Select CITYWALK Mall

CONTENTS

Key Plan

Site plan

Site Context

Introduction

Architects & developers

Landscaping

Floor Plans

Basement

Parking

Atrium & Skylight

Cinema

INTRODUCTION

Select CITYWALK is a 1.3 million Sq. ft air-conditioned, vibrant and upscale destination Shopping Centre.

Select CITYWALK houses • 3 floors of shopping area• 2 separate 5-storey blocks containing I. Office space II. Serviced Apartments• Outdoor open-air plaza, approx. 1 lakh sq. ft. • Water bodies & fountains• An amphitheatre• Six screen PVR Cinemas

LOCATION Located within India's most affluent & high-end urban area -South Delhi.

A3 District centre, Saket New delhi.

1 square meter (m2) = 10 square foot (ft2)

• ARCHITECTS- TEVATIA CHAUHAN & SHARMA ARCHITECTS (P) LTD.

• DVELOPERS- SELECTINFRASTRUCTURE(P) LTD.

• Completed in 2007

• Plot area 15884 sq. meters

• Landscaped Plaza of 8992 sq. meters.

PRESS ENCLAVE MARG

MANDIR MARG Select City Walk MallDLF PLACE

KEY PLAN

Cinema

Main 30m wide roadService 10m wide road

30m wide road in front, MANDIR MARG

SITE PLAN

SITE CONTEXT

• Bust stop- Khirki Village, 100m

• Malviya nagar metro station -1km

• IGI airport-15.6 km

• DLF place mall-200 m

• MGF metropolitan mall-100 m

• Qutub minar-3.7 km

BUILT & UNBUILT SPACES

Built-up space / open space activities ratio = 6 acres / 2 acres = 3:1

Activities ratio:

• Retail= 40%• Recreational= 20%• Dining=10%• Cinemas= 15%• Services/facilities= 15%

Total Area With Basements = 91623.807 Sq.m

Basement Area = 41578.5(3L VLS)

Weekend Holiday Footfalls- 70,000Weekdays Footfalls- 25,000

• Permissible Ground Coverage = 9686.86 sqm

• Permissible Floor Area (Without Basements) 44623.44 sqm

• Permissible Floor Area (With Basements) 92276.94 sqm

• Maximum Height of the Building Max 38m from Road LvI

• Multiplex Block 19m from Road LvI

Total area Without Basments = 43970.307 Sqm

Total area With Basements = 91623.807 Sqm

Plot Area 15884 Sq. Meters

Youth

Centre Stage (Celebration)

Family & Tradition

PLANNING CONCEPT

The planning of the SCW mall is divided into 4 categorization-

1. Family & tradition space2. Celebration (centre-sage)3. High-voltage (youth)4. Open plaza/ Landscaped area (ground

floor)

BUT, the actual planning is different from concept planning.

3-d Model of SCW Mall

Interconnection of Mall & Cinema hall

by Foyer

Aerial view of model, showing parking &

landscaping

AREA STATEMENT

BASEMENTS =41578.5(3L VLS) +6075(3L VLS =47653.5 SQ.M

GROUND FLOOR =9622.345+ 1756.46(MULTIPLEX) =11378.81 SQM

FIRST FLOOR =10803.323+2012.72 (MULTIPLEX) =12816.043 SQ.M

SECOND FLOOR =6568.06 SQ.M

THIRD FLOOR =2921.226 SQM

FOURTH FLOOR =2776.216 SQM

FIFTH FLOOR =2467.621 SQM

SIXTH FLOOR =2268.241 SQM

SEVENTH FLOOR =1948.80 SQM

FOYER AREA IN MULTIPLEX= 825.29 SQ.M

TOTAL WITHOUT BASMENTS =43970.307 SQM

TOTAL WITH BASEMENTS =91623.807 SQM

LANDSCAPING

• Comprises of 4 acres of outdoor open plaza, for art exhibitions & performances.

