PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
ADDENDUM - 2
To
EXPRESSION OF INTEREST vide Ref Number- 02/2018-19 dated 10-01-2018
For Shortlisting of
a. System Integrators for SITC and O&M of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. on EPC /
Revenue Sharing Model
b. Concessionaires for SITC and O&M for Smart Poles, City Wi-Fi, Smart City Kiosk and Variable Message Display (VMD) etc. on Revenue Sharing
Model
This is to kindly inform all the participating applicants/bidders that PCSCL has decided to cancel the aforementioned EOI, both the projects, with immediate
effect i.e. from February 23, 2018; thus, scheduled bidder’s presentation, bid opening and other related activities pertaining to above mentioned EOI stands
cancelled. PCSCL shall be refunding the EMD amount for all the bidder/applicant’s those have submitted their bids.
Sd/-
(Shravan Hardikar, IAS)
CEO & Director,
Pimpri Chinchwad Smart City Limited (PCSCL)
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
CORRIGENDUM - 5
To
EXPRESSION OF INTEREST vide Ref Number- 02/2018-19 dated 10-01-2018
For Shortlisting of
a. System Integrators for SITC and O&M of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. on EPC /
Revenue Sharing Model
b. Concessionaires for SITC and O&M for Smart Poles, City Wi-Fi, Smart City Kiosk and Variable Message Display (VMD) etc. on Revenue Sharing
Model
Key Dates / Timelines Revision for Project 2:
Sr. No. EOI Clause Revised Clause
1.
Invitation to Bid (IFB) & Control Sheet
Period of Sale/download of Bidding Document (Start/ End Date): Between 10-01-2018,18:00 Hrs & 01-03-2018,15:00 Hrs
2.
Manner, Start/ End Date for the submission of Bids
Start Date: 10-01-2018. 18:00 Hrs
End Date: 01-03-2018, 15:00 Hrs
3. Date/ Time/ Place of Bid Opening
Date: 01-03-2018, Time: 16:00 Hrs
4. Date of Technical Presentation: Shall be communicated later
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
Project 2 Pre-Qualification Revisions:
Existing Clause Details Revised Clause
A Board Resolution or Power of Attorney, in the name of the person executing the
bid, authorizing the signatory to commit the Applicant
The person issuing the Power of Attorney shall possess Board Resolution in his
favour for granting such rights.
In case of generic Board Resolution or Power of Attorney, the same shall be certified
by Company secretary.
This is applicable to the sole applicant or each of the members of the consortium, in
case of consortium.
A Board Resolution or Power of Attorney, in the name of the person executing the
bid, authorizing the signatory to commit the Applicant
The person issuing the Power of Attorney shall possess Board Resolution in his
favour for granting such rights.
In case of generic Board Resolution or Power of Attorney, the same shall be certified
by Company secretary.
This is applicable to the sole applicant or each of the members of the consortium, in
case of consortium.
In the event of a consortium, one of the applicant shall be designated as a "Lead
Partner/ Applicant". Consortium is allowed with up to 3 consortium members including
the Lead Applicant. The lead applicant should have majority stake in the consortium
which may be an incorporated or non-incorporated JV.
As part of the EOI response, applicant can propose two consortium member, in case
of consortium, and shall have provision to propose 3rd consortium member, if required,
at the time of RFP stage
In the event of a consortium, one of the applicant shall be designated as a "Lead
Partner/ Applicant". Consortium is allowed with up to 3 consortium members including
the Lead Applicant. The lead applicant should have majority stake in the consortium
which may be an incorporated or non-incorporated JV.
As part of the EOI response, applicant can propose two consortium member, in case
of consortium, and shall have provision to propose 3rd consortium member, if required,
at the time of RFP stage
The sole applicant or any member of consortium, in case of consortium, should have
an annual turnover of at least INR 500 Cr. from providing services to Telecom
Operators in last three financial years, i.e FY 14-15; FY 15-16 , FY 16-17.
The sole applicant or any member of consortium, in case of consortium, should have
an annual turnover of at least INR 500 Cr. in last three financial years, i.e FY 14-
15; FY 15-16 , FY 16-17.
The sole applicant or any member of the consortium, in case of consortium, should
have a relevant experience of:
Supply, Installation, Commissioning and Operations / Maintenance Services for
Smart Poles / Telecom Tower / BTS / GBM(s) Infrastructure & services in last 3 years
as on date of submission of EOI response and currently having at least 3000 such
Smart Poles / Telecom Tower / BTS / GBM(s) operational, as on date of submission
of EoI, with minimum operational annual revenue of 200 cr.
Or
The sole applicant or any member of the consortium (in case of consortium) or Sole
Applicant / Lead member‘s named subcontractor, should have a relevant
experience of:
Supply, Installation, Commissioning and Operations / Maintenance Services for
Smart Poles / Telecom Tower / BTS / GBM(s) Infrastructure & services in last 5 years
as on date of submission of EOI response and currently having at least 1000 such
Smart Poles / Telecom Tower / BTS / GBM(s) operational, as on date of submission
of EoI.
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
Existing Clause Details Revised Clause
Project experience of Supply, Installation, Commissioning and Operations &
Maintenance Services, for any one of the below mentioned “specific business area”,
which is either completed or ongoing in last 5 years as on date of submission of EOI
response
Specific business area:
1. WiFi Infrastructure & services with at least 200 access points
2. City Kiosk Infrastructure & services with at least 50 kiosks
3. Variable Message Display Infrastructure & services with at least 50 displays
Or
Project experience of Supply, Installation, Commissioning and Operations &
Maintenance Services, for any two of the below mentioned “specific business area”,
which is either completed or ongoing in last 5 years as on date of submission of EOI
response
Specific business area:
1. WiFi Infrastructure & services with at least 200 access points
2. City Kiosk Infrastructure & services with at least 50 kiosks
3. Variable Message Display Infrastructure & services with at least 50 displays
The applicant should possess any one of the below mentioned certification, which are
valid at the time of bidding:
ISO 9001:2008/2015 / TL 9000 certification
ISO 20000:2011 for IT Service Management
ISO 270001:2013 for Information Security Management
The bidder shall possess all the licenses and shall comply with all the rules of the
country that are required to provide telecom infrastructure and services throughout
the period of contract.
The applicant should possess any one of the below mentioned certification, which are
valid at the time of bidding:
ISO 9001:2008/2015 / TL 9000 certification
ISO 20000:2011 for IT Service Management
ISO 27001:2013 for Information Security Management
The bidder shall possess all the licenses and shall comply with all the rules of the
country that are required to provide telecom infrastructure and services throughout
the period of contract.
The applicant should have at least 250 resources on payroll of the applicant’s
organization at the time of submission of EoI response
The applicant should have at least 100 resources on payroll of the applicant’s
organization at the time of submission of EoI response
Note:
Named Subcontractor is the one whose details shall be furnished by the applicant as part of its EOI response and the same subcontractor shall
be required to perform the subcontracted part of the project during the project implementation phase. However, even if the work is sub-
contracted / outsourced, the sole responsibility of the work shall lie with the lead bidder. The sole applicant / lead bidder shall be held
responsible for any delay/error/non-compliance etc. of its sub-contracted vendor.
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
Other Points:
Existing Clause Details Revised Clause
EOI Document Project 2:
Selection of Concessionaires for SITC and O&M for Smart Poles, City Wi-Fi,
Smart City Kiosk and Variable Message Display (VMD) etc. on Revenue Sharing
Model.
EOI Document Project 2:
Selection of System Integrator / Concessionaires for SITC and O&M for Smart Poles,
City Wi-Fi, Smart City Kiosk and Variable Message Display (VMD) etc. on EPC /
Revenue Sharing Model.
Through-out the EOI Document for Project 2: “Concessionaire” to be read as
“System Integrator / Concessionaire”.
Thus, applicants are allowed to submit their response to EOI Project 2 in either of
EPC or PPP mode and the same shall be highlighted by the applicant as part of the
EOI response document.
EOI Section 9.2 Project 2:
Concessionaire shall be required to take the fibre network at the Smart Pole
location, last mile, from PCSCL on Rental Basis and shall also share the revenue
earned by selling services through Smart Pole Infrastructure with PCSCL on
percentage basis during the concessionaire period
EOI Section 9.2 Project 2:
In case of PPP mode (Revenue Sharing Mode), Concessionaire shall be required to
take the fibre network at the Smart Pole location, last mile, from PCSCL, on Rental Basis
and shall also share the revenue earned by selling services through Smart Pole
Infrastructure with PCSCL on percentage basis during the concessionaire period
Sd/-
(Shravan Hardikar, IAS)
CEO & Director,
Pimpri Chinchwad Smart City Limited (PCSCL)
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
CORRIGENDUM - 4
To
EXPRESSION OF INTEREST vide Ref Number- 02/2018-19 dated 10-01-2018
For Shortlisting of
a. System Integrators for SITC and O&M of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. on EPC /
Revenue Sharing Model
b. Concessionaires for SITC and O&M for Smart Poles, City Wi-Fi, Smart City Kiosk and Variable Message Display (VMD) etc. on Revenue Sharing
Model
Key Dates / Timelines Revision:
Sr.
No.
EOI Existing
Clause Existing Clause Details Revised Clause
1.
Invitation to Bid (IFB) & Control Sheet
Period of Sale/download of Bidding Document (Start/ End Date): Between 10-01-2018,18:00 Hrs & 12-02-2018,16:00 Hrs
Period of Sale/download of Bidding Document (Start/ End Date): Between 10-01-2018,18:00 Hrs & 14-02-2018,15:00 Hrs
2.
Manner, Start/ End Date for the submission of Bids
Start Date: 10-01-2018. 18:00 Hrs
End Date: 12-02-2018, 16:00 Hrs
Manner, Start/ End Date for the submission of Bids
Start Date: 10-01-2018. 18:00 Hrs
End Date: 14-02-2018, 15:00 Hrs
3. Date/ Time/ Place of Bid Opening
Date: 12-02-2018, Time: 17:00 Hrs
Date/ Time/ Place of Bid Opening
Date: 14-02-2018, Time: 16:00 Hrs
4. Date of Technical Presentation: February 16, 2018 (Time shall be informed later)
Date of Technical Presentation: Tentatively February 21, 2018 (Confirmation shall be provided soon)
sd/-
(Shravan Hardikar, IAS)
CEO & Director,
Pimpri Chinchwad Smart City Limited (PCSCL)
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
CORRIGENDUM - 3
To
EXPRESSION OF INTEREST vide Ref Number- 02/2018-19 dated 10-01-2018
For Shortlisting of
a. System Integrators for SITC and O&M of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. on EPC /
Revenue Sharing Model
b. Concessionaires for SITC and O&M for Smart Poles, City Wi-Fi, Smart City Kiosk and Variable Message Display (VMD) etc. on Revenue Sharing
Model
The applicants are required to kindly consider the following corrigendum pertaining to the aforementioned EoI:
1. Key Dates / Timelines Revision:
Sr.
No.
EOI Existing
Clause Existing Clause Details Revised Clause
1.
Invitation to Bid (IFB) & Control Sheet
Period of Sale/download of Bidding Document (Start/ End Date): Between 10-01-2018,18:00 Hrs & 09-02-2018,18:00 Hrs
Period of Sale/download of Bidding Document (Start/ End Date): Between 10-01-2018,18:00 Hrs & 12-02-2018,16:00 Hrs
2.
Manner, Start/ End Date for the submission of Bids
Start Date: 10-01-2018. 18:00 Hrs
End Date: 09-02-2018, 18:00 Hrs
Manner, Start/ End Date for the submission of Bids
Start Date: 10-01-2018. 18:00 Hrs
End Date: 12-02-2018, 16:00 Hrs
3. Date/ Time/ Place of Bid Opening
Date: 09-01-2018, Time: 17:00 Hrs
Date/ Time/ Place of Bid Opening
Date: 12-02-2018, Time: 17:00 Hrs
4. Date of Technical Presentation: February 14, 2018 (Time shall be informed later)
Date of Technical Presentation: February 16, 2018 (Time shall be informed later)
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
2. Project 1 Pre-Qualification Revisions:
S.No Criteria Details Documents to be Submitted
1. Legal Entity
The Sole applicant or each of the members of the consortium, in case of
consortium should be an entity registered in India under the Companies
Act 1956 / 2013 or /LLP registered under LLP Act 2008 or subsequent
amendments thereto.
The entity should have been in operational existence for last three years.
Certificate of incorporation / Partnership deed
GST Registration Certificate
Certificate of commencement of business (if
applicable)
2.
Board
Resolution /
Power of
Attorney in
favour of
authorised
signatory
A Board Resolution or Power of Attorney in A Board Resolution or Power
of Attorney, in the name of the person executing the bid, authorizing the
signatory to commit the Applicant
The person issuing the Power of Attorney shall possess Board Resolution
in his favour for granting such rights.
In case of generic Board Resolution or Power of Attorney, the same shall
be certified by Company secretary.
This is applicable to the sole applicant or each of the members of the
consortium, in case of consortium.
Board Resolution;
OR
Power of Attorney with appropriate supporting
documents as per the format of this EoI document
3. Consortium In the event of a consortium, one of the applicant shall be designated as a
"Lead Partner/ Applicant". Consortium is allowed with up to 2 consortium
members including the Lead Applicant. The lead applicant should have
In case of consortium, the applicants shall submit
a power of attorney in favour of the lead applicant
clearly mentioning their association for the project
and nominating the Lead applicant to participate
in the bid. The same shall be signed by the
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No Criteria Details Documents to be Submitted
majority stake in the consortium which may be an incorporated or non-
incorporated JV.
authorized signatory of all the consortium
members.
4. Financials
The sole applicant or any member of consortium, in case of consortium,
should have an:
Average annual standalone turnover of at least INR 500 cr. in last three
financial years i.e. FY 14-15; FY 15-16, FY 16-17.
AND
Average annual turnover of at least INR 50 Cr. from provision of “Telecom
Infrastructure/Fibre cable & associated infrastructure” implementation
and maintenance services in last three financial years, i.e. FY 14-15; FY
15-16, FY 16-17.
Extracts from the audited balance sheet and profit
& loss;
OR
Certificate from the statutory auditor
5. Networth
The Sole applicant or each of the members of the consortium, in case of
consortium, should have positive net worth as per the audited
consolidated financial statements in each of the last 3 financial years (FY
14-15; FY 15-16, FY 16-17).
Certificate from the statutory auditor
6. Technical
Capability
The sole applicant or each member of the consortium, in case of
consortium, should have relevant experience related to provisioning of
“Telecom Infrastructure/Fibre cable & associated infrastructure”
implementation and maintenance services in last five financial years
Project or Contract, with a single client, of value not less than INR 100
Cr of which project component of value at least INR 60 Cr should have
been completed and should be in operations for last 1 year, as on date
of submission of EOI
Certified copy of the relevant Work Order(s) and
satisfactory implementation completion &
satisfactory services completion certificate(s) (on
the letterhead of the company issuing the
certificate);
OR
Work Orders + Self certificate of completion
(Certified by the statutory auditor);
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No Criteria Details Documents to be Submitted
OR
Two projects or contracts each having value not less than INR 80 Cr
which project component of value at least INR 48 Cr should have been
completed and should be in operations for last 1 year, as on date of
submission of EOI
OR
Three projects or contracts each having value not less than INR 50 Cr
which project component of value at least INR 30 Cr should have been
completed and should be in operations for last 1 year, as on date of
submission of EOI
For the applicants who have created / implemented “Telecom
Infrastructure/Fibre cable & associated infrastructure”, for their internal
capital use or as a shared services on commercial basis, shall submit the
Statutory Auditor Certificate for substantiating such claims.
7. Certifications
The sole applicant or any member of the consortium, in case of
consortium, should possess any one of the below mentioned certification,
which are valid at the time of bidding:
ISO 9001:2008/2015 / TL 9000 certification
ISO 20000:2011 for IT Service Management
ISO 270001:2013 for Information Security Management
The bidder shall possess all the licenses and shall comply with all the
rules of the country that are required to provide telecom infrastructure and
services throughout the period of contract.
Copy of Valid Certificate(s) issued by
competent authority
Undertaking that these certifications shall be
kept valid during the EoI & RFP process and
thereafter, in case of award of order, for the
entire project duration
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No Criteria Details Documents to be Submitted
8.
Self -
Declaration on
Non Blacklisting
The Sole applicant or each of the members of the consortium, in case of
consortium, should not have been blacklisted by any Govt. entity or any
PSU in India as on the date of bid submission
As per the Proforma 4 of this EoI document and to
be counter signed by Applicant’s Country Head or
the Company Secretary
9. Manpower
Strength
The Sole applicant or any member of the consortium, in case of
consortium, should have at least 250 resources on payroll of the
applicant’s organization at the time of submission of EoI response
Certificate from the Company Secretary
Note: Bidder company credential would be considered for only 100% subsidiaries.
3. For Project 1 & Project 2 wherever, Statutory Auditor Certificate has been asked, an applicant (lead bidder or consortium member) is allowed to submit
the CA Certificate / Company Secretary Certificate as part of its EOI response. However, an applicant (lead bidder or consort ium member) shall be
liable for submission of the Statutory Auditor Certificate latest by February 23, 2018. In case of failure to furnish the Statutory Auditor Certificate by the
due date, an applicant (lead bidder or consortium member) shall be disqualified, in the EOI stage, and submitted EMD shall be forfeited.
