration, searches, or sorts- Suitability for assumed workload (scalability)- Choice of parameters (e.g., step size and convergence criteria)- Poorly understood or not yet identified

Relating component behavior to system behavior- Complex (and possibly unknown) interactions of components- Many states and modes (dynamic load balancing, fault tolerance)

Page 25: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 25 2005 by Richard D. Stutzke

Possible Performance Analysis Techniques

• Order of magnitude calculations• Analytic model• Simple queueing results• Bottleneck analysis• Semi-analytic models (e.g., PDQ by Gunther)• Queueing network models• Simulation models• Smart stubs• Benchmark runs on similar system• Measurement of actual system

Page 26: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 26 2005 by Richard D. Stutzke

Comparison of Options

Estimation Measurement

Characteristic Analytic Models Simulation Smart Stubs Benchmark Runs

Choice of Performance Measures Limited Many Limited Limited

Level of Detail Limited Arbitrary Varies Varies

Accuracy (Realism and Fidelity) Approximate Good Good Perfect

Steady State Behavior Yes Yes Yes Yes

Transient Response Limited Yes Yes Yes

Range of Off-Nominal Conditions Some Wide Some Limited

Effort to Develop and Validate the Model or Tool High to Extra High Low to High Low Not Applicable

Effort to Use the Model or Tool (set up, configure, calculate, measure)

Low Low to Very High

Nominal to Very High

Medium to Very High

Page 27: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 27 2005 by Richard D. Stutzke

Performance Estimation is a Cyclic Process

Acceptable performance

Unacceptable performance infeasible

feasible

Assess performance risk

Identify critical use cases

Select keyperformance scenarios

Run and evaluate performance model(s )

Construct performance model(s )

Define quantitative performance objectives

Revise performance objectives

Modify product architecture and design

Modify/create scenarios

Verify and validate models

START

Next IterationAcceptable

performanceUnacceptable performance infeasible

feasible

Assess performance risk

Assess performance risk

Identify critical use cases

Identify critical use cases

Select keyperformance scenarios

Select keyperformance scenarios

Run and evaluate performance model(s )

Run and evaluate performance model(s )

Construct performance model(s )

Construct performance model(s )

Define quantitative performance objectives

Define quantitative performance objectives

Revise performance objectives

Revise performance objectives

Modify product architecture and design

Modify product architecture and design

Modify/create scenarios

Modify/create scenarios

Verify and validate models

Verify and validate models

STARTSTART

*Adapted from Figure 2-1 in [Smith, 2002]. Used with permission.

Next IterationNext Iteration

Page 28: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 28 2005 by Richard D. Stutzke

Product Quality

Page 29: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 29 2005 by Richard D. Stutzke

Quality Factors Vary by System and Stakeholder

0

10

20

30

40

50

60

70

80

90

100Correctness

Performance

Dependability

Usability

EfficiencySupportability

Maintainability

Interoperability

Portability

User

Developer

Perfect

Page 30: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 30 2005 by Richard D. Stutzke

Example: Product Dependability

Installed and Configured

Software

Assumed Operational

Profile

Actual Operational

Profile

Test Platform

Estimated Dependability

Observed Correctness

Actual Dependability

Operational Platform

User Acceptance

Functional Test Cases

Integrated Software

Page 31: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 31 2005 by Richard D. Stutzke

Estimating Challenges

• Distinguishing faults, failures, and problem reports• Understanding fault generation and detection

– Product requirements and architecture– Process (methods, reviews, tests, tools)

• Relating faults to operational failures– Failures often arise from occurrence of multiple events– Assumed operational profile– Predicting the actions of users and abusers

• The “product” evolves during development– Add new features– Revise the design

Page 32: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 32 2005 by Richard D. Stutzke

Testing (Measurement) Challenges

• Test profile differs from the operational profile

• Detection is flawed (Type 1 and Type 2 errors)– Test case (or peer review) fails to expose a real fault– Test case reports a defect when there is actually no fault

• Comprehensive testing is seldom possible– Many combinations to cover (inputs, modes, internal states)– Limited time for testing– Never trigger some faults (so never see resulting failure)

• The product changes during testing– Remove defects (“reliability growth”)– Add defects (“bad fixes”)– May even add features– Every change gives a new product to sample

