Post on 02-Oct-2021
International Journal of Scientific Engineering and Research (IJSER) www.ijser.in
ISSN (Online): 2347-3878, Impact Factor (2014): 3.05
Volume 3 Issue 5, May 2015 Licensed Under Creative Commons Attribution CC BY
Time Impact Analysis on Construction Projects
1Jorvekar Shreyas Praaprao,
2Sushma Shekhar Kulkarni
1P.G.Scholar, Department of Civil Engineering, Rajarambapu Institute of Technology, Islampur, Maharashtra, India
2Director, Rajarambapu Institute of Technology, Islampur, Maharashtra, India
Abstract: Time impact analysis (TIA) is a forward looking tool. This analysis takes into account a schedule that does not include a
delay & one which includes delay. The difference between these two schedules is considered to be the impact of delay for time duration
considerations. The research includes application of TIA on two construction projects and then finding the reasons for delays of those
projects. Along with the learning’s of case study, i.e. the discovered causes for delays & from the literature survey done, a questionnaire
was prepared & questionnaire survey was carried out. A total of 28 causes were identified and classified under 8 major groups. The total
numbers of respondents in this survey were 68, out of which 32 were clients, 12 were consultants & 24 were contractors. This
questionnaire was circulated among the professionals in the industry to find the factor which contributes the most to the construction
project delays. Top ten causes affecting delays the most were identified. This research would be helpful for the stakeholders to act on the
critical causes & further reducing the delays.
Keywords: Forward looking tool, TIA, Stakeholders, Questionnaire
1. Introduction
Construction industry is a vast industry involving number of
participants & varied products. So along with this vastness &
variations come various problems. These problems may be
faced before construction (planning), during construction
(execution), & post construction (in the form of
maintenance).The overall effect of all these problems is
project delays which the Project Management Consultants
(PMC) need to tackle with. These project delays gives rise to
extra resources, extra project cost (cost overruns). The main
participants of the project are owner (company), project
management consultants, structural consultants & the
contractors. These parties keep on blaming each other for the
project delays which take place during the project. There are
continuous disputes between the owner & the contractors,
which the PMC needs to resolve. The time allotted for the
project performance is equally important for the client
contractor and the consultants.
A construction projects, unlike any other project, is expected
to be completed in a certain time that is planned ahead of
starting the physical task of the project during the early
phases. A construction project involves a considerable
amount of finance that goes to staff, machinery and the
capital investment therefore any delay in the completion time
will result in huge losses. The impact of delay is experienced
by all involved parties. Some of the main effects which occur
due to the delays can be named as time overrun, cost overrun,
and disputes between different parties, settlements, lawsuits,
and total abandonment [9].
2. Research Methodology
The research methodology for this study contains two phases.
The first phase includes collection of field data by actually
being on the site. The collection of data has been done in
following way- prepare schedule for the project using
Microsoft Project, perform monitoring & application of TIA
i.e. finding the difference between the prepared schedule &
the actual tracked schedule for calculating the delays
occurred. The difference represents the delay in the project.
Then the activities in which delays have occurred were
studied & the causes for these delays were found. Along with
these causes other causes for construction project delays
were also found from the literature survey done. Also
responsibility analysis i.e. who was responsible for the delays
in the project was found.
The second phase included the formulation of a questionnaire
based on the causes found from the first phase. For this a
total of 28 causes were identified & classified under 8 major
groups. Then this questionnaire was circulated to the
stakeholders of various projects & professionals in the
industry & they were asked to rank these causes or factors in
the questionnaire.
3. Data Collection
The first phase contains actual data collection from two
construction sites & application of TIA i.e. difference
between planned schedule & tracked schedule i.e. actual time
required for the activities to complete.
1.1 Case Study 1
Project - Sugar factory expansion & construction of
cogeneration plant (Boiler Section), Sangamner, Dist-
Ahmednagar
Client - Sahakarmaharshi Bhausaheb Thorat Sahakari Sakhar
Karkhana, Sangamner
Contractor - Pratibha Constructions, Kolhapur
This project included erection of a boiler & its other
supporting machinery. Basically it was a work of industrial
shed along with the erection of machinery. The project
duration was of 6 months & project cost went up to 1.5 Cr.
