AHSANULLAH UNIVERSITY OF SCIENCE & TECHNOLOGY
Course No : CE-416.Course Title : Prestress Concrete Design
Sessional.
2
Prestress Loss
3
Welcome To Our Presentation
4
Group Members
10.01.03.062 - Shahriar Mujthahid Hossain.10.01.03.063 - H.M.Suruzzaman.10.01.03.065 - Sabbir Bin Delwar.10.01.03.066 - Md. Imran Islam.10.01.03.069 - Tasfia Ahmed.10.01.03.072 - Mohammad Shakib Rahman.10.01.03.075 - Munshi Md. Rasel.10.01.03.076 - Md.Moinul Islam.
5
What is Pre-stressed Concrete?
– Internal stresses are induced to counteract external stresses.
– In 1904, Freyssinet attempted to introduce permanent acting force in conc. to resist elastic forces under loads and was named
“Pre stressing”.
6
Introduction
• In prestressed concrete applications, most
important variable is the prestress.
• Prestress does not remain constant with time.
• Even during prestressing of tendons, and transfer
of prestress, there is a drop of prestress from the
initially applied stress.
• Reduction of prestress is nothing but the loss in
prestress.
7
Prestress Loss
• loss in prestress is the difference between initial prestress and
the effective prestress.
• Loss of prestress affects
– the strength of member and
– member’s serviceability [ Stresses in Concrete, Cracking, Camber and Deflection ]
8
Types
Loss of prestress is classified into two types:
1. Immediate Losses
immediate losses occur during prestressing of tendons,
and transfer of prestress to concrete member.
2. Time Dependent Losses
Time dependent losses occur during service life of
structure.
9
Prestress Losses
ImmediateTime
Dependent
Relaxation
Anchorage Slip
Elastic Shortening
Friction
ShrinkageCreep
Types According To Time
10
Prestress Losses
Concrete Steel
Relaxation
ShrinkageElastic
ShorteningCreep
Anchorage Slip
Friction
Types According To Material
11
Types of Prestressing Systems
I . Pre-tensioning: In Pre-tension, the tendons are tensioned before the
concrete is place. After the concrete hardened, the tension force is released.
II . Post tensioning: In Post tension, the tendons are tensioned after the
concrete has hardened.
12
Example of Pre-tensioning
Fig : Pre-tensioned electric pole
13
Example of Post-tensioning
Fig : Post-tensioning of a box girder
14
Losses in Various Prestressing Systems
Type of Loss Pre-tensioning Post-tensioning
1. Elastic Shortening Yes
i. No, if all the cables are simultaneously tensioned.
ii. If the wires are tensioned in stages loss will exist.
2. Anchorage Slip No Yes3. Friction Loss No Yes
4. Creep and Shrinkage of Concrete Yes Yes
5. Relaxation of Steel Yes Yes
15
Immediate Loss
16
Elastic Shortening
• It is the shorten of concrete member, when the prestress is
transferred to concrete, the member shortens and the prestressing
steel also shortens in it. Hence there is a loss of prestress.
Original length of member at transfer of prestress
Length after elastic shortening
Pi
P0
17
Elastic Shortening at Pre-tensioned Members
When the tendons are cut and the prestressing
force is transferred to the member, concrete
undergoes immediate shortening due to prestress.
Tendon also shortens by same amount, which leads
to the loss of prestress.
18
Pre-tensioning of a member
Prestressing bed
Elastic Shortening at Pre-tensioned Members
19
Elastic Shortening at Post-tensioned Members
If there is only one tendon, there is no loss because
the applied prestress is recorded after the elastic
shortening of the member.
For more than one tendon, if the tendons are
stretched sequentially, there is loss in a tendon
during subsequent stretching of the other tendons.
20
Casting bed
Duct
jackAnchorage
Post-tensioning of a member
Elastic Shortening at Post-tensioned Members
21
Anchorage Slip
• In most Post-tensioning systems when the prestress force is transferred from the jack to the anchoring ends, the wedges slip over a small distance.
• Loss of prestress is due to the consequent reduction in the length of the tendon.
• Amount of slip depends on type of anchorage system.
22
Force variation diagrams for various stages
a) The initial tension at the right end is high to compensate for the anchorage slip. It corresponds to about initial prestress. The force variation diagram (FVD) is linear.
b) After the anchorage slip, the FVD drops near the right end till the length lset.
Note : Effect of anchorage slip is present up to a certain length, called the setting length lset.
23
Force variation diagrams for various stages
c) The initial tension at the left end also corresponds to about initial prestress. The FVD is linear up to the centre line of the beam.
d) After the anchorage slip, the FVD drops near the left end till the length lset. It is observed that after two stages, the variation of the prestressing force over the length of the beam is less than after the first stage.
24
Typical values of anchorage slip
Anchorage System Anchorage Slip (Δs)
Freyssinet system 12 - 5mm Φ strands 12 - 8mm Φ strands
4 mm 6 mm
Magnel system 8 mm
Dywidag system 1 mm
25
Frictional Loss• The friction generated at the interface of
concrete and steel during the stretching of a curved tendon in a post-tensioned member.
• The friction in the jacking anchoring system is generally small.
• More serious frictional loss occurs between the tendon and its surrounding material.
