PLN –SOLAR POWER DEVELOPMENT PLAN: TARGET AND EXPERIENCES
PT PLN (Persero)
0
E L E C T R I C I T Y F O R A B E T T E R L I F E
Gas
Geothermal
Hydro
LNG
HSD MFO
Coal
As an archipelago country, thousands of islands are not
electrified yet
1 5 Provinces with the electrification ratio of less than 60 %,
in some area the duration of service are less than 12 hrs.
Generated power in the remote area mostly supplied by
diesel power, with an expensive transportation cost and
fuel supply security problem
PLN - high generation cost at the remote island
PLN plan to accelerate the RE target and reducing oil
consumption by ulilization of renewable energy
Trend of cost reduction and efficiency improvement on PV
technology
1
Background
E L E C T R I C I T Y F O R A B E T T E R L I F E
Gas
Geothermal
Hydro
LNG
HSD MFO
Coal
PLN Plan and Policy ( RUPTL 2010 -2019 ) :
• The growth of electricity demand by 9,2 % annually which
supplied by various energy resources
• Electrification ratio grows from 68 % in 2010 to be 91 % by 2019.
• The program to reduce oil consumption from 19 % to 3 % by
2015.
• With the dominant of coal power plant development (58 %), the
contribution of renewable energy will increase from 12 % ( 2010
) to be 19 % ( 2019 ).
• The utillisation of Solar has been planned in the RUPTL ( general
plan for electricity supply).
2
Long Term Energy Development Plan
E L E C T R I C I T Y F O R A B E T T E R L I F E
Indonesia Energy Policies to Reduce GHG
emission• Presidential Decree No 5/2006 regarding National Energy Policy
• Presidential Decree No. 4/2010 that assigns PLN to accelerate development of power generation plants using renewable energy, coal and gas. The renewable energy portion is 40% of the total capacity listed in this program
Oil
20 %
Gas 30 %
Coal 33 %
N&RE
17 %
Bio-fuel 5 %
Geothermal 5 %
Biomass, Nuclear,
Hydro, Solar Power,Wind Power 5 %
Coal Liquefaction 2 %
Target of National Energy Mix 2025
(Based on Presidential Regulation No. 5/2006)
E L E C T R I C I T Y F O R A B E T T E R L I F E
Realisation and Projection of Electricity Demand 2010-2019 (GWh)
-
50,000
100,000
150,000
200,000
250,000
300,000
350,000
400,000
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Realization Projection
Indonesia electricity demand is predicted to grow at average of 9.2% annually (Java-Bali 8.97%, West Indonesia 10.2% dan East Indonesia 10.6%)
327 TWh
252 TWh
54 TWh
28 TWh
133 TWh
104 TWh
20 TWh
10 TWh
E L E C T R I C I T Y F O R A B E T T E R L I F E
Projection of Electricity Demand 2010-2019
IB : 10,2%
21 TWh
54 TWh
IT : 10,6%
11 TWh28 TWh
JB : 8,97%
115 TWh
252 TWh
Average of national electricity demand growth 2010-2019 is 9,2% annually.
5
E L E C T R I C I T Y F O R A B E T T E R L I F E
2011
-
2014
2015
-
2020
2021
-
2025
PV DEVELOPMENT ROAD MAP
- Acceleration of
RE < 60%
- Security and
consumption reduction of
diesel fuel
- 9 locations of outer
islands/ border /isolated
- 100 locations (2011 ),
20MW
- 900 locations (2012-
2014), 150 MW.
- PV’s Industry will
develop
- Implementation of FIT
policy
- PV Price more
competitive
- Reduction of diesel
fuel
- PV system for rural
electricity
- Extension of
Existing capacity
- Plan of 450 MW PV
- Development of
commercial
scale
2010
- Pilot Project
PV Plants in
6 locations of
resort islands:
- P Bunaken
- P Derawan
- G Trawangan
- P B Naira
- P Raja Ampat
- P Tomia
E L E C T R I C I T Y F O R A B E T T E R L I F E
Criteria for PV Location Selection
Main Criteria• Remote area/remote island: transportation problem, security
of supply, costly oil price• Boundary area: social - political aspect• RE ratio of less than 35 % will be prioritized• Population distribution: population spread • Mini Hydro and Thermal resources are unavailable• Solar Radiation Level: Sufficient
Optional Criteria• Existing system: small diesel capacity (+/- 100 kW),
service hour of less than 24 hrs• Global issues (GHG, Saving Energy)
E L E C T R I C I T Y F O R A B E T T E R L I F E
Design Configuration Option:
OFF GRID:
Off grid: Communal System (LV feeder, 230 V/ 400 V or MV line 20 kV, PV and Storage Bank /Battery, sevice hour :12 hr, load : 20 –50 kW)
ON GRID :
Hybrid System: Exist.Diesel+PV+Battery + Others ( connected to existing MV Line, service hour : 24 hours, load > 50 - 300 kW
Grid Connected: On grid System ( connected to existing MV line and without battery, service hour: 24 hours, load: > 300 kW )
E L E C T R I C I T Y F O R A B E T T E R L I F E
WILAYAH INDONESIA
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 TOTAL
PLT Surya MWp 20 40 50 60 70 70 75 75 80 80 620
Indonesia Timur MWp 18 25 34 40 45 45 45 45 50 50 397
Indonesia Barat MWp 2 14 15 18 20 20 20 20 20 20 168
Jawa Bali MWp - 1 1 2 5 5 10 10 10 10 54
PENGEMBANGAN PEMBANGKIT LISTRIK PLT SURYA
TAHUN ( 2011 - 2020 )
No Pembangkit StnTAHUN
E L E C T R I C I T Y F O R A B E T T E R L I F E
PLN – PV PLAN
DEVELOPMENT PLAN OF PHOTOVOLTAIC ( 2012 -2014)
WILAYAHNUMBER OF LOCATIONS
KAPASITAS PV (KWp)
EASTERN INDONESIA 293 51,3
WESTERN INDONESIA 358 61,8
JAWA BALI 19 6,3
GRAND TOTAL 674 119,4
E L E C T R I C I T Y F O R A B E T T E R L I F E
BIG SCALE PV ( SYSTEM PEAK LOAD > 5 MW )
West Indonesian : 21 locations, capacity: 86 MW
East Indonesian: 50 locations, capacity : 216 MW
Total : 71 Locations with total capacity of 302 MW
E L E C T R I C I T Y F O R A B E T T E R L I F E
Conclusion
CONCLUSION• As the electricity demand growing rapidly, PLN has
plan an additional capacity of 55.484 MW and
renewable energy share will increase from 12 % to 19
% with total capacity of 11.540 MW on the year of
2019.
• Considering the Indonesia potential on Solar, the
trend of cost reduction and efficiency improvement,
PLN has plan to develope 620 MW of Solar PV by
2020.
• The use of Solar Energy will be for supply in non-
electrified remote area and to replace the use of
Diesel Fuel [Fossil Fuel] in electrified Areas
• 12
E L E C T R I C I T Y F O R A B E T T E R L I F E
13
Thank You…