Scheduling & tracking for the project was done using
Microsoft Project. The tracked schedule showing delays in
the activities marked as red bar is shown in fig 1 below:
Paper ID: IJSER15214 141 of 146
International Journal of Scientific Engineering and Research (IJSER) www.ijser.in
ISSN (Online): 2347-3878, Impact Factor (2014): 3.05
Volume 3 Issue 5, May 2015 Licensed Under Creative Commons Attribution CC BY
The delay occurred in following activities
Casting of the footings
Shuttering for the columns
Casting of the columns
The reasons & responsible factors for the delay were-
The payment of contractor for concreting work was not
done regularly so the casting work was stopped by the
contractor. (Responsibility- Client)
The surveyor has to perform quantity, billing works too,
along with the survey works so there is delay from his side
for marking of shuttering of the footing which further leads
to delay in casting. (Responsibility- Contractor)
Shuttering works for the column should have been started
along with the completion of the footings, but it didn’t
happened so, shuttering for the columns were placed after
all the footings were completed. (Responsibility-
Contractor)
Total financial Impact due to delay
=8000 + 7200+ (10,750+3500)
=Rs 29,450 /-
Figure 1: Tracked schedule of case study 1
1.2 Case Study 2
Project – 84 m chimney for boiler of sugar
factory.Sangamner, Dist- Ahmednagar
Client – Sahakarmaharshi Bhausaheb Thorat Sahakari
Sakhar Karkhana, Sangamner
Contractor – Shree Ranga Engineers Pvt Ltd, Hyderabad
This project included construction of concrete chimney of 84
m height & 3.4 m diameter using slipform technique. The
project duration was of 4 months & project cost went up to
1.5 Cr. Scheduling & tracking for the project was done using
Microsoft Project. The tracked schedule showing delays in
the activities marked as red bar is shown in fig 2 below.
Delay occurred in the following activities:
Foundation of the chimney
Setting up the slipform assembly
Dismantling
Mechanical ladder & platforms
The reasons or responsible factors for the delay were:
• The material was supplied by the client, due shortage of 32
mm bar diameter with the suppliers, the client asked the
structural designers to make changes in the design of
foundation, this took time & hence a delay of 5 days
occurred. (Responsibility- Client)
• RMC plant location was a bit far away on the site so the
contractor was in search of miller/transit mixer for 3 days.
(Responsibility- Contractor)
• Also separate electricity & water connections were not
given near this chimney site by the client. (Responsibility-
Client)
• There was shut down i.e. no electricity during the setting
up of assembly for 2 days(Responsibility- Client)
• The wind velocity was very high which caused problems
for the labours working at height for dismantling of the
slipform assembly. (Responsibility- Natural)
• The client asked the contractor to keep curing the chimney
continuously even when the dismantling & mechanical
ladder fitting works were going on which posed problems
for the labours & work has to be stopped for some time.
(Responsibility- Client)
Paper ID: IJSER15214 142 of 146
International Journal of Scientific Engineering and Research (IJSER) www.ijser.in
ISSN (Online): 2347-3878, Impact Factor (2014): 3.05
Volume 3 Issue 5, May 2015 Licensed Under Creative Commons Attribution CC BY
Calculations of time over-runs:
The project was to be completed on 24-03-2015, but it was
completed on 7-04-2015 .There was a total delay of 10 days
in the project
% time overrun = (Project delay / Original project duration)
x100
% time overrun = (10/106) x 100 = 9.45 %
Total Impact= 10,000+11250+22750+21000+7000+2000
=Rs74,000
Figure 2: Tracked schedule of case study 2
4. Field Observations
From the above two case studies following observations were
done
General Causes of Delays on Construction Projects are-
1. Improper site layout (Responsibility- Contractor)
2. Excavated & demolished material was not properly
dumped (Responsibility- Contractor)
3. Improper management of labour (Responsibility-
Contractor) 4. Site supervisor or in charge was overloaded with extra
work & had to look after number of nearby sites
(Responsibility- Contractor) 5. Personnel's on site have to also perform works other than
the work allotted to them(e.g.-surveyor)
(Responsibility- Contractor) 6. Improper management of activities (Responsibility-
Contractor) 7. If rules & regulation set by the client not followed by
contractor(Safety) (Responsibility- Contractor)
8. Delay in material supply is a major cause too
(Responsibility- Contractor)
9. Change orders (Changes in design or any other
specification changes by the client) (Responsibility-
Client)
10. Improper maintenance & setup of equipments &
plants(RMC) (Responsibility- Contractor)
11. Discontinuous & illegal supply of electricity
(Responsibility- Client) 12. Shutdown (electricity or any other reason )
(Responsibility- Client) 13. Delay in billing & payments of labour (Responsibility-
Contractor) 14. Failure in investigation of type of strata before starting
excavation (Responsibility- Contractor)
15. Fleet of equipments not managed properly(transit mixer)
(Responsibility- Contractor) 16. Seasonal changes also affects the progress of the project
(Environmental causes) 17. Heavy rains can stop the work completely
(Environmental causes) 18. Cold weather hampered the setting of concrete & hence
delay(Chimney site night shift) (Environmental causes)
19. Legal formalities & paperwork to be done for procuring
materials (Responsibility- Client) (Responsibility-
Client) 20. Failure of equipments (e.g. chimney site-mixer)
(Responsibility- Contractor) 21. Slow decision making from client side (Responsibility-
Client)
Paper ID: IJSER15214 143 of 146
International Journal of Scientific Engineering and Research (IJSER) www.ijser.in
ISSN (Online): 2347-3878, Impact Factor (2014): 3.05
Volume 3 Issue 5, May 2015 Licensed Under Creative Commons Attribution CC BY
22. If timely promotions & increment of the employees is
not done, they may be discouraged towards their work
resulting in delays too. (Responsibility- Contractor)
23. Clearances not given from client side to start work e.g.-
clearing power cables or underground conditions
(Responsibility- Client)
1.3 Responsibility Analysis
The above causes were studied & analysis was done to find
out who was responsible for the delays whether it was the
client, contractor or environmental causes or others. Based
upon the observation following analysis was done as shown
in Figure 3.
