Operational Qualification ProtocolVial Washer
National Institutes of HealthOperational Qualification Protocol
Equipment:Vial Washer
Protocol #: E-0001-2009-01 Date: 2/8/2010
Facility:National Institutes of Health
Location:9000 Rockville Pike Building 10 Room 1C166A5ABethesda, MD 20892
Revision:None
Title:Operational Qualification Protocol for the Vial Washer.Objective:The objective of this protocol is to document the satisfactory operation of the vial washer used for manufacturing at National Institutes of Health, Inc.
Written By: Narlin BeatyTitle: Qualification Process Solutions
Signature:
Date:
Approved By: ______________________
Title: _____________________________
Signature:
Date:
Approved By: ______________________
Title: _____________________________
Signature:
Date:
Approved By: ______________________
Title: _____________________________
Signature:
Date:
Qualification Process
Solutions, Inc.
PROPRIETARY INFORMATION:Unauthorized Duplication Is Prohibited
DOCUMENT NUMBER E-0001-2009-01 DATE: 2/8/2010 Page 1 of 29
REVISION NUMBER None
Author: Narlin Beaty ______________________ Revision Date: None
Operational Qualification
EQUIPMENT NAME: Vial Washer Equipment No: ________________
OPERATIONAL QUALIFICATION
FOR THE
VIAL WASHER
INSTALLED
AT
NATIONAL INSTITUTES OF HEALTH
BUILDING 10BETHESDA, MD 20892
QUALIFICATION PROCESS SOLUTIONS
13406 BLYTHENIA RD
PHOENIX, MD 21131
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 2 of 29
TABLE OF CONTENTS1.0 Purpose32.0 Scope 33.0 Equipment Description 34.0 Responsibilities 35.0 Reference Documents 36.0 Definitions 47.0 Test Function Number One: OQ Signature Verification List (Attachment #1) 48.0 Test Function Number Two: Test Equipment (Attachment #2) 44.0 Test Function Number Three: Procedure List (Attachment #3) 59.0 Test Function Number Four: Operator Controls and Indicators (Attachment #4) 510.0 Test Function Number Five: Operator Interface (Attachment #5) 511.0 Test Function Number Six: Functional Verification (Attachment #6) 512.0 Test Function Number Seven: Alarms, Safeties and Interlocks (Attachment #7) 613.0 Test Function Number Eight: Sequence of Operations (Attachment #8) 614.0 Test Function Number Nine: Maximum / Minimum Values (Attachment #9) 615.0 Deviation Reporting Log (Attachment #10) 716.0 Operational Qualification Protocol Review (Attachment #11) 717.0 Summary Report Requirements 718.0 Attachment List8
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 3 of 29
1.0 Purpose
The objective of this protocol is The objective of this test function is to verify that the Vial Washer, described in Section 3.0, operates in accordance to manufacturers’ specification, and in accordance with Current Good Manufacturing Practices (cGMP’s).
2.0 Scope
This Operational Qualification pertains to the verification of the operation of the equipment described in Section 3.0 of this protocol, to be installed in the Clean Prep Room at National Institutes of Health, 9000 Rockville Pike Building 10 Pharmacy, Bethesda, MD 20892. This protocol is specific to the Vial Washer and related instrumentation and equipment. This protocol is limited to the sterile manufacturing space. Connected equipment and utilities for this system are not covered in this protocol; refer to specific equipment validations if applicable.
3.0 Equipment Description
The vial washing system consists of a batch washer, and vial plate sets for individual vial sizes, used to wash vials prior to dry heat depyrogenation. Wash media surfaces are constructed of 316 stainless steel, and the base frame is aluminum with 304 stainless steel exterior surfaces.
Plastic wrapped vial packages are received and logged. The vial packages are placed onto flip trays and the plastic is removed while retaining the packaging pattern. An additional set of trays are used to flip and place the vial pack into the vial washer. The vial washer is equipped with a single spray nozzle per vial.
An operator initiates a washing cycle through a PanelView Display and the vials are washed with an alternating series of Water For Injection and Pure Steam. Washed vials are then removed and transferred to trays for dry heat depyrogenation.
