Post on 26-May-2020
ID Task
Mode
Task # Task Name Duration Start
1 MSD I - Detailed Design Review 1 day Sun 11/3/13
2 Thermoelectrics 9 days Mon 11/4/13
3 T2 Testing 3 days Wed 11/6/13
4 T67 CAD model 3 days Mon 11/4/13
5 T3 Final selection 3 days Thu 11/7/13
6 Heat Source & Spreader 18 days Mon 11/4/13
7 T7 Detailed model 3 days Wed 11/6/13
8 T68 CAD - Heat Source 3 days Thu 11/7/13
9 T77 CAD - Heat Spreader 3 days Thu 11/7/13
10 T8 Final Selection 2 days Thu 11/14/13
11 T30 Material 3 days Mon 11/18/13
12 Primary Insulation 24 days Mon 11/4/13
13 T12 Testing Clamping force 2 days Mon 11/25/13
T F S S M T W T F S S M T W T F S
Oct 27, '13 Nov 3, '13 Nov 10, '13
October 2013 November 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: MSD1 Detailed Design
Date: Sun 12/8/13
ID Task
Mode
Task # Task Name Duration Start
14 T13 More Information 7 days Mon 11/4/13
15 T14 Real dimensions for optimizer 3 days Thu 11/14/13
16 T69 CAD model 2 days Mon 11/11/13
17 T15 Final Selection 2 days Wed 11/27/13
18 Secondary Insulation 24 days Mon 11/4/13
19 T18 Dimensions 3 days Thu 11/14/13
20 T19 More options 2 days Mon 11/4/13
21 T20 Final 1 day Thu 11/7/13
22 Heat Sink 35 days Mon 11/4/13
23 T25 Attachment 1 day Tue 11/5/13
24 T66 Detailed model - ANSYS 12 days Mon 11/4/13
25 T26 Options 10 days Mon 11/4/13
26 T27 Final Selection 3 days Thu 11/14/13
T F S S M T W T F S S M T W T F S
Oct 27, '13 Nov 3, '13 Nov 10, '13
October 2013 November 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: MSD1 Detailed Design
Date: Sun 12/8/13
ID Task
Mode
Task # Task Name Duration Start
27 T29 Testing plan 5 days Mon 12/16/13
28 Clamping 24 days Mon 11/4/13
29 T32 Bolt location 5 days Wed 11/13/13
30 T33 Plate bending model 7 days Sun 11/17/13
31 T34 Enclosure bending model 1 day Mon 11/4/13
32 T69 CAD - plate 5 days Mon 11/11/13
33 T70 CAD - socket 1 day Mon 11/4/13
34 T71 CAD - bolt 7 days Sun 11/17/13
35 T47 Final plate selection 3 days Mon 12/2/13
36 Seals 24 days Mon 11/4/13
37 T37 Gasket options 3 days Wed 11/6/13
38 T38 Dimensions 10 days Sun 11/17/13
39 T39 Gasket vs O-ring - Why? 1 day Tue 11/5/13
T F S S M T W T F S S M T W T F S
Oct 27, '13 Nov 3, '13 Nov 10, '13
October 2013 November 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: MSD1 Detailed Design
Date: Sun 12/8/13
ID Task
Mode
Task # Task Name Duration Start
40 T41 Flange design 1 day Wed 11/6/13
41 T42 Options for flange 1 day Mon 11/4/13
42 T72 CAD - Flange 1 day Thu 11/7/13
43 T73 CAD - Seals 1 day Thu 11/7/13
44 Conduit 1 day? Mon 11/25/13
45 T43 Final connector 1 day Thu 11/7/13
46 T45 Final seal selection 1 day Wed 11/6/13
47 Enclosure 27 days Mon 11/4/13
48 T50 Shape 1 day Mon 11/4/13
49 T51 Dimensions 1 day Thu 11/7/13
50 T52 Material 1 day Mon 11/11/13
51 T53 Make vs. Buy 1 day Wed 11/6/13
52 T74 CAD - Lid 1 day Mon 11/11/13
T F S S M T W T F S S M T W T F S
Oct 27, '13 Nov 3, '13 Nov 10, '13
October 2013 November 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: MSD1 Detailed Design
Date: Sun 12/8/13
ID Task
Mode
Task # Task Name Duration Start
53 T75 CAD - Other 1 day Mon 11/11/13
54 T76 CAD - Assembly 1 day Mon 11/11/13
55 T54 Manufacture 1 day Mon 11/11/13
56 T53 Tether 1 day Mon 11/11/13
57 T61 Lid Location 1 day Mon 11/11/13
58 Testing 24 days Mon 11/4/13
59 T57 Tank options 3 days Wed 11/20/13
60 T58 Temperature control of tank 3 days Mon 12/2/13
61 T59,T60 Sensors (& purchase) 2 days Tue 12/3/13
62 T62 Safety 2 days Tue 12/3/13
63 T63 Detailed test plan 3 days Thu 11/21/13
64 T64 Final Tank 3 days Mon 12/2/13
65 Electrical Documentation and Presentation
21 days
Tue 11/5/13
T F S S M T W T F S S M T W T F S
Oct 27, '13 Nov 3, '13 Nov 10, '13
October 2013 November 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: MSD1 Detailed Design
Date: Sun 12/8/13
ID Task
Mode
Task # Task Name Duration Start
66 Battery Model 16 days Tue 11/5/13
67 T78 Spice Battery model 16 days Tue 11/5/13
68 T79 Simulink Battery Model 16 days Tue 11/5/13
69 T80 Thermoelectric Model 16 days Tue 11/5/13
70 T81 Full Circuit Model (DC-DC Converter)
7 days Thu 11/7/13
71 T82 Create schematics and plots of all data
