THERMOGRAPHY REPORT
Report No. :- 01
MAIN LOCATION:- SWITCH YARD (400 KV), BAY-02
Location Equipment Date Cursor-1 Cursor-2 Diff. Temp.
ISOLATOR
(402-89-AL)CT SIDE
06.04.10 55.6 38.2 17.4
Objective:- R
Basic Observation:- . Ris over heated.
Analysis & Recommendation:- Rtemp. is in semi critical range so close monitoring
is needed. Should be attended in the next priority.
Client Analysis by:- Client Representative:-
8/12/2019 Thermography of Switchyard
2/8
THERMOGRAPHY REPORT
Report No. :- 02
MAIN LOCATION: - SWITCH YARD (400 KV), BAY-05
Location Equipment Date Cursor 1 Cursor 2 Diff.
Temp.
Avg.
Temp.
ISOLATOR
(405-89-TB)CT SIDE
21.02.2011 53.2 35.2 35.3 44.2
Objective:- B
Basic Observation:- . Bis over heated.
Analysis & Recommendation:- Btemp is in semi critical range and may createproblem in near future so it should be attended in next priority .
Client Analysis by:- Client Representative:-
8/12/2019 Thermography of Switchyard
3/8
THERMOGRAPHY REPORT
Report No. :- 03
MAIN LOCATION:- SWITCH YARD (400 KV), BAY-02
Location Equipment Date Cursor-1 Cursor-2 Diff. Temp.
ISOLATOR
(402-89-AA)CENTRE
06.04.10 69.2 43.4 25.8
Objective:- B
Basic Observation:- . Bis over heated.
Analysis & Recommendation:- Btemp. is in semi critical range and may create
problem in near future so close monitoring is needed.
Client Analysis by:- Client Representative:-
8/12/2019 Thermography of Switchyard
4/8
THERMOGRAPHY REPORT
Report No. :- 04
MAIN LOCATION:- SWITCH YARD (400 KV), BAY-03
Location Equipment Date Cursor-1 Cursor-2 Diff. Temp.
ISOLATOR
(403-89-AT) 1BBUS 2 SIDE
06.04.10 67.3 35.6 31.7
Objective:- R
Basic Observation:- . Ris over heated.
Analysis & Recommendation:- :- Rtemp. is in semi critical range so it should be
under regular monitoring .Check the loose connection .
Client Analysis by:- Client Representative:-
8/12/2019 Thermography of Switchyard
5/8
THERMOGRAPHY REPORT
Report No. :- 05
MAIN LOCATION: - SWITCH YARD (400 KV), BAY-07
Location Equipment Date Cursor 1 Cursor 2 Diff.
Temp.
Avg.
Temp.
ISOLATOR
(407-89-AA)
BREAKER
SIDE
22.02.2011 53.3 34.8 18.5 44.05
Objective:- Y
Basic Observation:- . Yis over heated.
Analysis & Recommendation: - Ytemp is in semi critical range and may createproblem in near future so it should be attended in next priority.
Client Analysis by:- Client Representative:-
8/12/2019 Thermography of Switchyard
6/8
THERMOGRAPHY REPORT
Report No. :- 06
MAIN LOCATION: - COOLING TOWER
Location Equipment Date Max.
Temp.
Min.
Temp.
Diff.
Temp.
Avg.
Temp.
CT #3 SWITCH
GEAR ROOMFAN G
02.05.2011 103.2 52.8 50.4 64.3
Objective:- R
Basic Observation:- . Ris over heated.
Analysis & Recommendation:- Rtemp is in semi critical range and may createproblem in near future so it should be attended in next priority .
Client Analysis by:- Client Representative:-
8/12/2019 Thermography of Switchyard
7/8
THERMOGRAPHY REPORT
Report No. :-07
MAIN LOCATION :- COOLING TOWER
Location Equipment Date Cursor 1 Cursor 2 Diff.
Temp.
CT #2 SWITCH
GEAR ROOMFAN - K
22.12.2010 126.8 80.3 46.5
Objective:- R,Y
Basic Observation:- . R,Y is over heated.
Analysis & Recommendation:- R,Y temp. is in critical range so it should beattended as soon as possible.
Client Analysis by:- Client Representative:-
8/12/2019 Thermography of Switchyard
8/8
THERMOGRAPHY REPORT
Report No. :- 08
MAIN LOCATION:- TRANSFORMERS
Location Equipment Date Cursor-1 Cursor-2 Diff.
Temp.
GTG 1A GSU TRANSFORMER
BUSHING
30.01.10 55.5 42.9 12.6
Basic Observation:- R is heated.
Analysis & Recommendation:- R transformer bushing Temp is high so it should beattended with next priority .
Client Analysis by:- Client Representative:-