THE FINANCIALS

The loan for TPF campus

Update

THE FINANCIALS

For the building project

The built up area

First Floor: 2123 sq ft

Ground Floor: 2128 sq ft

Basement Floor: 1641 sq ft

Cost per floor

First Floor: 21 Lacs/ about 48,000 CHF

Ground Floor: 21 Lacs / about 48,000 CHF

Basement Floor: 16 Lacs/ about 36,000 CHF

Constructing the Shishukendra

The activity spaces

A slide for the little ones!

Steps for the oldies!

Ground Floor: Resource Center for Youth and Development

A training hall and space for print and net-based materials and resources

The North side: Staff space

Office rooms

Workstations to seat up to 18 staff members

The East side: the utility corner

The kitchen and store

The washrooms

Sit out and relaxation point!

First Floor: Library and Training Hall

Training Hall for 20 – 25 participants

Library and Resource Center