SPS Customer Meeting
Transmission DiscussionJune 9, 2008
3
SPP Transmission Expansion Plan (STEP)
Annual ProcessFocus is overall reliability of entire SPP regionSPP conducts the studies for 10 years outSPP invites participation in process
Spring Meeting held on May 21, 2008Summer Meeting – August 13, 2008Fall Meeting - ?
4
SPP STEP
User Input sought by SPP and SPSStudy synopsis
SPP uses various models to test system under different flow conditionsPurpose is to determine upgrades to support increasing loads, sold transmission service Results are “Notices to Construct” (“NTC”) to Transmission Owners each February - letters are on the SPP website
5
SPP STEP
Project TrackingTransmission Owners or constructors response to the NTCTracking Spreadsheet - included in SPP web site, e.g. MOPC Meeting Materials (public) Many SPS projects have gone through SPP’s analysis and verification in the STEPTiming Issues between SPP Need Date and Feasible In-Service Date
6
SPS Projects Under Construction
7
COMPLETED PROJECTSXFR(2) - Denver City 115/69 kV – Upgrade 40MVA > 84MVAXFR - Mustang Station N. 115 kV - Mustang Station 230 kV –
Upgrade 150MVA > 250MVAXFR(2) - Bailey Co 115/69 kV – Upgrade 40MVA > 84MVAXFR(2) - Terry Co 115/69 kV – Upgrade 40MVA > 84MVA,
One installed, one delivered and in queue Line – Amarillo South – Springdraw 115kV - In-service 6/08XFR – Lubbock East 230/115kV – New 250MVATUCO – 230 kV Bus rebuilt as breaker and a half constructionTUCO – Added –50/+150 MVAR static VAR controllerVarious – Added 250 MVAR of 230 kV capacitor banks in Lubbock area
8
IN-PROGRESS PROJECTSMulti - Seminole - Hobbs Project 230 kV
10185 >Re-conductor and reconfigure around Seminole to Hobbs & Add 230 kV line from Mustang to Seminole10186 >Add 230 kV line from Hobbs to Seminole10187 >Add 1st 230/115 kV auto at Seminole Interchange – 150 MVA10188 >Add 2nd 230/115 kV auto at Seminole Interchange – 150 MVA10189 >Extend & re-terminate the Gaines-Amerada Hess Co2 Sub 115 kV line to Seminole10190 >Add 2nd 115 kV line from Amerada Hess Co2 Sub to SeminoleMustang to Seminole lines awaiting CNN approvals.Seminole to Hobbs Plant lines in progress for routing.Awaiting land acquisition for switching and substations.
Hobbs Plant > Transmission and Substation ready for plant.
9
Multi - Seminole - Hobbs Project 230 kV
Mustang Station
-Willard
83
LTG McConal
Z21
T20
Z46
T57
Y95
V66
Jaybee
Seagraves Int.
Denver City Int.
Wasson Sitching Sta.
ODC
Wasson Pump
San Andress
East Denver City
ShellC3
Denver City
Shell #7
C2Allred
El Paso
Shell CO2
BennettPhillips Pump
#1
Russell Pool
Amfrac Mid American
K55
V53
V54
V80
K 20
Y99
Y98
Y86
Y98
T16
T13Tenneco
Boardman
Flannagan
West Hobbs
Sw. Sta.
East Sanger
S. HobbsS. Hobbs
Taylor Sw. Sta.
MillenNE.
Hobbs
N. Hobbs
West Bender
Sanger Sw. Sta.
T14
T15
V54
K20
Gaines Co. Int.
Doss Int.
AHCO 2
T40T39
Monument
Cooper Ranch
Drinkard
Eunice
Seminole
Hobbs
Eunice
Lovington
Maddox
Lea Co. Int
Lea Road
Ward
Seagraves
Moss
LTG-Seagraves
180
385
62
83
214
206
385
62 180
188
176
176
234
48318 132
83
82
83
K49
Lea Co.Waits Sub.
TEXAS GAINES CO.
YOAKUM CO
.
TERRY CO.
LEA CO.
Construct the new Seminole Interchange and reconfigure 115 kV line terminations.
Construct approximately 18 miles 230 kV line from Mustang Station to the new Seminole Interchange .
