Post on 22-Dec-2015
Software Project Planning
Infsy 570
Dr. R. Ocker
SWE economics analysis (Boehm, 84): throughout the software lifecycle, there
are many decision situations involving limited resources
Examples feasibility phase
– how much should we invest in analyses? plans and requirements phase
– how rigorously should we specify requirements? design phase:
– should we use existing sw which does not completely meet the requriements?
test phase:– how much testing is enough?
Analyzing risk and uncertainty can apply basic micro economic analysis to
these questions in sw engineering, must make decisions
under conditions of uncertainty can reduce uncertainty, and therefore make
better decisions, by buying information e.g. prototyping is a way of buying
information to reduce uncertainty about risky functionality
Question must ask:
How much information-buying is enough?
Project Planning
sw project management process begins with project planning
objective of sw project planning - to provide a framework for manager to make reasonable estimates of resources, costs and schedules
project estimation
first step in project planning
estimate resources, cost, and schedule for sw development project
requires experience and access to historical information
project estimation
estimation is risky business - lots of uncertainty due to:– project complexity– project size– degree of structural uncertainty - degree to
which requirements are solidified– availability of historical information
risk - measured by degree of uncertainty in quantitative estimates
project estimation
evolutionary process models - iterative view of development
possible to revise the estimate estimates made at beginning of sw
project should be updated regularly estimates should define “best case” and
“worst case”
Activities associated with project planning Software scope resources project estimation decomposition
1. software scope
want to establish a project scope that is unambiguous and understandable at management and technical levels
describes:– function– performance – constraints– interfaces– reliability
2. resources
must estimate resources required to accomplish the development effort
fig. 5.2 development resources pyramid
a. hw and sw tools
foundation of resources pyramid, provides infrastructure to support development
sw engineering environment must prescribe the time-frame required
for hw and sw verify that these resources will be
available
b. reusable sw components
next level, can reduce development costs
reuse considerations often ignored can greatly reduce development time
c. people - top of pyramid
select skills needed
each resource specified with 4 characteristics 1. description of resource 2. statement of availability 3. chronological time resource will be
needed 4. duration of time resource used
3. project estimation
cost estimates must be provided up front
but... the longer we wait, the more we know, and the better our estimates
a. use of decomposition techniques: divide and conquer approach decompose project into major functions
and related swe activities cost and effort estimates performed in
stepwise fashion
b. empirical estimation models
can complement decomposition techniques or used alone
model is based on historical data examples: LOC, FP SW cost estimation relies on good
historical data
4. decomposition techniques
decompose the problem (i.e., sw project estimation) into set of smaller problems
from chp. 3 - 2 types of decomposition a. decomposition of the problem b. decomposition of the process before decomposition, must understand project
scope and generate estimate of project size accuracy of estimate strongly influenced by
accuracy of size estimate
Problem-based estimation
direct measure - LOC indirect measure - FP a. begin with bounded statement of sw scope b. decompose sw into problem functions that
can each individually be estimated c. apply sizing measure to each function
– e.g. LOC, FP, OO (classes, objects) d. apply baseline productivity metrics (e.g.,
LOC/pm, FP/pm)
decomposition
decomposition is different for LOC vs. FP:
for LOC - decomposition must be detailed
for FP - looking at input, output, inquiries, data files, interfaces etc.
planner uses historical data or intuition (not recommended)
estimation
make 3 estimates for each function: optimistic, most likely, pessimistic then compute 3 point or expected value see 5.1 then apply historical LOC or FP
productivity data (e.g. FP/pm)
Process-based estimation
most common technique for estimating project
process is decomposed into a small set of activities or task
effort required to complete each is estimated
Process-based estimation
a. determine sw functions using project scope document
b. meld sw process activities and functions determine sw process activities that
must be performed for each function functions and process activities can
be part of a table - see fig 3.2
Process-based estimation
c. apply average labor rates to the effort estimated for each process activity
d. compute costs and effort for each function and software process activitey
can perform process-based estimate independently of LOC or FP
then have 2-3 estimates of cost and effort to compare and reconcile
5. empirical estimation models
The COCOMO Model: Constructive Cost Model [Boehm, 1984]
hierarchy of 3 increasingly detailed software estimation models:
model 1
Basic COCOMO model computes effort and cost estimated as
LOC
model 2
Intermediate COCOMO model computes effort and cost using a set of
cost drivers includes subjective assessments of
product, hw, personnoel, and project attributes
model 3
Advanced COCOMO model incorporates the intermediate version
with an assessment of the cost dirver’s impact on each step (analysis, design, etc.)
Steps for intermediate level (see Boehm, 1984 for detailed example):
Four steps
Step 1 - Nominal effort estimation determine project’s development mode
(organic, semidetached, embedded) estimate size of the project
Step 2 - Determine effort multipliers 15 cost drivers within model - each has
a rating scale and a set of effort multipliers which modifies step 1 estimate
Step 3 - Estimate development effort compute estimated development effort
= nominal effort X product of effort multipliers for 15 cost driver attributes
Step 4 - Estimate related project factors model has additional costing estimation
relationships for computing dollar cost of project and for breakdown by lifecycle phase and by type of project acitivity
can estimate project schedule
9 Management Guidelines for better cost estimating (Lederer and Prasad)
paper reports results of survey on cost estimating practices of 115 computer professionals
Need for better estimates
63% of all large projects (over $50,000) significantly overrun cost estimates
only 25% of projects completed at cost reasonably close to project estimate
Guidelines
Based on results of survey, authors developed 9 guidelines for better cost estimation
1. Assign the initial estimating task to the final developers 2 approaches: a. separate-function approach
– use experienced group of estimators to conduct the feasibility study and prepare initial project estimate
b. combined-function approach– final analysts and programmers prepare initial
estimate during feasibility study– get more accurate estimates with this approach
2. Delay finalizing the initial estimate until the end of a thorough study
often prepare initial cost estimate at beginning of project and then revise it (repeatedly) during the project
found that revision of estimate does not increase accuracy
people seem to look to the original estimate, not the revised estimate, when judging cost estimation accuracy -- so better to be right the first time!
3. Anticipate and control user changes when lots of changes, like trying to
estimate cost of a moving target estimators need to thoroughly understand
user requirments before they estimate its cost– should be able to reduce and control frequent
change requests– discourage unnecessary user changes -
charge extra!
4. Monitor the progress of the proposed project
5. Evaluate project progress by using independent auditors most projects usually monitored by
those involved in it more accurate estimates occur when
independent auditors are present
6. Use the estimate to evaluate project personnel cost estimating used more for project
planning and control than for evaluation of personnel
could use positive rewards for personnel who provide accurate estimates and for those that meet the estimates
7.Computing management should carefully study and approve the cost estimate need to conduct a cost/benefit review
before system development begins
8. Rely on documented facts, standards, and simple arithmetic formulas rather than guessing, intuition, personal memory, and complex formulas.
greater accuracy found when do the above
less accuracy when rely on intuition and personal memory, which is customary
9. Don’t rely on cost estimating software for an accurate estimate. packages don’t improve estimation, and
lower the satisfaction level of the estimators
Words of wisdom
there is no way a cost estimation technique can compensate for the lack of definition or understanding of the sw job to be done
Words of wisdom
there is no magic formula that will provide an easy and accurate substitute for the process of thinking through and fully understanding the nature of the software product to be developed
Words of wisdom
unless a software project has clear definitions of its key milestones and realistic estimates of the time and money it will take to achieve them, there is no way that a project manager can tell whether the project is under control or not