Resettlement Monitoring Report
This report has been submitted to ADB by the Project Management Office of Hefei Municipal Government and is made publicly available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB.
Project Number: 36595 December 2008
PRC: Anhui Hefei Urban Environment Improvement Project
Prepared by Hefei Municipal Government With the assistance of Coal Industry Hefei Design Institute PRC For Hefei Municipal Government Hefei Urban Construction Investment Company Hefei Chao Lake Ecological and Environmental Improvement Construction and Administration Bureau Hefei Xincheng State Assets Operating Co. Ltd.
HEFEI URBAN ENVIRONMENT IMPROVEMENT PROJECT
ADB LOAN NO.: 2328-PRC
External Resettlement Monitoring and Evaluation Report
No. 2
Coal Industry Hefei Design Institute
January 2009
Hefei Urban Environment Improvement Project
1
Catalog
I INTRODUCTION ..............................................................................................................................1
1.1 PROJECT OVERVIEW.................................................................................................................1 1.1.1 Project Components ................................................................................................1 1.1.2 Project Content and Project Scale .............................................................................1
1.2 PROJECT PROGRESS................................................................................................................3 1.3 BRIEFING ON RESETTLEMENT ARRANGEMENT PLAN .........................................................4
1.3.1 Summary of project influences ....................................................................................4 1.3.2 Compensation Standard................................................................................................6 1.3.3 Organization Structure and Responsibilities ...........................................................7
1.4 EXTERNAL MONITORING.........................................................................................................10 1.4.1Monitoring Agency ..........................................................................................................10 1.4.3 Monitoring and evaluation measures ......................................................................10
II THE FIRST SURVEY ON BASELINE AND RESETTLEMENT..................................... 11
2.1 SURVEY TIME AND CONTENTS .............................................................................................. 11 2.2 CHANGES DURING THE IMPLEMENTATION OF THE PROJECT ...........................................17 2.3 CURRENT AFFECTED PEOPLE AND ENTERPRISE................................................................19
III MONITORING AND EVALUATION ................................................................................................20
3.1 PROGRESS OF LAND ACQUISITION AND DEMOLITION........................................................20 3.1.1 Progress of land acquisition .......................................................................................20
3.2 PROGRESS OF BUILDING DEMOLITION AND ARRANGEMENT ............................................22 3.2.1Progress of building demolition ..................................................................................22 3.2.2 Resettlement Arrangement Plan...............................................................................23 3.2.3 Infrastructure construction on affected area and assigned area ....................24
3.3 RESETTLEMENT FUND UTILIZATION .....................................................................................25 3.3.1 Resettlement Fund Utilization....................................................................................25
3.4 CHANGE OF LIVING CONDITION OF AFFECTED PEOPLE ....................................................26 3.4.1 Investigation on living condition of affected people ............................................26
3.5 PUBLIC PARTICIPATION ...........................................................................................................27 3.5.1 Survey on public opinions ...........................................................................................27
3.6 COMPLAINT DEAL PROCEDURE AND EFFICIENCY EVALUATION........................................29
IV CONCLUSIONS ON MONITORING AND EVALUATIONS...........................................30
4.1 PROBLEMS ENCOUNTERED DURING THE IMPLEMENTATION OF THE PROJECTS..........30
Hefei Urban Environment Improvement Project
1
I Introduction 1.1 Project Overview
1.1.1 Project Components Hefei Urban Environment Improvement Project (HUEIP) Utilizing ADB Loan
has eight sub-projects in implementation so far. They are: Banqiao River
Rehabilitation and Flood Control Improvement, Ershibu River Rehabilitation and
Flood Control Improvement, Sili River Rehabilitation and Flood Control
Improvement, Improvement of Hefei Municipal Sewers, Improvement of the Closed
Qingxi Road Landfill Site, Shiwuli River WWTP and associated pipeline networks,
Wangtang WWTP Phase II, and Improvement of Chao Lake Ecological Environment
and Flood Control Works。
1.1.2 Project Content and Project Scale In the past few years, along with the Great Construction in Hefei, the population
in the city has increased a lot and industrialization is speeded up, which resulted
serious surface water pollution. Except a few water courses, majority of other water
bodies has pollutant concentrations exceeding Hefei City Environmental Functional
Standard. Water quality in Chao Lake has exceeded National Surface Water
Environmental Quality Class III, while water in Nanfei River, Shiwuli River and
Ershibu River has exceeded Class V. At present, the wastewater treatment ratio is
only 66%. Associated with industrial wastewater, the treatment ratio is only 50%.
More than half of the wastewater is dumped into the water course directly, which will
join Chao Lake finally. Part of the water courses has lost its function, which greatly
threatens the Chao Lake water quality.
The HMG has be aware of the environmental degradation problem. To solve the
similar problems, and maintain the sustainability of Hefei City, a multi-organization
composed environmental protection plan was developed. Thus, HMG has made a list
of key projects, and requested ADB for funding, which is Hefei Urban Environmental
Improvement Project (HUMIP). The HUMIP is a key component to achieve the goals.
This project will improve the public wastewater treatment and flood control to
improve the environment. Meanwhile, through reduced poverty, new employment
opportunities, attracting investment and business activities, and reduce the possibility
to get diseases related to wastewater and air born, Hefei residents will earn a better
Hefei Urban Environment Improvement Project
2
living condition.
HUEIP project includes building up wastewater treatment plants, wastewater
sewers, closed landfill improvement, dredging and anti-flood infrastructure, and Chao
Lake Ecological Environmental Improvement. The summary of the project is listed in
Table 1.1.1.
