Shooting Schedule

Day/date Int/ExtDay/Night

Shot description/summary

Location Characters Art department/Equipment/ Special requirements.

17th September

Ext/Day Focus on close-ups of the performer and guitar. Establishing shots of the location. The establishing shots will be to show the location.

An isolated field at Stylam Road

Performer/Bella Warren

Guitar/Chair

19th September

Ext/Day Look at footage and redo some shots as a back-up and add anything that needs to be added. If we can’t access a guitar by this date then we will use a guitar from school.

An isolated field at Stylam Road

Performer/Bella Warren

Guitar/Chair

24th September

Ext/Day Film mid-shots and extra close-ups. Film the performer lip syncing and playing the guitar. Film extra for back up.

An isolated field at Stylam Road

Performer/Bella Warren

Guitar/Chair

26th September

Ext/Day Film medium long shots and film extra if needed.

An isolated field at Stylam Road

Performer/Bella Warren

Guitar/Chair

1st October(back up)

Ext/Day Review footage and film anything that needs to be added or redo some shots that need to be redone.

An isolated field at Stylam Road

Performer/Bella Warren

Guitar/Chair

3rd October(back up)

Ext/Day If there is anything else that needs to be filmed then use this as a last chance to get some extra shots.

An isolated field at Stylam Road

Performer/Bella Warren