N
S
EW
Hobbs Station
NewSeminole
Interchange
HiggSwitching
MAPCO
LEGEND
230 kV LINE115 kV LINE69 kV LINE
NEW 230 kV LINENEW 115 kV LINE
18
180
K49
US HIGHWAYSTATE ROAD
CIRCUIT ID
WATER / DRAINAGE
SUBSTATION or INTERCHANGE
TexasSeminole
NEW 230 kV LINE
NEW MEXICONEW MEXICO
StationCunningham
10
HOBBS PLANT – Lea County
11
IN-PROGRESS PROJECTS (cont.)
Line - Plainview-Floyd-Crosby – 115kV line, in progress – ISD 12\1\08XFR – Kress 115/69 kV - Upgrade 40MVA > 84MVA – ISD 6\1\08XFR – Tuco Interchange 230/115kV – Add 250MVA – ISD Fall 2008XFR(2) – Nichols 230/115kV - Upgrade 150MVA > 250MVA –ISD 12\1\08Multi – Hitchland – Texas Co. 230kV & 115kV
Construct new 345/230/115kV Hitchland Interchange to V30, on trackConstruct double-circuit 115kV line from Hitchland Interchange to V30 – ISD 6\2010
XFR(2) – Hale Co. 115/69kV – Upgrade 40MVA > 84MVA – ISD 11\14\08Line – Plant X – Tolk Station West 230kV – Wave traps – ISD ?
12
Line – Plainview - Floyd-Crosby –
115kV
HALECO.
FLOYDCO.
Plainview
Lockney
Floydada
Petersburg
LHE-Plainview
NorthPlainview
LHE-Finney
EastPlainviewPlainview City
WestPlainview
Westridge
South Plainview
CoxInterchange
LHE-Providence
AikenRural
LHE-Aiken
Irick
Barwise
LHE-Harmony
Floyd Co.Interchange
LHE-Petersburg
AllmonSPEC-Becton
LHE-Wilson &
Ellen
LHE-Lone Star
LockneyRural
ToLHE-South
Plains
ToLHE-
Cedar Hill
South Floydada
27
70
Y-76
70
Y-74V-07
Y-77
Y-96
Z-38
T-68
J-01
62
T-65
Z-36
Wreckout ~21 miles of 69kVline from Cox Interchange toFloyd County Interchange ,then rebuild to double circuitdesign for 115kV and 69kV.
ToBriscoe &LHE-South
Plains
N
S
EW
Aiken
Barwise
Construct a new 115kVbus with three (3)115kV line terminalsand one (1) 115kVtransformer terminal atCox Interchange .
Rebuild the 69 kV linefrom Lockney Tap toLockney RuralSubstation.
Lockney Tap
TexasLubbock
LEGEND
SPS 230 kVSPS 345 kV
SPS 115 kVSPS 69 kVREC 69 kVCounty Line
City Limits
REC or Municipal STATIONSPS STATION
207 State Highways
' SPEC ' South Plains Electric Cooperative, Inc.'LHE ' Lighthouse Electric Cooperative, Inc.
SPS Transmission Line Designation
'SEC ' Swisher Electric Cooperative, Inc.
J-01
Proposed 115 kV line
US Highways70
27 Interstate Highways
13
W.P
.EW.T.U.
Amarillo
Liberal EnglewoodElkhart
GateKnowles
Forgan
Beaver
Tyrone
Hooker
Hardesty
Optima
Guymon
Goodwell
Keyes
Boise City
Texhoma
Dalhart
Stratford
Cactus
Sunray
Dumas
Gruver
Spearman
Perryton
Booker Darrouzett Follett
Higgins
Canadian
Channing
Vega
Adrian
Fritch Borger
Stinnett
Sanford
Panhandle
White Deer
Claude
Groom
Pampa
Mclean
Miami
Mobeetie
Wheller
Shamrock
Valero
T.C.
T. C.
T.C.
T.C.
T.C.
T.C.
T.C.
T.C.
T.C.
T. C.
T.C.
T.C.
T.C.
T.C.
T.C.
T.C.
T. C.
T.C.
Ochiltree Co .Interchange
N.P.N. P.N.P.
N.P.N.P.N.P.
N.P. N.P.
N.P.
N.P.
N. P.
N.P.
SpearmanInterchange
N.P.
N.P.
PringleInterchange
Moore Co.Interchange
Sherman Co .Interchange
DalhartInterchange
DallamInterchange
Etter
Dumas19th St .
Potter Co.Interchange
Bushland Interchange Randall Co.
Interchange
Coulter Interchange
Amarillo South
East Plant
Nichols Sta.
Harrington Sta
.
Kirby Sw. Sta.
Grapevine Interchange
Bowers Interchange
Kingsmill Interchange
G.B. G.B.