Sd/-
(Shravan Hardikar, IAS)
CEO & Director,
Pimpri Chinchwad Smart City Limited (PCSCL)
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
Response to Pre bid Queries
for
EXPRESSION OF INTEREST vide Ref Number- 02/2018-19 dated 10-01-2018
For Shortlisting of
a. System Integrators for SITC and O&M of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. on
EPC / Revenue Sharing Model
b. Concessionaires for SITC and O&M for Smart Poles, City Wi-Fi, Smart City Kiosk and Variable Message Display (VMD) etc. on Revenue
Sharing Model
Project 1:
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
1 ATC Timelines need to be extended, Page no. 5
End date of Submission of Bid (IFB): 30th January 2018 Technical presentation date: 2nd February 2018
Since the pre-bid meeting is held on 18th January and lot of clarity is expected to be provided during the meeting, and keeping into consideration the large scale of project, it requires good amount of time to fully prepare for effective participation. Therefore requesting to extend the end date by at least 4 weeks Technical presentation should be at least 10 days after the bid submission date. Bid submission end date: 28th Feb 2018 Technical Presentation date: 15th March 2018
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
2 ATC ROW charges Need clarity on exclusivity right with respect to OFC network
Exclusivity is required to make strong business case else it can disrupt the business model as well as aesthetics of the city in case fiber is laid time and again in the city by various operators/ end- customers Exclusive rights for minimum 10 years timeframe. No new permissions to be ranted for similar project in the region
Details shall be provided as part of the RFP document. However, you may please submit your propositions as part of your EOI response document
3 ATC ROW charges RoW charges specific to the area
OFC laying permission only on restoration basis The bidder to be allowed to lay OFC in the defined area without paying any RoW charges
Details shall be provided as part of the RFP document
4 ATC Qualification criteria: Financial, Page no. 24
Average annual turnover of Rs. 500 crs. : Extract from the audited balance sheet and P&L
Only the Balance sheet and P&L pages from the audited balance sheet to be provided We need not submit the full Directors report
Please refer Corrigendum
5 ATC
Qualification criteria: Technical Capability Page no. 24
One project of value not less than Rs. 100 cr. Or two projects of value not less than Rs. 80 cr. Or three projects of value not less than Rs. 50 cr.
IP-1 players do not carry out such kind of one time projects. They engage in long term contracts with various telecom service providers, Internet service providers etc. This should be redefined , in terms of total networth, assets on ground & annual project
Long terms contracts shall be considered but applicant to clearly certify, from the Statutory auditor, the cost of provisioning products and/or services in last 3 years as part of the contract
6 ATC
Qualification criteria: Certifications, Page no. 24
ISO 9001: 2009 ISO 20000:2011
Certifications depends on the sector to which the participants belongs. There are certain certification applicable to manufacturing industry may not be applicable to telecom infra providers Industry specific certifications may be provided
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
7 ATC Qualification criteria:Manpower StrengthPage 25
Applicant to have at least 1000resources on payroll at the time ofsubmission of E01 response
As an entity at National level, the organisation may have more than1000 resources on payroll but may be under different legalentities which have come together through merger andacquisition route but carrying out 1 common business of providing Telecom infrastructure services to customersAs long as undertaking is given by the entity at National level that under various legal entities they have more than 1000 resources on payroll, it should be fine with the authorities
Please refer Corrigendum
8 BSNL General Route details For carrying out survey for laying OFC, details of route & locations are required.
Details shall be provided as part of the RFP document
9 BSNL General Reinstatement charges Clarification required for reinstatement charges to be paid for PCMC for setting up of passive infra(OFC) to carry out trenching/HDD
Details shall be provided as part of the RFP document
10 BSNL EMD Exempt of EMD BSNL being 100% owned Govt. of India PSU, requested to exempt this clause for PSUs.
No change, as per EOI document
11 BSNL EMD EMD Whether EMD in the form of bank guarantee is acceptable?
As per EoI document
12 Indus Towers About the EoI Document, Page 7
Project 1 - Supply Installation, testing and Commissioning and O&M of Smart City field infrastructure comprising of Passive Fiber Network, Poles and Gantries etc. on EPC/PPP Model
We request to please clarify the engineering dimension of Poles and gantries to be installed as part of project.
Details shall be provided as part of the RFP document
13 Indus Towers Project 1, Page 8 To create a uniform Pole Infrastructure across the city for hosting various IoT, Smart City
We understand that the installation of IoT and Smart devices are not in the scope of Bidder.
Yes, the understanding is correct. As part of project 1,
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
& telecom devices like CCTV camera, traffic detectors, Wi-Fi access points, 4G, 5G BTSs etc. in a planned & structured manner, so as to avoid repeated digging and infrastructure laying work in the city.
applicant is only required to create Pole Infra
14 Indus Towers
We request Authority to allow Bidder to utilize the Uniform Pole infrastructure for monetization through telecom installations and advertisement. Further, Authority shall provide free RoW for additional space for Equipment installation as required.
The mentioned Pole Infrastructure are meant specific for hosting Smart City elements like CCTV camera, Access Points, environment sensors, traffic detectors etc.. However, please submit your propositions as part of your EOI response document
15 Indus Towers
Please confirm if concessionaire will have exclusive right of fiber monetization based on objective mentioned – to avoid repeated digging and infrastructure laying work in the city.
Details shall be provided as part of the RFP document. However, you may please submit your propositions as part of your EOI response document
16 Indus Towers
9.1 Project 1 Page 15
Route Survey & Network Design Preparation
We request the authorities to provide GIS map with road width & developments plan (current & future) which would help in fiber planning.
All the available details shall be provided to the selected applicant
17 Indus Towers Procure, Supply, Install & Commission of all Passive Infrastructure
It is assumed that 750Kms roll-out will happen is phase manner with mutually agreed plan based on priorities of PCMC & concessionaire. Request to please confirm.
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
18 Indus Towers Procure, Supply, Install & Commission Pole Infrastructure
We request Authority to provide us a clarity on the following; a. Height of - 600 numbers of unipole mentioned for mounting CCTV? b. Height of - 30 numbers of unipole for large VMDs? c. Please provide the dimensions of Gantry structure? d. We understand it is only the pole structure for the above three mentioned and VMD is not under the Project 1 scope? e. We understand that all pole locations in project-1 will be allocated along with space for cabinet to establish Fiber PoP.
a. To be provided as part of RFP document b. To be provided as part of RFP document c. To be provided as part of RFP document d. Yes, the understanding is correct e. Yes, the understanding is correct
19 Indus Towers
SI shall be responsible for laying of 3 ducts (indicative) using Horizontal Directional Drilling (HDD) / Open Trenching (OT) Technique
We suggest that Bidder shall be allowed to define number of ducts basis requirement inclusive of deliverable of connecting all Authority designated locations, other possible locations for OFC connectivity.
Please submit your propositions as part of your EOI response document
20 Indus Towers 9.1 Project 1 Page 16
Reinstatement and restoration
While SI will be responsible for R&R, no other charges like RoW, RI, annual rent will be levied on concessionary for entire concession period, in case of PPP model (revenue sharing)
Details shall be provided as part of the RFP document. However, you may please submit your propositions as part of your EOI response document
21 Indus Towers General We understand that Authority will provide Bidder with single window of clearance for any RoW permission for executing the project.
Yes, the understanding is correct for the approved route. Further, details shall be furnished as part of the RFP document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
22 Indus Towers General Project 1
Please clarify; a. What monetization proposition would RFP include if PPP model is selected? b. If the project is decided to be EPC, it is request to include monetization of 1-2 ducts by the bidder so as to bring the overall project cost down for the concessionaire and make it a win win proposition.c. If it is going to be an EPC model, could you share some light on the connectivity charges?
a. Please submit your propositions as part of your EOI response documentb. Please submit your propositions as part of your EOI response documentc. Please submit your propositions as part of your EOI response document
23 Indus Towers General Permission to use of land to erect smart poles
We understand that the Rights to provide RoW has been vested to PCSCL by PCMC
Selected applicant shall be granted requisite rights by the competent authority
24 Indus Towers General Permission for site allocation
We understand that the site will be allocated by the Authority within the agreed timelines as the same will have an impact on meeting the project implementation timelines and revenue generation thereafter.
Yes, the understanding is correct
25 Indus Towers 5. Control Sheet, Page 10
Last date for submission of EoI response
As the submission of response to EoI is on a stringent deadline, we request Authority to extend the submission by further 15 days
Please refer Corrigendum
26 Indus Towers 9.1 Project 1, Page 14
Optical Fiber
We request Authority to allow Concessionaire to connect its existing cellular towers/poles with the Optical Fiber which improves the overall telecom network in the city with 3G / 4G / 5G & WiFi and future technologies
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
27 Indus Towers
We request Authority to waive off any RoW, RR, RI or any other charges for installation of Optical Fiber (in case of PPP implementation). Further, we request Authority to waive-off any other charges, fee, property tax or any other payment payable to local body for setting up of project facility, associated infrastructure.
Please submit your propositions as part of your EOI response document
28 Indus Towers Page 20 PCSCL will release separate RFP for Project 1 and Project 2.
We suggest Authority to look for same partner for combined scope of both projects in order to have better synergy and options for revenue generation.
Please submit your propositions as part of your EOI response document
29 Indus Towers General Materially Adverse Government Action (MAGA)
“Materially Adverse Government Action (MAGA)” means any act or omission by the PCSCL or any relevant public authority, which occurs during the term of this project execution and which (i) renders the Concessionaire unable to comply with any of its obligations as per the Agreement and/or (ii) has a material adverse effect on the cost or the profits arising from such performance and/or (iii) any judgment or order of any court of competent jurisdiction or statutory authority in India made against the Concessionaire in any proceedings for reasons other than on account of breach thereof, or of any Agreement, or enforcement of the signed Agreement or exercise of any of its rights under the Agreement.We suggest the Authority to include the aforementioned clause while drafting the T&C of the RFP.
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
30 Indus Towers
12.1 Qualification Criteria for shortlisting of System Integrator for Project 1, Page 24/25
Point 5 - Technical Capability
While we have vast experience related to provisioning of Telecom Infrastructure / Fibre cable, we request Authority to consider; -> We understand Telecom Infrastructure includes Telecom Towers as well. Please confirm? If not, we request you to please add Tower Infrastructure as well as qualification criteria -> Request for allowing another eligibility other than 100, 50 Cr projects, where in bidder has total telecom tower infrastructure in excess of 10,000 numbers or 1000 Cr Value -> Self Certification (on Bidder's letter head) for project completion with all the required project details (no Work Order)
Please refer Corrigendum
31 Indus Towers Point 6 - Certifications
We request you to modify the clause as per following;The applicant should possess any one of the below mentioned certification which are valid at the time of bidding:> ISO 9001:2008/TL 9000 certification> ISO 20000:2011 for IT Service Management> ISO 27001:2013 for Information Security Management SystemThe bidder shall possess all the licenses and shall comply with all the rules of the country that are required to provide telecom infrastructure and services throughout the period of contract.
Please refer Corrigendum
32 Inspira
Enterprise India Pvt Ltd
Page no.24 and Section no.12.1.3 Pre-Qualification Criteria
Extracts from the audited balance sheet and profit & loss; OR Certificate from the statutory auditor
Please change it to average annual turnover of at least INR 300 Cr from IT products and services in last 3
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
33 Inspira
Enterprise India Pvt Ltd
Page no.24 and Section no.12.1.8 Pre -Qualification Criteria
The applicant should have at least 1000 resources on payroll of the applicant’s organization at the time of
Request you to consider 150+ resource Please refer Corrigendum
34 L&T
Page 1 EXPRESSION OF INTEREST for Shortlisting of
a. System Integrators for SITC and O&M of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. on EPC / Revenue Sharing Model
Request you to keep the Project 1 on only EPC model. Our understanding is there is no revenue sharing or PPP model for project 1. Please clarify.
Details shall be provided as part of the RFP document. However, you may please submit your propositions as part of your EOI response document
35 L&T
12. Qualification criteria Page 24 3. Financials
Extracts from the audited balance sheet and profit & loss; OR Certificate from the statutory auditor
Request you to modify this clause as: Extracts from the audited balance sheet and profit & loss; OR Certificate from the statutory auditor /independent chartered accountant
Please refer Corrigendum
36 L&T 12. Qualification criteriaPage 243. Financials
The applicant should have an average annual turnover of at least INR 500 Cr. from provision of Telecom Infrastructure / Fibre cable Infra supply and services (fibre cable network implementation including trenching, ducting, cable laying, termination, other requisite activities and O&M of that network) in last three financial years, i.e FY 14-15; FY 15-16 , FY 16-17.
Request you to modify this clause as below: The applicant should have an average annual turnover of at least INR 500 Cr. from provision of ICT /Telecom Infrastructure / Fibre cable Infra supply and services (fibre cable network implementation including trenching, ducting, cable laying, termination, other requisite activities and O&M of that network) in last three financial years, i.e FY 14-15; FY 15-16 , FY 16-17.
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
37 L&T
12. Qualification criteria Page 24 4. Networth
Certificate from the statutory auditor
Request you to modify this clause as Certificate from the statutory auditor OR Certificate from the statutory auditor /independent chartered accountant
No change, as per EOI document
38 L&T
12. Qualification criteria Page 24 5. Technical capability
Certified copy of the relevant Work Order(s) and satisfactory implementation completion & satisfactory services completion certificate(s) (on the letterhead of the company issuing the certificate); OR Work Orders + Self certificate of completion (Certified by the statutory auditor);
Request you to modify this clause as Certified copy of the relevant Work Order(s) and satisfactory implementation completion & satisfactory services completion certificate(s) (on the letterhead of the company issuing the certificate); certificate(s) OR Work Orders + Self certificate of completion (Certified by the statutory auditor); OR Self certified Partial completion undertaking+ LOA/Purchase Order copies (Certified by the statutory auditor/ Independent Chartered Accountant)
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
39 L&T
12. Qualification criteriaPage 245. Technical capability
The applicant should have relevant experience related to provisioning of Telecom Infrastructure / Fibre cable supply and services (fibre cable network implementation including trenching, ducting, cable laying, termination, other requisite activities and O&M of that network) in last three financial years, i.e FY 14-15; FY 15-16, FY 16-17.· One project of value not less than INR 100 CrOR· Two projects each having value not less than INR 80 CrOR· Three projects each having value not less than INR 50 CrThe quoted project should be completed and shall be in operations for last two years at the time of submission of EoI response.
Request you to modify this clause as;The applicant should have relevant experience related to provisioning of ICT/ Telecom Infrastructure / Fibre cable supply and services (fibre cable network implementation including trenching, ducting, cable laying, termination, other requisite activities and O&M of that network) in last Five financial years, i.e FY 12-13, FY 13-14, FY 14-15, FY 15-16, FY 16-17.· One project of value not less than INR 100 CrOR· Two projects each having value not less than INR 80 CrOR· Three projects each having value not less than INR 50 CrThe quoted project should be completed and shall be in completed and in operations for at least One Year at the time of submission of EoI response.
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
40 L&T 6. Certifications Page 25
The applicant should possess below mentioned certification which are valid at the time of bidding: · ISO 9001:2008/TL 9000 certification · ISO 20000:2011 for IT Service Management
Request you to modify this clause as: The applicant or any of its majority shareholding subsidiary should possess below mentioned certification which are valid at the time of bidding: · ISO 9001:2015/TL 9000 certification OR · ISO 20000:2011 for IT Service Management / ISO 27001:2013 certificate
Please refer Corrigendum
41 L&T
7. Self - Declaration on Non BlacklistingPage 25
As per the Proforma 4 of this EoI document and to be counter signed by Applicant’s Country Head or the Company Secretary
Request you to modify this clause as As per the Proforma 4 of this EoI document and to be counter signed by Applicant’s Country Head or the Company Secretary OR Authorized Signatory.
No change, as per EOI document
42 L&T 8. Manpower Strength Page 25
Certificate from the Company Secretary
Request you to modify this clause as Certificate from the Company Secretary/ Self undertaking from HR Head
No change, as per EOI document
43 RailTel General Extension of Bid Submission Date till 12th feb
As the site locations are many and diverse, we need more time for feasibility check, we require more time for tie-ups with SI partner for the proper techno commercial solution
Please refer Corrigendum
44 RPG Infra Pg 24, Sec 12.1, S.No. 1
EoI Application/response is to be submitted by individual entities and consortiums are not allowed at this stage
If bidder is not qualifying on EOI for Project 1 currently but if at RFP stage consortium is allowed, can the bidder participate in the RFP?
RFP shall only be issued to the selected applicant
45 RPG Infra Will the RoW/RI charges be waived off for the selected bidder
Details shall be provided as part of the RFP document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
46 RPG Infra Pg 15, Sec 9.1 Procure, Supply, Installation & Commission of all the Passive Infrastructure
Please share the details of existing fiber availability around the PC area. Will this fiber be available to the bidder? Does all fiber need to be relaid? Does PCMC have any existing concessionaries for Fibers and Poles?
Details shall be provided as part of the RFP document
47 RPG Infra Pg 15, Sec 9.1
Reinstatement & Restoration: SI shall be responsible for performing the reinstatement and restoration of the sites back to the previous/normal conditions as per the RFP specifications at all the respective site locations.
Please share the details of existing assets and their locations which have to restored
Details shall be provided as part of the RFP document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
48 RPG Infra Pg 8, Sec 4, Key Objectives & Goals
Under Project 1, PCSCL intends to create passive infrastructure components, either through EPC model or PPP (revenue sharing) model, like laying of Optical Fibre based Network (City Network) and erection of Pole Infrastructure for mounting IoT & Smart City devices across the city; Fibre Network is planned to connect all the PCMC offices (Zone & Ward Offices), health & citizen facilitation centres, key areas like markets, religious places, bus stops etc. whereas the Pole Infrastructure shall be setup at various traffic junctions, key city places for hosting CCTV cameras, traffic detectors, variable message displays, public address system, WiFi access points etc.
Consider combining the scope for the Project 1 and Project 2 (as well as any future projects for ICCC) under single MSI to drive efficiency in project management. A divided MSI scope will create issues with SLA adherence as some activities can be in overlap or fall in no man's land. Furthermore O&M will be a challenge.
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
49 RPG Infra Pg 24, Sec 12.1, S.No. 1
EoI Application/response is to be submitted by individual entities and consortiums are not allowed at this stage
Consortium must be allowed in Project 1 as well because some diverse capabilities of SI and service provider will be required.
No change, as per EOI
50 RPG Infra Pg 24, Sec 12.1, S.No. 3
The applicant should have an average annual turnover of at least INR 500 Cr. from provision of Telecom Infrastructure / Fibre cable Infra supply and services (fibre cable network implementation including trenching, ducting, cable laying, termination, other requisite activities and O&M of that network) in last three financial years, i.e FY 14-15; FY 15-16 , FY 16-17.
The PQ requirement on annual turnover of Rs. 500 cr is extremely high given the scope of the project. The fiber laying portion of the scope is relatively small and such a high number on revenue will restrict major players from participating.We suggest to keep qualifying criteria on turn over as Rs. 200 cr
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
51 Sterlite Pg. No. 7, Section 3
Supply, Installation, Testing & Commissioning and Operations & Maintenance of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. under Engineering Procurement and Commissioning (EPC) / PPP mode (Revenue Sharing Model)
Please confirm whether any commitments are to be done by the MSI for revenue sharing.
