Prestressed Concrete – Erection

Post on 25-Feb-2022

9 views 0 download

Transcript of Prestressed Concrete – Erection

1

Prestressed Concrete – Erection

2018 Bridge Construction Inspection School

Chuck Snyder

VDOT Staunton District

Bridge Maintenance Specialist

Road and Bridge Specifications

2007 & 2016 Specifications:

• 405.05 (g) – Waterproofing PS Members

• 405.05 (h) – Handling, Storing, and Erecting PS Members

• 405.06 – Tolerances PS Members

• 408.03 12.(g) Placement – Elastomeric Bearing Pads

2

Bearing Pad & Expanded Rubber Joint Material Location

Direction Setting Members

Begin Setting Members at High Point of Bridge Seat Crown.

3

Setting Prestressed Members

Step 1 – Bearing Pad Layout

5

Setting Prestressed MembersStep 2 - Mark initial pad location.

Step 3 – Dust with dry cement, replace pad.

4

Setting Prestressed Members

Step 4 - Member Setting Sequence

Step 5 - Setting prestressed member.

Setting Prestressed Members

5

Step 6 - Check for bearing with feeler gauge.

Setting Prestressed Members

Step 7 – Pick-up P.S. MemberStep 8 – Lift pad determine non-bearing area

Setting Prestressed Members

6

Setting Prestressed Memebers

Step 9 – Outline non-bearing.

11

Step 10 - Apply a stiff epoxy mortar to non-bearing areas. Repeat process as necessary.

Setting Prestressed Members

7

Setting Prestressed Members

Step 10a - Epoxy mortar mix (finer sand preferred)

Setting Prestressed Members

Step – 11 – Reposition Pads

14

8

Setting Prestressed Memberes

Step 12 – Repeat Steps 5 & 6.

15

Setting Prestressed Members

Shims may be added if epoxy build-ups become excessive (> ½”). Shims should always be inserted Under the pad, during the initial setting.

After initial setting and bearing pad has been built-up with epoxy and does not have full bearing than shims may be added on top of the pad. (Once epoxy build-up sets, almost impossible to shim at bottom of pad).

9

Setting Prestressed Members

17

Bearing checked after epoxy mortar had set beneath the pad. Shim with copper or stainless steel shims on top of pad.

Setting Prestressed MembersShims on top of Bearing Pads – WrongShims to be placed on bottom of pad if not previously built up with epoxy.

10

Setting Prestressed Members

Pad racked laterally (transverse)

19

Stainless Steel Shims

11

Mortar Seepage Thru Joint

Non-Bearing Pad

12

Questions?

23

1

Prestressed Concrete – Shear Keys, Post-tension & Epoxy Overlays

2018 Bridge Construction Inspection School

Chuck Snyder

VDOT Staunton District

Bridge Maintenance Specialist

Handling, Storing & Erecting Prestressed Members

2016 Road and Bridge Specifications Section 405.05 (h):

• Shear keys and recesses shown on plans shall be filled with mortar conforming to Section 218. Mortar shall be applied in one continuous operation for each span.

• The following types of “mortar” will be used as shown on the Plans:1. Engineered Cementitious Composite (ECC)

2. Very High Performance Concrete (VHPC)

• Waterproofing material applied to top of units in the field, longitudinal joints shall be sufficiently smoothed to prevent damage to material.

2

2

Epoxy Bridge Deck Overlays

2016 Road and Bridge Specifications Section 431:

• Epoxy overlay shall NOT be placed on hydraulic cement concrete (prestressed members) that is less than 28 days old.

• Epoxy overlay MAY be placed on shear key mortar that has been cured a minimum of 7 days.

• Bridge deck cleaning and testing of trial patches shall be in accordance with VTM-92.

• Test patches for tensile strength must be obtained for each span or 300 square yards, whichever is the smaller area.

• Epoxy overlay shall be applied in 2 separate courses. Total of the 2 applications shall not be less than 7.5 gallons per 100 square feet.

3

Shear Key Detail

Grout used for shear keys shall beEngineered Cementitious Composite (ECC)

4

3

Shear Key Detail

Manual of Structure and Bridge Division.

5

Shear Key Detail with VAMC Blockouts

Very High Performance Concrete (VHPC) shall be used to fill shear keys and blockouts for Virginia Adjacent Member Connections (VAMC).

6

4

Shear Key Detail with VAMC Blockouts

7

Longitudinal Shear Key Being Prepared For Grout

8

5

Shear Key Backer Rod

9

Grouted Longitudinal Shear Key

Mortar to be applied in one continuous operation for each span.

10

6

Example of Kevlar Material11

Waterproof Pier Joint

12

7

Longitudinal Shear Key & Transverse Pier Joint Waterproofing

13

Skewed Prestressed Members Post Tension – Two Members

14

8

Post-tensioning Transverse Tendons (Rod)

15

Post-tensioning Transverse Tendons (Cable)16

9

Transverse Tie Rod Too Long

17

Proposed Correction For Vertical Offset Between Adjacent Slabs After Setting

18

10

Epoxy Overlay Test Patch & Test Equipment (2016 R & B Spec. Section 431.03)

Epoxy Test Patch

Epoxy Pull Test Equipment

19

Vertical Offset Between Adjacent Members

20

11

Bridge Deck Epoxy Overlay Application

21

Bridge Deck Epoxy Overlay - First Coat Application After Shear Keys Waterproofed

22

12

Bridge Deck Epoxy Overlay - Applying Second Coat

23

Slab End Waterproofing 4” Kevlar Overlap Lifting Strands Cut Off, Cover with 1/8” Thick Epoxy Mortar

Lifting Strands

24

13

Waterproof Outside Vertical Edge& Transverse Tie Blockout

Grout & waterproof blockout after transverse tie rods are tensioned.

25

EP-3 Waterproofing Vertical Side of Exterior Members - Applied at Plant

26

14

Waterproofing Slab Ends @ Abutments

27

Waterproofing Slab Ends@ AbutmentsExample 1 (Correct?)

28

15

Waterproofing Slab Ends(Example 2 – Correct?)

29

Waterproofing Abutment Slab EndsExample 3 – (Correct?)

30

16

End of Prestress Members Offset

31

Example #1: Leaking Joint& Damaged Bridge Seat

32

17

Example #2: Leaking Longitudinal Joint & Damaged Prestressed Slab/Box

33

Example #3: Leaking longitudinal Joint& Damaged Prestressed Slab/Box

34

18

Prestressed Member Reinforcing Steel –ST0404

4”

2” Max. Clearance

35

Questions?

36