Table 1.1.1: Project Content and project scale
Project Component Description
1 Build Shiwuli River WWTP
Construction contents (1) Design, land acquisition, equipment and vehicle purchase, employer 38 staffs. Construction contents (2) By 2010, wastewater treatment capacity shall reach 50,000 m3/day Construction contents(3) By 2010, build 73.3km serer mains (D300-D1200), and build up a pumping station.
2 Build Wangtang WWTP Phase II and associated pipeline networks
Construction contents (4) Design, land acquisition, equipment and vehicle purchase, employer staffs. Construction contents (5) By 2010, wastewater treatment capacity shall reach 100,000 m3/day Construction contents (6) By 2011, build 33km serer mains (D300-D1400), and build up a pumping station.
3 Improvement of the whole Hefei City Sewer
Construction contents (7) By 2010, install pipes with different diameters 206 km, to connect current Wangtang Phase I, Zhuzhuanjing, Caitianpu and Wangxiaoying WWTPs. Construction contents (8) By 2010, install a pumping station and a GIS system.
4 Improvement of the Closed Qingxi Road Landfill Site
Construction contents (9) By 2008, install a impermeable wall, capping, leachate collection and gas collection system, and do landscaping.
5 Ershibu River Rehabilitation and Flood Control Improvement
Construction contents (10) By 2012, finish river dredging, widening and reinforcing. Construction contents (11) By 2012, install rain water drainage pipeline of 12 km (D400-D1200), and two rain water pumping stations. Construction contents (12) By 2012, install sewer mains of 16km (D300-D800) and two wastewater pumping stations. Construction contents (13) By 2012, finish all accessory works.
6 Banqiao River Rehabilitation and Flood Control Improvement
Construction contents (14) By 2011, finish river dredging, widening and reinforcing. Construction contents (15) By 2011, build roads along the rivers and other accessory works. Construction contents (16) By 2011, build wastewater hold up net, and do necessary landscaping.
7 Sili River Rehabilitation Construction contents (17) By 2010, finish river dredging
Hefei Urban Environment Improvement Project
3
Project Component Description
and Flood Control Improvement
and widening of 3.14 km, and do reinforcing. Construction contents (18) By 2010, build rainwater drainage pipeline (D400-D1800), wastewater mains (D300-D800) and one rainwater pumping station. Construction contents (19) By 2010, finish necessary accessory works.
8 Chao Lake Ecological Environment and Flood Control Works
Construction contents (20) By 2010, improve the collapsed area of 20.62km. Reinforce anti-wave plat and protection line of 56.33km. Reinforce anti-wave wall of 23km. Construction contents (21) By 2010, finish round road of 49.39km. Construction contents (22) Finish necessary accessory works.
1.2 Project Progress So far, the Preliminary Design (PD) of all sub-projects has been approved by
Hefei Municipal Development and Reform Committee (HMDRC). The progress of
each sub-project is listed in the table 1.2.1.
Table 1.1.1: Project Progress
Sub-project Progress
1 Build Shiwuli River WWTP
Civil works and equipment installation of Phase I have been finished. Civil work of phase II has been basically completed,
2 Build Wangtang WWTP Phase II and associated pipeline networks
Construction of pipelines has been completed, Civil work of phase I has been basically completed, Civil works for phase II is in the bidding process, equipment installation has not commenced.
3 Improvement of the whole Hefei City Sewer
40% has been finished
4 Improvement of the Closed Qingxi Road Landfill Site
finished
5 Ershibu River Rehabilitation and Flood Control Improvement
PD was approved on July 8th 2008. The construction of 1st package has commenced.
6 Banqiao River Rehabilitation and Flood Control Improvement
70% workload has been finished
7 Sili River Rehabilitation and Flood Control Improvement
Construction has commenced, procedures on land acquisition and demolition have passed, with 90% finished.
8 Chao Lake Ecological Land measurement, relevant approval procedure and
Hefei Urban Environment Improvement Project
4
Sub-project Progress
Environment and Flood Control Works
resettlement compensation completed in Feixi county.
1.3 Briefing on Resettlement Arrangement Plan
1.3.1 Summary of project influences According to the established Resettlement Arrangement Plan (RAP), the
influences of the eight implemented sub-projects are listed below:
1. Improvement of the Closed Qingxi Road Landfill Site
The project covers an area of 534 mu, within which, 181 mu originally used by
landfill was assigned with no cost, 100 mu of sludge pond land by Water Supply
Corporation was provided by the Commission of Construction with no cost, and 253
mu was newly acquired. The land acquisition will influence the Qilitang group of
Qingxi road Shejuwei, without any demolition. Totally 32 household is affected, with
131 head in total.
2. Sili River Rehabilitation and Flood Control Improvement The permanent land acquisition will influence three farmer groups in Luyang
District community. Permanent land acquisition is 181 mu, with 37 household of 152
people influence. There is no temporary land acquisition. Demolition of houses will
be 11328m2, with direct influence on 22 household of 90 people. Three enterprises
have been affected due to the demolition of walls. There are 95 employees in this
enterprise, and their lives will not be affected.
The land acquisition and demolition works are expected to start on May 2007,
and terminated on November 2008, which lasts for 18 months. Before the
remuneration has been distributed, no civil work shall be started. To ensure the
successful implementation of the project, except internal monitoring, an external
monitoring agency shall be employed to do monitoring every six months. Land
acquisition remuneration and arrangement fee budget is about 32.2 million RMB,
including basic fee, related tax and preparation fee (10% of basic fee) on permanent
land acquisition and temporary acquisition. The arrangement fee shall take about
13% of the total budget of the project.
3. Ershibu River Rehabilitation and Flood Control Improvement
According to the FSR, 3 counties and 11 villages will be affected. Details are
Hefei Urban Environment Improvement Project
5
listed below:
a) 1922 people of 541 households will be affected by land acquisition;
b) 771 people of 209 households will be affected by demolition. The total
demolition area is 43870m2;
c) 10 enterprises and shops will be affected. Among those, 2 enterprises will be
affected on their walls, without income loss. Other eight are house changed shops.
In total, 2693 people of 750 households will be affected, within which 329
people of 96 households will be affected by both land acquisition and demolition. 4. Banqiao River Rehabilitation and Flood Control Improvement
736 mu (49 hectares) land shall be acquired permanently. RP is based on the FSR
of the project, and is subject to modification of future detailed design. IA shall try to
minimize the influence of the project on the community.
According to the FSR, six villages and communities within Xinzhan and Luyang
District will be affected. Details are listed below: 736 mu land will be acquired to
widen the river bank, with 470 households of 1412 people affected. Temporary land
shall take 70 mu thin farmland by the river, with no one to resettle. Demolition area is
180m2 , with one household of 8 people affected.
5. Shiwuli River WWTP and associated pipeline networks
WWTP will be located to the west of Xiaofan Village, and to the east of
Guchengyu. Totally 77.8 mu will be acquired, within which farmland will be 50.6 mu.
25 mu land will be acquired as temporary acquired land, which are mainly along city
road and a few farmland. 61 households in Dayu Town Luji village No.2 village group
will be affected, with farmland for 256 people. No resettlement or demolition.
Though sewer pipeline construction will take some temporary land, however, as
the constructions of mains will use pipe jacking technology, and the placement of
pipes will take place during same time as road construction and installation of other
infrastructure, thus the placement of those pipes will not involve land acquisition.
However, as the component of the road construction, according to ADB requirement,
due diligence shall be conducted.
6. Improvement of Hefei Municipal Sewers
1.5 mu land shall be permanently acquired. The land belongs to one household
of Caoshuwang Village in Yaohai District. 40 mu land shall be temporarily occupied
Hefei Urban Environment Improvement Project
6
during the construction of the pipeline to facilitate the construction of pipeline. As
there is no building or other infrastructure on this land, thus no one will be affected.
7. Wangtang WWTP Phase II and associated pipeline networks Wangtang WWTP Phase II is located in the area surrounded by Qianshan Road,
Qingxi Road, Qingyang Road, Gaoliu Road and Jinniu Road. The Phase I project 80
thousand m3/d was completed and trailly started on September 2003. In January 2004,
it was officially started. The land for Phase II project has already been acquired during
Phase I project, without any resettlement or demolition work. The pumping station
has also been finished, with the owner of Hefei Municipal Construction Commission.
The land was transferred with no charge.
Though sewer pipeline construction will take some temporary land, however, as
the constructions of mains will use pipe jacking technology, and the placement of
pipes will take place during same time as road construction and installation of other
infrastructure, thus the placement of those pipes will not involve land acquisition.
However, as the component of the road construction, according to ADB requirement,
due diligence shall be conducted.
8. Chao Lake Ecological Environment and Flood Control Works
The project will acquire land of 172 mu, within which water land of 139.6 mu,
dry land of 9.54mu, wild land of 15 mu, fish pond (water pond) of 7.6 mu. Permanent
land acquisition results the land loss of five towns and eight villages. Two of the
towns are located in Feixi County, one is in Baohe District, and two are located in
Feidong County. During the construction, 178.4 mu land is temporarily taken for one
year. It is estimated this temporary land acquisition will influence 210 household.
1.3.2 Compensation Standard According to relevant laws and regulations, and Hefei Group Owned Land
Acquisition Measure (HMG order No. 136, effective since May 1st, 2008), the
compensation rate is listed in Table 1.3.1. During the implementation of the
resettlement, May 1st 2008 will be a dividing time point. Before that date, Document
No 138 will be used as the guideline; while after that date, Document No. 136 will be
used as the guideline.
1.3.1 Compensation Standard for Land Acquisition and Demolition
Hefei Urban Environment Improvement Project
7
Items Unit Rate Note
I. Group Owned Land
1.1 Permanent Acquisition RMB/mu 21000
1.2
Resettlement
Compensation
(age under 16)
RMB/capita 12,000 Before May 1st, 2008, the rate is
10,000RMB/capita
1.3
Resettlement
Compensation
(age above 16)
RMB/capita 12,000
Before May 1st, 2008, the rate is
also 12000RMB/capita.
However, after May 1st, 2008, all
with age above 16 is acquired
into the land acquired farmer
annuity guarantee system.
1.4 Seeding Charge RMB/mu 700
II. Above ground
Affiliated
2.1 Tree RMB/piece 75
2.2 Tomb RMB/piece 650
2.3 Electric pole RMB/root 200
2.4 Wall RMB/meter 50
2.5 Concrete Road RMB/m2 100
2.6 Sand Road RMB/m2 50
III. House Resettlement
Compensation
3.1 Domicile Resettlement RMB/m2 1000
3.2 Move Compensation RMB/unit 400
3.3 Affiliated RMB/unit 5000
3.4 Enterprise Resettlement RMB/m2 144
3.5 Temporary housing
compensation RMB/m2 72
3.6
Temporary settlement
compensation for
enterprises
RMB/m2 90
1.3.3 Organization Structure and Responsibilities
At present, the eight being implemented projects are part of HUEIP funded by ADB loan. Hefei Municipal Government (EA) has set up the project leading group, which is ADB Project Management Office (PMO). The PMO is as the secretary agency for EA. Hefei Urban Construction Investment Corporation is the
Hefei Urban Environment Improvement Project
8
implementation agency (IA). Hefei Drainage Management Office (HDMO) is the executive agency. (Note, for Chao Lake project, the executive agency is Chao Lake Construction Management Bureau under Hefei Water Affair Bureau) Under HDMO, there is a ADB fund project construction office, under which there is a resettlement arrangement department. Figure 1.3.2 shows its structure.
Figure 1.3.2 Organization Structure for Resettlement
IA plays a very important role in the resettlement arrangement. Except IAs,
others organizations are also very important. Table 1.3.3 listed all relevant
organizations and staffs. Table 1.3.4 lists the responsibilities.
Table 1.3.3 Staffing
Organizations People
Hefei Project Management Office (HPMO) 1 Hefei Land Management Bureau (HLMB) 1~10 Hefei Planning Bureau (HPB) 3 Hefei Water Affaire Bureau (HWAB) 3 Hefei Drainage Management Office (HMDO-IA) 10
General Department
Hefei Drainage Management Office (HDMO)
Engineering Department
Resettlement Department
Planning and Finance
Department
ADB Project Construction Office
Resettlement Office of district/county
Affected communities and villages
Hefei Urban Environment Improvement Project
9
Hefei Demolition and Arrangement Management Office (HDAMO) 6 Xinzhan District, Yaohai District, Luyang District,, Feidong County and Changfeng County
5~10
Communities/villages 25 Law consulting service 1 Hefei Design Institute (DI) 3 External Monitoring Agencies 3
Table 1.3.4 Organization Responsibilities
Organization Responsibility
Prepare RAP and organize for implementation Monitoring the utilization of resettlement fund Coordinate and monitor the resettlement arrangement work Coordinate monitoring/management activities, including engaging external monitoring agencies. Submit profess report to ADB
Hefei project impelemntation agency-HPMO
Coordinate and deal with the conflict and questions raised. Contact consulting agency to evaluate the impacts of the project Organize social-economic survey Apply to HPB and HLMB for Land Use Permit Apply for Building Demolition Permit Responsible for municipal infrastructure demolition Draft RP schedule timeline Engage HLMB and HDAMO to sin the land acquisition and demolition contract. Pay the arrangement fee according to the contract.
Hefei Drainage Management Office (HMDO)
Monitor and evaluate
Establish related laws and regulations on land use Participate in evaluating remuneration and RP Process land acquisition Participate social-economic survey Participate in drafting RP and examine the RP Issue construction land use permit Lead, coordinate and monitor the land acquisition work Coordinate and deal with the conflice and problems during land acquisition and distribution. Register land acquisition and post for public review If necessary, organize the public participation and public hearing
Hefei Land Management Bureau (HLMB)
Deal with arrangement and remuneration distribution Confirm land (blue line) river way alignment control line Hefei Planning
Bureau (HPB) Assign land use certificate according to the plan Examine and approve the remuneration plan on demolition and arrangement. Issue house demolition permit. Register and manage house demolition documents
Hefei Demolition and Arrangement Management Office (HDAMO)
Manage relevant documents
Hefei Urban Environment Improvement Project
10
Organization Responsibility
Coordinate and arbitrate conflict during the land demolition Assist social-economic survey Assist to establish arrangement plan Monitor community/resident committee to arrange and recover the affected people’s lives.
District /county governments
Report the complaints and suggestion to upper level governments. Participate social-economic survey Participate in composing arrangement plan Assist in public consulting and communication on demolition policy Consulting land remuneration distribution and arrangement fund Organize the production and recover incomes. Report the complaints and suggestion to upper level governments.
Communities/village committees
Provide support to people in difficulty Optimize the plan to minimize the impact of RP. Suggest/clarify land acquisition and demolition influence scope Assist EA during the preparation of RP
Consulting and design agencies
Provide technical support on data collection and processing Provide technical support on land acquisition and arrangement External
Monitoring Agencies
As independent monitoring agency, monitor the implementation of the resettlement plan and report to EA and ADB.
1.4 External Monitoring
1.4.1Monitoring Agency Environmental Engineering Design & Research Institute in Coal Industry Hefei
Design Institute was engaged by HDMO and Chao Lake Construction Management
Bureau to provide external monitoring and evaluation for land acquisition and
resettlement.
1.4.2 Monitored and evaluated items and objectives According to RAP, external monitoring and evaluation shall provide
independent monitoring and evaluations. Through examination and interview, land
acquisition and resettlement arrangement fund distribution shall be monitored and
evaluated to analyze the living conditions of affected people. Information shall be
fully collected, problems shall be identified and suggestions shall be provided to
related governments to facilitate them to control the whole project.
1.4.3 Monitoring and evaluation measures
Through onsite interview, analysis and evaluation, whole survey and onsite survey shall be conducted on project progress, financing, organization, and management. Survey shall also be conducted by random sampling. For typical affected people, random sampling shall be conducted. The targets are 10% household
Hefei Urban Environment Improvement Project
11
whose housing was demolished or whose land was lost.
II The first survey on baseline and resettlement 2.1 Survey Time and Contents
Early at the beginning of the project in 2006, as the assistant unit for RAP preparation, Coal Industry Hefei Design Institute Environmental Engineering Institute (“the Institute”) made the preliminary baseline survey on resettlement. The Institute made the first baseline survey on resettlement during July 20th 2008 to July 27th 2008. Based on the previous accomplishment, guided by ADB specialist and assisted by each IAs, the Institute conducted the second survey during December 1st 2008 to January 20th 2009.
The survey includes: (1)Land acquisition influence survey: Changes of land before vs after; income
before vs after; (2)Social-economic survey: Including basic information (population, name,
professional, land, etc), living condition survey (education, employment, income, etc); (3)Public opinion survey; (4)Survey on affected households: housing condition before vs after, including area, structure, affiliate, etc; (5)Survey on affected enterprises: name of enterprise, nature, scale, production
value, number of employees, area, affected conditions, etc; ( 6 ) Survey on vulnerable groups: number of household, remuneration
distribution etc; (7)Organization condition: staffing and working conditions; (8)Communications: which communications channels shall be used, whether the
remuneration standards are known by large mass, etc; (9)Money distribution: divided by planned and actual, including to different
levels, achieving status shall be monitored, etc; (10)Collect photos, audio, video, real stuffs, etc.
The survey shall be conducted against the implementation schedule. For projects which have not been implemented yet, additional survey might be conducted during the next Phase survey.
The followings are photos during the investigation:
Hefei Urban Environment Improvement Project
12
Photo 1 Construction site of Sili River Project
Photo 2 Housing for resettlement under construction
Hefei Urban Environment Improvement Project
13
Photo 3 Improvement of the Closed Qingxi Road landfill Site
Photo 4 Residential areas in Yandian town before
relocation-Chao Lake Project
Hefei Urban Environment Improvement Project
14
Photo 5 Public Announcement on Resettlement at Feixi Road section
-Chao Lake Project
Photo 6 Public Announcement on Resettlement in Feixi section
-Chao Lake Project
Hefei Urban Environment Improvement Project
15
Photo 7 House built by peasants’ own in the resettlement of Feixi section
-Chao Lake Project
Photo 8 In-house investigation on resettlement at Feixi section
-Chao Lake Project
Hefei Urban Environment Improvement Project
16
Photo 9 In-house investigation on resettlement at Feixi section -Chao Lake
Project
Photo 10 Chao Lake Project construction site
Hefei Urban Environment Improvement Project
17
2.2 Changes during the implementation of the project Due to the long time gap between FSR and PD, especially due to the detailed
study in PD according to actual conditions, the confirmed land acquisition scope
might be different from original RAP. Meanwhile, RAP was composed on 2006, the
design changes and development of the city was not reflected, thus several changes on
land type, number of demolished house, affected household number were found in
this survey. Projects with changes are mainly Improvement of the Closed Qingxi Road
Landfill Site, Sili River Rehabilitation and Flood Control Improvement, Banqiao
River Rehabilitation and Flood Control Improvement, Ershibu River Rehabilitation
and Flood Control Improvement and Chao Lake Ecological Environment and Flood
Control Works. Others have few changes. Details are listed in Table 2.2.1.
Table 2.2.1 Actual status compared with RAP
Items Actual Condition RAP Note
Improvement of the Closed Qingxi Road Landfill Site
All acquired land is state owned. No group owned land will be acquired, so no resettlement work will be implemented.
The project covers an are of 534
mu, within which, 181 mu originally
used by landfill was assigned with no
cost, 100 mu of sludge pond land by
Water Supply Corporation was
provided by the Commission of
Construction with no cost, and 253
mu was newly acquired. The land
acquisition will influence the
Qilitang group of Qingxi road
Shejuwei, without any demolition.
Totally 32 household is affected, with
131 head in total.
PD was adjusted
with actual condition.
Sili River Rehabilitation and
Flood Control Improvement
Actual acquired land is 205.28mu, influencing Sili River, Taohua Garden and Wuli Guai communities. Totally 320 people shall be resettled. Others are the same as RAP.
The permanent land acquisition will influence three farmer groups in Luyang District community. Permanent land acquisition is 181 mu, with 37 households of 152 people influence. There is no temporary land acquisition. Demolition of houses will be 11328m2,with direct influence on 22 household of 90 people. Three enterprises have been affected due to
PD was adjusted
with actual condition
Hefei Urban Environment Improvement Project
18
the demolition of walls. There are 95 employees in this enterprise, and their lives will not be affected.
Banqiao River Rehabilitation and
Flood Control Improvement
Same as RAP
Six villages and communities within Xinzhan and Luyang District will be affected. Details are listed below: 736 mu land will be acquired to widen the river bank, with 470 households of 1412 people affected. Temporary land shall take 70 mu thin farmland by the river, with no one to resettle. Demolition area is 180m2 ,with one household of 8 people affected.
--
Ershibu River Rehabilitation and
Flood Control Improvement
PD was approved on July 8th, 2008, there are certain modifications against RAP. 40% of demolition finished, final data info remains to be prepared.
This project involves permanent land
acquisition of 1426.4 mu, of which
there are 1076.6 mu of group owned
land and 140 mu of state owned land;
578 household of 2060 people shall
be affected in land acquisition, no
temporary land acquisition involved;
demolition area is 43870 m2 which
shall affect 363 household of 1323
people; 96 household of 329 people
shall be affected in both land
acquisition and house relocation.
PD was adjusted
with actual condition
Shiwuli River WWTP and associated
pipeline networks
Same as RAP
Totally 77.8 mu will be
acquired. 61 households in Dayu
Town Luji village No.2 village group
will be affected, with farmland for
256 people. No resettlement or
demolition.
——
Wangtang WWTP Phase II and associated
pipeline networks
Same as RAP
Land has been acquired during
the Phase I WWTP project. No
further resettlement or demolition is
needed.
——
Improvement of the whole Hefei
City Sewer
5 mu land will be temporarily
acquired. Others are
1.5 mu land shall be permanently acquired. The land belongs to one
household of Caoshuwang Village in
Construction technology
was
Hefei Urban Environment Improvement Project
19
the same as RAP. Yaohai District. 40 mu land shall be temporarily occupied during the
construction of the pipeline.
improved
Chao Lake Ecological
Environment and Flood Control
Works
Permanent land acquisition actual measured is 301 mu, of which Feidong county accounts for 152 mu , Feixi county 38 mu and Baohe District 111 mu, Presently, Demolition and relocation in Feidong has been finished, actual demolished area 9156 m2 which is over the planned area by 1589 m2; Some demolition in Baohe District has been completed; there is no progress with Feidong county.
The project will acquire land of
172 mu, within which water land of
139.6mu, dry land of 9.54mu, wild
land of 15 mu, fish pond (water
pond) of 7.6mu. Permanent land
acquisition results the land loss of
five towns and eight villages. Two of
the towns are located in Feixi
County, one is in Baohe District, and
two are located in Feidong County.
During the construction, 178.4 mu
land is temporarily taken for one
year. It is estimated this temporary
land acquisition will influence 210
household.
The demolition area by PD is 49967
m2, of which Feixi county accounts
for 7567 m2, Feidong county 1400
m2 and Baohe District 41000 m2.
PD was adjusted
with actual condition
2.3 Current affected people and enterprise
According to the survey on the project progress and onsite investigation, so far, the land acquisition and demolition influences are listed below in Table 2.3.1.
Table 2.3.1 Current affected people and enterprise
Items Affected
Enterprises Affected Village Affected
People Note
Improvement of the Closed Qingxi Road Landfill Site
No No No No group owned
land to be
acquired Sili River Rehabilitation and Flood Control Improvement
No
Sili River, Taohua
Garden and
Wuliguai
communities.
292 people ——
Banqiao River Rehabilitation and Flood Control
No Wangchengdian
Community 8
8 people been
affected in
housing
demolition; for
Hefei Urban Environment Improvement Project
20
Improvement other
villages/towns
some land
acquisition on
the river bank
sides will be
involved, no
housing
demolition.
Ershibu River Rehabilitation and Flood Control Improvement
No - -
Process of
obtaining
approval on
land
acquisition was
completed in
Oct,2008, 40%
of workload has
been finished,
final data info
remains to be
prepared. Shiwuli River WWTP and associated pipeline networks
No Dayu Town Luji
village
61
households,
256 people
——
Wangtang WWTP Phase II and associated pipeline networks
No No No No permanent
land
acquisition
Improvement of the whole Hefei City Sewer
No No No
Land in Phase II
project has
been acquired
in Phase I
project
Chao Lake Ecological Environment and Flood Control Works
No Feixi County-Liuhe
town, Yandun town
and Sanhe town 301
Land
acquisition for
Feixi county
has been
completed; the
rest land
acquisition is
under going.
III Monitoring and Evaluation
3.1 Progress of land acquisition and demolition
3.1.1 Progress of land acquisition
The survey indicates that by January 20, 2009, the land acquisition and
Hefei Urban Environment Improvement Project
21
demolition is as below: (1)Improvement of the Closed Qingxi Road Landfill Site
According to the adjustment on Preliminary Design, permanent land acquisition
will be 281 mu (18.7 hectare), which are all state owned. Within those 281mu land,
181 mu was original landfill land 100mu (12 hectare) and sludge ponds of Water
Supply Corporation No. Plant 100mu, which are all assigned yet. Due to the
optimization of design, planned acquired group owned land in Wulidun Community
Qingxi road sub-community in Shushan District will not be acquired any more. The
project was completed in September 2008 and went through the project
implementation evaluation.
(2)Sili River Rehabilitation and Flood Control Improvement
So far, 60% of the resettlement work has been finished. HDMO has already signed
contracts with each community. Hefei Land Resource Bureau also distributed the
Claim Document on Land Acquisition Remuneration and Resettlement of Hefei Land
Resource Bureau. The documents are HLRLC 2008 No.4 HLRLC 2008 No.5 and
HLRLC 2008 No.6.
( 3 ) Banqiao River Rehabilitation and Flood Control
Improvement PD has been approved. Investigation on land has been finished. Applying for
approval on land acquisition has been through, 60% of land acquisition has been
finished, compensation for affected 180 m2. of housing demolition has been made.
(4)Ershibu River Rehabilitation and Flood Control Improvement
PD has been approved. Investigation on land has been finished. Applying for
approval on land acquisition has been through, 40% of land acquisition has been
completed.
(5)Shiwuli River WWTP and associated pipeline networks
So far, the resettlement work has been finished already. The project IA,HDMO,
has already signed land acquisition contract with each community. Hefei Bureau of
Land Resources also distributed the Letter about Land Acquisition Remuneration and
Resettlement Method to each community. Compensation has been made to the
affected Luji village, Dayu town for land acquisition.
(6)Improvement of Hefei Municipal Sewers
Hefei Urban Environment Improvement Project
22
This project doesn’t involve permanent land acquisition. (7)Wangtang WWTP Phase II and associated pipeline networks Land for Wangtang WWTP Phase II has already been acquired in Phase I project.
Thus, no more land acquisition is needed.
(8)Chao Lake Ecological Environment and Flood Control Works Land acquisition, demolition and relocation in Feixi country has been finished,
measurement and investigation on land acquisition in Feidong county and Baohe
District is in process.
3.2 Progress of building demolition and arrangement
3.2.1Progress of building demolition
According to the adjustment of each PD, through on site interview, the progress of building demolition is listed in Table 3.2.1.
Table 3.2.1 Demolition List Demolition
(m2) Items Planned Actual
Reason for changes Remarks
Improvement of the Closed Qingxi Road Landfill Site
0 0 No demolition ——
Sili River Rehabilitation and Flood Control Improvement
31000 20000
Too much time consumed on the document and approval application
——
Banqiao River Rehabilitation and Flood Control Improvement
180 180 In process of the
applying for approval
Reschedule the plan and coordinate related parties to accelerate the process
Ershibu River Rehabilitation and Flood Control Improvement
60000 28000 Approval procedure takes up too much
time
Reschedule the plan and coordinate related parties to accelerate the process
Shiwuli River WWTP 0 0 No demolition —— Improvement of Hefei Municipal Sewers
0 0 No demolition ——
Wangtang WWTP Phase II and associated pipeline networks
0 0 No demolition ——
Chao Lake 49967 9156 - Demolition planned is
Hefei Urban Environment Improvement Project
23
Ecological Environment and Flood Control Works
49967 m2, of which Feixi
7567 m2, Baohe District
41000 m2;
Land acquisition in
Feixi county has been
completed, actual
demolition area is 9156
m2 which exceeds the
planned area by 1589 m2;
There is no progress made
for Feidong county and
Baohe District. 3.2.2 Resettlement Arrangement Plan
According to the progress of each project, through onsite survey, the construction
of each arrangement house is listed below in Table3.2.2.
Table 3.2.2 Arrangement Status
Items Arrangement Status Note
Improvement of the Closed Qingxi Road Landfill Site
No demolition ——
Sili River Rehabilitation and Flood Control Improvement
Construction of the relocated houses have been completed, relocatees have moved in. ——
Banqiao River Rehabilitation and Flood Control Improvement
The demolished place was not dwelling houses, therefore there was no centralized
relocation as a result. ——
Ershibu River Rehabilitation and Flood Control Improvement
Relocated houses are under construction ——
Shiwuli River WWTP No demolition —— Improvement of Hefei Municipal Sewers No demolition —— Wangtang WWTP Phase II and associated pipeline networks
No demolition ——
Chao Lake Ecological Environment and Flood Control Works
Compensation in money form was made to the affected people for them to build houses by their own, therefore there was no centralized relocation arrangement. Some houses have been completed.
——
The arrangement house for Sili River project is Siquan Garden. This garden lies at the crossing of Feixi Road and Linquan Road, which was planned to finish in August 2008. The relocatees have moved in. Photo of this garden is below:
Hefei Urban Environment Improvement Project
24
Photo 1 Building for resettlement in construction-Aug.2008
Photo 2 The affected people moved in the new building-Dec.2008
3.2.3 Infrastructure construction on affected area and assigned area According to the progress of the project, through onsite investigation, the
Hefei Urban Environment Improvement Project
25
infrastructure construction on affected area and assigned area is presented in Table
3.2.3. Table 3.2.3 Infrastructure construction on affected area and assigned area
Items Infrastructure Construction Note
Improvement of the Closed Qingxi Road Landfill Site No demolition —— Sili River Rehabilitation and Flood Control Improvement Completed ——
Banqiao River Rehabilitation and Flood Control Improvement
No
Demolition area 180 m2, no centralized relocation
arrangement. Ershibu River Rehabilitation and Flood Control Improvement
Under construction ——
Shiwuli River WWTP and associated pipeline networks
No demolition ——
Improvement of Hefei Municipal Sewers No demolition —— Wangtang WWTP Phase II and associated pipeline networks
No demolition ——
Chao Lake Ecological Environment and Flood Control Works
Affected people build houses by their own ——
3.3 Resettlement Fund Utilization
3.3.1 Resettlement Fund Utilization According the progress, through onsite investigation, the resettlement fund
utilization condition is listed in Table 3.3.1.
Table 3.3.1 Resettlement Fund Distribution Table Investment
(10 thousand RMB)
Items Planne
d Accumul
ated
Whether the
remuneration has
been distribut
ed
Reason for advance or delay Actions
Improvement of the Closed Qingxi Road Landfill Site
0 0 —— —— No group owned land to be acquired
Sili River Rehabilitation and Flood Control
3223 1900 Yes Being public posted for land acquisition
remuneration
Accelerate the remuneration process
Hefei Urban Environment Improvement Project
26
Improvement Banqiao River Rehabilitation and Flood Control Improvement
8050 4200 Yes During the process to apply for land
acquisition
Accelerate the land acquisition procedure
Ershibu River Rehabilitation and Flood Control Improvement
19493 7800 Yes During the process to apply for land
acquisition
Accelerate the land acquisition procedure
Shiwuli River WWTP
772.9 772.9 Yes ____ The fund is in place
Improvement of Hefei Municipal Sewers
0 0 —— —— No group owned land to be acquired
Wangtang WWTP Phase II and associated pipeline networks
0 0 —— —— No group owned land to be acquired
Chao Lake Ecological Environment and Flood Control Works
1186.4 742.45 Yes Proceeding as scheduled
Need to speed up the next move
3.4 Change of living condition of affected people
3.4.1 Investigation on living condition of affected people
The survey is focused on Sili River project and Chao Lake Ecological Environment and Flood Control Works which have both finished the land acquisition process. Survey was conducted to affected people with random sampling and in-house interview. Totally, 50 households were interviewed. Questions on transport, medical condition, education condition, living condition change, people’s happiness in affected area and arrangement are were raised.
The result of the survey is summarized in Table 3.4.1 Table 3.4.1 Public Living Condition Survey
Items Choice I Improved no change worse
Transport 44 6 0 II Improved no change worse
Medical condition 45 5 0 III Improved no change worse
Education 45 5 0
Hefei Urban Environment Improvement Project
27
IV Improved no change worse Living condition 50 0 0
V Improved no change worse Employment 48 2 0
VI Satisfied Partially satisfied
Basically satisfied Not happy
Living happiness 20 28 2 0 The combination of those projects with the project in Great Construction, greatly
improve the city image and environment of Hefei. For example, arrangement house
and associated roads for Sili River project and roads in Shiwuli River project as well
as other associated roads built along the project construction all make very positive
contribution to the living condition of surrounding residents. The survey results
indicates that 90% of interviewees think the transport, medical, education conditions,
employment opportunity and living condition have been improved.
3.5 Public Participation
3.5.1 Survey on public opinions
To make the affected people arranged better, keep and maintain the legal rights of demolished people and enterprises, reduce the compliant and conflict, and achieve the resettlement arrangement objective, a random sampling questionnaire survey was conducted. This survey was conducted to affected people in Sili River project and Shiwuli River WWTP project, where land acquisition processes is finished.
Public opinion gathering includes:
(1) Do you know the resettlement remuneration policy?
(2) Are you content with the land acquisition and demolition remuneration
policy?
(3) Are you content with arrangement work?
(4) Any public services you have be offered during the land acquisition and
demolition?
(5) Is remuneration and arrangement received?
(6) Has your legal rights been offended?
(7) If you think your rights is offended, do you know the normal claim
channel?
(8) While your rights are being offended, whether your claim is dealt with in
Hefei Urban Environment Improvement Project
28
time?
(9) Are you content with the results of the claim?
(10) Results are summarized in Table 3.5.1 Table 3.5.1 Public Participation
Items Choice I known unknown
Do you know the resettlement
remuneration policy? 50 0
II Satisfied Partially satisfied
Bascially satisfied Not happy
Are you content with the land acquisition
and demolition remuneration policy?
10 31 9 0
III Satisfied Partially satisfied
Bascially satisfied Not happy
Are you content with arrangement work? 36 11 3 0
IV Professional Training
Improvement on
infrastructureOthers No
Any public services you have be offered
during the land acquisition and
demolition?
12 27 11 0
V All Partial No Is remuneration and
arrangement received? 40 10
VI Yes No don’t know
Has your legal rights been offended? 0 45 5
VII known unknown If you think your rights
is offended, do you know the normal
complaint channel?
50 0
VIII in time not in time While your rights is
being offended, 45 5
Hefei Urban Environment Improvement Project
29
whether your claim is dealt with in time?
IX Satisfied Partially satisfied
Bascially satisfied Not happy
Are you content with the results of the
claim? 35 12 3 0
The result indicates that 96% of interviewees know the remuneration standards;
78% of interviewees are content with the policy or basically content with the policy; and 94% are content with the resettlement arrangement work.
3.5.2 Public Participation
Onsite survey is specially emphasized. Public participation from related residents and communities is very important. They shall participate in the economic survey and the composition of resettlement plan. Public shall be consulted, and communicated with land acquisition policy, there shall be public announcement on resettlement compensation. People in the affected area themselves, shall be responsible for relocation of the rest land, organize production, submit opinions and suggestions to upper level government and provide proper help to people in difficulty.
Thus, during the demolition, the residents have the rights of known and participation. This will ensure the smooth moving of the project.
3.6 Complaint deal procedure and efficiency evaluation
Through information collection and onsite interview, land acquisition and demolition of each project is all assigned to the Demolition Office of each district/county. While the project IAs assisted the demolition offices, the staffing of organization will be improved, and the demolition efficiency shall be improved.
If affected people are not content with the remuneration, or think they are
treated unfairly during the arrangement, they can go through relevant procedures.
There are five main complaint channels in Hefei: (1) Project IA; (2) external
monitoring agency; (3) town committee/community and county land management
bureau and demolition arrangement office; (4) HMG; and (5) Law procedure.
It shall be emphasized that HMG has set up an independent external monitoring
agency, composing of 20 high level leaders from HMG. This agency is called Hefei
Land Acquisition and Resettlement Arrangement Supervization and Management
Committee. The main responsibility of this committee is to examine and supervise the
remuneration distribution. If the remuneration value and distribution time is different
from the Document, the Committee has the right to stop the construction. Thus, if
Hefei Urban Environment Improvement Project
30
affected has different opinions, he might complain at any time to the member of the
Committee while they are supervising on site.
According to Table 3.5.1, 90% of interviewees know the normal compliant channel, and are content with the complaint results.
IV Conclusions on monitoring and evaluations
4.1 Problems encountered during the implementation of the projects
There are totally eight sub-projects under Hefei ADB Loan. Those involving large amount of resettlement arrangement works are: Sili River Rehabilitation and Flood Control Improvement, Ershibu River Rehabilitation and Flood Control Improvement, Banqiao River Rehabilitation and Flood Control Improvement Chao Lake Ecological Environment and Flood Control Works and Shiwuli River WWTP. Projects of Improvement of Hefei Municipal Sewers,Wangtang WWTP Phase II and associated pipeline networks and Improvement of the Closed Qingxi Road Landfill Site involve few resettlement arrangement work. For the current five projects involving large amount of resettlement, Sili River project has already finished land measurement, resettlement contract has been concluded with the affected community committee, the compensation for partly completed demolition has been made; Shiwuli River project also finished land acquisition process, the compensation amount of RMB 1.758 million which was due to pay earlier back has been in place with the village committee; The project progress for Chao lake Ecological Environment and Flood Control Works is ongoing smoothly, demolition and relocation for Feixi county has been completed and compensation fund has been in place; Land measurement for Ershibu river project, Banqiao river project have been finished, some contracts have been concluded and compensation work has started, however the progress needs to speed up, for along with the time, the planned resettlement fund might be adjusted due to the elevated price and related laws, which will influence the budget and schedule of the project. Of the three projects involving a small amount of resettlement, Qingxi Road Landfill and Wangtang WWTP Phase II projects have finished land acquisition work. For the distribution of the remuneration fund, part of the interviewees thought the remuneration speed is relative slow, and hope related organizations might work together to accelerate the distribution speed.
4.2 Project influence At present, Wangtang WWTP Phase II and associated pipeline networks doesn’t
involve permanent land acquisition. Temporary land acquisition might occur during
Hefei Urban Environment Improvement Project
31
the construction. Temporary in original RAP has been optimized in design and construction. Environmental minimization measures and road construction measures have been reduced greatly. There is no more direct affect to surrounding residents. For other items, through survey, 90% of the interviewees know the resettlement plan. For all items which have finished the process of land acquisition, affected people are generally content with the arrangement work.