Visit to C.H. Corn Power PlantFebruary 1, 2007Located 20 miles

southwest of Tallahassee at southern tip of Lake Talquin

One of only two hydroelectric plants in state of Florida

Visit to C.H. Corn Power PlantThree turbines – one

Kaplan and two propellerMaximum power

generation of 12 MWTypical power output is

about 3 MW12 MW is about 3% of

Tallahassee’s typical power need of 425 MW

Visit to C.H. Corn Power PlantBuilt in 1929 by West Florida

Power CompanyAbandoned as a power plant

in 1970Refurbished in 1981 by City

of Tallahassee as a hydroelectric demonstration project

Became fully operational in 1985 under City of Tallahassee Electric Utility Services

Visit to C.H. Corn Power Plant

User Demands

Water Wheel

Generator Head

Rectifier Bridge

Battery Monitor

DC Disconnect

Charge Controller

Dissipating Load

Inverter

NautilusBattery

User Demands

Generator Head

Dissipating Load

and/or InverterAC Controller

Water Wheel

Nautilus

Charge Controller Dissipating Load

DC Disconnect Inverter

DC Signal

Net Meter

UtilityBattery Monitor

Battery

Water Wheel

Nautilus

Grid Connected System w/ No Battery

AC Signal

Dissipating Load

AC Controller

Utility

Net Meter

Utility

Gridpoint Connect

User Demands

or

Renewable Energy

(Can operate in grid connected or islanded mode)

GridpointAll in one design

Integrated inverter, controller, power electronics

Plug and playBattery storageCircuit protectionOnline monitoringCurrently designed for

photovoltaics (interest sparked)

Turbine Options & Costs

ABS Alaskan (www.absak.com)

Nautilus: 3 turbines needed each priced at $10,600 Total = $31,800 Power 3 x 1900 W = 5700 W 50 year expected life

Neptune: 3 turbines needed each priced at $XXXXX Total = $XXXX Power 3 x 1900 W = 5700 W 50 year expected life.

Turbine Options & Costs

Energy Systems & Design (www.microhydropower.com)

LH1000: 9 turbines needed each priced at $2,625

Total = $23,625 Only one year warranty

Water Wheel CostsWater Wheel Factory

Overshot design9 ft diameter, all steel

structure$12,000 Also considered is a

breast wheel design, doubling the price of the original wheel

No Longer Under ConsiderationVoith Siemens Turbine

$500,000Construction Costs

Sponsor only requires component selection and general layout

Turbine and Water Wheel Decision Matrix

Rate0.0562

kW hr

Money Saved (Dollars)

One Year

Pexpavg Rate 1 yr 4.73 103

Fifty Years

Pexpavg Rate 50 yr 2.365 105

IEEE 1547Standard for Interconnecting Distributed Resources with

Electric Power Systems250kW or more requires monitoringIsolation device requiredFrequency must be within 0.5Hz of gridVoltage must be within 10% of grid voltagePhase angle must be within 20° of grid phase

Websitewww.fsuhydroturbine.comPrevious presentations,

fall report, etc available on site

In process of mirroring site to www.eng.fsu.edu/ME_senior_design/2007/team5/index.html

Converting to html

Remaining Schedule

Questions?