PS Planning

Fernando Pedrosa

2

Table of Contents

• Progress report on the activities between 12th December to 10th January 2020

• Works foreseen for the next 2 weeks

09-Jan-2020

3

12th December 2019As presented the 12th December 2019 / As performed

09-Jan-2020

4

13th December 2019As presented the 12th December 2019 / As performed

09-Jan-2020

5

16th December 2019As performedAs presented the 12th December 2019

09-Jan-2020

6

17th December 2019As performedAs presented the 12th December 2019

09-Jan-2020

7

18th December 2019As performedAs presented the 12th December 2019

09-Jan-2020

8

19th December 2019As performedAs presented the 12th December 2019

09-Jan-2020

9

20th December 2019As performedAs presented the 12th December 2019

09-Jan-2020

10

06th January 2019As performedAs presented the 12th December 2019

09-Jan-2020

11

07th January 2019As performedAs presented the 12th December 2019

09-Jan-2020

12

08th January 2019As performedAs presented the 12th December 2019

09-Jan-2020

13

9th January 2020

• LV consolidation

• Removal of the temporary

shielding blocks around

the LBE dump and BI line

(including evacuation

from the PS)

• Cabling campaign PSB to

PS (BTP)

• Cabling campaign C12/23

(B355 to PS ring)

• Consolidate the slabs and

their supports on the

outer side of the ring

09-Jan-2020

14

10th January 2020

• Platform modification

• LV consolidation

• F16.QDN180 and

F16.STP176 re-

installation

• Cabling campaign PSB to

PS (BTP)

• Cabling campaign C12/23

(B355 to PS ring)

• Consolidate the slabs and

their supports on the

outer side of the ring

• BHZ40 alignment

09-Jan-2020

15

13th to 15th January 2020 F61 line works

• Equipment installation

Cabling campaign C12

Installation of a rigid RF line for the SS88, SS89 and SS08 cavities

Cooling modifications for the BGI82 and BGI84

EN-CV cable installation between B355 and Septum pump in SS53

Longitudinal dumper installation works

PS SWY

activities in

the next slide

09-Jan-2020

16

13th January 2020

• Platform modification

• LV consolidation

• Install the F16.QDE180

• Install the F16.STP176

• Installation of the

“Potance” needed for the

F16.QFO165 removal

• LTB re-alignment

• Cabling campaign PSB to

PS (BTP)

• Cabling campaign C12/23

(B355 to PS ring)

09-Jan-2020

17

14th January 2020

• Platform modification

• LV consolidation

• Removal of the

F16.QFO165 magnet

• Cabling campaign PSB to

PS (BTP)

• Cabling campaign C12/23

(B355 to PS ring)

• LTB re-alignment

• TPS15 replacement

09-Jan-2020

18

15th January 2020

• LBS.DVT10 installation

• LV consolidation

• Cabling campaign PSB to

PS (BTP)

• Cabling campaign C12/23

(B355 to PS ring)

• LTB re-alignment

09-Jan-2020

19

16th to 20th January 2020 F61 line works

• Equipment installation

Cabling campaign C12

Installation of a rigid RF line for the SS88, SS89 and SS08 cavities

Cooling modifications for the BGI82 and BGI84

Longitudinal dumper installation works

PS SWY

activities in

the next slide

09-Jan-2020

20

16th January 2020

• LBS.DVT10 alignment

• LTB re-alignment

• LV consolidation

• F16.STP152 (x2)

installation

• Cabling campaign PSB to

PS (BTP)

• Cabling campaign C12/23

(B355 to PS ring)

09-Jan-2020

21

17th January 2020

• LV consolidation

• F16.STP152 (x2)

installation

• Installation of the BI line

vacuum pipe that goes

inside the shielding wall

• BI line drilling and

supports installation

• Cabling campaign PSB to

PS (BTP)

• Cabling campaign C12/23

(B355 to PS ring)

• LTB re-alignment

09-Jan-2020

22

20th January 2020

• LV consolidation

• Install the F16.QFO165

magnet

• Removal of the “Potance”

needed for the

F16.QFO165 removal and

installation

• LT.QDE70 installation

• BI line drilling and

supports installation

• Cabling campaign C12/23

(B355 to PS ring)

• Scaffolding installation

• Connection of all BTP

equipment to the services

in the area not affected by

the scaffolding

• LTB re-alignment

09-Jan-2020

23

21st January 2020 Start the MU90 re-installation

F61 line works

• Equipment installation

Cabling campaign C12

Installation of a rigid RF line for the SS88, SS89 and SS08 cavities

Cooling modifications for the BGI82 and BGI84

EN-CV cable installation between B355 and Septum pump in SS53

Longitudinal dumper installation works

PS SWY

activities in

the next slideMU90 re-

installation

09-Jan-2020

24

21st January 2020

• LV consolidation

• Cabling campaign from

the PSB (BI, LBE and

LBS lines)