Please submit your propositions as part of your EOI response document
52 Sterlite Page -7/3. About the EoI Document
Project 1 – Supply, Installation, Testing & Commissioning and Operations & Maintenance of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. under Engineering Procurement and Commissioning (EPC) / PPP mode (Revenue Sharing Model)
Kindly confirm the Project-1 competition time line. Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
53 Sterlite Page -7/3. About the EoI Document
Project 1 – Supply, Installation, Testing & Commissioning and Operations & Maintenance of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. under Engineering Procurement and Commissioning (EPC) / PPP mode (Revenue Sharing Model)
Kindly provide the Guidelines & Revenue sharing period time line
Please submit your propositions as part of your EOI response document
54 Sterlite
Page -15 / System Integrator Scope of Work:
System Integrator Scope of Work: SI shall be responsible for laying of 3 ducts (indicative) using Horizontal Directional Drilling (HDD) / Open Trenching (OT) Technique as per directions of PCSCL and blowing of fiber (96/48 core) basis on the finalized route plan and appropriate network topology to ensure adequate redundancy at each of the network node level
Being a city area, In Open Trench (OT) Techniques, suggest to keep trench depth of 1.2 meter only .
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
55 Sterlite Page -15. System Integrator Scope of Work:
System Integrator Scope of Work:Procure, Supply, Installation & Commission of all the Passive Infrastructure: SI shall be responsible for laying of 3 ducts (indicative) using Horizontal Directional Drilling (HDD) / Open Trenching (OT) Technique as per directions of PCSCL and blowing of fiber (96/48 core) basis on the finalized route plan and appropriate network topology to ensure adequate redundancy at each of the network node level. Indicative city wide fiber network route length is estimated to be 750 km, across the city, which shall be finalized after the detailed survey and route finalization activity,
We suggest to have single duct with high fiber count cable with ribbon design. This will help in ease of laying and maintenance of the Fiber optic network. Also, it will be beneficial to PCSCL in leasing out the ribbon cable to the probable tenants and have the revenue generated from day 1.
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
56 Sterlite Page -15. System Integrator Scope of Work:
System Integrator Scope of Work: Procure, Supply, Installation & Commission of all the Passive Infrastructure: SI shall be responsible for laying of 3 ducts (indicative) using Horizontal Directional Drilling (HDD) / Open Trenching (OT) Technique as per directions of PCSCL and blowing of fiber (96/48 core) basis on the finalized route plan and appropriate network topology to ensure adequate redundancy at each of the network node level. Indicative city wide fiber network route length is estimated to be 750 km, across the city, which shall be finalized after the detailed survey and route finalization activity,
Request to clarify the uses of 3 ducts.
Details shall be provided as part of the RFP document. However, you may please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
57 Sterlite Page -15. System Integrator Scope of Work:
System Integrator Scope of Work:Procure, Supply, Installation & Commission of all the Passive Infrastructure: SI shall be required to procure & supply all the passive components and accessories required for laying of duct and blowing of fibre including duct pipes, jointers, couplers, fibre cable, splicer, jointer etc. SI shall be responsible for laying of 3 ducts (indicative) using Horizontal Directional Drilling (HDD) / Open Trenching (OT) Technique as per directions of PCSCL and blowing of fiber (96/48 core) basis on the finalized route plan and appropriate network topology to ensure adequate redundancy at each of the network node level. Indicative city wide fiber network route length is estimated to be 750 km, across the city, which shall be finalized after the detailed survey and route finalization activity,
As per network Architecture kindly share the fiber Kms scope segregation i.e. how many km OFC in core, aggregate , access & Service layer network against estimated route length of 750 Km.
Details shall be provided as part of the RFP document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
58 Sterlite Page -16 /Reinstatement & Restoration
Reinstatement & Restoration: SI shall be responsible for performing the reinstatement and restoration of the sites back to the previous/normal conditions as per the RFP specifications at all the respective site locations.
Kindly confirm, who will pay the ROW (Right of Way) charges for PCMC area?
RoW charges will be waived off for the selected bidder
59 Sterlite Page -16 /Reinstatement & Restoration
Reinstatement & Restoration: SI shall be responsible for performing the reinstatement and restoration of the sites back to the previous/normal conditions as per the RFP specifications at all the respective site locations.
Kindly confirm, who will pay ROW charges for OFC route falling in other than PCMC area, viz. Railway Crossing, PWD, cantonment area etc.?
Details shall be provided as part of the RFP document
60 Sterlite
Page -16 /System Integrator Scope of Work:
System Integrator Scope of Work: Provide Operation & Maintenance Services for the Passive Infrastructure, OFC Network and Pole Infrastructure, for a contract period from the date of Commissioning of the system.
Kindly confirm the Time Frame for O&M.
Details shall be provided as part of the RFP document. However, you may please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
61 Sterlite Page-8/ 4. Intent
4. IntentTo lay the foundation of a Smart City, Under Project 1, PCSCL intends to create passive infrastructure components, either through EPC model or PPP (revenue sharing) model, like laying of Optical Fibre based Network (City Network) and erection of Pole Infrastructure for mounting IoT & Smart City devices across the city; Fibre Network is planned to connect all the PCMC offices (Zone & Ward Offices), health & citizen facilitation centres, key areas like markets, religious places, bus stops etc. whereas the Pole Infrastructure shall be setup at various traffic junctions, key city places for hosting CCTV cameras, traffic detectors, variable message displays, public address system, Wi-Fi access points etc.
Kindly share the locations details of Zonal Offices & Ward Offices, citizen facilitation centres, markets, religious places, bus stops, Traffic Junctions in the RFP so that OFC Network- Architecture with different layer can be worked out accordingly .
Details shall be provided as part of the RFP document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
62 Sterlite Page-16/System Integrator Scope of Work:
System Integrator Scope of Work:Note: All the active electronics like switch, UPS, power meter, power banks etc. at the centralized as well as at field level shall be out of scope of the SI.
Kindly share the OFC Network Architecture in RFP as OFC Network Architecture Viz. No. of Core Nodes, No. of Aggregates Nodes, No. of Access Nodes and their route path is derived based on active elements network topology /architecture.
Please submit your propositions as part of your EOI response document
63 Sterlite Pg. No. 8, Section 4
PCSCL is looking for partners to work with it, in PPP model (on revenue sharing basis), for study, design, engineer, supply, plan, construct, develop, install, commission, test, deploy, support, maintain and operate the end-to-end Smart Pole, City Wide Wi-Fi, VMD and Smart City Kiosk projects on Design, Build, Finance, Operate and Transfer (DBFOT) mode for a specified Concession Period.
We recommend to opt for an EPC based model looking at the trends in other smart city RFPs. Under PPP model, there is a possibility that the bid may get heavy on cost side. The reasons for increased cost under PPP model , apart from certain basic inputs required to be added to the cost, large amount of margins are made provision of, to cover project risk, operation risk, financial risk and political risk etc.
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
64 Sterlite Pg. No. 11, Section 6.11
Shortlisting of interested applicants i.e. SIs for Project 1 and Concessionaires for Project 2; who shall further participate in the respective projects RFP stage.
We suggest to come up with a combined RFP for both the Projects looking at the trends of other Smart Cities RFPs. It will be in benefit to PCSCL in getting right partner for long term association (Design and O&M phase), cost competitive bid, ease in execution.
Please submit your propositions as part of your EOI response document
65 Sterlite
Clause 12 12. Qualification Criteria, EOI Page No. 24, Sl. No 3
Financials:The applicant should have an average annual turnover of at least INR 500 Cr. from provision of Telecom Infrastructure / Fibre cable Infra supply and services (fibre cable network implementation including trenching, ducting, cable laying, termination, other requisite activities and O&M of that network) in last three financial years, i.e. FY 14-15; FY 15-16 , FY 16-17.
We request you to modify the clause as:The applicant should have an average annual turnover of at least INR 200 Cr. from provision of Telecom Infrastructure / Fibre cable Infra supply and services (fibre cable network implementation including trenching, ducting, cable laying, termination, other requisite activities and O&M of that network) in last three financial years, i.e. FY 14-15; FY 15-16 , FY 16-17. This will help PCSCL to have more competent and competitive participation from the industry.
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
66 Sterlite
Clause 12 12. Qualification Criteria, EOI Page No. 24, Sl. No 2
Board Resolution / Power of Attorney in favour of authorised signatory A Board Resolution or Power of Attorney in the name of the person executing the bid, authorizing the signatory to commit the Applicant
Please allow bidder's to submit Photostat copy of the general power of attorney duly notarized along with the copy of Board resolution who is providing power of attorney to the signing authority. However the Original power of Attorney as per RFP format shall be submitted by bidder during bid submission against RFP.
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
67 Sterlite
Clause 12 12. Qualification Criteria, EOI Page No. 24, Sl. No 5
Technical Capability:The applicant should have relevant experience related to provisioning of Telecom Infrastructure / Fibre cable supply and services (fibre cable network implementation including trenching, ducting, cable laying, termination, other requisite activities and O&M of that network) in last three financial years, i.e. FY 14-15; FY 15-16, FY 16-17.· One project of value not less than INR 100 CrOR· Two projects each having value not less than INR 80 CrOR· Three projects each having value not less than INR 50 CrThe quoted project should be completed and shall be in operations for last two years at the time of submission of EoI response.
We request you to allow bidders to submit on-going projects also. For on-going Project, relevant work order(s) and certificate(s) (on the letterhead of the company issuing the certificate) with details from the client(s) stating that the minimum value of works executed is greater than a value of INR 100 Cr. and total payments done against the project as on the certificate date.
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
68 Vikram
Teleinfra Pvt. Ltd.
9. Scope of Work, Page No. 14, Section No. 9.1
EPC Model / Public Private Partnership Model
Can we have OFC Network and Passive Infra on PPP and Poles and Gantries under EPC
Please submit your propositions as part of your EOI response document
69 Vikram
Teleinfra Pvt. Ltd.
Page No. 15, Procure, Supply, Installation
SI shall be responsible for laying of 3 ducts
We would like to lay 8 or more ducts keeping in mind the future requirement.
Please submit your propositions as part of your EOI response document
70 Vikram
Teleinfra Pvt. Ltd.
9. Scope of Work, Page No. 14, Section No. 9.1
EPC Model / Public Private Partnership Model
Can we have OFC Network and Passive Infra on PPP and Poles, Gantries & VMD under EPC
Please submit your propositions as part of your EOI response document
71 Vikram
Teleinfra Pvt. Ltd.
General Point not mentioned
Since we will do OFC Network on PPP Basis, we request exclusivity of ROW where no other operators would be given ROW other than us else it will be difficult on PPP model.
Details shall be provided as part of the RFP document. However, you may please submit your propositions as part of your EOI response document
72 Vikram
Teleinfra Pvt. Ltd.
12.1 Qualification criteria for shortlisting of SI for Project 1 Page no 24 point no 1. Legal Entity:
Consortiums are not allowed at this stage
Request for Consortium as project 2 Already has this policy and will help even other specialised SI other than telecom operators and increase competition and an opportunity for many to participate
No change, as per EOI document
73 Vikram
Teleinfra Pvt. Ltd.
12.1 Qualification criteria for shortlisting of SI for Project 1 Page no 24 point no 3. Financials
The applicant should have an average annual turnover of at least INR 500 Cr
Considering the Project Cost Annual Turnover should not be more than 20 Cr, Annual Turnover of consortium of SI and Sister Concerns (if any) to be at least 25 Cr
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
74 Vikram
Teleinfra Pvt. Ltd.
12.1 Qualification criteria for shortlisting of SI for Project 1 Page no 25 point no 5. Technical Capability
* One project of value not less than INR 100 Cr - One Project with Length of Trenching, Ducting and Cable Laying not less than 150 Kms OR * Two projects each having value not less than INR 80 Cr - Two Projects with length of Trenching, Ducting and Cable Laying not less than 40 Kms. OR *Three projects each having value not less than INR 50 Cr - Three Projects having length not less than 35 Kms
Criteria for Total distance ( in Kms) over Total Value( in Rs) is suggested as the cost for laying OFC and Duct varies as per methodology (HDD, Open Trenching, Aerial), Protection (DWC, GI, Concrete) Ranges from Rs. 3 Lakhs to 35 Lakhs per KM and most of the times material is Free Issue Material. Thus cost and rates will change and small lengths may have very high value ... so length will be a proper criteria in terms of capacity to execute.
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Pre Bid
Queries
75 Vikram
Teleinfra Pvt. Ltd.
12.1 Qualification criteria for shortlisting of SI for Project 1 Page no 25 point no 6. Certifications
The applicant should possess below mentioned certification which are valid at the time of bidding:* ISO 9001:2008/TL 9000 certification* ISO 20000:2011 for IT Service ManagementThe bidder shall possess all the licenses and shall comply with all the rules of the country that are required to provide telecom infrastructure and services throughout the period of contract.
Either ISO 9001 : 2008 or ISO 20000:2011 for IT Service Management The Bidder should possess IP 1 License and ISP License for Pune District
Please refer Corrigendum
76 Vikram
Teleinfra Pvt. Ltd.
12.1 Qualification criteria for shortlisting of SI for Project 1 Page no 25 point no 8. Manpower Strength
The applicant should have at least 1000 resources on payroll of the applicant’s organization at the time of submission of EoI response
The Applicant should have atleast 100 resources on payroll / contract / outsource. As this is the Infrastructure work and not software development. As the most of infrastructure industries runs on contractual labour / subcontractor and one Engineer is required for 80 kms of route length.
Please refer Corrigendum
77 Vikram
Teleinfra Pvt. Ltd.
12.1 Qualification criteria for shortlisting of SI for Project 1 Page no 24 point no 3. Financials
The applicant should have an average annual turnover of at least INR 500 Cr
Considering the Project Cost Annual Turnover should not be more than 20 Cr considering 35 Pc of work done. Request for Annual Turnover of consortium of SI and or Sister Concerns (if any) to be at least 25 Cr
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
Project 2:
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
1 ATC Speed of WI Fl Page no. 19
2 Mbps speed for first 60 mins and thereafter downgraded to 1Mbps
Very high speed is expected which could be difficult from implementation perspective and network constraints Speed could be 1 Mbps for 1st 30 mins. Thereafter speed of 512 kbps
Please submit your propositions as part of your EOI response document
2 ATC Smart kiosk, Page no. 17
List of components is very high in no.s
The list of components expected in Smart kiosk is very high and could be deterrent in successful implementation of the same There could be 2 lists, Mandatory list to capture top 4-5 components and an optional list for remaining components
Please submit your propositions as part of your EOI response document
3 ATC Monetizing models
Not very clearly articulated
Needs more clarity on monetization model post submission of Bid and before participation in the RFP to be released, Scope and responsibility needs to be transparently defined
Please submit your propositions as part of your EOI response document
4 ATC
Connecting last mile with existing Telecom tower present
Current EOI does not talk about whether the existing telecom towers in the city can be connected with OFC being planned to be laid
Connecting existing telecom infrastructure with OFC as per envisaged project can add value to the society/public of the smart city IP-1 should be allowed to stretch last mile connectivity with their existing infrastructure in the rekon
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
5 Cisco Page No. 16, 9.2 Project 2:
Please add “City Wide Transport Network with support of IP/MPLS, 6PE and 6VPE mode for IPV6 transport over IPV4, ECMP, LDP, BGP Prefix independent control for IPV4 and IPV6, RSVP, Loop free alternate FRR (IPFRR) and MPLS-TE with FRR for sub 50 msec node and link protection. Network shall support IPSLA and Y.1731 for performance monitoring. Network shall support MEF for Ethernet based services like PW, VPLS or ATOM."
As mentioned in EOI, PCSCL is looking for services like Smart Pole, CCTV Camera, Wi-Fi, Smart Lighting, Traffic and Whether Sensors, Variable message display units along with numerous IOT and Smart City Devices. In case of smart cities there is always a requirement to provide dedicated internet or MPLS WAN connectivity to tenants. To successfully implement and run various smart city services and tenants connectivity, IP MPLS based transport network uses dynamic protocols to ease the operational burden and ensure self-healing of network and plays very crucial role. IP MPLS based network are enabled with features like faster convergence and industry wide accepted technology for critical applications and scalability. It provides simplification with optimal utilization of resources and readiness for all future traffic and connectivity requirements. IP MPLS based network will provide reliable, robust and scalable network platform to ensure isolated/dedicated routing and forwarding policies, QoS policies and traffic engineering policies for each smart city service and tenants connectivity. So we hereby request you to add requirement of reliable, robust and scalable city wide transport network requirement as part of EoI.
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
6 Cisco Page No. 16, 9.2 Project 2:
Please add "City Wide Transport Network with support of IP/MPLS, 6PE and 6VPE mode for IPV6 transport over IPV4, ECMP,LDP, BGP Prefix independent control for IPV4 and IPV6, RSVP, Loop free alternate FRR (IPFRR) and MPLS-TE with FRR for sub 50 msec node and link protection. Network shall support IPSLA and Y.1731 for performance monitoring. Network shall support MEF for Ethernet based services like PW, VPLS or ATOM."
It was understood during the prebid meeting that the project 2 requires the SI to install the active components such as Wifi APs, Switches, UPS, etc. at the junction/smart pole. However, this approach is incomplete as these junctions/poles/edge locations will require an active network to connect to which is not mentioned in the EoI. How is that being met? Where would this ring/junctions terminate? Also, the EoI reads PCSCL would provide the connectivity to the SI in project 2. Understanding is: Scenario1: Connectivity from project 1, but this is only passive infra which cannot be used for directly connecting these devices/poles unless there is a core network. Scenario 2: Connectivity from Service provider - This also requires a core network to be establish for the ring/edge locations to converge and terminate. The entire vision of the smart city should be to have a common wired network which can be segregated into multiple different secure private (virtual) networks as per the b/w or fibre cores required, for multiple use cases as the citizen service deliveries grow - e.g Smart City, FTTx, CCTV, network for PCMC offices, etc. However, the current scope could result into a fragmented approach where multiple players would create their own network on the passive network - thus leading to huge costs in future as well as major manageability, O&M, security issues. This would also lead to lower monetization for each of the use cases as the capex investment would be required every time. It is desired that PCSCL provides a ready intelligent smart network for players/ businesses, citizens to leverage. We would be glad to discuss our thoughts on this.
