The Logical Flow of Project
Scheduling…
1. Work Break Down Structure (WBS)
2.Resources, Roles & Performance Measures
3.Dependency Diagram
4. Programme Evaluation Review Technique
(PERT)
5.Gantt Analysis
6. Project Budget
www.derekhendrikz.com
the WBS subdivides the project
tasks into smaller work elements
www.derekhendrikz.com
www.derekhendrikz.com
the WBS aims to outline the project
activities in detail
the WBS takes the form of an organogram,
where objectives are translated to
action programmes, which translates to
performance measures, etc…
www.derekhendrikz.com
WBS Organogram…
4
3
2
1 Project X
Objective 1
Action Programm
e 1
Performance Indicator
1
Performance Indicator
2
Action programm
e 2
Objective 2
www.derekhendrikz.com
Practical Exercise…
Use your workplace project as practical exercise to plan
and schedule your actions.
Also use the objectives designed during the project brief
as base-line for the development of your WBS.
The first part of this exercise will be to relate your primary
objectives to tasks, and then to relate your tasks to
performance measures and resources needed.
Tasks do not have to be progressive in nature and the
numbers must follow through irrelevant of which objective
you are busy with.
www.derekhendrikz.com
Linking Tasks to Objectives…
Task:
That which must be done to realise a project objective.
Predecessors:
The tasks that precede the current task.
Performance measures:
How will we know that the task is done?
Resources Needed:
What resources do we need to successfully complete the
task?
www.derekhendrikz.com
Rules of a Logic (dependency) Diagram…
Time flows from ‘start’ to ‘finish’.
Each key stage must be described
separately.
Show the dependency links with
arrows, e.g. ‘C’ can only take place
once ‘B’ and ‘A’ has been done.
www.derekhendrikz.com
Sample of a Logic (dependency) Diagram…
www.derekhendrikz.com
Answer to exercise 2(a)…
www.derekhendrikz.com
Answer to exercise 2(b)…
www.derekhendrikz.com
Critical Path Method
www.derekhendrikz.com
Answer to exercise 3(a)…
www.derekhendrikz.com
Answer to exercise 3(b)…
www.derekhendrikz.com
PERT (Programme Evaluation Review Technique)
www.derekhendrikz.com
Answer to exercise 4(a)…
www.derekhendrikz.com
Answer to exercise 4(b)…
www.derekhendrikz.com
Answer to exercise 4(c)…
www.derekhendrikz.com
Answer to exercise 4(d)…
www.derekhendrikz.com
Answer to exercise 4(e)…
www.derekhendrikz.com
Answer to exercise 4(f)…
www.derekhendrikz.com
Answer to exercise 4(g)…
www.derekhendrikz.com