The machine is password protected. As delivered, the default password is 2040 (ancillary document gives current password as 1111 and backdoor password as 1357).
4.0 Responsibilities
4.1 Qualification Process Solutions, LLC (QPS)
4.1.1 It is the responsibility of QPS to write this protocol.4.1.2 It is the responsibility of QPS to execute this protocol.
4.2 National Institutes of Health, Inc. (NIH)
Following the execution, NIH will approve the final report associated with this protocol, indicating the executed protocol was completed correctly and all acceptance criteria were met.
5.0 Reference Documents
5.1 Cozzoli Vial Washer O&M5.2 Reference drawings
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 4 of 29
Title Drawing Number DateBasic Machine – SS 320479 2 Jun 2005GW24 Floor Plan FP-1221 22 Apr 2002
Frame Assy 320478 2 Jun 2005Basin and Basin Cover
Assy318893 19 Apr 2002
Inside/Outside Wash Assy – Burkert Valves
320507 8 Jul 2005
Drain Assy 318894 19 Apr 2002Spray Nozzle Assy 308976 20 May 1987
Electrical Schematic (3 drawings)
901690 06 Oct 2006
Pneumatic Schematic 901689 27 Sept 2006Flow Schematic (8.5 x
11”)901688 27 Sept 2006
5.3 Vendor certifications
6.0 Definitions
6.1 Critical Instrumentation – Critical instruments are defined as those whose performance will affect the operation of the system and/or the quality attributes of the processed materials. Critical instruments are calibrated and certified using standards that are traceable to NIST (National Institutes of Standards and Testing).
6.2 Non-Critical Instrumentation – Instrumentation provided for indication or convenience purposes only.
7.0 Test Function Number One: OQ Signature Verification List (Attachment #1)
7.1 ObjectiveTo identify and document all personnel involved in executing this protocol.
7.2 Procedure Verify that each person who executes this protocol signs Attachment #1. Each person must be identified by name, title, company, signature, initials and date on the attached form.
7.3 Acceptance CriteriaSignatures from all personnel involved in execution of this protocol shall be present.
8.0 Test Function Number Two: Test Equipment (Attachment #2)
8.1 Objective To verify and document all test equipment
8.2 Procedure 8.2.1 Complete a list of all the instruments required for conducting OQ testing.8.2.2 Verify that the test equipment/instruments are calibrated and the reference standards
are traceable to National Institute for Standards and Technology (NIST) or other approved standard.
8.2.3 Complete the applicable attachment, indicating the equipment description, ID/serial number, calibration date, re-calibration date.
8.3 Acceptance Criteria
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 5 of 29
All test equipment required for execution shall be calibrated with copies of calibration records attached.
4.0 Test Function Number Three: Procedure List (Attachment #3)
8.4 ObjectiveThe objective of this test function is The objective of this test function is to verify that the Standard Operating Procedures (SOP’s) necessary for proper operation of the equipment have been identified and that when drafted have been attached to this qualification.
8.5 Procedure8.5.1 List and attach SOPs needed for the operation and/or maintenance of this equipment.8.5.2 Complete the applicable attachment with a list of all applicable SOP’s. 8.5.3 If SOPs have been drafted for this equipment, or SOPs are already approved and in
place, then attach copies of the SOPs.8.6 Acceptance Criteria
All associated SOP’s for operation and maintenance shall be listed.
9.0 Test Function Number Four: Operator Controls and Indicators (Attachment #4)
9.1 Objective The objective of this test function is to verify that the controls and indicators operate as specified by vendor recommendations.
9.2 Procedure9.2.1 Operate the control switches listed in the attachment.9.2.2 Visually verify and document the actual equipment response.9.2.3 Document any discrepancies in Attachment #10, Deviation Reporting Log. If any
variances/deviations are present, complete the appropriate deviation/variance form.9.3 Acceptance Criteria
All operator controls and indicators tested shall conform to the expected response.
10.0 Test Function Number Five: Operator Interface (Attachment #5)
10.1 ObjectiveThe objective of this test function is to ensure proper communication between the operator interface, PLC, and equipment.
