Progress Status at Pour 5,6 Locations

Post on 30-Jan-2016

225 views 0 download

Tags:

description

Progress Status a

Transcript of Progress Status at Pour 5,6 Locations

Progress Status at Podium LB 6,7 & UB 5 Locations

Status as on 24th Nov’15

30% staging works yet to be done at pour 5 UB location.

Retaining wall (Dependent activity ) not yet casted at pour 5 UB location

40% shuttering works yet to be done at pour 5 UB location.

Staircase columns not yet casted at pour 5 location.

20% shuttering work yet to be done at pour 6 location.

No manpower been deployed for reinforcement works at Pour 6 location.

Beam B34 bottom not yet initiated at pour 6 location.

Rain water tank bottom slab not yet casted at pour 6 location.

16 columns yet to be casted at pour 7 location .

Casting of starters not been initiated at pour 7 locations