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
7 Forbes
Technosys 18/ Concessionaire
Concessionaire shall also be responsible to procure, supply, install and manage all the active devices/equipment’s like network switch, power meter, UPS, battery banks etc. required for the operations of Telecom and other Smart City components that would be installed on Smart Poles and provide Operations & Maintenance services during the contract/concession period.
power back up to be clearly mentioned The same shall be shared as part of the RFP document
8 Forbes
Technosys 17/ Smart Kiosk
PCSCL intends to deploy Smart City Kiosk Terminal at key locations across the city
PCSCL to confirm whether the kiosk to be installed will be in Indoor or Outdoor (open to air) environment. PCSCL to confirm whether the Kiosk will be installed inside the cabin if getting installed in outdoor environment? PCSCL to confirm whether the cabin needs to be provided by bidder or PCSPL will provide the same?
Smart Kiosk are planned to be deployed in both the indoor and outdoor environment. Further, details on the same shall be shared as part of the RFP document
9 Forbes
Technosys 17/ Smart Kiosk
Panic Button and Phone Handset
PCSCL to confirm the working of Panic Button and Phone Handset? Whether a Video conferencing needs to be done after panic button is pressed? How it will integrate with controller system.
The same shall be shared as part of the RFP document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
10 Forbes
Technosys 17/ Smart Kiosk
PCMC Smart City Kiosk
PCSCL to confirm whether the kiosk software needs to be supplied by the bidder along with the kiosk?
The same shall be shared as part of the RFP document
11 Forbes
Technosys 17/ Smart Kiosk
MIFARE Card Reader / Writer Credit card / debit card / NFC interface
PCSCL to confirm the working application on the kiosk of MIFARE Card Reader / Writer and Credit card / debit card / NFC interface
The same shall be shared as part of the RFP document
12 Forbes
Technosys 17/ Smart Kiosk PCMC Smart CityKiosk No specifications mentioned for components
The same shall be shared as part of the RFP document
13 Forbes
Technosys 17/ Smart Kiosk transactional
We request PCSCL to confirm the type of transaction
The same shall be shared as part of the RFP document
14 Forbes
Technosys 17/ Smart Kiosk navigational
PCSCL need to confirm who will provide for navigation.
The same shall be shared as part of the RFP document
15 Forbes
Technosys 17/ Smart Kiosk G2C services
PCSCL Need to confirm the type of G2C services and their API for different services.
The same shall be shared as part of the RFP document
16 Forbes
Technosys Smart Kiosk Central server
PCSCL need to confirm if there is any middleware/central server involved in the system
The same shall be shared as part of the RFP document
17 Forbes
Technosys
26/Qualification Criteria for Shortlisting of Concessionaire for Project 2:
Financials We request PCSCL to keep an annual turnover atleast INR 250 Cr
Please refer Corrigendum
18 Forbes
Technosys
26/Qualification Criteria for Shortlisting of Concessionaire for Project 2:
Networth We request PCSCL to consider the positive networth of our parent company as we are own and full subsidiary of Forbes and Company Limited
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
19 Forbes
Technosys General Point not mentioned
(As confirmed by the by Mr. Vikas of E &Y (the consultant) and towards the end of the meeting the same thing is also confirmed by Mr. Shravan Hardikar IAS –(CEO & Director PCSCL) that the association between bidder and OEM should be build at the stage of EOI and it can’t be changed at RFP stage. Our submission: Request to introduce a clause covering the above point at the EOI stage to avoid any confusion or ambiguity on “association between the OEM & Bidder”.)
No change, as per EOI
20 Forbes
Technosys General Point not mentioned
We request you to mention a clause where it states that the bidder has to mention the name of the OEM of the components they would quote during the EOI and RFP stage.
No change, as per EOI
21 IBM General Extension of Bid Submission Date by 1 week atleast
There are multiple legal processes that we have to complete within our organization before responding to the EOI, this will take some time and hence the request of extension.
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
22 Indus Tower 3. About the EoI Document, Page 7
Project 2 - Study, design, engineer, supply, installation, testing & commissioning and Operations & Maintenance of Smart Poles, City wide WiFi, Smart City Kiosk and Variable Message Display (VMD) etc. on end-to-end basis in Design, Build, Finance, Operate and Transfer (DBFOT) mode for a specified Concession Period on PPP Mode (Revenue Sharing Model)
We understand that the end of the Concession period the project assets needs has to be transferred to the Authoritcy. However, Monetization of the smart poles would be done through the use of these poles by Telecom operators. As a UASL/UAL license holder from DOT, telecom operators are abided by the regulations which mandates them to provide telecom coverage continuity. In absence of this continuity / disruption of telecom network, they would be in breach of regulation. Hence, we suggest that the project shall be implemented on Built-Own-Operate (BOO) basis. Requesting for a concession period of 20 years. Post concession period Concessionaire shall be allowed to use the telecom poles for the purpose of servicing the telecom customers at a mutually agreed consideration. At the same time, Authorities can use the same poles for hosting smart services or the rest of the assets other than smart poles can be transferred to the Authority. This creates a win win situation.
Please submit your propositions as part of your EOI response document
23 Indus Tower 5. Control Sheet, Page 10
Last date for submission of EoI response
As the submission of response to EoI is on a stringent deadline, we request Authority to extend the submission by further 15 days
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
24 Indus Tower Concessionaire Scope of Work, Page 18
Also, applicant shall be responsible for provisioning & managing the centralised IT Infra like server, storage, security etc. at its own end and as per the RFP specifications.
We request you to confirm whether the location & space for setting up the centralised IT infra for project 2 will be provided by the Authority?
Yes, the understanding is correct. Further details shall be furnished as part of the RFP document
25 Indus Tower 9.2 Project 2, Page 16
We understand that the cost of the electricity for non-revenue generating components like Public Wi-Fi, VMD and Smart Kiosk will be borne by the Authority.
All the components of Project 2 has revenue generating capabilities. The cost of electricity to be borne by the selected bidder for all the components mentioned in the Project 2.
26 Indus Tower 9.2 Project 2, Page 16
> 12-15 meter Smart Pole > 25-30 meter Smart Pole
Please let us know the mechanism for identifying the number of Smart Poles. Does the bidder have an option to choose the split of the number of poles? Also, are the locations finalized or Concessionaire will be allowed to do a site survey for finalization. Further, please share the locations if finalized by the Authority. We also request for allowing advertisement by installing VMD on the 300 numbers of Smart Poles envisaged.
1. Please submit your propositions as part of your EOI response document 2. Locations shall be mutually finalised by the purchaser and the selected bidder 3. Please submit your preferred locations list as part of your EOI response document 4. Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
27 Indus Tower 9.1, Project 2, Page 17
Smart Kiosk
Requesting the Smart Kiosk to be a one time ask from the RFP and subsequent O&M scope should rest with the Authority. Also request the number of Kiosk should be reduced from 210. It seems on the higher side considering 181 sq. km. of area in PCMC - which probably could be at important locations with higher footfall.
No change, as per EOI
28 Indus Tower 9.2 Project 2: Page 18
Procure, Supply, Installation & Commissioning of Smart Pole, Smart City Kiosk, VaMS and City Wi-Fi Infrastructure
Please clarify if total pole structures to be installed as part of project 1 and Project 2 are not overlapping. Project 1 has 600 number of unipoles & Project 2 has 300 Smart poles – which means the total is 900 poles.Requesting for providing space at the base of the Smart Poles with an area of 4x4 meter to install battery backup and other equipment’s.
Yes, the understanding is correct. However, the mentioned numbers are only indicative. For the requisite space for infra installation, please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
29 Indus Tower 9.2 Project 2, Page 18
4. Variable Message Display (VMD) Further, it is planned to monetize the VMD for revenue generation while offering fixed Air Time for PCSCL for city related campaigns and information
While a specific time during the day will be reserved for city specific information/campaigns. We request Authority to allow Concessionaire to monetize it through advertisement. Further, Concessionaire shall be allowed to install Digital/Conventional billboards on Smart Poles for advertisement. Requesting VMD numbers to be reviewed and reduced. It seems on the higher side considering 750 Km of route length in the PCMC area. Normally VMDs are deployed on the important locations.
Please submit your propositions as part of your EOI response document
30 Indus Tower Monetization & Revenue Sharing of Smart Poles, Smart City Kiosk, VMD and City Wi-Fi, Page 19
Smart Pole fibre termination, interconnect links and space shall be leased from PSSCL on fixed rental basis.
While the cost of the project execution is to be borne by the Concessionaire, we request Authority to waive off RoW & RR charges, wherever applicable, for installation of smart components. Further, we request Authority to waive-off any charges, fee, property tax or any other payment payable to local body for setting up of project facility, associated infrastructure and poles.
The details shall be provided as part of the RFP document. However, you may please submit your propositions as part of response to EOI document
31 Indus Tower We understand that Authority will provide the necessary RoW (without any charge) for laying incremental OFC up to the nearest PoP.
The details shall be provided as part of the RFP document. However, you may please submit your
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
propositions as part of your EOI response document
32 Indus Tower
Provisioning of Internet Bandwidth, Page 19
Currently it is planned to provide unlimited City wide free Wi-Fi service to the citizens, without time limit, at 2 Mbps speed for first 60 mins and thereafter downgraded to 1Mbps.
We would like to bring to your notice that this is a big deterrent for business model for telecom service providers and currently not a norm in the industry either locally or internationally. We request Authority to reduce the same to 30 min / 1 GB per month per user along with a minimum throughput of 512kbps per user
Please submit your propositions as part of your EOI response document
33 Indus Tower Page 20 PCSCL will release separate RFP for Project 1 and Project 2.
We suggest Authority to look for same partner for combined scope of both projects in order to have better synergy and options for revenue generation.
Please submit your propositions as part of your EOI response document
34 Indus Tower General We understand that Authority will provide Bidder with single window of clearance for any RoW permission for executing the project.
The details shall be provided as part of the RFP document.
35 Indus Tower General Permission to use of land to erect smart poles
We understand that the Rights to provide RoW has been vested to PCSCL by PCMC
Selected applicant shall be granted requisite rights by the competent authority
36 Indus Tower General Permission for site allocation
We understand that the site will be allocated by the Authority within the agreed timelines as the same will have an impact on meeting the project implementation timelines and revenue generation thereafter.
Yes, the understanding is correct
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
37 Indus Tower General Project 2: Allocation of alternate site
We understand that if due to any unavoidable reasons the Authority is not able to approve any Smart Pole site location, the Authority shall provide an alternate location within 100 meter radius
All the locations pertaining to specific solution components need purchaser approval and the same/alternate location shall be made available to the applicant.
38 Indus Tower General Materially Adverse Government Action (MAGA)
“Materially Adverse Government Action (MAGA)” means any act or omission by the PCSCL or any relevant public authority, which occurs during the term of this project execution and which (i) renders the Concessionaire unable to comply with any of its obligations as per the Agreement and/or (ii) has a material adverse effect on the cost or the profits arising from such performance and/or (iii) any judgment or order of any court of competent jurisdiction or statutory authority in India made against the Concessionaire in any proceedings for reasons other than on account of breach thereof, or of any Agreement, or enforcement of the signed Agreement or exercise of any of its rights under the Agreement.We suggest the Authority to include the aforementioned clause while drafting the T&C of the RFP.
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
39 Indus Tower
12.2 Qualification Criteria for shortlisting of Concessionaire for Project 2, Page 26
Point 6 - Technical Capability
We request to delete the additional qualification for experience in 3 specific business areas mentioned (Wi-Fi, Kiosk & VMD) or replace the same with an ÖR instead of an AND. Or we request you to consider O&M of more than 5000 Telecom Towers as one of the Specific business area in addition to Wi-Fi, Kiosk, and Variable Message Display.
Please refer Corrigendum
40 Indus Tower
The implementation of Smart Poles and IoTs have taken a kick start within last few months. Most of the projects have been awarded during the year 2017-18.Hence we request you to consider the experience of fy 2017-18 as well.
Please refer Corrigendum
41 Indus Tower
While we have vast experience related to provisioning of Telecom Infrastructure, we request Authority to consider LoI/ LoA/ WO/Contract Agreement / Self Certificate for completion for showcased project.
Please refer Corrigendum
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
42 Indus Tower
The Sole applicant or any member of the consortium, in case of consortium, should possess below mentioned certification which are valid at the time of bidding: · ISO 9001:2008/TL 9000 certification · ISO 20000:2011 for IT Service Management The bidder shall possess all the licenses and shall comply with all the rules of the country that are required to provide telecom infrastructure and services throughout the period of contract.
We request you to modify the clause as per following; The applicant should possess any one of the below mentioned certification which are valid at the time of bidding: > ISO 9001:2008/TL 9000 certification > ISO 20000:2011 for IT Service Management > ISO 27001:2013 for Information Security Management System The bidder shall possess all the licenses and shall comply with all the rules of the country that are required to provide telecom infrastructure and services throughout the period of contract.
Please refer Corrigendum
43 L&T
6.1 Stage 1 – Expression of Interest6.1.1 PurposePage 11
6.1 Stage 1 – Expression of Interest6.1.1 Purpose· Shortlisting of interested applicants i.e. SIs for Project 1 and Concessionaires for Project 2; who shall further participate in the respective projects RFP stage.
As per current scenario, PPP Model / Revenue Sharing Model is not successful for other infrastructure projects. Hence, we feel that for smart city projects also, the proposed PPP model would not be successful. We will have a detailed presentation on the business model and challenges in this model during our presentation stage. Hence, we kindly request you to keep the same EPC model for project 2 also, i.e. on EPC model rather than going for PPP Model / Revenue Sharing Model.
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
44 L&T 3. About the EoI Document Page 7
Project 1 – Supply, Installation, Testing & Commissioning and Operations & Maintenance of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. under Engineering Procurement and Commissioning (EPC) / PPP mode (Revenue Sharing Model) Project 2 - Study, design, engineer, supply, installation, testing & commissioning and Operations & Maintenance of Smart Poles, City wide WiFi, Smart City Kiosk and Variable Message Display (VMD) etc. on end-to-end basis in Design, Build, Finance, Operate and Transfer (DBFOT) mode for a specified Concession Period on PPP Mode (Revenue Sharing Model)
As per current scenario, PPP Model / Revenue Sharing Model is not successful for other infrastructure projects. Hence, we feel that for smart city projects also, the proposed PPP model would not be successful. We will have a detailed presentation on the business model and challenges in this model during our presentation stage. Hence, we kindly request you to combine both Project 1 & Project 2 and release EOI on EPC model.
Please submit your propositions as part of your EOI response document
45 L&T Addendum Earnest Money Deposit
General Please provide EMD format.
EMD shall be deposited through PCMC’s e-Procurement portal i.e. https://www.pcmcindia.gov.in and a scanned copy of the same should also be uploaded as part of response to EoI document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
46 Microfocus General Suggested for EMS with a PPT (HPE Software Write-up) and Analyst report for reference
There is a need to have elaborated technical specifications towards Enterprise Management System (EMS) and Performance load testing – Not just a mention of the same in the RFP.
The same shall be shared as part of the RFP document
47 RPG Infra Pg 16, Sec 9.2
The design of the Smart Pole shall be such that it can host multiple equipment and services. Below are the two variants of poles with internal power backup that are planned to be developed: 12-15 meter Smart Pole 25-30 meter Smart Pole
Are the poles of height 25-30 m required only from Telecom perspective or they will have Smart functionalities as well? Considering RoW and space issues can we keep a Smart Pole design where the maintenance/junction boxes are mounted on the Pole and no other on-ground erection is required.
Smart Pole shall also be required to deploy other Smart City elements. Please submit your propositions as part of your EOI response document
48 RPG Infra Pg 18, Sec 9.2
Concessionaire Scope of Work: Also, applicant shall be responsible for provisioning & managing the centralised IT Infra like server, storage, security etc. at its own end and as per the RFP specifications
Has PCMC identified specific needs for IT Infra required?
The same shall be shared as part of the RFP document
49 RPG Infra Pg 19, Sec 9.2
As part of EoI response, concessionaire to suggest on managing the City wide WiFi Internet bandwidth operational cost during the period of contract
As per EoI bandwidth to be made available (free) for public usage is already mentioned. Can this be altered / charged?
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
50 RPG Infra Pg 16, Sec 9.2
Study, design, engineer, supply, installation, testing & commissioning and Operations & Management of Smart Poles, City wide WiFi, Smart City Kiosk and Variable Message Display (VMD) etc. on end-to-end basis in Design, Build, Finance, Operate and Transfer (DBFOT) mode for a specified Concession Period on revenue sharing Model
Consider changing the model for Project 2 to an EPC model. Revenue sharing / PPP model has not been successful in various other cities (Bhopal, Jabalpur, Indore) leading to very few/no bidders
Please submit your propositions as part of your EOI response document
51 RPG Infra Pg 8, Sec 4, Key Objectives & Goals
Under Project 2, PCSCL is looking for partners to work with it, in PPP model (on revenue sharing basis), for study, design, engineer, supply, plan, construct, develop, install, commission, test, deploy, support, maintain and operate the end-to-end Smart Pole, City Wide Wi-Fi, VMD and Smart City Kiosk projects on Design, Build, Finance, Operate and Transfer (DBFOT) mode for a specified Concession Period.
Consider combining the scope for the Project 1 and Project 2 (as well as any future projects for ICCC) under single MSI to drive efficiency in project management. A divided MSI scope will create issues with SLA adherence as some activities can be in overlap or fall in no man's land. Furthermore O&M will be a challenge.
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
52 RPG Infra Pg 26, Sec 12.2, S No. 4
The sole applicant or any member of consortium, in case of consortium, should have an annual turnover of at least INR 1000 Cr. from providing Shared Telecom Towers Services to Telecom Operators in last three financial years, i.e FY 14-15; FY 15-16 , FY 16-17.
The PQ criteria for lead bidder for Project 2 is not in sync with the scope of the project. The experience in commissioning telecom towers is not suitable for Smart Pole design and/or commissioning. Request you to allow same PQ as Project 1 in Project 2 as an alternate option.
Please refer Corrigendum
53 Sterlite Pg. No. 17 Section 9.2
City Wi-Fi
Will there be any segregation for free and premium Wi-Fi usage. Ideally, in most of the smart cities, it is observed that 30 minutes of free Wi-Fi with 1Mbps bandwidth per day is given. After exhausting 30 minutes of free Wi-Fi, customer can buy premium Wi-Fi package.