10.2 Procedure 10.2.1 Display the operator interface screen listed on the attachment.10.2.2 Visually verify and document the actual results of the functions that appear on the
operator interface. 10.2.3 Document any discrepancies in Attachment #10, Deviation Reporting Log.
10.3 Acceptance CriteriaThe actual results of operator interface screens shall conform to the expected responses.
11.0 Test Function Number Six: Functional Verification (Attachment #6)
11.1 Objective The objective of this test function is to verify and document the operation and functionality of the equipment.
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 6 of 29
11.2 Procedure11.2.1 Follow the procedures in the attachment. 11.2.2 Visually verify and document the actual responses as pass or fail against the expected
results.11.2.3 Document all operational parameters used during execution. 11.2.4 Document any discrepancies in Attachment #10, Deviation Reporting Log.
11.3 Acceptance CriteriaAll functional requirements must conform to the expected responses, be explained, or treated as a deviation.
12.0 Test Function Number Seven: Alarms, Safeties and Interlocks (Attachment #7)
12.1 Objective The objective of this test function is to verify and document the operation and functionality of the alarms, safeties and interlocks.
12.2 Procedure12.2.1 Follow the procedures in the attachment. 12.2.2 Visually verify and document the actual responses as pass or fail against the expected
results.12.2.3 Document all operational parameters used during execution. 12.2.4 Document any discrepancies in Attachment #10, Deviation Reporting Log.
12.3 Acceptance CriteriaAll safeties and interlock requirements must conform to the expected responses.
13.0 Test Function Number Eight: Sequence of Operations (Attachment #8)
13.1 ObjectiveThe objective of this test function is to verify and document the operational sequence of the system.
13.2 Procedure13.2.1 Execute the procedures in the order listed.13.2.2 Observe the expected operations and write “Pass” if the results were as expected, and
“Fail” if the expected operation did not take place. 13.2.3 Document any discrepancies in Attachment #10, Deviation Reporting Log.
13.3 Acceptance CriteriaThe operating sequence occurs as expected.
14.0 Test Function Number Nine: Maximum / Minimum Values (Attachment #9)
14.1 ObjectiveThe objective of this test function is to verify the maximum and minimum allowable values of changeable setpoints.
14.2 Procedure 14.2.1 Display the changeable setpoint on the attachment and test maximum and minimum
values.14.2.2 Visually verify and document the actual results of the functions that appear on the
operator interface.
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 7 of 29
14.2.3 Document any discrepancies in Attachment #10, Deviation Reporting Log. 14.3 Acceptance Criteria
The actual results of the changeable setpoint limits shall conform to the expected responses.
15.0 Deviation Reporting Log (Attachment #10)
15.1 Objective The objective of this test function is to document any deviation to the stated test procedure or acceptance criteria, and to evaluate the deviation relative to acceptability of the qualification study.
15.2 Procedure 15.2.1 Document all deviations found during execution.15.2.2 Use additional pages as needed to discuss and explain any deviations.15.2.3 Initial review (Protocol Review) should be completed once all deviations have been
satisfactorily addressed.15.2.4 Prior to NIH approval of the document the deviation form shall be reviewed and
approved internally by NIH personnel. 15.3 Acceptance Criteria
15.3.1 All deviations shall be properly documented on Attachment 11 and subsequent attached pages.
16.0 Operational Qualification Protocol Review (Attachment #11)
16.1 Objective The objective of this test function is to document that this protocol has been reviewed for completeness as per Qualification Process Solutions, LLC Requirements.
16.2 ProcedureComplete attachment with name, title, signature and date.
17.0 Summary Report Requirements
17.1 Objective The objective of this test function is to provide an overview of the test results during the execution of this operational qualification.
17.2 Procedure17.2.1 Generate a final summary on completion of this protocol execution.
17.2.1.1 Compile a summary of the results obtained.17.2.1.2 Generate a conclusion regarding the acceptability of the qualification
results. 17.2.1.3 Include a statement of conformance to the specified acceptance criteria for
each test function. Specifically comment on any deviations and corrective actions taken.
17.2.1.4 Determine the overall executed protocol acceptability.17.2.2 Attach the completed, executed and approved protocol to the final report.
