Citrus County Board of County CommissionersOctober 14th, 2014

ProjectDetails• Important connection

linking Withlacoochee State Trail (46 miles) to Dunnellon Trail (2.5 miles)

Project Steps• Evaluation of alignment alternatives - Complete• Public meeting held on 9/15/2014 - Complete• BOCC selection of preferred alignment - Today• Acquisition of grant funding – Next Step• Design and permitting of trail connector• Construction

Alignment Alternatives

• Withlacoochee State Trail (Gulf Junction Trailhead)

• Dunnellon Trail (CR 39 Trailhead)

• US 41 Crossing

Alternative 1• 1.09 miles• No private property

required• Easement required

from Duke Energy• US 41 Overpass

required• Trailhead to

Trailhead

• 1.28 miles• No private property

required• Easement required

from Duke Energy• US 41 Overpass

required• Trailhead to

Trailhead

Alternative 2

• 1.34 miles• Private property

required• US 41 Overpass

required• US 41 Overpass

ramps may impact existing business access

• Not Trailhead to Trailhead

Alternative 3

• 1.66 miles• Private property

required• US 41 Overpass

not required• Right-of-Way

required from CSX• Not Trailhead to

Trailhead

Alternative 4

Public Meeting Results• Well attended and collaborative• Comment cards indicated support of

Alternative #1 (direct Trailhead to Trailhead connector)

• Significant dialogue related to Delmane Drive typical section:• One 12-ft wide multi-use trail vs. two 6-ft wide sections• Physical separation from vehicular travel lane• This topic will be addressed fully during design stage

and will consider Right-of-Way and Drainage characteristics

Similar to the existing trails (12 foot wide multi-use path)

Withlacoochee State Trail Dunnellon Trail

Alternative 1 Characteristics:Path Typical Section

Alternative 1 Characteristics:Delmane Drive

Preliminary Concept

Alternative 1 Characteristics:Delmane Drive

Preliminary Concept

Alternative 1 Characteristics:Preliminary Bridge Concept

RecommendedAlternative:Alternative 1• Shortest• Trailhead to Trailhead• No private property

acquisition• No significant issues

identified• Public support• Finalize typical section