Page 33: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 33 2005 by Richard D. Stutzke

Comparison of Options

Estimation Measurement

Characteristic Analytic Models Simulation Stress Tests Operational Use

Choice of Quality Measures* Limited Limited Limited Limited

Level of Detail Limited Varies Limited to dependability

Varies

Accuracy (Realism and Fidelity) Approximate Varies Perfect (if product is complete)

Good

Effort to Develop and Validate the Model or Tool High to Extra High Low to High Low Not Applicable

Effort to Use the Model or Tool (set up, configure, calculate, measure)

Low Low to Very High

Low to Medium Nominal to Medium

*Dependability is most objective and mature. Customer preference is subjective.

Page 34: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 34 2005 by Richard D. Stutzke

Determining Product DependabilityConcept

Definition

SystemDefinition

SoftwareRequirements

Analysis

ProductDesign

DetailedDesign

Coding andUnit Testing

IntegrationTesting

Dependability(Stress)TestingFactory

AcceptanceTesting

SiteOperational

Testing

Operations

SpecifyDependability

Goal

EstimateDependability(“Prediction”)

MeasureDependability(“Estimation”)

ObserveDependability

ApplicationMetrics

RequirementMetrics

DesignMetrics

CodeMetrics

DesignMetrics

TestData

TestData

TestData

TestData

ActualPerformance

Page 35: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 35 2005 by Richard D. Stutzke

Process Performance

Page 36: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 36 2005 by Richard D. Stutzke

Process Control: Measurements + Models

Predict Process

Performance

Predict Process

Performance

Control the

Process

Control the

Process

Execute the

Process

Execute the

Process

Measure the

Process

Measure the

Process

Define and Improve the

Process

Define and Improve the

Process

Data, Information, and Measurements

Predictions

Defined (and Improved) Process

Legend

Data, Information, and Measurements

Predictions

Defined (and Improved) Process

Data, Information, and Measurements

Predictions

Defined (and Improved) Process

Legend

Page 37: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 37 2005 by Richard D. Stutzke

• Key Questions

– What is the current performance?– Is this value "good"?– Is it changing?– How can I make the value “better”?

• Candidate Attributes*

– Definition (completeness, compatibility)– Usage (compliance, consistency)– Stability (repeatability, variability)– Effectiveness (capability)– Efficiency (productivity, affordability)– Predictive Ability (accuracy, effects of tailoring and improvements)

*Motivated by [Florac, 1999, Section 2.4]

Measuring Process Performance

Page 38: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 38 2005 by Richard D. Stutzke

Goal Measure

Completeness The number of process elements added, changed, and deleted during tailoring.

Compliance Number of discrepancy reports generated by Quality Assurance audits

Stability (volatility) The number of process elements changed within a specified time interval.

Effectiveness Product quality

Effectiveness Defect leakage to subsequent phases

Efficiency Productivity (or production coefficient)

Efficiency Rework as a fraction of total effort

Predictability Probability distribution for an estimated quantity or related statistics

Some Examples

Page 39: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 39 2005 by Richard D. Stutzke

Type Handles Unstable Processes?

Representation of Process Mechanisms

Examples

Statistical No None Statistical process control

Functional No Explicit Parametric models (algorithms based on causal mechanisms). COQUALMO and staged models.

Dynamic Yes Implicit (via propagation)

System dynamics models (Coupled equations embody the causal mechanisms. Solving numerically gives predicted behavior.)

Types of Process Performance Models

Page 40: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 40 2005 by Richard D. Stutzke

Comparison of Options

Measurement Estimation

Characteristic Statistical Functional Models Dynamic Simulation

Choice of Performance Measures Limited Limited Many

Level of Detail Limited Varies Arbitrary

Accuracy (Realism and Fidelity) Perfect (for specified scope)

Approximate Varies

Steady State Behavior Yes Yes Yes

Transient Response No Limited Yes

Range of Off-Nominal Conditions Limited Some Wide

Effort to Develop and Validate the Model or Tool Low to High Low to High Low to Very High

Effort to Use the Model or Tool (set up, configure, calculate, measure)

Medium to High Low Low to High

Page 41: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 41 2005 by Richard D. Stutzke

