SUWECO MINI-HYDRO DEVELOPMENT PROJECTS

CAPACITY: 2.1 MW

CAPACITY: 1.5 MW

Solong Mini-Hydro Plant Project

Brgy. Solong, San Miguel, Catanduanes

SOLONG MINI-HYDRO PLANT PROJECT(REVISED QTO)

ITEM NO. ACTIVITY WT %

QUANTITY RELATIVE WEIGHT (%) %

COMPLETEDPreviou

sPrese

ntTo Date

A. CIVIL WORKS 68.051

64.313 0.150 64.46

3 94.728

B. ELECTRO-MECHANICAL WORK

14.512

14.180 0.030 14.21

0 97.916

C. ENGINEERING SERVICES 2.707 2.707 2.707 100.00

D. 13.2 KV TIE LINE, from Solong Powerhouse to Grid 0.370 0.366 0.366 99.00

E. ADMINISTRATIVE/FINANCIAL COST

14.360

14.356

14.356 100.00

% OF ACCOMPLISHMENT(ACTUAL)

95.923 0.180 96.10

3

% OF ACCOMPLISHMENT(PLAN)

100.00

100.00 0.000 100.0

0

SUMMARY OF ACCOMPLISHMENTSAs of March 1-7, 2010

Dam/Weir Structure

Headrace Pipe

Forebay Structure

Penstock Line

Powerhouse Building

Electro-Mechanical Works

Installation of Water Turbines

Installation of Water Turbines

Sub-Station of Solong Mini-Hydro Power Plant

Sub-Station of Solong Mini-Hydro Power Plant

Hitoma 01Mini-Hydro Plant

Project

Brgy. Obi, Caramoran, Catanduanes

HITOMA 01 MINI-HYDRO PLANT PROJECT(REVISED QTO)

ITEM NO. ACTIVITY WT %

QUANTITY RELATIVE WEIGHT (%) %

COMPLETEDPreviou

sPrese

ntTo Date

A. CIVIL WORKS 55.605

53.353 0.271 53.62

4 96.437

B. ELECTRO-MECHANICAL WORK

22.177

21.004 - 21.00

4 94.709

C. ENGINEERING SERVICES 3.975 3.975 - 3.975 100.00

D. 13.2 KV TIE LINE, from Solong Powerhouse to Grid 1.497 0.823 - 0.823 55.00

E. ADMINISTRATIVE/FINANCIAL COST

16.745

16.745 - 16.74

5 100.00

% OF ACCOMPLISHMENT(ACTUAL)

95.901 0.270 96.17

1

% OF ACCOMPLISHMENT(PLAN)

100.00

100.00 - 100.0

0

SUMMARY OF ACCOMPLISHMENTSAs of March 1-7, 2010

Dam/Weir Structure

Headrace Pipe

Forebay Structure

Penstock Line

Powerhouse Building