Post on 07-Jan-2016
description
SPSU 15.4.2008
Progress on coatings and grooves
M.Taborelli
-Progress on C based coatings-Progress on SEY instrument-Progress on grooves
SPSU 15.4.2008
Effect of the sputtering gas used during carbon film deposition: Ne and Kr
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
C run 3, 2hair, 2092-a
bottom,
C run 4, bottom 2h
air
C Ne,bottom, 2hair, 2097-b
rela
tive
yie
ld
500Vdeposited w ith Kr w ith Kr,in SPS linernow
deposited w ith w ith Ne
Progress on coatings
Lowest yield up to now
SPSU 15.4.2008
Complete yield curve (measured at CSIC-Madrid)
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
0 100 200 300 400 500 600 700 800 900
Primary Energy (eV)
SE
Y
After 2 weeks air exposure
dep. with Kr
Dep. with Ne
Progress on coatings
measured at CERN after 2h air after 14 d air
SPSU 15.4.2008
Progress on coatings
Both coatings are quiteCompact and well adhering
C(Kr), in SPS now
C(Ne)
SPSU 15.4.2008
Progress on coatings
The reason of the lower SEY is not understood yet-Implanted gas? some of the Kr deposited coating show Kr in
the spectra (original reason for the Ne trial!) -No difference in the C1s XPS spectra-No difference in the content of O-difference in morphology, xtalline structure……?
0
10000
20000
30000
40000
50000
60000
278280282284286288290292294
binding energy [eV]
Inte
nsi
ty (a
rb. u
n.)
2094-a r4
2097-a
2097-b
C(Ne)
C(Kr)
C1s XPS
SPSU 15.4.2008
Plans for next coatings (….find candidate for next liner)
- reproduce a C(Ne) coating and its SEY
- make rough surface (Cu or Zr) as substrate for low SEY (C) coating
- BC with lower amount of B (B4C has a rather high yield, already measured)
- SiC, TiB2
SPSU 15.4.2008
0.50
0.70
0.90
1.10
1.30
1.50
1.70
1.90
2.10
2.30
0 200 400 600 800 1000 1200 1400 1600 1800 2000
primary electron energy in eV
seco
ndar
y el
ectr
on Y
iled
Cu first
Cu second
Cu fine scan
Cu last
Progress on SEY instrument
First data from new system: unbaked copper
SPSU 15.4.2008
Progress on SEY instrument
Still to be optimized, verified…built:
- Control of focussing (at present some 2 mm spot, but notwell controlled above 1000eV)
-Position (distance) with respect to “optics”-Beam position stability at low Ep and magnetic field screening
-Load lock and transfer to XPS still under construction
-SPS transfer chamber under construction (J.Axensalva and J.Ramillon)
Phase II:-Faster acquisition to avoid high dose...however it seems to be already OK-Implement flood gun for conditioning with e-beam
SPSU 15.4.2008
Grooves made at CERN workshop with cutting tool(J.M.Geisser, S.Atieh)
Progress on grooves
On copper: tool well aligned, small radii on top and bottom, but burrsalong the grooves
On stainless steel 304L:Preliminary trial without perfect alignment of the tool: large radius at the bottom
2mm
SPSU 15.4.2008
Progress on grooves
Grooves in copper
SPSU 15.4.2008
To continue the work:
Progress on grooves
Cost of what has been done until now (short piece on steel and copper): 2000 CHF work + 2000 CHF tool = 4000 CHF
To produce 800 mm x 100 mm (or 400 mm + 400 mm) on steel: 2000 CHF tools + 4000 CHF work =6000 CHF
If we go on the entire amount will be charged: 10000 CHF