• Landscaped plaza of 8992 sq. meters.

• An OAT, with a capacity of 200+ people.

• 5 staircases leading to basement.

• Statues & Sculptures were placed all around the landscaping.

• Flooring: Marble, Granite Slabs, Vitrified Tiles8m high Buddha statue

Grand front entranceStaircases leading to basement

View of OAT

View of StageArea-15x5m Tread- 750mmRiser-300mm

Fountain in front of stage

Sitting space around trees Sculpture & Fountain View of Mall & fountain

CIRCULATION

ENTRANCES

• There were 2 main entrances to the mall.

• One from the front & 2nd from the rear side.

• On the front side, 4 main entries were present.

• Passage Running on one side of L-shape building, is

1. 2.5m wide2. Distance between columns- 6m3. Column size-600x450

Rear Entrance

Front Entrance

GROUND FLOOR PLAN

4 lift lobby

2 washrooms

1 feeding & resting room

3 escalators

Atrium at entrance

4 different entrances at front side.

1 entry from rear side.

6 Staircases

Family & tradition

Youth

Celebration, centre stage

Corridor 20 m wide & Atrium

GROUND FLOOR =9622.345+ 1756.46(MULTIPLEX) =11378.81 SQM

GROUND FLOOR PLAN

Lift & StaircasesEscalatorsWashroomRamps

FIRST FLOOR

4 lift lobby

2 washrooms

3 escalators

6 Staircases

Family & tradition

Youth

Celebration, centre stage

Corridor 20 m

Balcony area, 6m wide

FIRST FLOOR =10803.323+2012.72 (MULTIPLEX) =12816.043 SQ.M

SECOND FLOOR

Restaurants

Youth area

Celebration, centre stage

Corridor 8 m wide

4 lift lobby

2 washrooms

3 escalators

6 Staircases

Exit of cinema from 2nd floor.

Terrace garden for food court

SECOND FLOOR =6568.06 SQ.M

SECOND FLOOR PLANLift & StaircasesEscalatorsWashroom

BASEMENT

PARKINGBASEMENT SERVICES

• 1300 cars can be parked in 3 different floors of basement at one time.

• Basement 1- Offices, Parking for 370 cars, Loading & unloading area, Garbage disposal area

• Basement 2- Parking 470 cars

• Basement 3- Parking 270 cars

• Basement height- 3.5m

• Grid 6x6m

• BASEMENTS =41578.5 sq.m (3L VLS)

• There were two separate entries which were connecting to the parking, from ground floor.

• One was used for general entry of cars & The other was used by service vehicles.

• There were 4 lifts which were connecting basement to upper floors.

• Toilets and locker rooms Provided for the drivers.

• Signage are clearly marked in the basement.

• Throughout the basement, fire fighting equipment's like sprinklers, Fire hose reel, Fire extinguishers were present

Before entering to the mall from basement, security barrier has to be crossed over.

Ramp within basement, connecting 1 floor of basement to another.

Electronic Boards

BASEMENT SERVICES

It includes

A. Fire fighting equipment'sB. Emergency exitsC. Loading & unloading areaD. Garbage Collection area Main UPS room

Electric roomAir extractorsFire Hose Reel & Exit Door

Air Extractors in basement. Sprinklers were provided all over the basement

Service lift, connecting basement to upper floors of mall

Goods were delivered & stored first to basement, & from there it goes to upper floors

GARBAGE AREA

Composting Area Segregation Area Segregated waste for recycling

The waste from restaurants was collected in basement, through shaft.

There were 3 separate areas, which were dividing the waste into different categories.

After separation, waste is dispose of through garbage trucks.

EXTERNAL FINISH

The entire complex is finished with combination of • Granite• ACP cladding• Acrylic paint • Structural glazing

At the upper level on the front facade, space has been provided for• Advertisements• Forthcoming attractions • Cinema posterswhich are visible from a distance governing the external elevation.