• The process definition– Detail

– Stability

– Tailoring

• The process execution

– Compliance

– Consistency

• The model’s scope, and validity

– Relevant factors and interactions

– Fidelity

Factors Affecting Predictive Accuracy

Page 42: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 42 2005 by Richard D. Stutzke

Summary

Page 43: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 43 2005 by Richard D. Stutzke

Estimation and Measurement Are Coupled

• Estimates provide predicted information to:– Assess product and project feasibility– Evaluate tradeoffs in performance, quality, cost, and schedule– Identify and obtain resources– Prepare plans to coordinate and track work

• Measurements provide actual information to:– Verify expectations and detect deviations– Control processes (preserve estimating assumptions, adapt to

changes)– Prepare revised estimates– Formulate, validate, and calibrate predictive models– Improve decision making for projects and businesses– Help the business adapt to changing conditions

Page 44: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 44 2005 by Richard D. Stutzke

Recurring Themes

• Estimation is a continuing process– Accuracy usually increases with time (“learning curve”)– You get what you pay for at any particular time– Perfectly accurate estimates are impossible (and are not

needed!)• A little, good data goes a long way (90/10 rule)

– There are never enough resources (time, money)– Use Goal – Question – Measurement to choose– Precise definitions are essential (e.g., “line of code” and

“defect”)• Some quantities are harder to estimate than others

Page 45: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 45 2005 by Richard D. Stutzke

Relative Estimation Difficulty

1. Project Cost

2. Product Size

3. Project Effort

4. Project Schedule

5. Product Performance

6. Product Quality

7. Process Performance

Increasing Difficulty

Page 46: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 46 2005 by Richard D. Stutzke

References (1 of 2)General

[Stutzke, 2005] Estimating Software-Intensive Systems: Projects, Products, and Processes, Richard D. Stutzke, Addison-Wesley, 2005, ISBN 0-201-70312-2.

Project Effort, Cost, and Schedule

[Boehm, 2000] Software Cost Estimation with COCOMO II, Barry W. Boehm, Chris Abts, A. Winsor Brown, Sunita Chulani, Bradford K. Clark, Ellis Horowitz, Ray Madachy, Donald Reifer, and Bert Steece, Prentice-Hall, 2000, ISBN 0-13-026692-2.

[Boehm, 1981] Software Engineering Economics, Barry W. Boehm, Prentice-Hall, 1981, ISBN 0-13-822122-7.

Product Performance

[Jain, 1991] The Art of Computer Systems Performance Analysis Techniques for Experimental Design, Measurement, Simulation, and Modeling, Raj Jain, John Wiley and Sons, 1991, ISBN 0-471-50336-3.

[Gunther, 2000] “The Practical Performance Analyst: Performance-By-Design Techniques for Distributed Systems”, Neil J. Gunther, Authors Choice Press (an imprint of iUniverse.com, Inc.), 2000, ISBN 0-595-12674-X. Originally published in 1998 by McGraw-Hill as ISBN 0079-12946-3.

[Smith, 2002] Performance Solutions: A Practical Guide to Creating Responsive, Scalable Software, Connie U. Smith and Lloyd G. Williams, Addison-Wesley, 2002, ISBN 0-201-72229-1.

Page 47: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 47 2005 by Richard D. Stutzke

References (2 of 2)

Product Quality

[Kan, 2003] Metrics and Models in Software Quality Engineering, 2nd edition, Stephen H. Kan, Addison-Wesley, 2003, ISBN 0-201-72915-6.

[Lyu, 1996] “Handbook of Software Reliability Engineering”, Michael R. Lyu (editor), IEEE Computer Society Press (McGraw-Hill), 1996, ISBN 0-07-039400-8. An excellent, up-to-date coverage of the subject.

Process Performance

[Florac, 1999] Measuring the Software Process: Statistical Process Control for Software Process Improvement , William A. Florac and Anita D. Carlton, Addison-Wesley, 1999, ISBN 0-201-60444-2.

[Madachy, 2005] Software Process Modeling with System Dynamics, Raymond J. Madachy, John Wiley & Sons, 2005, ISBN 0-471-27555-0.

Page 48: 2005 by Richard D. Stutzke Estimation Perspectives (v5)1 Estimation Perspectives Richard D. Stutzke (SAIC) 25 October 2005 Presented at the 20th International.

Estimation Perspectives (v5) 48 2005 by Richard D. Stutzke