26
Frictional loss occurs only in Post-tensioned Members
• The loss due to friction does not occur in pre-tensioned members because there is no concrete during the stretching of the tendons.
• Friction is generated due to curvature of tendon, and
vertical component of the prestressing force.
A typical continuous post-tensioned member
27
Frictional Loss
Frictional Loss is the summation of– Friction Loss Due to length Effect.– Friction Loss Due to Curvature Effect.
• Length Effect: If the profile of cable is linear, the loss will be due to straightening or stretching of the cables.
• Curvature Effect: If the profile is curved, there will be loss in stress due to friction between tendon and the duct or between the tendons themselves.
28
Length & Curvature Effects
29
Methods available to “Reduce” the frictional losses
1. Cables should pass through metal tubes.2. The bends should be through as small an
angle as possible.3. Radius of curvature for bends should be
large.4. Prestressing the wire from both ends.5. Over-tensioning the wires.
30
Time Dependent Losses
31
Creep of Concrete
• The Continuous deformation of concrete with time under sustained load.
Factors affecting creep of concrete• Age
• Applied Stress level
• Density of concrete
• Cement Content in concrete
• Water-Cement Ratio
• Relative Humidity and
• Temperature
32
Condition for calculating the loss of prestress due to creep.
• Creep is due to sustained (permanent) loads only. Temporary
loads are not considered in calculation of creep.
• Since the prestress may vary along the length of the
member, an average value of the prestress is considered.
33
Shrinkage of Concrete
• Shrinkage of concrete is defined as the contraction due to loss of moisture.
• Due to the shrinkage of concrete, the prestress in the tendon is reduced with time.
34
Shrinkage of Concrete
• For pre-tensioned members, transfer commonly takes place after 24 hours after casting and nearly all shrinkage takes place after that.
• For post-tensioned members, stressing may takes place after one day or much later, thus a large percentage of shrinkage may already taken place by them.
35
Relaxation
Relaxation is the reduction in stress with time at
constant strain.
– decrease in the stress is due to the fact that some
of the initial elastic strain is transformed in to
inelastic strain under constant strain.
– Percentage of relaxation varies from 1 to 5%.
36
Factors effecting Relaxation :
• Time
• Initial stress
• Temperature and
• Type of steel.
37
Method Available to Reduce The Loss due to Relaxation
• Choice of proper steel helps to reduce this loss.
• Prestressed wires have lesser creep. • Galvanised wires also have no creep.• overstressing steel about 10% above its initial
stress and then releasing it to the initial stress
38
Calculation of Total Amount of Loss
39
Loss of Prestress=Initial Stress-Effective Stress
40
Initial Prestress
• Deducting the loss due to anchorage take-up and friction, initial prestress is obtained.
• If prestress is measured at the time of pulling the wire, the stress is termed as the jacking stress.
• if jacketing stress is treated as the initial stress, effective stress is jacketing stress minus all losses.
41
Effective Prestress
• Initial Prestress in steel minus the losses is known as the effective or design prestress.
Effective prestress=Initial prestress-Losses
Note: For Pre-Tension system , Pretension Losses are used instead of losses.
For Post-Tension system , Post-Tension Losses are usedinstead of losses.
42
Total Amount Of Losses According To Tensioning System
• Total pretension losses=Loss due to creep +Elastic shortening + Shrinkage +Steel Relaxation.
• Total post-Tension Loss=Loss due to creep +
Elastic shortening + Shrinkage +Steel Relaxation +Anchorage slip +
Friction.
43
Total Losses
• It is difficult to generalize the amount of loss of prestress, because it is dependent on so many Factors :
The properties of concrete & steel.Curing & moisture condition.Magnitude & time of application of prestress.Process of prestress.
44
Method of Loss Estimation
• There are two methods that can be used to estimate losses in prestressed concrete: (a)lump sum approximations;
(b)refined estimations.
One should keep in mind that all estimates for prestress loss are just that – ESTIMATIONS .
45
Lump Sum Estimation For Prestress Loss
• First introduce by the ACI-ASCE Committee 423 in 1958.
Table : AASHTO Lump Sum Losses. Total Loss
Types of prestressing steel
f’c=28 MPa f’c=35 MPa
Pretensioning strand
310 MPa
Posttensioning wire or strand
220 MPa 230 Mpa
Bars 150 MPa 160 Mpa
46
AASHTO-LRFD Specifications
For Lump-Sum estimates following conditions should met :1. Members that are post-tensioned must be non-segmental
members with spans less than 160 feet and concrete stressed an age of 10-30 days.
2. Members that are pretensioned must be stressed at an age where the concrete strength is not less than 3,500-psi.
3. Members must be made from normal weight concrete.4. Members cannot be steam-cured, nor moist-cured.5. The prestressing steel must be normal or low-relaxation.6. There must be Average exposure conditions at the site.
47
Thumb rule of Losses
• For average steel and concrete properties ,the tabulated percentages may be taken as representative of the average losses.
Pretensioning ,% Posttensioning. %
Elastic shortening & bending of concrete
4 1
Creep of concrete 6 5
Shrinkage of concrete 7 6
Steel relaxation 8 8
Total Loss 25 20
48
Comparison Between RCC & Prestress Concrete
49