Please submit your propositions as part of your EOI response document
54 Sterlite Pg. No. 17 Section 9.2
City Wi-Fi Is there any requirement for Wi-Fi Mobile App. A Mobile App (iOS and Android) will help citizens to seamlessly login to City Wi-Fi
Please submit your propositions as part of your EOI response document
55 Sterlite Pg. No. 17 Section 9.2
City Wi-Fi What will be the O&M/AMC/Warranty period for the Project-1 & Project
Please submit your propositions as part of your EOI response document
56 Sterlite Page no 17, Smart Kiosk
Smart Kiosk Is it Indoor Kiosk or Outdoor Kiosk? And who will provide the Shelter for the Kiosk
The same shall be shared as part of the RFP document
57 Sterlite
Page no 15, System Integrator Scope of Work
Approx. 600 Unipole with cantilevers for mounting CCTV cameras, traffic sensors, IoT devices etc.
Bird spikes should be consider for CCTV camera/other Smart element
Please submit your propositions as part of your EOI response document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
58 Sterlite
Page -8/Project-1. About the EoI Document /Key Objective & goals
To create a uniform Pole Infrastructure across the city for hosting various IoT & Smart City devices like CCTV camera, traffic detectors, Wi-Fi access points etc. in a planned & structured manner, so as to avoid repeated digging and infrastructure laying work in the city.
Kindly confirm the maximum and minimum height of pole and Pole specifications. Kindly confirm the devises such as CCTV, Wi-Fi and traffic detectors may place on one pole. If yes then how may locations
The same shall be shared as part of the RFP document
59 Sterlite
Page -8/Project-1. About the EoI Document /Key Objective & goals
To create a uniform Pole Infrastructure across the city for hosting various IoT & Smart City devices like CCTV camera, traffic detectors, Wi-Fi access points etc. in a planned & structured manner, so as to avoid repeated digging and infrastructure laying work in the city.
Kindly confirm the Lightening arrester requirement and earth pit for the same on each pole
The same shall be shared as part of the RFP document
60 Sterlite Page -18/ EoI Document
Concessionaire shall also be responsible to procure, supply, install and manage all the active devices/equipment’s like network switch, power meter, UPS, battery banks etc.
Kindly confirm scope of SI for the provisioning of power for the field elements from the state electricity board. And how far power connection from the poles. Power backup required
The same shall be shared as part of the RFP document
61 Sterlite Page -16/ About the EoI Document
Note: All the active electronics like switch, UPS, power meter, power banks etc. at the centralized as well as at field level shall be out of scope of the SI.
Kindly confirm the field rack specifications. Weather UPS be place in same field rack or UPS will have separate rack
The same shall be shared as part of the RFP document
62 Sterlite Page -16/9.2 Project 2
Smart Pole: 25-30 meter Smart Pole
What are the smart elements to be installed on this pole as height of the pole is too high.
The same shall be shared as part of the RFP document
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
S.No. Name of
Organization
EOI Document Reference(s)
(Clause number / page)
Content of EOI requiring Clarification
Points of clarification Response to Queries
63 Vikram
Teleinfra Pvt. Ltd.
Page No. 16, Section No. 9.2, Study Design Engineer ….
Smart Pole Can we have this on EPC Please submit your propositions as part of your EOI response document
64 Wipro Limited
EOI PCMC, Page
No. 9, Section No. 3
End-to-end basis in Design, Build, Finance, Operate and Transfer (DBFOT) mode for a specified Concession Period on PPP Mode (Revenue Sharing Model)
We strongly prefer to have Capex and Opex Model on both the porjects. Esp. Project 2
Please submit your propositions as part of your EOI response document
65
Wipro Limited
EOI PCMC, Page No. 29, Section No. 12.2
Supply, Installation, Commissioning and Operations & Maintenance Services for Smart Poles / Telecom Tower / BTS / GBM(s) Infrastructure & services in last 3 years i.e FY 13-14,
We would like amend the clause as below "Supply, Installation, Commissioning and Operations or Maintenance Services for Smart Poles / Telecom Tower / BTS / GBM(s) Infrastructure & services in last 3 years i.e FY 13-14, FY 14-15, FY 15-16, FY 16-17 and currently having at least 3000 such Smart Poles / Telecom Tower / BTS / GBM(s) operational, as on date of submission of EoI, with minimum operational annual revenue of 200 cr.
Please refer Corrigendum
Wipro Limited
FY 14-15, FY 15-16, FY 16-17 and currently having at least 5000 such Smart Poles / Telecom Tower / BTS / GBM(s) operational, as on date of submission of EoI, with minimum operational annual revenue of 200 cr.
sd/-
(Shravan Hardikar, IAS)
CEO & Director,
Pimpri Chinchwad Smart City Limited (PCSCL)
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
CORRIGENDUM - 2
To
EXPRESSION OF INTEREST vide Ref Number- 02/2018-19 dated 10-01-2018
For Shortlisting of
a. System Integrators for SITC and O&M of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. on EPC /
Revenue Sharing Model
b. Concessionaires for SITC and O&M for Smart Poles, City Wi-Fi, Smart City Kiosk and Variable Message Display (VMD) etc. on Revenue Sharing
Model
The applicants are required to kindly consider the following corrigendum pertaining to the aforementioned EoI:
1. Key Dates / Timelines Revision:
Sr.
No.
EOI Existing
Clause Existing Clause Details Revised Clause
1.
Invitation to Bid (IFB) & Control Sheet
Period of Sale/download of Bidding Document (Start/ End Date): Between 10-01-2018,18:00 Hrs & 30-01-2018,18:00 Hrs
Period of Sale/download of Bidding Document (Start/ End Date): Between 10-01-2018,18:00 Hrs & 09-02-2018,16:00 Hrs
2.
Manner, Start/ End Date for the submission of Bids
Start Date: 10-01-2018. 18:00 Hrs
End Date: 30-01-2018, 18:00 Hrs
Manner, Start/ End Date for the submission of Bids
Start Date: 10-01-2018. 18:00 Hrs
End Date: 09-01-2018, 16:00 Hrs
3. Date/ Time/ Place of Bid Opening
Date: 31-01-2018, Time: 16:00 Hrs
Date/ Time/ Place of Bid Opening
Date: 09-02-2018, Time: 17:00 Hrs
4. Date of Technical Presentation: February 2, 2018 (Time shall be informed later)
Date of Technical Presentation: February 14, 2018 (Time shall be informed later)
2. Project 1 Pre-Qualification Revisions:
Existing Clause Details Revised Clause
A Board Resolution or Power of Attorney in the name of the person executing
the bid, authorizing the signatory to commit the Applicant
A Board Resolution or Power of Attorney, in the name of the person executing
the bid, authorizing the signatory to commit the Applicant
The person issuing the Power of Attorney shall possess Board Resolution in
his favour for granting such rights.
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
Existing Clause Details Revised Clause
In case of generic Board Resolution or Power of Attorney, the same shall be
certified by Company secretary.
The applicant should have an average annual turnover of at least INR 500 Cr.
from provision of Telecom Infrastructure / Fibre cable Infra supply and
services (fibre cable network implementation including trenching, ducting,
cable laying, termination, other requisite activities and O&M of that network)
in last three financial years, i.e FY 14-15; FY 15-16 , FY 16-17.
An average annual standalone turnover of at least INR 500 cr. In last three
financial years i.e. FY 14-15; FY 15-16, FY 16-17.
AND
An average annual turnover of at least INR 50 Cr. from provision of
“Telecom Infrastructure/Fibre cable & associated infrastructure”
implementation and maintenance services in last three financial years, i.e.
FY 14-15; FY 15-16 , FY 16-17.
The applicant should have relevant experience related to provisioning of
Telecom Infrastructure / Fibre cable supply and services (fibre cable network
implementation including trenching, ducting, cable laying, termination, other
requisite activities and O&M of that network) in last three financial years, i.e
FY 14-15; FY 15-16, FY 16-17.
One project of value not less than INR 100 Cr
OR
Two projects each having value not less than INR 80 Cr
OR
Three projects each having value not less than INR 50 Cr
The quoted project should be completed and shall be in operations for last
two years at the time of submission of EoI response.
The applicant should have relevant experience related to provisioning of
“Telecom Infrastructure/Fibre cable & associated infrastructure”
implementation and maintenance services in last five financial years
Project or Contract, with a single client, of value not less than INR 100 Cr
of which project component of value at least INR 60 Cr should have been
completed and should be in operations for last 1 year, as on date of
submission of EOI
OR
Two projects or contracts each having value not less than INR 80 Cr
which project component of value at least INR 48 Cr should have been
completed and should be in operations for last 1 year, as on date of
submission of EOI
OR
Three projects or contracts each having value not less than INR 50 Cr
which project component of value at least INR 30 Cr should have been
completed and should be in operations for last 1 year, as on date of
submission of EOI
For the applicants who have created / implemented “Telecom
Infrastructure/Fibre cable & associated infrastructure”, for their internal capital
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
Existing Clause Details Revised Clause
use or as a shared services on commercial basis, shall submit the Statutory
Auditor Certificate for substantiating such claims.
The applicant should possess below mentioned certification which are valid
at the time of bidding:
ISO 9001:2008/TL 9000 certification
ISO 20000:2011 for IT Service Management
The bidder shall possess all the licenses and shall comply with all the rules
of the country that are required to provide telecom infrastructure and services
throughout the period of contract
The applicant should possess any one of the below mentioned certification,
which are valid at the time of bidding:
ISO 9001:2008/2015 / TL 9000 certification
ISO 20000:2011 for IT Service Management
ISO 270001:2013 for Information Security Management
The bidder shall possess all the licenses and shall comply with all the rules
of the country that are required to provide telecom infrastructure and services
throughout the period of contract.
The applicant should have at least 1000 resources on payroll of the
applicant’s organization at the time of submission of EoI response
The applicant should have at least 250 resources on payroll of the applicant’s
organization at the time of submission of EoI response
Note: Bidder company credential would be considered for only 100% subsidiaries.
3. Project 2 Pre-Qualification Revisions:
Existing Clause Details Revised Clause
A Board Resolution or Power of Attorney in the name of the person
executing the bid, authorizing the signatory to commit the Applicant
This is applicable to the sole applicant or each of the members of the
consortium, in case of consortium.
A Board Resolution or Power of Attorney, in the name of the person executing
the bid, authorizing the signatory to commit the Applicant
The person issuing the Power of Attorney shall possess Board Resolution in his
favour for granting such rights.
In case of generic Board Resolution or Power of Attorney, the same shall be
certified by Company secretary.
This is applicable to the sole applicant or each of the members of the consortium,
in case of consortium.
In the event of a consortium, one of the applicant shall be designated as
a "Lead Partner/ Applicant". Consortium is allowed with up to 3 consortium
members including the Lead Applicant. The lead applicant should have
majority stake in the consortium which may be an incorporated or non-
incorporated JV.
In the event of a consortium, one of the applicant shall be designated as a "Lead
Partner/ Applicant". Consortium is allowed with up to 3 consortium members
including the Lead Applicant. The lead applicant should have majority stake in
the consortium which may be an incorporated or non-incorporated JV.
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
Existing Clause Details Revised Clause
As part of the EOI response, applicant can propose two consortium member, in
case of consortium, and shall have provision to propose 3rd consortium member,
if required, at the time of RFP stage
The sole applicant or any member of consortium, in case of consortium,
should have an annual turnover of at least INR 1000 Cr. from providing
Shared Telecom Towers Services to Telecom Operators in last three
financial years, i.e FY 14-15; FY 15-16 , FY 16-17.
The sole applicant or any member of consortium, in case of consortium, should
have an annual turnover of at least INR 500 Cr. from providing services to
Telecom Operators in last three financial years, i.e FY 14-15; FY 15-16 , FY 16-
17.
The sole applicant or any member of the consortium, in case of
consortium, should have a relevant experience of:
Supply, Installation, Commissioning and Operations & Maintenance
Services for Smart Poles / Telecom Tower / BTS / GBM(s) Infrastructure
& services in last 3 years i.e FY 13-14, FY 14-15, FY 15-16, FY 16-17
and currently having at least 5000 such Smart Poles / Telecom Tower /
BTS / GBM(s) operational, as on date of submission of EoI, with minimum
operational annual revenue of 200 cr.
AND
Project experience of Supply, Installation, Commissioning and Operations
& Maintenance Services, for any one of the below mentioned “specific
business area”, which is either completed or ongoing in last 5 years i.e
FY 12-13, FY 13-14, FY 14-15, FY 15-16, FY 16-17.
Specific business area:
1. WiFi Infrastructure & services with at least 200 access points
2. City Kiosk Infrastructure & services with at least 50 kiosks
3. Variable Message Display Infrastructure & services with at least
50 displays
The sole applicant or any member of the consortium, in case of consortium,
should have a relevant experience of:
Supply, Installation, Commissioning and Operations / Maintenance Services for
Smart Poles / Telecom Tower / BTS / GBM(s) Infrastructure & services in last 3
years as on date of submission of EOI response and currently having at least
3000 such Smart Poles / Telecom Tower / BTS / GBM(s) operational, as on date
of submission of EoI, with minimum operational annual revenue of 200 cr.
Or
Project experience of Supply, Installation, Commissioning and Operations &
Maintenance Services, for any one of the below mentioned “specific business
area”, which is either completed or ongoing in last 5 years as on date of
submission of EOI response
Specific business area:
1. WiFi Infrastructure & services with at least 200 access points
2. City Kiosk Infrastructure & services with at least 50 kiosks
3. Variable Message Display Infrastructure & services with at least 50
displays
The applicant should possess below mentioned certification which are
valid at the time of bidding:
ISO 9001:2008/TL 9000 certification
ISO 20000:2011 for IT Service Management
The applicant should possess any one of the below mentioned certification, which
are valid at the time of bidding:
ISO 9001:2008/2015 / TL 9000 certification
ISO 20000:2011 for IT Service Management
ISO 270001:2013 for Information Security Management
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
Existing Clause Details Revised Clause
The bidder shall possess all the licenses and shall comply with all the rules
of the country that are required to provide telecom infrastructure and
services throughout the period of contract
The bidder shall possess all the licenses and shall comply with all the rules of the
country that are required to provide telecom infrastructure and services
throughout the period of contract.
The applicant should have at least 1000 resources on payroll of the
applicant’s organization at the time of submission of EoI response
The applicant should have at least 250 resources on payroll of the applicant’s
organization at the time of submission of EoI response
Note: Bidder company credential would be considered for only 100% subsidiaries.
4. Other Points:
EOI Clause Clarification
9. Scope of Work, sub section 9.2 Project 2
City wide WiFi, Smart Kiosk and VMD shall be deployed all across the city, including Smart Pole
locations and beyond, and selected applicant shall be responsible for the deployment &
monetization of Infra & related systems at each of the identified locations.
13.8 Proforma 8: Applicant’s Suggestions &
Recommendations
For both the projects, an applicant is proposed to submit its suggestions/recommendations on
the following, as part of its response to EOI document, basis which purchaser shall decide on
the Project Execution Methodology:
Technical Architecture
Business Model
Operation Model
Sd/-
(Shravan Hardikar, IAS)
CEO & Director,
Pimpri Chinchwad Smart City Limited (PCSCL)
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
CORRIGENDUM
To
EXPRESSION OF INTEREST vide Ref Number- 02/2018-19 dated 10-01-2018
For Shortlisting of
a. System Integrators for SITC and O&M of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc.
on EPC / Revenue Sharing Model
b. Concessionaires for SITC and O&M for Smart Poles, City Wi-Fi, Smart City Kiosk and Variable Message Display (VMD) etc. on
Revenue Sharing Model
The applicants are required to kindly consider the following corrigendum pertaining to the aforementioned EoI:
Sr.
No.
EOI Existing
Clause Existing Clause Details Revised Clause
1.
Invitation to Bid (IFB)
Period of Sale/download of Bidding Document (Start/ End Date): Between 10-01-2018,18:00 Hrs & 20-01-2018,18:00 Hrs
Period of Sale/download of Bidding Document (Start/ End Date): Between 10-01-2018,18:00 Hrs & 30-01-2018,18:00 Hrs
2.
Manner, Start/ End Date for the submission of Bids
Start Date: 10-01-2018. 18:00 Hrs
End Date: 20-01-2018, 18:00 Hrs
Manner, Start/ End Date for the submission of Bids
Start Date: 10-01-2018. 18:00 Hrs
End Date: 30-01-2018, 18:00 Hrs
3. Date/ Time/ Place of Bid Opening
Date: 21-01-2018, Time: 16:00 Hrs
Date/ Time/ Place of Bid Opening
Date: 31-01-2018, Time: 16:00 Hrs
4.
Section 5: Control Sheet
Date of Pre Bid Meeting : 12:00 hrs on January 17, 2018 at PCMC Head Office(4
th Floor)
Date of Pre Bid Meeting : 11:00 hrs on January 18, 2018 at PCMC Head Office (4
th Floor)
5. Last date for submission of EoI response : Till 18:00 hrs on January 20, 2018
Last date for submission of EoI response : Till 15:00 hrs on January 30, 2018
6. Date of Technical Presentation: January 31, 2018 (Time shall be informed later)
Date of Technical Presentation: February 2, 2018 (Time shall be informed later)
Sd \-
(Shravan Hardikar, IAS)
CEO & Director,
Pimpri Chinchwad Smart City Limited (PCSCL)
PIMPRI CHINCHWAD SMART CITY LIMITED Registered Office: Administrative Building, PCMC,
Mumbai Pune Road, Pimpri, Pune- 411018 e-mail: smartcity@pcmcindia.gov.in
ADDENDUM
To
EXPRESSION OF INTEREST vide Ref Number- 02/2018-19 dated 10-01-2018
For Shortlisting of
a. System Integrators for SITC and O&M of Smart City field infrastructure comprising
of Passive Fibre Network, Poles and Gantries etc. on EPC / Revenue Sharing Model
b. Concessionaires for SITC and O&M for Smart Poles, City Wi-Fi, Smart City Kiosk
and Variable Message Display (VMD) etc. on Revenue Sharing Model
The following clause is to be construed as part of the aforementioned Expression of Interest
henceforth:
Earnest Money Deposit (EMD)
The Applicant participating in the EoI process must furnish the Earnest Money Deposit (EMD) i.e.
