THE NEW SUEZ CANAL CHALLENGE · 2016. 3. 16. · 2 NEW SUEZ CANAL Two way traffic over 71 km Scope...

Post on 20-Aug-2020

0 views 0 download

Transcript of THE NEW SUEZ CANAL CHALLENGE · 2016. 3. 16. · 2 NEW SUEZ CANAL Two way traffic over 71 km Scope...

\

1

JAAP DEKKER PROJECT DIRECTOR

LONDON

15 MARCH 2016

THE NEW SUEZ CANAL CHALLENGE

\

2

NEW SUEZ CANAL

Two way traffic over 71 km

Scope Challenge Consortium = parallel to original canal over 35 km (KP58.2 – KP 92.6)

Cutting transit time from 20hrs to 11hrs

Increase capacity from 49 ships/day tot 97 ships/day

Increase in Revenues

SUEZ CANAL

\

3

2000 – 600 BC

Several dynasty’s have “dredged” canals connecting the Nile with the Red Sea

1798 NAPOLEON

Interest in finding the remains of an ancient waterway passage

1804 erroneous “survey measurements” indicated a height difference of 10m between Mediterranean & Red Sea

SUEZ CANAL HISTORY

\

4

1854

Ferdinand de Lesseps enlisting the interest of the Egyptian viceroy Said Pasha in the project.

1858

La Compagnie Universelle du Canal Maritime de Suez. Private Egyptian concern, its stock owned chiefly by French and Egyptian interests.

1859

Start of the works

1869

17 November 1869 Opening of the Suez Canal

SUEZ CANAL HISTORY

\

5

SUEZ CANAL HISTORY

\

6

THE SUEZ CANAL – AUGUST 2014 17,000 VESSEL TRANSITS PER YEAR

5 BILLION USD TRANSIT FEES PER YEAR

5% OF EGYPT’S GDP

CANAL ONE WAY TRAFFIC

\

7

THE SUEZ CANAL – THE FUTURE 30,000 VESSEL TRANSITS PER YEAR

12 BILLION USD TRANSIT FEES PER YEAR

25% OF EGYPT’S GDP (INC SCZONE)

THE GOAL IS TWO WAY TRAFFIC

TO BE ACCOMPLISHED IN 1 YEAR

\

8

TENDER ANNOUNCEMENT - 5TH AUGUST 2014

Depth: 24 m

Width: 147 -177 m (toe line)

Length: 35 km

Volume: 170 million m3

President Abdel Fattah al-Sisi “The Project has to be finished within one year”

TENDER PROCESS

\

9

TENDER PROCESS SCOPE OF WORKS CHALLENGE CONSORTIUM

35 km Channel (Lot 2,3,4 &5)

2 Service Channels

\

10

THE CHALLENGE:

Project governed by time pressure but with a fixed end date of August 1st 2015

No preparation period

Record number of equipment required

Record daily productions

Technically not complicated – main challenges in logistics, organization and planning

CHALLENGE CONSORTIUM

\

11

1 YEAR INCLUDING TENDER 13 AUGUST 2014 RECEIVED TENDER

17 SEPTEMBER TENDER SUBMISSION

20 SEPT – 15 OCT NEGOTIATIONS

15 OCTOBER 2014 CONTRACT AWARD

17 OCTOBER 7 DREDGERS DEPARTED

5 NOVEMBER 2014 1ST DREDGER COMMENCED

\

12

STARTING THE PROJECT $1,500,000 PROJECT

220 MILLION M3 OF DREDGING

10 MONTHS TO GO

21 CUTTER SUCTION DREDGERS

5 TRAILING SUCTION HOPPER DREDGERS

2000 PEOPLE ON SITE

1.4MIO M3 PER DAY (PEAK PRODUCTIONS)

1,500M3 FUEL PER DAY

\

13

EQUIPMENT WAS UNDERWAY

Brazil

Russia

Indonesia

Persian Gulf

LOCAL EQUIPMENT SUPPLIERS

Quick start and direct available

Competitive and paid in EGP

Limited reclamation experience

PREPARING ON THE GO

\

14

PHASE 01

\

15

CREATING ACCESS

Access via the north & south entrance

Access via 2 Service Canals

Access via 2 Cross Canals (not part of the design)

Floatation dredging only

MAKING SPACE

\

16

PHASE 02: CREATING SPACE

More CSD equipment arriving

Creating width and depth

Plan ahead the shore connections

TSHD’s added to the fleet

AND MORE SPACE

\

17

PHASE 03: CREATING A CANAL

Use equipment to the maximum

Prepare areas for final surveys

Clean up high spots and reducing the capacity

Handover and acceptance by the Client

DELIVERING THE NEW CANAL

\

18

CHALLENGES, EXTRA M3

\

19

THINK IN SOLUTIONS

Site is a military zone

Both canals dissect the area

Road connections between Sinai and Ismailia area

Irrigation channel crossing the New Canal route

Accommodation for all

Late IT (Wi-max) availability

Working in Consortium with 4 different Partners

45 Nationalities

Use dredgers to their maximum capability

AND THE ENVIRONMENT CONTINUES

\

20

DREDGERS DO NOT COME ALONE

\

21

HUMAN RESOURCES:

Almost 2000 people on site

Up to 200 drivers

4 Accommodation barges

1 Cruise vessel

40 Auxiliary vessels

DREDGERS DO NOT COME ALONE

0

500

1000

1500

2000

2500

0

100

200

300

400

500

600

700

800

Man

pow

er T

otal

Man

pow

er p

er c

ompa

ny

Month

NMDC Boskalis Van OordJan De Nul Hired TOTAL

\

22

DREDGERS DO NOT COME ALONE

\

23

Main office Mercure Hotel

Accommodation Barges

Morgan Hotel

\

24

MOBILISATION COMPLETED IN JUNE

DEMOB COMMENCED IN MAY

CANAL DELIVERED 1 AUGUST 2015

DEMOB COMPLETED 31 OCTOBER 2015

MOB DREDGING AND DEMOB AT ONCE

\

25

SUEZ CANAL PROJECT PROGRESS PICTURES:

\

26

SUEZ CANAL PROJECT PROGRESS PICTURES:

\

27

\

28

\

29

\

30

1 AUGUST 2015 – FINAL COMPLETION