N. P.
Gray Co . Interchange
Magic City Sub
Riverview
Excell Sub
ColeInterchange
OKLAHOMA
KANSAS
TEXAS
R.B.
TC- Whiting Texas Co. Interchange
Hitchland Interchange
Wildorado
50mi. H.I. To Moore Co.
35mi. H.I. To Pringle (ISD 6/2011)
35mi. H.I. To Ochiltree(ISD 6/2011)
35mi. H.I. To Dallam
35mi. Dallam to Potter
Hutchinson Co. Interchange
Lines for Moore, Dallam, Potter
ISD 6/2010 Blackhawk
Multi – Hitchland–Texas Co. 230kV & 115kV
14
IN-PROGRESS PROJECTS (cont.)
XFR(2) – Floyd Co. 115/60kV – Upgrade 40MVA > 84MVA – ISD 6\2008XFR(2) – Lubbock East 115/69kV - Upgrade 40MVA > 84MVA –ISD 12\2008XFR(2) – Cochran 115/69kV - Upgrade 40MVA > 84MVA – ISD 12\2008Device – Nichols-Whitaker Sub 115kV, Nichols-Cherry 115kV –Terminal upgrades/verifications – ISD 12\2008Line – Curry Co. Interchange – Farmers Electric REC – Clovis 115kV – Terminal upgrade - ISD 12\2008Multi – Seven Rivers – Pecos – Potash 230kV – ISD 6\2009XFR – Yoakum Co. Interchange 230/155kV – ISD 6\2009
15
Multi–Seven Rivers–Pecos–Potash 230kV
16
IN-PROGRESS PROJECTS (cont.)
Multi – State Line – Graves 230kV/115kV – ISD 6\2010
Construct new 230/115kV Wheeler InterchangeConstruct new 115kV line from Wheeler Interchange to new Graves Sub.Construct new Substation for Graves.
17
Stateline – Wheeler Project Simplified Diagram
•GB-WHEELER•Approx. 7 MILES
•CS
•DISTRIBUTION
•115/13.2 kV•10 MVA
•CB
SUBSTATION•GRAVE
•115/69 kV•40 MVA•BOWERS
•CS •FUTURE
•WHEELER SUBSTATION
•ELK CITY
•GRAPEVINE
•150 MVA
•230/115 kV
18
Projects Under ReviewXFR(2) – Carlsbad Interchange - 115kV & 69kV Interchange. Needs 69kV study. Generator may defer, new load may require 115kV. No switching available.XFR – Crosby Co. Interchange - 115kV & 69kV Studies will be conducted to further analyze 69 kV systemLine – Hasting – Van Buren 69 kV & Northwest – North Amarillo SW 69kV - No Project: The recommended reconductor will not be necessary after the Channing & Tascosa loads are converted to 115 kV (ISD 2010)Line – Roosevelt Co. Interchange 115kV – Curry Co.
Interchange 115kv, needs additional studyXFR(2) – Hereford 115/69kV Ckt 1 & 2, No Project. New system configuration mitigates this project.
19
Projects Under Review (cont.)
Line – DF Smith Interchange – DS #21 115kV line, this needs additional studyXFR – Bowers 115/69kV #2 , No Project. New system configuration mitigates this project.Line – DF Smith – DS #21 115kV, this needs additional studyXFR – DF Smith 230/115kV , this needs additional studyLine – South Georgia Interchange – Osage Switching Station
115kV, this needs additional studyXFR – Lynn Co. 115/69kV 3rd XFR, This needs additional studyLine – Lyntegar REC – Brownfield 69kV – Terry Co. Interchange
69kV, this needs additional study
20
Projects Under Review (cont.)
Additional Areas Requiring Study:
Carlsbad Area; Ocotillo Substation conversionRoswell Area; Price Substation/Pine Lodge Substation conversionDalhart Area; 69 kV Capacity IssuesWheeler Area; 69 kV Capacity IssuesAmarillo Area; 115 kV and 69 kV Capacity IssuesHart Area; 69 kV Capacity IssuesPlainview Area; 69 kV Capacity IssuesBrownfield Area; 69 kV Capacity IssuesArea Southeast of Seagraves; 69 kV Capacity IssuesSeminole Area; 69 kV Capacity Issues
21
Proposed Projects
22
Multi – Legacy Interchange – Gains Co. & Doss Upgrades 115/69kV
Gaines Co. Int.