INR Five (5) lacs, for the respective category of the project, accompany the response to EoI
document without which the bid shall be rejected forthwith. No interest will be paid by PCSCL on
the amount of EMD.
Form of EMD: The EMD shall be deposited through PCMC’s e-Procurement portal i.e.
https://www.pcmcindia.gov.in and a scanned copy of the same should also be uploaded as
part of response to EoI document.
EMD Validity: The EMD shall be valid for a period of Two Months from the date of
submission of EoI response.
Refund of EMD: The earnest money deposit by all the applicants shall be
returned/refunded soon after final acceptance of response to EoI document and shortlisting
of applicant/bidders for the RFP stage.
Forfeiture of EMD: The EMD taken from the applicant shall be forfeited in the following
cases by giving proper notice to the applicant with reasonable time before EMD is forfeited
:-
o When the applicant withdraws its bid proposal after opening of bids.
o In case, an applicant has, directly or indirectly or through an agent, engaged in
corrupt practice, fraudulent practice, coercive practice, undesirable practice or
restrictive practice (collectively the “Prohibited Practices”) either in furnishing the
document/certificates, to be submitted as part of response to EoI document, or
during the Selection Process.
Sd \-
(Shravan Hardikar, IAS)
CEO & Director,
Pimpri Chinchwad Smart City Limited (PCSCL)
EXPRESSION OF INTEREST
for
Shortlisting of
a. System Integrators for SITC and O&M of
Smart City field infrastructure comprising of
Passive Fibre Network, Poles and Gantries
etc. on EPC / Revenue Sharing Model
b. Concessionaires for SITC and O&M for
Smart Poles, City Wi-Fi, Smart City Kiosk
and Variable Message Display (VMD) etc.
on Revenue Sharing Model
EOI Ref Number- 02/2018-19
Date: 10-01-2018
Pimpri Chinchwad Smart City Limited
(PCSCL), Pimpri
Pimpri Chinchwad Smart City Limited Expression of Interest
2 | P a g e
Table of Contents
1. Abbreviations ........................................................................................................................................ 4
INVITATION FOR BID (IFB) ..................................................................................................................... 5
2. Disclaimer.............................................................................................................................................. 6
3. About the EoI Document ....................................................................................................................... 7
4. Intent ..................................................................................................................................................... 8
5. Control Sheet ...................................................................................................................................... 10
6. On-boarding of System Integrator & Concessionaire - Process ......................................................... 10
6.1 Stage 1 – Expression of Interest ................................................................................................. 11
6.1.1 Purpose ............................................................................................................................... 11
6.1.2 Role of Applicant ................................................................................................................. 11
6.1.3 Role of PCSCL .................................................................................................................... 12
6.2 Stage 2 – Request for Proposal .................................................................................................. 12
6.2.1 Purpose ............................................................................................................................... 12
6.2.2 Role of Applicant ................................................................................................................. 12
6.2.3 Role of PCSCL .................................................................................................................... 12
7. Project Background ............................................................................................................................. 13
8. Geographical Scope ............................................................................................................................ 14
9. Scope of Work ..................................................................................................................................... 14
9.1 Project 1 ...................................................................................................................................... 14
9.2 Project 2: ..................................................................................................................................... 16
10. Instruction to Participants .................................................................................................................... 20
10.1 Issue of EoI document ................................................................................................................ 20
10.2 Pre-bid Meeting & Clarifications .................................................................................................. 20
10.3 EoI preparation cost .................................................................................................................... 20
10.4 EoI Application/Response for Either/Both Projects ..................................................................... 21
10.5 Right to accept and reject any or all the EoI ............................................................................... 21
11. Preparation and submission of EoI document .................................................................................... 21
11.1 Language .................................................................................................................................... 21
11.2 Clarifications on EoI documents ................................................................................................. 21
11.3 Amendment of EoI document ..................................................................................................... 21
11.4 Alternative EoI documents by the Applicants.............................................................................. 22
11.5 Submission of EoI Document ...................................................................................................... 22
11.6 Authority to Sign .......................................................................................................................... 22
11.7 Items to be kept in mind while furnishing details......................................................................... 22
11.8 Confidentiality .............................................................................................................................. 22
11.9 EoI due date ................................................................................................................................ 23
Pimpri Chinchwad Smart City Limited Expression of Interest
3 | P a g e
11.10 Late/ Delayed EoI response .................................................................................................... 23
11.11 Modification/ Substitution/ Withdrawal of response ................................................................ 23
11.12 Evaluation ................................................................................................................................ 23
11.13 Clarifications Sought by PCSCL ............................................................................................. 23
11.14 Notifications ............................................................................................................................. 23
11.15 Inspection of site by the Applicants ......................................................................................... 23
12. Qualification Criteria ............................................................................................................................ 24
12.1 Qualification Criteria for shortlisting of System Integrator for Project 1: ..................................... 24
12.2 Qualification Criteria for shortlisting of Concessionaire for Project 2: ......................................... 26
13. Proformas ............................................................................................................................................ 28
13.1 Proforma 1: Cover Letter ............................................................................................................. 28
13.2 Proforma 2: Firm Details ............................................................................................................. 29
13.3 Proforma 3: Detailed experience format ..................................................................................... 31
13.4 Proforma 4: Self Declaration by Applicant .................................................................................. 32
13.5 Proforma 5: Power of Attorney .................................................................................................... 33
13.6 Proforma 6: Suggestions from Applicant .................................................................................... 34
13.7 Proforma 7: Applicant’s Experience & Learnings highlighting key issues & challenges
encountered ............................................................................................................................................ 36
13.8 Proforma 8: Applicant’s Suggestions & Recommendations ....................................................... 37
13.9 Proforma 9: Pre Bid Queries Format .......................................................................................... 38
Pimpri Chinchwad Smart City Limited Expression of Interest
4 | P a g e
1. Abbreviations
Term Definition
BOM Bill Of Material
BTS Base Transceiver Station
CAPEX Capital Expenditure
DPR Detailed Project Report
G2C Government to Citizen
G2G Government to Government
GB Giga Byte
GBM Ground Base Mast
GIS Geographical Information System
GoI Government of India
GoM Government of Maharashtra
ICT Information and Communication Technology
IP Internet Protocol
IT Information Technology
ITES Information Technology Enabled Service
Ltd. Limited
MB Megabits
Mbps Megabits per second
MoUD Ministry of Urban Development
NOC Network Operation Centre
O&M Operations and Maintenance
OFC Optical Fiber Cable
OPEX Operational Expenditure
PCMC Pimpri Chinchwad Municipal Corporation
PCSCL Pimpri Chinchwad Smart City Limited
PoP Point of Presence
PPP Public Private Partnership
RFP Request For Proposal
SI System Integrator
SITC Supply, installation, testing and commissioning
SLA Service Level Agreement
SPV Special Purpose Vehicle
TRAI Telecom Regulatory Authority of India
TSP Telecom Service Provider
Pimpri Chinchwad Smart City Limited Expression of Interest
5 | P a g e
INVITATION FOR BID (IFB)
Name & Address of the
Procuring Entity
Name: Pimpri Chinchwad Smart City Limited (PCSCL)
Address: 4th Floor, Pimpri Chinchwad Municipal Corporation
(PCMC) Main Building, Pimpri, Maharashtra – 411018
Tel: 020 – 67333333, 67331117
Fax: 020 - 27425600, 67330000
e-Mail ID: smartcity@pcmcindia.gov.in
Name & Address of the
Project Officer In-charge
Name: Nilkanth Poman
Designation: Joint Chief Executive Officer, PCSCL
Address: 4th Floor, Pimpri Chinchwad Municipal Corporation
(PCMC) Main Building, Pimpri, Maharashtra – 411018
Email: smartcity@pcmcindia.gov.in
Subject Matter of
Procurement
Expression of Interest (EoI) for Shortlisting of
a. System Integrators for SITC and O&M of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. on EPC Model
b. Concessionaires for SITC and O&M for Smart Poles, City Wi-Fi, Smart City Kiosk and Variable Message Display (VMD) etc. on revenue sharing model
Bid Procedure One Envelope / EoI Response Document (e-bid) through
https://www.pcmcindia.gov.in (eproc portal)
Websites for downloading
Bidding Document,
Corrigendum’s, Addendums
etc.
Websites: www.pcmcindia.gov.in &
http://www.smartcitypimprichinchwad.in
Period of Sale/download of
Bidding Document (Start/ End
Date)
Between 10-01-2018, 18:00 Hrs and 20-01-2018, 18:00 Hrs
Manner, Start/ End Date for
the submission of Bids
Manner: Online at eProc website (www.pcmcindia.gov.in)
Start Date: 10-01-2018. 18:00 Hrs
End Date: 20-01-2018, 18:00 Hrs
Date/ Time/ Place of Bid
Opening
Date: 21-01-2018,
Time: 16:00 Hrs
Place: Online at eProc website (www.pcmcindia.gov.in)
Sd \-
(Shravan Hardikar)
CEO & Director,
Pimpri Chinchwad Smart City Limited (PCSCL)
Pimpri Chinchwad Smart City Limited Expression of Interest
6 | P a g e
2. Disclaimer
This Expression of Interest (EoI) contains brief information about the Project and qualification
process for short listing of Applicants for RFP stage. This EoI is not an agreement or an offer by
the purchaser/authority to the applicants or any other person. The purpose of the document is to
provide the applicants with information to assist the formulation of their EoI application or
response to EoI Document (“the Application”).
While all efforts have been made to ensure the accuracy of information contained in this EoI
Document, this document does not purport to contain all the information required by the
Applicants. The Applicants may conduct their own independent assessment, site visit,
investigations and analysis and check the reliability, accuracy and completeness of the
information at their end and obtain independent advice from relevant sources as required before
submission of their EoI application. Pimpri Chinchwad Smart City Limited (PCSCL) and Pimpri
Chinchwad Municipal Corporation (PCMC), Government of Maharashtra or any of its employees
or advisors / representatives shall incur no liability under any law, statute, rules or regulations as
to the accuracy or completeness of the EoI Document.
PCSCL reserves the right to change any or all conditions/ information set in this EoI Document
by way of revision, deletion, updation or annulment through issuance of appropriate addendum
as the department may deem fit without assigning any reason thereof.
PCSCL reserves the right to accept or reject any or all applications without assigning any reasons
thereof. PCSCL will not entertain or be liable for any claim for costs and expenses in relation to
the preparation of the EoI applications to be submitted in terms of this Document.
Pimpri Chinchwad Smart City Limited Expression of Interest
7 | P a g e
3. About the EoI Document
The document carries all the necessary information regarding the project. This document also
serves the purpose of an indicative guide to the holistic approach for the implementation of various
ICT led Smart City Initiatives in the city.
The document begins with control sheet and subsequently describes the intent for the EoI
for shortlisting of System Integrators (SIs) and Concessionaires for the respective projects
as mentioned below, who will be further invited to submit technical and commercial
proposals:
o Project 1 – Supply, Installation, Testing & Commissioning and Operations &
Maintenance of Smart City field infrastructure comprising of Passive Fibre Network,
Poles and Gantries etc. under Engineering Procurement and Commissioning (EPC)
/ PPP mode (Revenue Sharing Model)
Project 2 - Study, design, engineer, supply, installation, testing & commissioning and
Operations & Maintenance of Smart Poles, City wide WiFi, Smart City Kiosk and
Variable Message Display (VMD) etc. on end-to-end basis in Design, Build, Finance,
Operate and Transfer (DBFOT) mode for a specified Concession Period on PPP
Mode (Revenue Sharing Model)
The geographical scope for the above mentioned Projects shall be Pimpri Chinchwad
municipal limits and adjoining areas basis suitability of the respective solution component.
The document further outlines the indicative process that shall be followed for on-boarding
of serious and qualified SIs & Concessionaires post the submission of Response to EoI
document followed by technical and commercial assessment through a RFP process.
The interested participants/entities may submit their EoI Application/Response to
EoI as per the details in this document, for either or both the projects. For each of
the project, a separate & specific set of EoI Application/Response to EoI is required
to be submitted.
The document provides a brief on the objective and intent of the purchaser, so as to enable
the participants to know about the project scope and city vision.
The document clearly defines the intent for which the document is released. The
categories/domains for applicants are defined under which the participants can apply and
the procedure is enlisted for the selection under these categories.
Stakeholders are clearly defined in the document for the various aspects of the process
and procedure. Various important key dates, venue details, contact information for
inquiries etc. are listed under the control sheet.
The pre-qualification criteria for respective project is enlisted in the subsequent sections
of this EoI document.
Pimpri Chinchwad Smart City Limited Expression of Interest
8 | P a g e
4. Intent
Ministry of Urban Development (MoUD), Government of India (GoI) has embarked on the Smart
Cities Mission programme which aims at bringing about urban transformation for cities covered
by this programme. The objective is to drive economic growth and improve the quality of life for
citizens by enabling local development and harnessing technology as a means to create smart
outcomes. Pimpri Chinchwad is one of the cities selected under the Smart City Mission of MoUD,
GoI.
To lay the foundation of a Smart City, Under Project 1, PCSCL intends to create passive
infrastructure components, either through EPC model or PPP (revenue sharing) model, like laying
of Optical Fibre based Network (City Network) and erection of Pole Infrastructure for mounting
IoT & Smart City devices across the city; Fibre Network is planned to connect all the PCMC offices
(Zone & Ward Offices), health & citizen facilitation centres, key areas like markets, religious
places, bus stops etc. whereas the Pole Infrastructure shall be setup at various traffic junctions,
key city places for hosting CCTV cameras, traffic detectors, variable message displays, public
address system, WiFi access points etc.
Under Project 2, PCSCL is looking for partners to work with it, in PPP model (on revenue sharing
basis), for study, design, engineer, supply, plan, construct, develop, install, commission, test,
deploy, support, maintain and operate the end-to-end Smart Pole, City Wide Wi-Fi, VMD and
Smart City Kiosk projects on Design, Build, Finance, Operate and Transfer (DBFOT) mode for a
specified Concession Period.
In reference to above, PCSCL intends to shortlist qualified applicants, for the respective projects,
and invites applicants to present their credentials and other details as part of their EoI response.
For both the projects, PCSCL hereby also invites additional/alternate suggestions from the
applicants for implementation and for partnership models for the aforementioned project’s solution
components and same shall be discussed during the pre-bid meeting pertaining to this EoI. The
applicants are required to suggest suitable model as part of its response to EoI and Technical
Presentation.
The interested participants are thereby invited to submit their responses in accordance to the
terms and conditions mentioned in this EoI document.
Key Objectives & Goals:
Project 1:
Create a scalable, robust, resilient, secure and long-lasting digital infrastructure that
interconnects citizens, government, business and communities and allows better data
management and control to offer richer application experiences.
OFC network shall serve as the backbone for all the connectivity requirements and ICT
led city initiatives planned or to be planned in next 20 years
To create a uniform Pole Infrastructure across the city for hosting various IoT & Smart City
devices like CCTV camera, traffic detectors, Wi-Fi access points etc. in a planned &
structured manner, so as to avoid repeated digging and infrastructure laying work in the
city.
Pimpri Chinchwad Smart City Limited Expression of Interest
9 | P a g e
Project 2:
Smart Pole:
Provide a Multi-function platform for hosting smart city elements like cellular telephony,
cameras, street lights, sensors, charging points etc. that blends easily into city aesthetics
City Wi-Fi:
To bridge the digital divide and to create a digitally connected ecosystem within the city
promoting economic development and increased access to digital inclusion for all
community member
Building wireless backbone that provides connectivity to smart city end devices for
providing improved municipal services
TO provision connectivity for city dwellers, tourists etc. on the move
Smart City Kiosk:
A Mobile/fixed Service Delivery based digital platform for city dwellers to interact with the
city administration on the move, engage with larger citizen group and get their participation
and feedback around services delivery.
Kiosk will act as digital interaction point for city services like city card recharge, mobility
ticketing, informative & transactional services to name a few.
Variable Message Display (VMD):
Real time information and communication display unit to apprise citizens on various City
centric information, traffic status & diversions, emergency related messages etc. with the
management & control function is centralized at City Operation Centre
In view of the above, PCSCL would shortlist SIs and Concessionaires for the respective projects
based on a pre-defined pre-qualification criteria as mentioned in the EoI document.
Pimpri Chinchwad Smart City Limited Expression of Interest
10 | P a g e
5. Control Sheet
Name of the EoI
Shortlisting of
c. System Integrators for SITC and O&M of Smart City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc. on EPC Model / PPP (revenue sharing) model
d. Concessionaires for SITC and O&M for Smart Poles, City
Wi-Fi, Smart City Kiosk and Variable Message Display
(VMD) etc. on revenue sharing model
Contact person of client Shri. Nilkanth Poman, Jt. CEO, PCSCL
Contact details of client
Pimpri Chinchwad Smart City Limited (PCSCL), 4th Floor, Pimpri Chinchwad Municipal Corporation (PCMC) Main Building, Pimpri, Maharashtra – 411018 Tel: 020 – 67333333, 67331117 Fax: 020 - 27425600, 67330000 e-Mail ID: smartcity@pcmcindia.gov.in
Date of start of issue of EoI January 10, 2018
Last Date and time for submission of pre-bid queries
Till 18:00 hrs on January 17, 2018
Date of Pre Bid Meeting 12:00 hrs on January 17, 2018 at PCMC Head Office, Pune - 411018
Last date for submission of EoI response
Till 18:00 hrs on January 20, 2018
Date of Technical Presentation
January 31, 2018 (Time shall be communicated later)
6. On-boarding of System Integrator & Concessionaire - Process
PCSCL intends to select a System Integrator for Project 1 and a Concessionaire for Project 2 for
providing end to end services. The process below broadly defines the overarching methodology
that will be used in order to select a SI and a Concessionaire for the respective projects through
a competitive bidding process among the qualified participants.
PCSCL has adopted a Two Stage bidding (collectively the Bidding Process); during the first stage
of Expression of Interest (EoI), prospective applicants/bidders having requisite capability for
undertaking the Scope of Work shall be shortlisted based on qualification criteria specified in the
EoI document. Only the participants qualified & shortlisted at EoI stage shall be invited for
Request for Proposal (RFP) stage.
Pimpri Chinchwad Smart City Limited Expression of Interest
11 | P a g e
6.1 Stage 1 – Expression of Interest
6.1.1 Purpose
Shortlisting of interested applicants i.e. SIs for Project 1 and Concessionaires for Project
2; who shall further participate in the respective projects RFP stage.
