Agenda
Studio ProjectTeam and RolesScheduleRoadmapToolsBudget
The Mappers: “We find your way” P&C #1 3
Agenda
Studio ProjectTeam and RolesScheduleRoadmapToolsBudget
The Mappers: “We find your way” P&C #1 4
Studio Project
Automated Testing FrameworkClient•
Main Objective• Develop a framework that will be integrated in testing
processes used by the Novabase Quality Assurance department
The Mappers: “We find your way” P&C #1 5
Agenda
Studio ProjectTeam and RolesScheduleRoadmapToolsBudget
The Mappers: “We find your way” P&C #1 6
Team and Roles
Team Mappers LOGO
Team RolesTeam Roles Assigned to
Project Leader António Alvim
Communication Manager António Alvim
Client Manager Pedro Mota
Process Manager Paulo Casanova
Configuration Manager Filipe Martins
System Manager Pedro Saraiva
The Mappers: “We find your way” P&C #1 7
Agenda
Studio ProjectTeam and RolesScheduleRoadmapToolsBudget
The Mappers: “We find your way” P&C #1 8
Schedule
Meetings• Internal (weekly)• Mentors (weekly)• Client
oKick-off (2008-09-12)
Process to perform meeting (all types)
The Mappers: “We find your way” P&C #1 9
Agenda
Studio ProjectTeam and RolesScheduleRoadmapToolsBudget
The Mappers: “We find your way”
We’ve done We’re doing We’re going to do
Roadmap
Group name and Corporate ImageMeetingsVirtual machine installation & Support ToolsCreated high-level PlanPrepared for the first P&C
Defining ProcessesPlanning group workAnalyzing client informationStart detailing the WBS
Second client meetingRequirement elicitation
P&C #1 10
The Mappers: “We find your way” P&C #1 11
Agenda
Studio ProjectTeam and RolesScheduleRoadmapToolsBudget
The Mappers: “We find your way” P&C #1 13
Agenda
Studio ProjectTeam and RolesScheduleRoadmapToolsBudget
The Mappers: “We find your way” P&C #1 14
Budget
Week 1 Week 2 Week 30
10
20
30
40
50
60
Time spentBudgeted
Num
ber o
f hou
rs
The Mappers: “We find your way” P&C #1 15
Questions
The Mappers: “We find your way” P&C #1 16
The Mappers: “We find your way” P&C #1 17
Example Estimation
The Estimative using COCOMO II
http://sunset.usc.edu/research/COCOMOII/expert_cocomo/expert_cocomo2000.html
Cocomo II Scenario 1 Scenario 2
New 4000 5000 Reused 0 0 Modified 0 0 Total 4000 5000
Effort Adjustment Factor = 2.0
Effort 26.7 Person-months 34.1 Person-months
Schedule 10.4 Months 11.3 Months
MBASE Phase Distribution
Effort (Person-months)
Effort Schedule (Months
Effort (Person-months)
Effort Schedule (Months
Inception 1.6 1.3 2 1.4 Elaboration 6.4 3.9 8.2 4.2 Construction 20 6.5 25.6 7 Transition 3.2 1.3 4.1 1.4