1-39,500115 /69
( EAST )
3-PT1-39,500( WEST )
115 /69
MY
Y
3- PT S,
Y,
Y
S
M
10.8 MVAR
TO TAYLOR
SWITCHINGSTATION
T16
Riley1-7.5 MVA
7768
7. 2 MVAR N.O.
7. 2 MVAR
115/691- 75 MVA
69/231- 20 MVA
69/121-12.5 MVA
Doss. Int.
7.2 MVAR
69 /1222 MVA
N.O.
69/121-9. 375 MVA
M69/12
1-12.5 MVA
LTG - Florey
RECAB189
Boardman Sub
Flannagan Sub
Tenneco Sub
Y98
Y86
T80
V94
NEW
NEW
Legacy Interchange
(NEW)
Construct ~ 1 mile of new
double-circuit 115 kV line
Expand the 115 kV bus for a new line
terminal.
Construct ~ 1 mile of new 115 kV line
Construct 115 kV bus for a new line
terminal.
Construct the 115/69 kV, 75/84 MVA Legacy Interchange with two 115 kV line
terminals and three 96 kV breakers
OpenMove Switch 7768 beyond Riley Tap &
Make Normally Open.
Convert this portion of Y98 from
69 kV to 115 kV.
~5.5 mi.
3.0 mi.
2.5
mi.
1.0
mi.
6.0
mi.
5. 0 mi.
5. 4 mi.
1.0
mi.
115/ 69 kV 1-75/84 MVA
N.O.N.O.
~5.5 mi.
23
Eagle Creek
Artesia
Z5 6
Z08
Navajo #4Navajo #3
Artesia Town
Navajo #1Navajo #2
Artesia Interchange
285
Artesia Country Club
Artesia 13th St . (West)
CVEC Artesia
Z12
Z56
EAGLE CREEK
24
W.P
.EW.T.U.
Amarillo
Liberal EnglewoodElkhart
GateKnowles
Forgan
Beaver
Tyrone
Hooker
Hardesty
Optima
Guymon
Goodwell
Keyes
Boise City
Texhoma
Dalhart
Stratford
Cactus
Sunray
Dumas
Gruver
Spearman
Perryton
Booker Darrouzett Follett
Higgins
Canadian
Channing
Vega
Adrian
Fritch Borger
Stinnett
Sanford
Panhandle
White Deer
Claude
Groom
Pampa
Mclean
Miami
Mobeetie
Wheller
Shamrock
Valero
T.C.
T. C.
T.C.
T.C.
T.C.
T.C.
T.C.
T.C.
T.C.
T. C.
T.C.
T.C.
T.C.
T.C.
T.C.
T.C.
T. C.
T.C.
Ochiltree Co .Interchange
N.P.N. P.N.P.
N.P.N.P.N.P.
N.P. N.P.
N.P.
N.P.
N. P.
N.P.
SpearmanInterchange
N.P.
N.P.
PringleInterchange
Moore Co.Interchange
Sherman Co .Interchange
DalhartInterchange
DallamInterchange
Etter
Dumas19th St .
Potter Co.Interchange
Bushland Interchange Randall Co.
Interchange
Coulter Interchange
Amarillo South
East Plant
Nichols Sta.
Harrington Sta
.
Kirby Sw. Sta.
Grapevine Interchange
Bowers Interchange
Kingsmill Interchange
G.B. G.B.
N. P.
Gray Co . Interchange
Magic City Sub
Riverview
Excell Sub
ColeInterchange
OKLAHOMA
KANSAS
TEXAS
R.B.
TC- Whiting Texas Co. Interchange
Hitchland Interchange
Wildorado
50mi. H.I. To Moore Co.
35mi. H.I. To Pringle (ISD 6/2011)
35mi. H.I. To Ochiltree(ISD 6/2011)
35mi. H.I. To Dallam
35mi. Dallam to Potter
Hutchinson Co. Interchange
Lines for Moore, Dallam, Potter
ISD 6/2010 Blackhawk
Multi – Hitchland–Texas Co. 230kV & 115kV
25
Questions?
26
Coordination of New Delivery Point Requests and Studies
Two FERC Tariffs in play - SPP OATT and XE OATT.SPP formed Delivery Point Addition Task Force (DPATF) to develop procedures for new connection requests - status ongoing.Old Solution - new SPP Tariff request for new delivery point on load went under Aggregate Transmission Service Study -not good at all!
27
Coordination of New Delivery Point Requests and Studies
SPP has agreed that until DPATF gets a final workable procedure, Trans. Owners will study requests
Upon completion of study, study to be provided to SPP for verification, and new loads included in model (assuming customer completes request).