Understand from the industry on various possible partnership models for the successful
implementation of various solution components pertaining to Project 1 and Project 2.
Finalization of RFP document basis various inputs/suggestions from the interested
applicants regarding scope of work, partnership models, implementation models etc. The
same shall be published for competitive bidding among shortlisted applicants
6.1.2 Role of Applicant
Applicants are advised to study all instructions, forms, terms, requirements and other
information in the EoI document carefully.
Submission of bid shall be deemed to have been done after careful study and examination
of the EoI document with full understanding of its implications.
The response to this EoI should be full and complete in all respects. Failure to furnish all
information required by the EoI document or submission of a proposal not substantially
responsive to the EoI document in every respect will be at the applicant's risk and may
result in rejection of their response.
The applicant will have to qualify in its own category it wishes to participate. In order to
qualify, the applicant will have to comply with the qualification criteria in the respective
category.
As part of the EoI stage, the participating SIs and Concessionaire are invited for a Pre Bid
meeting to discuss on the overall implementation methodology, partnership models,
functional and technical requirements of the respective solution components. PCSCL
encourages applicants to participate in the pre-bid meeting; however, participation in pre-
bid meeting is not mandatory.
Applicant is expected to share its experience in similar projects – key learning &
challenges, proposed solution, recommendations etc. The applicant can use the Proforma
6 & 7 format to share its experience as part of its response to EoI document.
Further, each applicant shall be required to make a detailed presentation covering
following, but not limited to:
o Suggestions on suitable partnership models and revenue generating opportunities for
the implementation of the respective project
o Suggestions/recommendations regarding grouping of solution components and
implementation methodology
o Any other inputs deemed desired for the success of the project
Pimpri Chinchwad Smart City Limited Expression of Interest
12 | P a g e
6.1.3 Role of PCSCL
PCSCL will make all the necessary efforts in order to clarify any query received with regard
to information shared with the respective applicants. PCSCL would also consider, to the
extent possible, any additional information or data requested by the SI/Concessionaire
that might be helpful in executing the PCSCL’s Smart City Project.
PCSCL and its representative will evaluate the response submitted by each applicant in
order to determine whether they are complete and conforms to the EoI requirements.
The applicants complying with respective qualification criteria under which they have
applied along with fulfilling all the other requirements under the EoI document will be
declared qualified for next stage.
The qualified participants will be listed on the e-Tendering portal
(https://www.pcmcindia.gov.in). Thereafter, they will be communicated with further
instructions under the bidding process.
6.2 Stage 2 – Request for Proposal
6.2.1 Purpose
Selection of a SI and a Concessionaire for the SITC and O&M of respective projects.
6.2.2 Role of Applicant
SI and Concessionaire is expected to submit a structured and organized technical
proposal comprising of the detailed solution design, technology, product specifications
and bill of material based on the functional and operational requirements as mentioned in
the RFP. PCSCL shall provide an indicative Bill of Material as part of the RFP, however,
the qualified applicant will have to do their own due diligence and include all the items that
are required to meet the required SLAs and uptime as well as the functional and
operational requirements laid down in the RFP.
Post submission of the detailed architecture as part of the technical proposal, the SI /
Concessionaire will be required to present the proposed solution to the technical
committee formed by PCSCL for their review and understanding.
Along with the technical proposal the SI / Concessionaire shall submit their financial
proposal as per the requirements of the RFP. The applicant is expected to comply with all
the procedures that will laid as part of the RFP document & provide all required information
in accordance to RFP response requirements.
The applicant will be required to lead the presentation during the Technology and Solution
Evaluation.
Applicant is expected to share its Experience in Similar Projects – Learning on Issues,
Challenges, Solution proposed, and Client Recommendations etc. The applicant can use
the Proforma 6 & 7 format to share its experience.
6.2.3 Role of PCSCL
To issue the RFP and clarifications
Pimpri Chinchwad Smart City Limited Expression of Interest
13 | P a g e
PCSCL shall evaluate the technology solution in accordance with the pre-defined criteria
for the respective applicants.
Post completion of technical evaluation, the financial bids of the technically qualified
applicants shall be opened and evaluated.
The most responsive applicant as per the evaluation process laid down in the RFP shall
be selected for the award of LOI.
Notwithstanding anything contained in the published EoI & RFP, PCSCL reserves the right
to accept or reject any Proposal and to annul the Selection Process and reject all
Proposals, at any time without any liability or any obligation for such acceptance, rejection
or annulment, and without assigning any reasons thereof.
7. Project Background
Under Ministry of Urban Development,
Government of India (GoI) Smart Cities
Programme, Pimpri-Chinchwad Smart City
Limited (the “Authority”), a Special Purpose
Vehicle (SPV) for Pimpri-Chinchwad Smart
City Project has been established as a
company under the Indian Companies Act
2013. The Authority would receive funding
from Government of India (GoI) and
Government of Maharashtra (GoM) for the
development of smart city in Pimpri-
Chinchwad. The Authority is a government-
owned company with equal shareholding
from Pimpri-Chinchwad Municipal
Corporation and the state government. Pimpri-Chinchwad Map
With the objective to usher Technology-led Transformation through creation of State-owned
robust, reliable and sustainable ICT infrastructure which would help in transforming Pimpri
Chinchwad into a Safe and Smart Sustainable City. PCSCL has identified below mentioned
identified ICT led Smart City Initiatives:
• City Network Backbone (Optical Fibre Cabling)
• Citizen Access Wi-Fi
• City Kiosk
• City Surveillance along with Video Analytics
• Smart Water Management
• Smart Sewerage Management
• Intelligent Traffic Management including
o Adaptive Traffic Management System
o Automatic Number Plate Recognition System
o Red Light Violation Detection System
o eChallan
o Variable Message Display (VMD)
o Public Address System
Pimpri Chinchwad Smart City Limited Expression of Interest
14 | P a g e
• GIS enablement of Smart City assets
• Smart Poles
• Smart Parking
• Smart Light
• Smart Environment
• Smart Transport - Bus Information System
• Smart City Mobile App
• Command & Control Centre & City Operation Centre
8. Geographical Scope
The Pimpri Chinchwad city is located at the coordinates 18°37’07.04”N 73°48’13.43”E and is in
Pune District of Maharashtra. It is at 530 meters (1740 ft.) above mean sea level and is situated
about 20 km to the east of Sahyadri ranges that run North to South in the Lonavala – Khandala
section between Harishchandra Range and Mahadeo range. The total area covered by PCMC is
181 sq. km approx. geographically, the rock structure underneath is igneous (basalt) type and the
soil is Red Soil.
From the administration view point, PCMC is divided into 8 Zones which are further divided into
32 Wards, as mentioned below, the geographical scope of the implementation of Project 1 and
Project 2 shall be the limits of PCMC jurisdiction and nearby localities/area.
9. Scope of Work
9.1 Project 1
Supply, Installation, Testing & Commissioning and Operations & Maintenance of Smart
City field infrastructure comprising of Passive Fibre Network, Poles and Gantries etc.
under Engineering Procurement and Commissioning (EPC) Model / Public Private
Partnership Model (revenue sharing)
PCSCL intends to establish a dedicated network backbone that can support all the current
planned initiatives like Wi-Fi, Kiosk, Water Grid Management, Sewerage Management, Street
Light Management, Traffic Management, Smart Parking, City Surveillance, Environment, Solid
S. # Zone Wards
1. A Ward no: 10, 14, 15 & 19
2. B Ward no: 16, 17, 18 & 22
3. C Ward no: 2, 6, 8 & 9
4. D Ward no: 25, 26, 28 & 29
5. E Ward no: 3, 4, 5 & 7
6. F Ward no: 1, 11, 12, & 13
7. G Ward no: 21, 22, 24 & 27
8. H Ward no: 20, 30, 31 & 32
Pimpri Chinchwad Smart City Limited Expression of Interest
15 | P a g e
Waste Management etc. and having scalability to accommodate future city’s ICT led
transformation.
Considering critical network design parameters such as secure, reliable, scalable, manageable,
interoperable, capable and resilient to have end-to-end service oriented network delivery, it is
proposed that a secure optical fibre network backbone based service delivery network shall be
established across the city.
The network backbone is expected to provide a converged network, bringing together different
city management vertical solutions on a common network infrastructure for Pimpri-Chinchwad.
The converged network shall facilitate information exchange between resources and applications
across different domains. It will be an end-to-end open platform enabling services across the city.
An overarching OFC-based network is being planned as part of Pimpri-Chinchwad City initiative,
which forms the backbone for all the envisaged applications. The network architecture being
proposed will comply with the best practices and industry standards to ensure high availability,
scalability, manageability and security for the information, services and solutions being managed
on the network.
The designed network shall provide uninterrupted services across the Pimpri-Chinchwad City
connecting seamlessly with various stakeholders. With the capability to handle high bandwidth
applications with low latency, the network forms the pivot for ICT based Smart City interventions
in PCMC.
The various locations that is planned to be connected via OFC based City Network are, but not
limited to, PCMC Zonal offices, Head Office & Ward Offices, City Operation Centre (COC), other
city administration’s important buildings like hospitals, gardens, health Centre, field locations
which have IoT / Smart City devices. Optical fibre shall be laid primarily along the road network
comprising main city roads and street roads.
System Integrator Scope of Work:
Route Survey & Network Design Preparation: SI shall be required to undertake detailed
survey of various locations planned to be covered with OFC network and prepare the route
map & network design.
Procure, Supply, Installation & Commission of all the Passive Infrastructure: SI shall
be required to procure & supply all the passive components and accessories required for
laying of duct and blowing of fibre including duct pipes, jointers, couplers, fibre cable,
splicer, jointer etc. SI shall be responsible for laying of 3 ducts (indicative) using Horizontal
Directional Drilling (HDD) / Open Trenching (OT) Technique as per directions of PCSCL
and blowing of fiber (96/48 core) basis on the finalized route plan and appropriate network
topology to ensure adequate redundancy at each of the network node level. Indicative city
wide fiber network route length is estimated to be 750 km, across the city, which shall be
finalized after the detailed survey and route finalization activity,
Procure, Supply, Install & Commission Pole Infrastructure: SI shall be required to
erect various types of Pole Infrastructure in the city at the identified locations specific to
the solution component requirement:
o Approx. 600 Unipole with cantilevers for mounting CCTV cameras, traffic sensors, IoT
devices etc.
o Approx. 30 Unipoles without cantilever for mounting large Variable Message Display
(VMD)
Pimpri Chinchwad Smart City Limited Expression of Interest
16 | P a g e
o Approx. 30 Gantry structure across the road for mounting large digital display units
(VMD) and hoardings.
Reinstatement & Restoration: SI shall be responsible for performing the reinstatement
and restoration of the sites back to the previous/normal conditions as per the RFP
specifications at all the respective site locations.
Provide Operation & Maintenance Services for the Passive Infrastructure, OFC
Network and Pole Infrastructure, for a contract period from the date of
Commissioning of the system.
Note: All the active electronics like switch, UPS, power meter, power banks etc. at the centralized
as well as at field level shall be out of scope of the SI.
9.2 Project 2:
Study, design, engineer, supply, installation, testing & commissioning and Operations &
Management of Smart Poles, City wide WiFi, Smart City Kiosk and Variable Message
Display (VMD) etc. on end-to-end basis in Design, Build, Finance, Operate and Transfer
(DBFOT) mode for a specified Concession Period on revenue sharing Model.
1. Smart Pole:
With numerous IoT & Smart City devices, sensors etc. are required to be installed
across the city, PCSCL looking to adopt an approach focusing on optimization of City
Passive Infra and enable smart solutions on aesthetically designed city infra which
adapts to city’s terrain, space and theme in order to create uniformity across the city
and simultaneously providing a platform, for city administration, which is having strong
revenue generation potential from various mounted devices.
In view of this, Smart Pole has been conceptualized to act as a multi-function platform,
having flexibility of adding wide array of accessories, for hosting various IoT devices
and sensors like, but not limited to:
Camouflaged design for Telecoms equipment’s for 2G/3G/4G/5G/LTE and IoT
networks
CCTV Camera
WiFi Access Points
Smart Light & High Masts Lights
Traffic & whether sensors
Variable message display units
Electric Car Charging Facility
Solar panel
Speakers
Mobile charging board
Garbage cans
The design of the Smart Pole shall be such that it can host multiple equipment and
services. Below are the two variants of poles with internal power backup that are
planned to be developed:
12-15 meter Smart Pole
25-30 meter Smart Pole
Pimpri Chinchwad Smart City Limited Expression of Interest
17 | P a g e
Concessionaire shall be required to take the fibre network at the Smart Pole location,
last mile, from PCSCL on Rental Basis and shall also share the revenue earned by
selling services through Smart Pole Infrastructure with PCSCL on percentage basis
during the concessionaire period.
2. Smart Kiosk:
With the objective to provide efficient, effective and equitable services to its citizen, PCSCL
intends to deploy Smart City Kiosk Terminal at key locations across the city to provide various
informative, transactional, navigational services along with other G2C services like AAPLE
SARKAR, ticketing, grievance services, utility payment services etc.
Indicative layout and components of Smart City Kiosk:
3. City Wi-Fi
In order to create a digitally connected ecosystem across the city, PCSCL plans to implement
City wide WiFi services for its citizen to connect and interact with PCMC digitally. Various
strategic locations shall be equipped with City Wi-Fi services like government offices, gardens,
religious places, markets etc. which shall further promote the Mobile Service Platform based
delivery.
4. Variable Message Display (VMD)
PCSCL plans to deploy Variable Messaging Display (VMD) across the city for disseminating
various key public information and other real time information collected through smart sensors
like environmental sensor, parking sensors, traffic sensors etc. The VMD system shall be
Sr. No.
Component
1 Panic Button
2 Camera
3 Touchscreen
4 Speakers
5 Biometric Scanner
6 Keyboard
7 MIFARE Card Reader / Writer
8Credit card / debit card / NFC interface
9 QR code / Bar code interface
10 Currency Acceptor
11 Laser Printer
12 Thermal Printer
13Dropbox For grievance & Feedback
14 Phone Handset
3
2 1
6
9 8 7
12 10
13
PCMC Smart City Kiosk
5
44
13
14
11
Pimpri Chinchwad Smart City Limited Expression of Interest
18 | P a g e
controlled and managed centrally and through mobile application interface as well by the city
administrations having user rights.
It is planned to deploy standard size VMD across the city using Unipole & Gantry Structure,
further details on the size and specification of the VMD shall be provided in the RFP document.
Further, it is planned to monetize the VMD for revenue generation while offering fixed Air Time
for PCSCL for city related campaigns and information.
For the implementation of above referred Project 2 solutions i.e. Smart Pole, Smart City Kiosk,
VMD and City WiFi, PCSCL intends to enter into the revenue sharing Model with the
Concessionaire. The qualified Concessionaire shall bring the expertise to Design, Implement and
maintain the services during the contract period while leverage the significant commercial
potential each solution possesses in order to result in a win-win situation for the citizens,
government and businesses.
The concessionaire shall be responsible to design, implement and maintain above solutions on
(DBFOT) model, and provide services as per the requirement of the RFP while enabling multiple
digital services in revenue sharing mode with PCSCL.
Concessionaire Scope of Work:
Survey & Design Preparation: Concessionaire shall be required to undertake detailed
survey and prepare the structural/solutions designs of various locations pertaining to the
deployment of City WiFi, VMD, Smart Pole and Smart City Kiosk locations. PCSCL shall
share the list of locations for City WiFi, VMD and Smart City Kiosk while concessionaire
shall identify and finalize the locations of Smart Pole in consultation with PCSCL.
Finalization of Smart Poles Design: Concessionaire shall finalise the modular structural
design of the Smart Pole which shall be conducive for even worst weather conditions and
shall be responsible for getting the structural approval from the PCSCL nominated agency
at its own cost. Smart Pole aesthetics and placement of other IoT devices shall be finalized
in consultation with PCSCL.
Procure, Supply, Installation & Commissioning of Smart Pole, Smart City Kiosk,
VaMS and City Wi-Fi Infrastructure: Concessionaire shall be required to procure, supply
and commission of all the passive components required for Smart Pole, Kiosk, VMD &
WiFi solution commissioning like Access Points (approx. 700), Kiosk Terminals (approx.
210), Smart Poles (approx. 300), VMD (approx. 150) etc. as per the detailed Technical &
Functional Requirement Specifications which shall be specified in the RFP document.
Also, applicant shall be responsible for provisioning & managing the centralised IT Infra
like server, storage, security etc. at its own end and as per the RFP specifications.
Concessionaire shall also be responsible to procure, supply, install and manage all the
active devices/equipment’s like network switch, power meter, UPS, battery banks etc.
required for the operations of Telecom and other Smart City components that would be
installed on Smart Poles and provide Operations & Maintenance services during the
contract/concession period.
Pimpri Chinchwad Smart City Limited Expression of Interest
19 | P a g e
Design, Supply & Implement Smart Pole, Smart City Kiosk, VMD and City Wi-Fi
Solutions:
Concessionaire shall provision requisite centralised systems and applications like
Kiosk Management System, WiFi AAA Authentication and Wireless Controller, VMD
Management System etc. required for the commissioning of Smart Pole, Smart City
Kiosk, VMD and City Wi-Fi solutions as per the specifications of the RFP.
PCSCL shall also define the various services/applications it intends to host on the
Smart City Kiosk and interfaces required with the third party systems in the RFP
document.
Concessionaire shall be responsible for integrating the aforementioned system with
PCSCL Smart City Integrated Operation Platform (IOP) for seamless flow of
information between various devices and systems, thus enabling consolidated
dashboard for city administration.
Reinstatement & Restoration:
Concessionaire shall be responsible for performing the reinstatement and restoration of
the sites back to the previous/normal conditions as per the RFP specifications.
Provisioning of Internet Bandwidth:
Concessionaire shall be responsible for provisioning of Internet Bandwidth for City wide
WiFi and Smart City Kiosks solutions in line with the requirement of the RFP document.
Currently it is planned to provide unlimited City wide free Wi-Fi service to the citizens,
without time limit, at 2 Mbps speed for first 60 mins and thereafter downgraded to 1Mbps.
Concessionaire shall strictly adhere with all the licensing requirements, for provisioning of
Internet Connectivity, as per applicable laws & regulations.