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 8 of 29
18.0 Attachment List
Attachment #1 OQ Signature Verification List 9
Attachment #2 Test Equipment 10Attachment #3 Procedure List 11Attachment #4 Operator Controls and Indicators 12Attachment #5 Operator Interface 13Attachment #6 Functional Verification 23Attachment #7 Alarms, Safeties and Interlocks 24Attachment #8 Sequence of Operation 25Attachment #9 Deviation Reporting Log 28Attachment #10 Operational Qualification Protocol Review 29
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 9 of 29
Attachment #1 OQ Signature Verification List
This section identifies the personnel conducting the Operational Qualification. Each person who will be executing this protocol shall complete an entry on the page.
Print Name TitleDepartment/
Company NameSignature Initials Date
Comments: ________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
Acceptance Criteria: Signatures from all personnel involved in execution of this protocol shall be present.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 10 of 29
Attachment #2 Test Equipment
This attachment identifies the instruments, equipment, and materials that are not part of the equipment or system being qualified, but are used in this qualification.
Equipment Description
Manufacturer ID# Serial #Certified/ Calibrated
Cal.Date
CalDue Date
Initials/Date
RiboflavinYes/No
Ultra-violet light Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Comments: ______________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
Acceptance Criteria: All test equipment required for execution shall be calibrated with copies of calibration records attached.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: _____________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 11 of 29
Attachment #3 Procedure List
List the Standard Operating Procedures (SOP) that are required for execution of this protocol.
SOP Number
SOP Revision #
Procedure TitleEffective
DateInitials/Date
Original Operation of the Vial Washer
Original Maintenance of the Vial Washer
Comments: ________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
Acceptance Criteria: A list of written procedures that are used to operate the equipment is provided above. If procedures are in draft form, attach a copy to the executed protocol.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 12 of 29
Attachment #4 Operator Controls and Indicators
Press the control keys The objective of this test function is to verify that the equipment/system operations function as indicated. Note: document any failing results.
Device Function Expected Results Pass/Fail Initials/Date Vial washer power on/off switch
Turns power on to the vial washer
Power comes on
Comments: ________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 13 of 29
Attachment #5 Operator Interface
Verify that the OIT screen and sub-screens are as expected. Note: Document any failing results.
Panelview Display
Screen 1 - First Screen: The OIT screen below will appear after powering up the vial washer. Values need not be as shown.
Function Expected Results Pass/Fail Initials/Date
This is the OIT opening screen. After powering up this screen appears. Pass/Fail
Comments: ________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 14 of 29
Attachment #5 Operator Interface (continued)
Verify that the OIT screen and sub-screens are as expected. Note: Document any failing results.
Panelview Display
Screen 2 - Main Screen: The screen below will appear after pressing F1 from the First Screen.
Function Expected Results Pass/Fail Initials/Date
This screen permits access to all of the other screens.
The screen displays as shown. Other screens can be accessed by pressing the appropriate function key.
Pass/Fail
Comments: ________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 15 of 29
Attachment #5 Operator Interface (continued)
Verify that the OIT screen and sub-screens are as expected. Note: Document any failing results.
Panelview Display
Screen 3 – Edit Recipe: The screen below will appear after pressing F1 Edit from the Main Screen, entering the correct password on the Password screen, and pressing F5 Done on the Password Screen.
Function Expected Results Pass/Fail Initials/Date
This screen displays recipe parameters and permits editing with the use of a password.
The screen displays as shown, though values may be different. Entry of the correct password activates the Edit mode. The program can be edited using the F1 through F10 keys and the numeric key pad. Pressing the F5 Done key returns the display to the Main screen.
Pass/Fail
Comments: ________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 16 of 29
Attachment #5 Operator Interface (continued)
Verify that the OIT screen and sub-screens are as expected. Note: Document any failing results.
Panelview Display
Screen 4 – Memory Recall: The screen below will appear after pressing F2 Recall from the Main Screen..
Function Expected Results Pass/Fail Initials/Date
This screen displays the current recipe number and permits the selection of a new recipe.
The screen displays as shown. A new recipe number can be selected using the numeric key pad. When the desired recipe is selected, pressing the F5 Done key returns the display to the Main screen.