28
Coordination of New Delivery Point Requests and Studies
Need the following data for a new requestDesired In service dateMap showing where the new point of service is locatedLoad projection at the new location, plus any load adjustments from neighboring subs, if affected, for 10 year periodAny special details about the load - large motor, across the line start, etc. Desired connection voltageDescription of customer substation , if known.
29
Coordination of New Delivery Point Requests and Studies
Reference - Xcel Energy Guidelines for Connection of Customer Loads
Link -http://www.xcelenergy.com/docs/corpcomm/TransmInterconnectedCustLoads.pdf
Send request to Annette GallegosStudy Agreement will be preparedAfter Study Agreement is signed, work starts!
30
Coordination of New Delivery Point Requests and Studies
Nominal 60 days, unless consultant is backlogged - few being done in SPS. Upon completion of study, results sent back to requestor. Results not posted on OASIS.Customer must indicate yes to proceed, or no to stop. If nothing heard in 45 days, SPS assumes no!If Yes, connection agreement (or E&P) prepared for signature. Upon signatures of Customer and SPS, capital work order opened and physical work can start.
31
Questions?
32
Generation Interconnection on Wholesale or Retail Systems
Process:SPP GI Study Methodology- If GI Request is on SPS-Owned Transmission System, SPP Will do
Studies Under the SPP OATTFeasibility - quick look System Impact - stability studies and Order 661 compliance (TNA-Insulation Coordination)Facilities Study. Related to construction. Done by SPS for SPP
Interconnect Agreement3 Party Agmt - SPP, SPS, and Generation Owner
33
Generation Interconnection on Wholesale or Retail Systems
SPP’s View of the Transmission in the SPS Balancing Authority (For GI Purposes)
SPS Transmission SystemAll of SPS-owned transmission except radial 69 kV lines.
Other Transmission SystemsMunicipalities, electric cooperatives, distribution systems, Customer-owned transmission buses or lines, and SPS-owned radial 69 kV lines
34
Generation Interconnection on Wholesale or Retail Systems
Who does GI studies on Other Transmission Systems?
SPS distribution - SPS Area EngineersElectric cooperatives, municipalities, transmission owning retail entities - the owners of those facilities or their consultants. SPP normally hasn’t done these studies. May allow them to enter SPP queue, pending a change in policy. SPP will do GI studies, today, only on SPS Transmission System.
35
Generation Interconnection on Wholesale or Retail Systems
Study Methodology for Other SystemsUp to the owner. Suggest patterning after SPP process, with consideration of the FERC Order 661 LVRT/Dynamic support issues.
What is the radial 69 kV issue on GI requests?For GI study purposes, SPP says these are not transmission but distribution lines, and thus any GI requests will not be put in their queue and transmission owner must study them. May have implications with state QF rules - unclear today.
36
Generation Interconnection on Wholesale or Retail Systems
Generation interconnection on other transmission systems provides no transmission service on SPS-owned transmission systemTransmission service must be requested separately through SPP or SPS processesParticipant in SPP Energy Imbalance Market today does not require transmission service
37
Questions?
38
Transmission Service Request/Study
Transmission Service Request for Firm SPP P-P or Network
Request made through SPP OASISShort Term- Studied by SPP Transaction EvaluatorLong term - SPP Aggregate Transmission Study
39
Transmission Service Request/Study
Trans. Service Request for Non-Firm SPP P-P
Request made through SPP OASISShort Term- Studied by SPP
Trans. Service Request for Xcel Energy Firm Network
Request made by letter to Annette GallegosStudied by SPS Transmission Planning..today
40
Transmission Service Request/Study
Trans. Service Request for Xcel Energy Short Term Firm Network
Request made on SPS OASISStudied by SPP
41
Transmission Service Request/Studyfor
Generators Connected to Others
Will depend on type of service requestedGen Owner may choose to go hourly non-firm
Evaluation becomes a real time view and may risk frequent curtailmentExample - SPP EIS MarketNo signals for transmission construction -increased congestion likely!
42
Questions?
43
Interconnection Agreements for Generators Connected to Others
SPP & SPS not party to IAIssues:
Compliance with transmission and distribution owners generation interconnection guidelinesCurtailment of generationUnderfrequency compliance with SPP criteriaVoltage/Power Factor/Operational IssuesOthers? Probably!