• Cabling campaign C12/23

(B355 to PS ring)

• Scaffolding installation

• Connection of all BTP

equipment to the services

in the area not affected by

the scaffolding

• LTB re-alignment

• F16.STP152 (x2) +

F16.STP176 +

F16.QDE180 +

F16.QDN165 alignment

• LT.QDE70 Alignment

09-Jan-2020

25

22nd January 2020 Finish the MU90 re-installation

F61 line works

• Equipment installation

Cabling campaign C12

Installation of a rigid RF line for the SS88, SS89 and SS08 cavities

Cooling modifications for the BGI82 and BGI84

EN-CV cable installation between B355 and Septum pump in SS53

Longitudinal dumper installation works

PS SWY

activities in

the next slideMU90 re-

installation

09-Jan-2020

26

22nd January 2020

• LV consolidation

• Cabling campaign from

the PSB (BI, LBE and

LBS lines)

• Cabling campaign C12/23

(B355 to PS ring)

• Lifting rail installation

• Connection of all BTP

equipment to the services

in the area not affected by

the scaffolding

• LTB re-alignment

• F16.STP152 (x2) +

F16.STP176 +

F16.QDE180 +

F16.QDN165 alignment

• LT.QDE70 Alignment

ACCESS to LT, LTB, BI, LBE, LBS:

Preferably from B353/central ring

/gallery 3/MU27

09-Jan-2020

27

23rd January 2020 MU90 alignment

F61 line works

• Equipment installation

Cabling campaign C12

Installation of a rigid RF line for the SS88, SS89 and SS08 cavities

Cooling modifications for the BGI82 and BGI84

EN-CV cable installation between B355 and Septum pump in SS53

Longitudinal dumper installation works

PS SWY

activities in

the next slide MU90

alignment

09-Jan-2020

28

23rd January 2020

• LV consolidation

• Cabling campaign from

the PSB (BI, LBE and

LBS lines)

• Lifting rail installation

• Connection of all BTP

equipment to the services

in the area not affected by

the scaffolding

• LT vacuum connection

and pump down

ACCESS to LT, LTB, BI, LBE, LBS:

Preferably from B353/central ring

/gallery 3/MU27

09-Jan-2020

29

24th January 2020 F61 line works

• Equipment installation

Cabling campaign C12

Installation of a rigid RF line for the SS88, SS89 and SS08 cavities

Cooling modifications for the BGI82 and BGI84

EN-CV cable installation between B355 and Septum pump in SS53

Longitudinal dumper installation works

PS SWY

activities in

the next slide

09-Jan-2020

30

24th January 2020

• LV consolidation

• Cabling campaign from

the PSB (BI, LBE and

LBS lines)

• Scaffolding dismantling

• Connection of all BTP

equipment to the services

in the area not affected by

the scaffolding

• LT vacuum connection

and pump down

ACCESS to LT, LTB, BI, LBE, LBS:

Preferably from B353/central ring

/gallery 3/MU27

09-Jan-2020

31

TT2

Apart of the cabling campaign this week we

don’t have much activities

09-Jan-2020

B.151• RF ISTs approved

in the LS2C

• Vacuum works

09-Jan-2020

B.269 - Report• Cabling campaign C17 ongoing

• Cabling between transformers and switchboard ongoing

• New HVAC Unit under test

09-Jan-2020

B.269 – Next 2 weeksIn the coming 2 weeks we will have some co-activity in the building that has

been discussed and documented in specific VICs

Note:

Planning and conditions agreed in the VIC must be respected – any change

needed must be re-discussed and documented

09-Jan-2020

AC CablingWIC

Smoke detection installation

False floor tiles installation

AC + C17 Cabling

B.355 – Next 2 weeks

TFB equipment

installation

C18b cabling

campaign

TE-EPC maintenance

works

EN-CV works in the new PS

CV cooling station

09-Jan-2020

36

B.359 – next 2 weeks

09-Jan-2020

TE-ABT control

works

AOB

• We are experiencing some difficulties on having the EDH

transport request made on time

• Please discuss the EDH requests with Yann if you have

questions and do it at least 1 week in advance for

everything that is in the planning

• If possible we would like to ask the equipment responsible

to remove the LTB line equipment shown in the picture to

avoid it gets damaged by accident:

09-Jan-2020

AOB

Sector under vacuum

• SS70 to SS80

• SS01 to SS10

09-Jan-2020