Pass/Fail
Comments: ________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 17 of 29
Attachment #5 Operator Interface (continued)
Verify that the OIT screen and sub-screens are as expected. Note: Document any failing results.
Panelview Display
Screen 5 - Purge: The screen below will appear after pressing F3 Purge from the Main Screen.
Function Expected Results Pass/Fail Initials/Date
This screen permits the air and water lines to be flushed.
The screen displays as shown. Purge time (up to 99 seconds) can be entered and air or liquid flush can be selected. Pressing F5 Done returns the display to the Main Screen.
Pass/Fail
Comments: ________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 18 of 29
Attachment #5 Operator Interface (continued)
Verify that the OIT screen and sub-screens are as expected. Note: Document any failing results.
Panelview Display
Screen 6 – Alarm History: The screen below will appear after pressing F4 Alarm from the Main Screen.
Function Expected Results Pass/Fail Initials/Date
This screen displays the alarm history and permits alarms to be acknowledged and cleared..
The screen displays as shown. All the alarms shown can be acknowledged and cleared. Pressing F5 Done returns the display to the Main Screen.
Pass/Fail
Comments: ________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 19 of 29
Attachment #5 Operator Interface (continued)
Verify that the OIT screen and sub-screens are as expected. Note: Document any failing results.
Panelview Display
Screen 7 – Password Edit: The screen below will appear after pressing F5 Pass.
Function Expected Results Pass/Fail Initials/Date
This screen enables the password to be changed.
The screen displays as shown. Entering the current password activates the password edit mode. A new password can be entered using the number key pad. Pressing F5 Done returns the display to the Main Screen.
Pass/Fail
Comments: ________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 20 of 29
Attachment #5 Operator Interface (continued)
Verify that the OIT screen and sub-screens are as expected. Note: Document any failing results.
Panelview Display
Screen 8 - Password: The screen below will appear when the F1 Edit key is pressed on the Main Screen.
Function Expected Results Pass/Fail Initials/Date
This screen enables a password to be entered to activate the .program edit mode.
The screen displays as shown. After entering the correct password and pressing the F5 Done key, the display goes to the Edit Recipe Screen.
Pass/Fail
Comments: ________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 21 of 29
Attachment #5 Operator Interface (continued)
Verify that the OIT screen and sub-screens are as expected. Note: Document any failing results.
Panelview Display
Screen 9 – Password Error: The screen below will appear if an incorrect password has been entered.
Function Expected Results Pass/Fail Initials/Date
This screen indicates that an incorrect password has been entered.
The screen displays as shown when an incorrect password is entered. Pressing the F5 Done key returns the display to the Password Screen.
Pass/Fail
Comments: ________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 22 of 29
Attachment #5 Operator Interface (continued)
Verify that the OIT screen and sub-screens are as expected. Note: Document any failing results.
Panelview Display
Alarm Banner: The screen below will appear when an alarm condition occurs. The message may be different from that shown.
Function Expected Results Pass/Fail Initials/Date
This screen displays current alarms.
The screen displays as shown with the current alarm condition listed. Pressing F1 acknowledges the alarm. Pressing F2 clears the alarm.
Pass/Fail
Comments: ________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 23 of 29
Attachment #6 Functional Verification
Verify that the equipment/system operations function as indicated.
Procedure Expected Result Pass/Fail Initials/Date
Material Handling
Use flip trays and load vials into washer. Wash vials. Remove vials and transfer them onto depyrogenation trays.
Repeat test for each vial size.
Vial packs fit into flip trays. Vials fit into vial holders. Vials transfer into depyrogenation trays correctly.
Pass/Fail
Washing Verification
Spray vials with riboflavin solution. Verify presence using black light. Load vials into washer run wash cycle. Inspect vials with black light.
Repeat test for each vial size.
Test results in the visual absence of riboflavin for all vial sizes.
Pass/Fail
Comments: _______________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 24 of 29
Attachment #7 Alarms, Safeties and Interlocks
Verify that the alarms, safeties and interlocks function as indicated.
Procedure Expected Result Pass/Fail Initials/Date
Low Pressure On WFI
While running a wash cycle, the equipment loses air pressure.
An alarm message appears on the display screen.
Pass/Fail
High Pressure On WFIAn alarm message appears on the display screen.