44
Modeling of New GenerationChange for 2008 STEP
Have a signed IA not on suspensionAcquired the funding for major equipmentSPP or XE transmission service study that has been completed, with little expected impacts from other entities that may not complete their transmission service requestAcquired air and environmental permits, where applicableStarted construction with major equipment awarded
Regular SPP modelsWill pursue details of how to model generation connected on a system not represented in the model
45
Questions?
SPP Model Building Process
DescriptionScheduleData Requirements
TransmissionGenerationOther
47
DescriptionConsists of developing computer based power flow and stability models that represent the transmission system for the purpose ofperforming planning studies.
Planning Studies Include: Generator & Load Interconnection Studies, Switching Studies, Motor Starting and Transient Stability Studies.
SPS as a member of SPP participates in the submission of data tothe SPP transmission planning models, with quarterly updates.SPS Powerflow Modeling Data Contact:
René Miranda (806) 378-2136, rene.miranda@xcelenergy.comConsists of building 16 seasonal models
April Light (L) Spring Peak (G) Summer Peak (S)Shoulder (SH) Fall Peak (F) Winter Peak (W)
The 2008 SPP Model Series Includes:2008G, 2008S, 2008SH, 2008F, 2008W2009L, 2009G, 2009S, 2009SH, 2009F, 2009W2010S, 2010W2013S, 2013W2018S
48
ScheduleSPP Model Development Process: Begins In August
Firm Transactions DataGenerator Workbook DataShort Circuit DataNew Load Data (Including Non-Scalable Load Data)New Transmission ProjectsModel building schedule can be made available once completed.
Quarterly UpdatesUpdated models are posted every quarter with any updated data submitted by the different owners.
Required DataModeling data should be submitted by mid August (or before) in case questions arise that need to be answered.
49
Data RequirementsRequirements For Getting Transmission System Modeled In The SPS/SPP Planning Models.
Transmission DataTransformer DataGenerator DataCustomer Load DataOther Data – Capacitors, etc.Customer Transmission ProjectsTransmission Contingency SwitchingMaintaining Up-To-Date Models
50
Data Requirements (continued)
Transmission DataTransmission Line Data
Positive & Zero Sequence, R, X, B (100 MVA Base, per-unit)Normal & Emergency Ratings (MVA), Summer & WinterLine Length (miles)Bus-to-Bus Terminating Points
51
Data Requirements (continued)Transformer Data
Preferred: Transformer Test Report (TTR)TTR Unavailable
Positive Sequence R and X (100 MVA Base, per-unit)Transformer Losses (No-Load & Full Load)Normal & Emergency Ratings (MVA), Summer & WinterZero Sequence Data (100 MVA Base, per-unit)Fixed Tap Data (e.g. 5 taps, ±5% from nominal, 2.5%/tap)Load Tap Control (LTC) Data (e.g. 33 taps, ±10% from nominal, 5/8%/tap)LTC Control BusConnection Type (Y-Y, Y-∆, Y-GndY, etc.)
52
Data Requirements (continued)Generator Data
Provided to SPP, via Generator Interconnection Request Process, normally
The data is used for both Steady-State and Stability Analysis
Manufacturer’s Generator Electrical Data SheetReactances (Saturated & Unsaturated Values for Direct & Quadrature Axis)Field Time ConstantsMachine Saturation DataMW & MVAr (min & max values)etc.
Generator step-up transformer data.Excitation System Model DataGovernor System Model DataStabilizer System Mode Data
All data must be submitted in Siemens PTI PSS™E Rev 30.3.2 powerflow model data format.
53
Customer Load Forecasts and SPP Models
We need your data!Need your forecast of peak load by seasons or years shown in SPP Model Building slidesData needs to be a Coincident Peak value, what the load is expected to be coincident with the SPS control area peak loadNon-Coincident Peak loads not usefulNo speculative new load points - new delivery points needs to have gone through study.
54
Getting Your Transmission System in the SPS/SPP Model
SPS can provide a bus number range as long as we know how many you needIntegration into SPS model - may take some time. Allow several weeks.
55
Getting Your Transmission System in the SPS/SPP Model
Transmission Contingency Switching Data needed What is your switching in specific outages?Can be modeled through our 69 kV Contingency Analysis ProgramSPS may need to know for STEP mitigation plansIf load can be transferred between stations, please tell us how much and where.
56
Questions?
57
Future Meetings
July 23 - SPP Region 1 Planning MeetingAmarillo - Ambassador Hotel
August/September - SPS Coordinated PlanningLikely Topics - STEP resultsNERC Compliance Issues through ModelingAny Others?
November - SPS Coordinated PlanningSTEP SummarySPS Proposed Projects
Any desired future topics or issues?