THE DESIGNER’S ROLE IN

ANTICIPATING & ADDRESSINGCONSTRUCTION HURDLES

Presented by Ashley Rao, AIA LEED AP

Leers Weinzapfel Associates

Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board.

COMMUNITY

INFRASTRUCTUREACADEMIC

CIVIC

MASS TIMBER

ADOHI HALLUNIVERSITY OF ARKANSAS

ADOHI HALLUNIVERSITY OF ARKANSAS

ARCHITECTURE & INTERIOR DESIGN

Leers Weinzapfel Associates

Modus Studio

Mackey Mitchell Architects

LANDSCAPE ARCHITECT

Olin

STRUCTURAL DESIGN

Equilibrium Consulting

Engineering Consultants, Inc

MEP/FP ENGINEERS

Bernhard TME

CIVIL ENGINEERS

Development Consulting, Inc.

SUSTAINABILITY

Entegrity

GRAPHIC DESIGN

Lizzy Lee Studio

CODE

Howe Engineers, Inc.

UNIVERSITY OF ARKANSAS

FACILITIES & PLANNING

UNIVERSITY OF ARKANSAS

HOUSING

UNIVERSITY OF ARKANSAS

FAY JONES SCHOOL OF

ARCHITECTURE

CONSTRUCTION MANAGER

Nabholz Construction

MASS TIMBER SUPPLIER

Binderholz / Holzpak

SITE PLAN

TYPICAL FLOOR PLAN

ANTICIPATINGCONSTRUCTION HURDLES

• CREATE A SHARED FOUNDATION OF KNOWLEDGE

• MAKE COST-EFFECTIVE DESIGN CHOICES

• EVALUATE CODE ISSUES EARLY

• CONSIDER SPECIES/FABRICATOR DIFFERENCES

• LEVERAGE PRE-FABRICATION POTENTIAL

2012 IBC

722.6.3 Design of fire-resistant exposed wood

members. The fire-resistance rating, in minutes, of

timber beams and columns with a minimum nominal

dimension of 6 inches (152 mm) is equal to:

Beams:

2.54Zb [4 -2(b/d)] for beams which may be exposed to

fire on four sides.

(Equation 7-18)

2.54Zb [4 -(b/d)] for beams which may be exposed to

fire on three sides.

(Equation 7-19)

Columns:

2.54Zd [3 -(d/b)] for columns which may be exposed to

fire on four sides

(Equation 7-20)

2.54Zd [3 -(d/2b)] for columns which may be exposed

to fire on three sides.

(Equation 7-21)

where:

b = The breadth (width) of a beam or larger side of a

column before exposure to fire (inches).

d = The depth of a beam or smaller side of a column

before exposure to fire (inches).

Z = Load factor, based on Figure 722.6.3(1).

TYPICAL MEMBER SIZE

SCREWS

TYPICAL MEMBER SIZE

SCREWS

TYPICAL MEMBER SIZE

TYPICAL MEMBER SIZE

SCREWS

COORDINATING PENETRATIONS

COORDINATING PENETRATIONS

PENETRATIONSCOORDINATING PENETRATIONS

ADDRESSINGCONSTRUCTION HURDLES

• PROTECT EXPOSED STRUCTURE

• ACCOMMODATE FIELD TOLERANCES

• ADDRESS NECESSARY FIELD MODIFICATIONS

TIMBER INSTALLATION

TRANSPORT PROTECTIONYARD STORAGE

STRUCTURE AS FINISH MATERIAL

STRUCTURE AS FINISH MATERIAL

STRUCTURE AS FINISH MATERIAL

CONCRETE COORDINATION & SEQUENCING

FIELD ADJUSTMENT MANUALTYPICAL CONNECTION

FIELD ADJUSTMENT MANUALFIELD ADJUSTMENT MANUALIF THE CONCRETE “OPENS”

FIELD ADJUSTMENT MANUALIF THE CONCRETE “CLOSES”

FIELD ADJUSTMENT MANUALFIELD DRILL JIG

MULTI-STORY COLUMN SPAN

STRUCTURE AS FINISH MATERIALFIELD MODIFIED

CORRECTLY INSTALLED

STRUCTURE AS FINISH MATERIAL

This concludes The American Institute of Architects Continuing Education Systems Course

QUESTIONS?