Figure 3: Pie diagram representing responsibility analysis
The results were as follows-
Client side causes - 26%
Contractor side causes - 61%
Environmental & other causes -13%
5. Questionnaire
Second phase consisted of preparation of questionnaire. By
taking into consideration above 23 causes from on field
observations & other causes identified from the literature
survey done, a total of 28 causes were finalised & classified
into 8 groups. The questionnaire was circulated to around 80
professionals from civil industry from the categories client,
consultants, and contractors, out of which 68 professionals
responded to the questionnaire. So the response rate is (68/80
* 100) 85 %, which is considered a good rate for such
surveys.
1.4 Data Analysis Approach
The data analysis was carried out using Statistical Package
for the Social Sciences (SPSS). SPSS was used to generate
the frequency (fi) of the response category index for the
delay causing factors. The relative importance index (RII)
for each factor was calculated using the frequency data for
each response categories generated from SPSS. The RII is
the calculation of the mean frequency of each responses
category index for the probability [5]. It is calculated using
equation (1) given below: n
∑ w i f i
i=1
RII = ________ (1)
n
∑ f i
i =1
Where fi is the frequency of the ith
response and wi is the
weight assigned to the ith
response.
6. Results and Findings
After the analysis done using SPSS, ranking to the causes
were given based responses given by the three categories i.e.
client, contractor, consultant.
The top ten factors based on the RII by considering all the
categories together are tabulated in Table no 1 below
Table 1: Ranking of all categories together
FACTORS /CAUSES RII RANK
DELAYED PAYMENTS & BILLS 0.782 1
POLITICAL ISSUES 0.776 2
LACK OF COORDINATION IN VARIOUS
DEPARTMENTS 0.767 3
LAND ACQUISITION 0.752 4
IMPROPER COMMUNICATION 0.747 5
BUILDING PERMITS & APPROVAL 0.717 6
SHOP DRAWING APPROVAL 0.691 7
MATERIAL PROCUREMENT & PRICE
VARIATION 0.673 8
RAINS 0.652 9
CHANGE ORDERS 0.641 10
The top ten factors based on the RII by considering the
responses of clients only, are tabulated in Table no 2 below.
Table 2: Ranking of factors by the clients
FACTORS /CAUSES RII RANK
POLITICAL ISSUES 0.775 1
LAND ACQUISITION 0.768 2
LACK OF COORDINATION IN VARIOUS
DEPARTMENTS 0.725 3
DELAYED PAYMENTS & BILLS 0.718 4
SHOP DRAWING APPROVAL 0.712 5
POOR FINANCIAL MANAGEMENT &
CONTROL 0.706 6
BUILDING PERMITS & APPROVAL 0.693 7
IMPROPER COMMUNICATION 0.687 8
DECISION MAKING IN DEVELOPMENT
STAGES 0.650 9
MATERIAL PROCUREMENT & PRICE
VARIATION 0.606 10
The top ten factors based on the RII by considering the
responses of contractors only, are tabulated in Table no 3
below.
Paper ID: IJSER15214 144 of 146
International Journal of Scientific Engineering and Research (IJSER) www.ijser.in
ISSN (Online): 2347-3878, Impact Factor (2014): 3.05
Volume 3 Issue 5, May 2015 Licensed Under Creative Commons Attribution CC BY
Table 3: Ranking of factors by the contractors
FACTORS /CAUSES RII RANK
DELAYED PAYMENTS & BILLS 0.825 1
IMPROPER COMMUNICATION 0.775 2
CHANGE ORDERS 0.766 3
LACK OF COORDINATION IN VARIOUS
DEPARTMENTS 0.741 4
POLITICAL ISSUES 0.733 5
MATERIAL PROCUREMENT & PRICE
VARIATION 0.708 6
BUILDING PERMITS & APPROVAL 0.700 7
LAND ACQUISITION 0.675 8
RAINS 0.666 9
SHOP DRAWING APPROVAL 0.641 10
The top ten factors based on the RII by considering the
responses of consultants only, are tabulated in Table no 4
below.