ATRIUM

Oval shaped Atrium present at the entrance of Mall.

Atrium covered with light membrane sheet of polycarbonate.

Around the atrium, Shops are located.

Outer view of atrium

Position of atrium

Below atrium space is used for performance or exhibition

SKYLIGHT

Glass panels around oval shaped atrium.

Connection of Atrium in between.

Running all along the mall.

Covered with same material as atrium.

Linear Slylights.

Position of skylight

STORES

Area to stores were assigned as per their requirements.’

Floor to floor height-4m

Stores equipped with fire fighting equipment's

Internal layouts varies individually.

Shops area ranges form 50 Sq.m- 1500sq.m

Exposed ceiling of Store, showing AC ducts & Wiring

Food Court

Situated on 2nd floor

Open terrace area was included with the food court, thus utilising the terrace

Seating capacity- 200 person

ATM placed at a distance of 100m

Food Court Seating areaFood court terrace ATM

KIOSKS

• Centrally placed at the corridor.

• Segregating corridors in two ways.

DISPLAYING AREA

• Beside kiosks Advertisements

were also present in corridor.

DOME

• G+7

• Top two floors used for services (washrooms, changing room)

• 5th floor assigned to fitness club

• 4th floor assigned to Buddha Bar(both 4th & 5th are not a part of SCW mall)

• 3rd floor- Children's play area & Restaurant area.

• Height 33m

• Balcony projected at the 4th floor, which was BAR

ACP claddingAdvertisement Area

Advertisement boards on front façade.

Projected shops on 1st floor.

ADVERTISEMENT

SERVICES

3 Escalators

6 Fire staircases

4 Lift lobby, comprises 2 lifts eachCapcaity-12

1 Feeding & resting room on GF only

Total 86+ fire hydrants chamber

Sprinklers placed at 2.6 m apart

Escalators

Washroom & Fire Exit

Auto pay station for parking

Sign boards all along the corridors

Escalators

Lift

Washroom

There were 2 washrooms present on each floor.

Each washroom comprises of • 5 washbasins• 6 urinals• 6 cubical• Hand dryer• Handicapped washroom

Total Area- 5mx8mWashbasins

Passage

Handicapped Washroom Urinals

PVR CINEMA

Beside the mall building, cinema is connected by a bridge from 1st floor.

Road width- 20m

Tickets for cinema can be purchased from ground floor & first floor.

Good point is ticket contour is just at the entrance of the mall.

Parking for cinema is same as for Mall.

Ticket contour at first floor

Ticket contour at ground floor

Cinema

BridgeMall

Size of plot 36x36m

G+2 

Multiplex consists of six cinemas2 - Gold class4 - premier class.

Main entry is through a bridge which connects the cinema & mall building from first floor.

1.5m wide staircase

Gold class capacity- 40

Premier class capacity- 420, 370, 120  

Entrance to cinema building from 1st floor of mall

Hydraulic lift for different abled with staircase at 1st

floor.

A

A- Adequate Measures for convenience of handicaps.B

B- Curtain glazing on north side.

C

C- Harsh south/southwest sun is dealt with by giving a buffer space(ramp)

D

D- Staircase to help In evacuation in case of fire emergency

E

E- Area Dedicated To Food Court

GROUND FLOOR PLAN

2 Gold class Cinema Hall

Capacity- 40 person

1756.46 SQ.M

A

A- Large foyer & waiting area.

B

B- Adequate Measures for Convenience of Handicaps

FIRST FLOOR PLAN

Entry from first floor to the mall.

Waiting Area

Washroom services.

2012.72 SQ.M

A

A- Adequate number of staircase to help in evacuation in case of fire/emergency

B

B- Adequate Measures For Convenience Of Handicaps

SECOND FLOOR PLAN

4 premier cinema hall

Capacity- 420, 370, 120

Thank You…….