Township of SouthgatePublic Information Meeting Agenda
November 7, 2018
7:00 PMCouncil Chambers
Pages
1. Call to Order
Planner Stredwick
2. Public Information Meeting
Link to online file: https://southgate.civicweb.net/filepro/documents/93123
2.1 Zoning By-law Amendment, Township File No. C17-18regarding Petawawa Biofuel Presentation (Non-Statutory publicInformation meeting) Mark Bell, Director, Petawawa Biofuel LPand Claire Allen, CH Four Biogas
2 - 26
3. Open Forum/Discussions
3.1 Presentation of written comments/questions received
3.2 Opportunity for verbal comments/questions
4. Adjournment
Three Design Changes forIncreased Odour Protection
1. Manure reception within Reception Building
2. Digestate tank loading within Reception
Building (Sept 2018)
• Simplified washdown of trucks
• Simplified spill containment
• Digestate virtually odourless
3. Updated design of odour control stacks for
increased redundancy and odour protection
(Sept 2018)
78
Updated Odour Control Stack Design
• Design features that remain:
– All displaced air is treated through an activated
carbon filter system before it is released to the
atmosphere
– Air tight tanks - reception, storage and AD
– No open storage of obnoxious materials
– Daily inspection of facility
– Delivery truck wash-down in enclosed building
– Good housekeeping – keeping site clean
89
Updated Odour Control Stack Design
• Design features that have changed:
– Multiple continuous emissions monitoring (CEM)
sensors for each stack
– Two carbon filters run in series both sized
complete full treatment of air
– SCADA system to automatically direct flow to
second filter should breakthrough occur
– Continuous air treatment during media change out
(design anticipates 1 media change per year)
910
CLARIFICATION OF OUTSTANDING ISSUES
ODOUR ASSESSMENT &
UPDATED EMISSION SUMMARY AND DISPERSION MODEL
1213
Odour Assessment
• Odour Assessment carried out on all 7 odour control stacks at the facility– Odour control at receiving area (6 stacks)
– Odour control at biogas upgrader (1 stack)
• Dispersion modelling of odour from each stack is compared to MECP threshold of 1 odour unit (OU)
• Dispersion model results indicate that odour emissions are a factor of 10 below MECP limit
1314
Odour AssessmentDispersion Modelling of Odours
14
Data used for odour assessment is from 2018 site emissions testing from similar AD facility in BC
15
Odour AssessmentOdour Dispersion Modelling Results
Point of Impingement OU
A 0.0481
B 0.0636
C 0.0823
D 0.0701
E 0.0636
F 0.0595
G 0.0459
H 0.0728
• Dispersion model results much lower than MECP threshold of 1 Odour Unit
• Dispersion model is a conservative screening method (“worst case”)
1617
Emissions Summary andDispersion Modelling
• Updates made to ESDM Report
– Some stack heights increased
– Effect of buildings included in modelling
– NOx modelling instead of NO2 modelling
• Result
– Negligible impact to emissions from the facility
– Emissions remain below MECP Guidelines
1718
Responses to Concerns Raised During Zoning Amendment Process
Review of Concerns Raised & Responses to Concerns
1819
Summary of Concerns Raised1.Daytime meeting not appropriate (regarding the June 27 Public Meeting)
2. Fugitive Odours from the Eco-Park 'nothing being done'; 'MOE does nothing'
3. Daytime meeting not advertised properly.
4. Location is too close to school and new subdivisions
5. The existing problems of fugitive emissions are not being addressed and this project will not improve the situation.
6. Odour concerns from Lystek and Go Bark
7. Confusion regarding the type of odour filtration - biofilter vs. activated carbon
8. Perception that the project is the same as the Elmira system
9. GHD review based on the technical information - recommended additional information
10. Backup sensors and secondary filters
11. Road Use, development agreement to be registered on title to include: site plan, citizen's advisory committee, road use, royalty payments, etc.
12. Information to be properly presented to public
13. Lame Duck Decision - prudency to defer
14. Planning Justification inadequately addressed PPS
15. Township to take 'every precaution' to ensure 'no negative effect on air quality'
16. Option A vs. Option B vs. Option C
17. Concerns at All Candidates Meetings - 'no more biosolids'; 'computer engineering people'; insufficient employment'
18. Concerns expressed at Open Houses 'lack of transparency'
19. Property Values in Dundalk are suppressed because of the industries in the Eco-Park
20. Project not viable if gas not sold
21. MOECP concerns
22. GHD Concerns
23. First Nations and Aboriginal Concerns
23. Adjacent Landowner Concerns 1920
Any Additional Questions?
Mark BellDirector
Petawawa Biofuel LP
Mark Bell mbell@petawawacorp.com
Tel: 416 209 7351
2021
What is Odour?
• The magnitude of odour impact depends on a number of factors
– Frequency of detection
– Intensity as perceived
– Duration of exposure
– Offensiveness
– Receptor sensitivity
2223
What is Odour?
• Odours may be perceived as pleasant or unpleasant.
• Main concern with odours is the its ability to cause a response in individuals that is considered to be objectionable or offensive
• Odour emission thresholds set are different around the world (often industry dependent)
– Ie: coffee roaster facility could have a higher emission threshold than a waste water treatment plant
2324
How Do You Measure Odour?
24
• Dynamic dilution olfactometer which controls flow and dilution rate of sample to an air panel
• Begin with high dilution value which is decreased (machine controls flow and dilution rates)
• Register response to odour (smell or not)
25