7 days Wed 11/20/13
72 T83 Add models and analysis to edge, link to site
10 days Fri 11/15/13
73 Electrical Design 21 days Tue 11/5/13
74 Design PCB and have verified 7 days Wed 11/20/13
75 T84 Find "ammeter" and order 3 days Tue 11/12/13
76 T85 Pick battery and order 8 days Tue 11/5/13
77 T86 Design DC-DC converter 8 days Tue 11/5/13
78 T87 Refine electronics power source - find regulator
6 days Thu 11/7/13
T F S S M T W T F S S M T W T F S
Oct 27, '13 Nov 3, '13 Nov 10, '13
October 2013 November 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: MSD1 Detailed Design
Date: Sun 12/8/13
ID Task
Mode
Task # Task Name Duration Start
79 T88 Pick Microcontroller 3 days Tue 11/12/13
80 T89 Design feedback system to microcontroller
4 days Tue 11/12/13
81 T90 Write pseudocode for controller 12 days Wed 11/13/13
82 T91 Pick connectors, wires 3 days Mon 11/18/13
83 Electrical Assembly 21 days?Tue 11/5/13
84 T92 Wiring/Connecting Subsystem Parts
85 Electrical Design Testing and Validation
86 T93 Validate MPPT algorithm/code
87 T94 Test DC-DC converter
88 Make Contacts 11 days Tue 11/5/13
89 T95 Request John to visit for review, discuss design plan with him
5 days Wed 11/6/13
90 T96 Find professor to discuss power electronics and circuit design, request meeting
7 days Wed 11/6/13
T F S S M T W T F S S M T W T F S
Oct 27, '13 Nov 3, '13 Nov 10, '13
October 2013 November 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: MSD1 Detailed Design
Date: Sun 12/8/13
ID Task
Mode
Task # Task Name Duration Start
91 Purchase 5 days Mon 12/16/13
92 T4 Purchase TEM 0 days Mon 12/16/13
93 T9 Purchase Heater 5 days Mon 12/16/13
94 T16 Purchase Primary Insulation 2 days Mon 12/16/13
95 T21 Purchase Secondary Insulation 1 day Mon 12/16/13
96 T28 Purchase Heat Sink 3 days Mon 12/16/13
97 T46 Purchase seal 1 day Mon 12/16/13
98 T44 Purchase connector Mon 12/16/13
99 T48 Purchase plate Mon 12/16/13
100 T65 Purchase Tank (if needed) Mon 12/16/13
T F S S M T W T F S S M T W T F S
Oct 27, '13 Nov 3, '13 Nov 10, '13
October 2013 November 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: MSD1 Detailed Design
Date: Sun 12/8/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Nov 10, '13 Nov 17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13
November 2013 December 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: MSD1 Detailed Design
Date: Sun 12/8/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Nov 10, '13 Nov 17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13
November 2013 December 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 10
Project: MSD1 Detailed Design
Date: Sun 12/8/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Nov 10, '13 Nov 17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13
November 2013 December 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 11
Project: MSD1 Detailed Design
Date: Sun 12/8/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Nov 10, '13 Nov 17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13
November 2013 December 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 12
Project: MSD1 Detailed Design
Date: Sun 12/8/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Nov 10, '13 Nov 17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13
November 2013 December 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 13
Project: MSD1 Detailed Design
Date: Sun 12/8/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Nov 10, '13 Nov 17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13
November 2013 December 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 14
Project: MSD1 Detailed Design
Date: Sun 12/8/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Nov 10, '13 Nov 17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13
November 2013 December 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 15
Project: MSD1 Detailed Design
Date: Sun 12/8/13
12/16
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Nov 10, '13 Nov 17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13
November 2013 December 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 16
Project: MSD1 Detailed Design
Date: Sun 12/8/13