Pass/Fail
Low Pressure On Inlet 3
While running a wash cycle, the equipment loses air pressure.
An alarm message appears on the display screen.
Pass/Fail
High Pressure On Inlet 3An alarm message appears on the display screen.
Pass/Fail
Comments: _______________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 25 of 29
Attachment #8 Sequence of Operation
Verify the sequence of operation.
Sequence Procedure Expected Results Pass/Fail Initials/Date
Power Up and System Operation
1Ensure that the machine powered.
Machine is powered. Pass/Fail
2 Verify air is on. Air pressure is on. Pass/Fail
3Turn the red power switch, on the lower control panel door, to the “I” position.
Power is on to the machine. Pass/Fail
4
Turn the power switch ON and press F1 to initialize PanelView, as prompted by display text.
The PanelView display comes on and shows the First Screen.
Pass/Fail
Normal Wash Sequence
5Using flip trays load vials into vial washer, close lid.
Vials are loaded and lid is closed.
Pass/Fail
6From the PanelView select F2 Recall.
The Recall screen appears, showing the current recipe number.
Pass/Fail
7 Press F5 DoneThe display returns to Main Screen
Pass/Fail
8Press the “Start” push-button to start the wash cycle.
PanelView display indicates valve operation, step timing, and alarm states. When run is finished, the display will light with “COMPLETE” message.
Pass/Fail
9 Remove vials. Vials appear visually clean. Pass/Fail
Comments: ________________________________________________________________________
___________________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 26 of 29
Attachment #8 Sequence of Operation (continued)
Verify the sequence of operation.
Sequence Procedure Expected Results Pass/Fail Initials/Date
Liquid Purge Sequence
10 Press F3 to select Purge.The PanelView display shows the Purge Screen.
Pass/Fail
11 Press F1 to select Water.The display shows Purge Water Lines
Pass/Fail
12Enter values between 1 and 99 seconds for the Purge Time Set and the Remaining Duration.
Time values are entered.
Pass/Fail
13Press the start pushbutton to run the purge cycle.
The purge cycle operates. Upon completion, the display returns to Main Screen.
Pass/Fail
Comments: ________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 27 of 29
Attachment #8 Sequence of Operation (continued)
Verify the sequence of operation.
Sequence Procedure Expected Results Pass/Fail Initials/Date
Air Purge Sequence
14 Press F3 to select Purge.The PanelView display shows the Purge Screen.
Pass/Fail
15 Press F2 to select Air.The display shows Purge Air Lines
Pass/Fail
16Enter values between 1 and 99 seconds for the Purge Time Set and the Remaining Duration.
Time values are entered.
Pass/Fail
17Press the start pushbutton to run the purge cycle.
The purge cycle operates. Upon completion, the display returns to Main Screen.
Pass/Fail
Comments: ________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Acceptance Criteria: The actual results are the same as the expected results or explained.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 28 of 29
Attachment #9 Deviation Reporting Log
Document all deviations found during execution. Note: Make additional copies of this attachment as necessary.
DEVIATION LOG
Deviation Number
Description Resolved (Y/N) Initials & Date
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Comments: _______________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Acceptance Criteria: A list of deviations resulting from the execution of this protocol shall be recorded.
Meets Acceptance Criteria? ( ) Yes ( ) No
Reviewed by: __________________________________ Date: __________
DOC # E-0001-2009-01OPERATIONAL QUALIFICATION PROTOCOL
VIAL WASHERNational Institute of Health, Building 10
Bethesda MD 20892Page 29 of 29
Attachment #10 Operational Qualification Protocol Review
Qualification Process Solutions, LLC signature below verifies this Operational Qualification protocol has been reviewed, for completeness and for accuracy of calculations. A separate final report will be written and attached to this protocol. The final report will discuss any deviations, conclusions, and/or recommendations resulting from the execution of the protocol.
Name (print):_____________________________________
Company (print): __________________________________
Title: ____________________________________________
Signature: ________________________________________ Date: _____________________
NIH Document Review Approvals:
Approved By: ______________________
Title: _____________________________
Signature:
Date:
Approved By: ______________________
Title: _____________________________
Signature:
Date: