Q4.11: Roadmap Overview

Post on 29-Nov-2014

280 views 3 download

description

Resource: Q4.11 Name: Roadmap Overview Date: 28-11-2011 Speaker: Mounir Basaibes

Transcript of Q4.11: Roadmap Overview

Linaro Roadmap Overview

Mounir Bsaibes

Agenda

•Quarterly cycle •Roadmap •Implementation

Heavily based on: •https://wiki.linaro.org/Process/Roadmap by Kiko •http://video.google.com/a/linaro.org/#/Play/contentId=e6b907c7f6597a7e by Joey •Life cycle graphs by Ilias •http://wiki.linaro.org/Process/* by various Linaro contributors

Quarterly* Cycles

* A quarter starts at one Connect and ends at the beginning of next Connect, so a quarter does not span exactly 3 months, it may be more of less than 3 months.

Three major phases:

1.Requirements gathering

2.@Connect

3.Implementation

Requirements and Linaro Roadmap

•Requirements

•Can be proposed by the member companies, the TSC,

Technical Lead, Linaro management and Engineers

•Product Management Council (PMC)

•Requirements are submitted to the PMC

•The PMC works with engineering to understand the

requirements feasibility, sizing and when they can be

implemented.

•Place requirements on the roadmap

•Linaro Roadmap

•Holds high level requirements

•Spans 2+ years

•Implemented as Kaban board

Requirement Submission https://linaro.papyrs.com/

Requirement can arrive

any time

New requirements

normally wait till the start

of next Connect to begin

the implementation

Requirements in current

quarter do not normally

change

Anatomy of a Roadmap Card

Name

Task Id

Link to

Papyrs

requirement

Card Type

Sponsor

Priority

Size: small,

medium or

epic

Tags:

components

affected

Linaro Roadmap: General View

Covers only

major

initiatives

Spans 2+

years

Actual plan

of

deliverables,

not a list of

possibilities

Linaro Roadmap: Card Life Cycle View

Draft Accepted Planned Ready Delivered

Normal Flow

Card Lifecycle: Planning Phase

Source by Ilias: https://wiki.linaro.org/Internal/People/IliasBiris?action=AttachFile&do=view&target=PlanningPhaseProcess.graphml

Card Lifecyle: Connect & Implementation Phase

Source by Ilias: https://wiki.linaro.org/Internal/People/IliasBiris?action=AttachFile&do=view&target=ImplementationPhaseProcess-v2.graphml

@ Connect

Implementation

Card

Ready

Implementation

Blueprint3

Blueprint1

Blueprint2

Milestone

12.01

Milestone

12.02

Milestone

12.03

Backlog

Launchpad Project Series 2012

Blueprint1

Blueprint2

Blueprint3

Card

Delivered

Card Lifecycle: End of Quarter Phase

Source by Ilias: https://wiki.linaro.org/Internal/People/IliasBiris?action=AttachFile&do=view&target=EndOfQuarterPhaseProcess.graphml

QUESTIONS

?

Backup