Table 4: Ranking of factors by the consultants
FACTORS /CAUSES RII RANK
LAND ACQUISITION 0.866 1
LACK OF COORDINATION IN VARIOUS
DEPARTMENTS 0.850 2
DELAYED PAYMENTS & BILLS 0.816 3
POLITICAL ISSUES 0.800 4
IMPROPER COMMUNICATION 0.783 5
SITE LAYOUT CHANGES 0.750 6
BUILDING PERMITS & APPROVAL 0.750 7
CHANGE ORDERS 0.733 8
SHOP DRAWING APPROVAL 0.733 9
MATERIAL PROCUREMENT & PRICE
VARIATION 0.733 10
7. Summary of Findings
The objective of the research was to find the in general the
causes & the responsible category for the delays of the
construction projects. The results were as follows- Client
side causes were 26% Contractor side causes were 61%
Environmental & other causes were 13%. The top ten factors
responsible for delays based on responses from all the
categories of respondents were as follows - delayed
payments & bills, political issues, lack of coordination in
various departments, land acquisition, improper
communication, building permits & approval, shop drawing
approval, material procurement & price variation, rains &
change orders.
8. Remedial Measures
From the above analysis done, following are the measures
which could be implemented to reduce the major delays:
i. There should be proper financial management, the
contractors must submit the bill as suggested by the
client & the client should see that the bills are cleared
as early as possible once the bill is submitted.
ii. For proper coordination between various departments
centrally located server with access to all departments
as well to all the stakeholders of the project should be
provided for smooth functioning.
iii. The policies for land acquisition should be such
prepared that there is no injustice made to the land
owners & they get proper values for their land. There
should be proper negotiations between the
stakeholders so the land acquisition becomes easy.
iv. The stakeholders should have clear idea about the
project. Meetings & other modern communication
tools like video conferencing, social networking sites
should be used for improved communication.
v. The lengthy documentation process should either be
reduced or digitalisation of this process should take
place so a person need no to go the offices for
approvals all the time.
vi. The shop drawing approvals should be fast, there
should be proper communication between the
contractor & the structural consultants so that the
drawing is handed over to contractor on time.
vii. Inventory management should be followed along with
application of techniques like ABC analysis for. The
client should have an alternative material supplier for
avoiding delays & price escalation.
References
[1] Cheryl Semple, Francis T. Hartman, and George Jergeas
(1994), “Construction Claims and Disputes: Causes and
Cost/Time Overruns.” J. Constr. Eng. Manage., 120(4),
page no. 785–795.
[2] David Arditi, Thanat Pattanakitchamroon (2006),
“Selecting a delay analysis method in resolving
construction claims”, International Journal Of Project
Management, page no. 145-155
[3] Ayman H, Al-Momani (2000), “Construction Delay: A
quantitative analysis”, International Journal Of Project
Management, page no. 51-59
[4] Daisy X. M. Zheng, S. Thomas Ng, and Mohan M.
Kumaraswamy (2004), “Applying a Genetic Algorithm-
Based Multiobjective Approach for Time-Cost
Optimization”, J. Constr. Eng. Manage., 130(2), page no
168–176
[5] Omayma Motaleb and Mohammed Kishk (2010), “AN
INVESTIGATION INTO CAUSES AND EFFECTS OF
CONSTRUCTION DELAYS IN UAE”
[6] Sadi A. Assaf, Mohammed Al-Khalil, and Muhammad
Al-Hazmi (1995), “Causes of Delay in Large Building
Construction Projects”, J. Manage. Eng., 11(2), page no
45–50.
[7] Awad S. Hanna, Jeffrey S. Russell, Erik V. Nordheim,
and Matthew J. Bruggink (1999). “Impact of Change
Orders on Labor Efficiency for Electrical Construction”,
J. Constr. Eng. Manage., 125(4), page no 224–232.
Paper ID: IJSER15214 145 of 146
International Journal of Scientific Engineering and Research (IJSER) www.ijser.in
ISSN (Online): 2347-3878, Impact Factor (2014): 3.05
Volume 3 Issue 5, May 2015 Licensed Under Creative Commons Attribution CC BY
[8] Zaki M. Kraiem and James E. Diekmann (1987),
“Concurrent Delays in Construction Projects” J. Constr.
Eng. Manage., 113(4), page no. 591–602 Sabah Alkass,
Mark Mazerolle& Frank Harris (2010), “Construction
delay analysis techniques”, Construction management
and Economics 14(5), pageno. 375-394.
[9] Aibinu, A and Jagboro, G (2002), “The effects of
construction delays on project delivery in Nigerian
construction industry.” International Journal of Project
Management, 20,593-9
Paper ID: IJSER15214 146 of 146