Provide Operation & Maintenance Services for the Smart Pole, Smart City Kiosk and
City Wi-Fi Infrastructure & Systems during the contract period:
Concessionaire shall be responsible for providing Operations & Maintenance services for
all the supplied IT and Non IT Infrastructure and systems during the contract period for all
the aforementioned solution components.
Monetization & Revenue Sharing of Smart Poles, Smart City Kiosk, VMD and City
Wi-Fi –
Concessionaire shall device possible means of monetizing the aforementioned assets in
consultation with PCSCL on revenue sharing mode (percentage basis) or as specified in the
RFP document. However, applicants may submit various revenue sharing models as part of
its EoI response.
Smart Pole fibre termination, interconnect links and space shall be leased from PSSCL
on fixed rental basis. The Concessionaire is free to further sub-lease Smart Pole Infra,
in revenue sharing model with PCSCL, to multiple service providers in consultation with
PCSCL.
Pimpri Chinchwad Smart City Limited Expression of Interest
20 | P a g e
As part of EoI response, concessionaire to suggest on managing the City wide WiFi
Internet bandwidth operational cost during the period of contract
Note:
PCSCL shall provide the fibre connectivity on rent at each of the Smart Pole, Smart City Kiosk,
VMD and City WiFi site, however, concessionaire has to provision the active electronics equipment
along with enclosure at its own end.
All the above mentioned quantities with respect to various solution components of Project 1 &
Project 2 are indicative and may undergo a change during the project implementation phase.
As part of its EoI response, Concessionaire to provide the indicative description on Smart Pole
location numbers & place, kind of fibre core requirement and other infra requirement as per the
provided template.
PCSCL will release separate RFP for Project 1 and Project 2.
10. Instruction to Participants
10.1 Issue of EoI document
EoI document can be downloaded from the website https://www.pcmcindia.gov.in
10.2 Pre-bid Meeting & Clarifications
i. Any clarification regarding the EoI and any other items related to this project can be
submitted to PCSCL as per the submission mode and timelines mentioned in the EoI
Control sheet.
ii. The Nodal Officer notified by the PCSCL will endeavor to provide timely response to all
queries. However, Purchaser makes no representation or warranty as to the
completeness or accuracy of any response made in good faith.
iii. At any time prior to the last date for receipt of bids, PCSCL may, for any reason, whether
at its own initiative or in response to a clarification requested by a prospective Applicant,
modify the EoI document by issuing a corrigendum.
iv. The corrigendum (if any) & clarifications to the queries from all Applicants will be posted
on http://www.pcmcindia.gov.in & http://www.smartcitypimprichinchwad.gov.in or may be
emailed to all participants of the pre-bid meeting.
v. Any such corrigendum shall be deemed to be incorporated into this EoI.
vi. In order to provide prospective Applicants reasonable time in which to take the
corrigendum into account in preparation of their bids, PCSCL may, at its discretion, extend
the last date for the receipt of EoI response.
vii. It is necessary that the pre-bid queries must be submitted in excel sheet format, along with
name and details of the organization submitting the queries as mentioned in the Proforma
9 of this EoI document.
10.3 EoI preparation cost
The Applicant shall bear all costs associated with the preparation and submission of the response
to the EoI. PCSCL, in any case, will not be responsible and liable for sub-costs, regardless of the
Pimpri Chinchwad Smart City Limited Expression of Interest
21 | P a g e
conduct or outcome of the EoI process. All papers/ documents submitted with the EoI are neither
returnable nor claimable
10.4 EoI Application/Response for Either/Both Projects
The interested applicants/entities may submit their EoI Application/Response to EoI as per the
details in this document, for either or both the projects. For each of the project, a separate &
specific set of EoI Application/Response to EoI is required to be submitted.
10.5 Right to accept and reject any or all the EoI
Notwithstanding anything contained in this EoI Document, PCSCL reserves the right to accept or
reject any EoI response and to annul the qualification process and reject all the EoI’s, at any time
without any liability or any obligation for such acceptance, rejection or annulment, without
assigning any reason.
PCSCL reserves the right to reject any EoI if:
At any time it is found that a material misrepresentation is made by the applicant, or
The applicant does not respond promptly and satisfactorily to the requests for
supplementary information required for the evaluation of the EoI.
The misrepresentation / improper response may lead to the disqualification of the
Applicant.
11. Preparation and submission of EoI document
11.1 Language
All information in the EoI must be in English. Information in any other language, if not
accompanied by an authenticated translation in English, shall not be considered. In the event of
any discrepancy between the offer in a language other than English and its English translation,
the English translation shall prevail.
11.2 Clarifications on EoI documents
Applicants requiring any clarification on the EoI may notify PCSCL in writing through an e-mail as
per the dates and details provided in Control Sheet.
PCSCL shall endeavor to respond to the questions raised or clarifications sought by the
Applicants. However, PCSCL reserves the right not to respond to any question or provide any
clarification, in its sole discretion, and nothing in this Clause shall be taken or read as compelling
or requiring the Authority to respond to any question or to provide any clarification.
PCSCL may also on its own motion, if deemed necessary, issue interpretations and clarifications
to all Applicants. All clarifications and interpretations issued by PCSCL shall be deemed to be
part of the EoI. Verbal clarifications and information given by PCSCL or its employees or
representatives shall not in any way or manner be binding on PCSCL.
11.3 Amendment of EoI document
Before the deadline for submission of EoI, the EoI document may be modified by the PCSCL by
issue of Addendum/ Corrigendum.
Pimpri Chinchwad Smart City Limited Expression of Interest
22 | P a g e
Any Addendum / Corrigendum issued shall be part of the EoI Document and it will be publicized
through the e-Tendering portal.
To give prospective Applicants reasonable time in which to take the Addendum/ Corrigendum into
account in preparing their EoI, extension of the deadline for submission of EoIs may be given as
considered necessary by PCSCL.
11.4 Alternative EoI documents by the Applicants
The applicants shall submit response which comply strictly with the requirements of the EoI
document. Alternatives or any modifications shall render the response invalid.
11.5 Submission of EoI Document
Applicant shall submit a digitally signed, encrypted and complete response to EoI document
comprising the documents and forms in accordance with e-Tendering Portal guidelines. The
submission has to be done electronically through the website and in accordance with the
procedures specified in the document. Proposals submitted by any other means will be rejected.
Applicant’s organization should be aware that the electronic procurement system does not allow
for any interlineations, erasures, or overwriting. Any modifications or revisions to the response
shall be done in accordance with e-Tendering portal guidelines.
The response or its modifications must be uploaded on the portal no later than the deadline
indicated in the Control Sheet, or any extension to this deadline. The electronic system will not
accept any Proposal or its modification for uploading after the deadline.
Once the response is uploaded on the portal, the system will generate a unique identification
number with the stamped submission time. The unique identification number with the time stamp
represents an acknowledgement of the EoI submission. Any other system’s functionality
requirements are specified in the Control Sheet.
11.6 Authority to Sign
An authorized representative of the applicant’s organization shall digitally sign the submission
letters, in the required format, as part of response to EoI document along with organization’s
Board Resolution in the name of the authorized signatory. In case of Power of Attorney is in favor
of authorized signatory, applicant shall submit the Board Resolution in favor of a person who has
further given that Power of Attorney to the authorized signatory.
11.7 Items to be kept in mind while furnishing details
While filling in the Information, following should be kept in mind
There shall be no additions or alterations except those to comply with the instructions
issued by PCSCL or as necessary to correct errors, if any, made by the Applicants.
Conditional EoI will be rejected
11.8 Confidentiality
All documents issued and information given to the Applicant shall be listed as Confidential.
Information relating to the examination, clarification, evaluation and recommendation for the
short-listed Applicants shall not be disclosed to any person not officially concerned with the
process.
Pimpri Chinchwad Smart City Limited Expression of Interest
23 | P a g e
11.9 EoI due date
EoI response must be submitted by the applicant at the time and date as mentioned in the control
sheet.
PCSCL may extend the deadline for submission of EoI response by issuing an amendment in
writing/notification in which case all rights and obligations of PCSCL and the Applicant previously
subject to the original deadline will be subject to new deadline.
11.10 Late/ Delayed EoI response
Any response submission after the specified date and time of receipt will not be allowed on e-
Tendering portal.
11.11 Modification/ Substitution/ Withdrawal of response
The Applicant will not be allowed to modify, substitute or withdraw its response to EoI after expiry
of the deadline for receipt of the EoI response.
11.12 Evaluation
For short listing process, PCSCL will determine whether each EoI document is responsive to the
requirements of the EoI Document. The EoI response shall be considered responsive if it contains
all the information, documents in formats specified in this EoI Document as per appended
annexures.
PCSCL reserves the right to reject any EoI response which is non-responsive and no request for
alteration, modification, substitution or withdrawal shall be entertained by PCSCL in respect of
such EoI response and such decision of PCSCL in this regard shall be binding on all applicants.
11.13 Clarifications Sought by PCSCL
To assist in the process of evaluation of EoI response, PCSCL may, at its sole discretion, ask any
Applicant for clarification on its EoI response. The request for clarification and the response shall
be in writing over email. No change in the substance of the EoI would be permitted by way of
such clarifications.
11.14 Notifications
PCSCL will notify the applicants for making presentation
The shortlisted applicants would receive RFP from PCSCL for next stage of evaluation
11.15 Inspection of site by the Applicants
Applicants are advised to inspect and examine the site and its surroundings and satisfy
themselves before submitting their EoI response as to the nature of the ground and sub-soil (as
far as is practicable), the form and nature of the site, the means of access to the site, the
accommodation they may require and in general shall themselves obtain all necessary
information as to risks, contingencies and other circumstances which may influence or affect their
intent to participate in RFP process. An Applicant shall be deemed to have full knowledge of the
site whether they inspect it or not and no extra charges consequent on any misunderstanding or
otherwise shall be allowed. Submission of an EoI response by an Applicant implies that he/she
has read this notice/ document and has made themselves aware of the scope and specifications
Pimpri Chinchwad Smart City Limited Expression of Interest
24 | P a g e
of the Project to be done and local conditions/ other factors having a bearing on the execution of
the Project.
12. Qualification Criteria
Interested Applicants should qualify all the below mentioned criteria.
12.1 Qualification Criteria for shortlisting of System Integrator for Project 1:
S.No Criteria Details Documents to be
Submitted
1. Legal Entity
The applicant shall be an entity registered in
India under the Companies Act 1956 / 2013
or /LLP registered under LLP Act 2008 or
subsequent amendments thereto. The entity
should have been in operational existence
for last three years.
EoI Application/response is to be submitted
by individual entities and consortiums are not
allowed at this stage
Certificate of
incorporation /
Partnership deed
GST Registration
Certificate
Certificate of
commencement of
business (if
applicable)
2.
Board Resolution /
Power of Attorney
in favour of
authorised
signatory
A Board Resolution or Power of Attorney in
the name of the person executing the bid,
authorizing the signatory to commit the
Applicant
Board Resolution;
OR
Power of Attorney with
appropriate supporting
documents as per the
format of this EoI
document
3. Financials
The applicant should have an average
annual turnover of at least INR 500 Cr. from
provision of Telecom Infrastructure / Fibre
cable Infra supply and services (fibre cable
network implementation including trenching,
ducting, cable laying, termination, other
requisite activities and O&M of that network)
in last three financial years, i.e FY 14-15; FY
15-16 , FY 16-17.
Extracts from the audited
balance sheet and profit &
loss;
OR
Certificate from the
statutory auditor
4. Networth
The applicant should have positive net worth
as per the audited consolidated financial
statements in each of the last 3 financial
years (FY 14-15; FY 15-16, FY 16-17).
Certificate from the
statutory auditor
5. Technical
Capability
The applicant should have relevant
experience related to provisioning of
Telecom Infrastructure / Fibre cable supply
and services (fibre cable network
implementation including trenching, ducting,
cable laying, termination, other requisite
Certified copy of the
relevant Work Order(s)
and satisfactory
implementation
completion & satisfactory
services completion
Pimpri Chinchwad Smart City Limited Expression of Interest
25 | P a g e
S.No Criteria Details Documents to be
Submitted
activities and O&M of that network) in last
three financial years, i.e FY 14-15; FY 15-
16, FY 16-17.
One project of value not less than INR
100 Cr
OR
Two projects each having value not less
than INR 80 Cr
OR
Three projects each having value not
less than INR 50 Cr
The quoted project should be completed and
shall be in operations for last two years at the
time of submission of EoI response.
certificate(s) (on the
letterhead of the company
issuing the certificate);
OR
Work Orders + Self
certificate of completion
(Certified by the statutory
auditor);
6. Certifications
The applicant should possess below
mentioned certification which are valid at the
time of bidding:
ISO 9001:2008/TL 9000 certification
ISO 20000:2011 for IT Service
Management
The bidder shall possess all the licenses
and shall comply with all the rules of the
country that are required to provide telecom
infrastructure and services throughout the
period of contract.
Copy of Valid
Certificate(s) issued
by competent
authority
Undertaking that these
certifications shall be
kept valid during the
EoI & RFP process
and thereafter, in case
of award of order, for
the entire project
duration
7. Self - Declaration
on Non Blacklisting
The applicant should not have been
blacklisted by any Govt. entity or any PSU in
India as on the date of bid submission
As per the Proforma 4 of
this EoI document and to
be counter signed by
Applicant’s Country Head
or the Company
Secretary
8. Manpower
Strength
The applicant should have at least 1000
resources on payroll of the applicant’s
organization at the time of submission of EoI
response
Certificate from the
Company Secretary
Note:
The applicant shall comply with all the prevalent regulations and norms of competent authority in
order to execute the defined scope of work during the contract period.
Pimpri Chinchwad Smart City Limited Expression of Interest
26 | P a g e
12.2 Qualification Criteria for shortlisting of Concessionaire for Project 2:
S.No Criteria Details Documents to be
Submitted
1. Legal Entity
The Sole applicant or each of the
members of the consortium, in case of
consortium should be an entity registered
in India under the Companies Act 1956 /
2013 or /LLP registered under LLP Act
2008 or subsequent amendments
thereto.
The entity should have been in
operational existence for last three years.
Certificate of
incorporation /
Partnership deed
GST Registration
Certificate
Certificate of
commencement of
business (if applicable)
2.
Board Resolution /
Power of Attorney
in favour of
authorised
signatory
A Board Resolution or Power of Attorney
in the name of the person executing the
bid, authorizing the signatory to commit
the Applicant.
This is applicable to the sole applicant or
each of the members of the consortium,
in case of consortium.
Board Resolution;
OR
Power of Attorney with
appropriate supporting
documents as per the format
of this EoI document
3. Consortium
In the event of a consortium, one of the
applicant shall be designated as a "Lead
Partner/ Applicant". Consortium is
allowed with up to 3 consortium members
including the Lead Applicant. The lead
applicant should have majority stake in
the consortium which may be an
incorporated or non-incorporated JV.
In case of consortium, the
applicants shall submit a
power of attorney in favour of
the lead applicant clearly
mentioning their association
for the project and nominating
the Lead applicant to
participate in the bid. The
same shall be signed by the
authorized signatory of all the
consortium members.
4. Financials
The sole applicant or any member of
consortium, in case of consortium, should
have an annual turnover of at least INR
1000 Cr. from providing Shared Telecom
Towers Services to Telecom Operators in
last three financial years, i.e FY 14-15;
FY 15-16 , FY 16-17.
Extracts from the audited
balance sheet and profit &
loss;
OR
Certificate from the statutory
auditor
5. Networth
The Sole applicant or each of the
members of the consortium, in case of
consortium, should have positive net
worth as per the audited consolidated
financial statements in each of the last 3
financial years (FY 14-15; FY 15-16, FY
16-17).
Certificate from the statutory
auditor
6. Technical
Capability
The sole applicant or any member of the
consortium, in case of consortium, should
have a relevant experience of:
Certified copy of the relevant
Work Order(s) and
satisfactory implementation
Pimpri Chinchwad Smart City Limited Expression of Interest
27 | P a g e
S.No Criteria Details Documents to be
Submitted
Supply, Installation, Commissioning
and Operations & Maintenance
Services for Smart Poles / Telecom
Tower / BTS / GBM(s) Infrastructure &
services in last 3 years i.e FY 13-14,
FY 14-15, FY 15-16, FY 16-17 and
currently having at least 5000 such
Smart Poles / Telecom Tower / BTS /
GBM(s) operational, as on date of
submission of EoI, with minimum
operational annual revenue of 200 cr.
And
Project experience of Supply,
Installation, Commissioning and
Operations & Maintenance Services,
for any one of the below mentioned
“specific business area”, which is either
completed or ongoing in last 5 years i.e
FY 12-13, FY 13-14, FY 14-15, FY 15-
16, FY 16-17.
Specific business area:
1. WiFi Infrastructure & services
with at least 200 access points
2. City Kiosk Infrastructure &
services with at least 50 kiosks
3. Variable Message Display
Infrastructure & services with at
least 50 displays
completion/in progress &
satisfactory services
completion/in progress
certificate(s) (on the
letterhead of the company
issuing the certificate);
OR
Work Orders + Self certificate
of completion with required
details (Certified by the
statutory auditor);
4. Certifications
The Sole applicant or any member of the
consortium, in case of consortium, should
possess below mentioned certification
which are valid at the time of bidding:
ISO 9001:2008/TL 9000 certification
ISO 20000:2011 for IT Service
Management
The bidder shall possess all the licenses
and shall comply with all the rules of the
country that are required to provide
telecom infrastructure and services
throughout the period of contract.
Copy of Valid
Certificate(s) issued by
competent authority
Undertaking that these
certifications shall be kept
valid during the EoI &
RFP process and
thereafter, in case of
award of order, for the
entire project duration
Pimpri Chinchwad Smart City Limited Expression of Interest
28 | P a g e
S.No Criteria Details Documents to be
Submitted
5. Self - Declaration
on Non Blacklisting
The Sole applicant or each of the
members of the consortium, in case of
consortium should not have been
blacklisted by any Govt. entity or any PSU
in India as on the date of bid submission
As per the Proforma 4 of this
EoI document and to be
counter signed by Applicant’s
Country Head or the
Company Secretary
6. Manpower
Strength
The Sole applicant or any member of the
consortium, in case of consortium, should
have at least 1000 resources on payroll of
the applicant’s organization at the time of
submission of EoI response
Certificate from the Company
Secretary
Note:
The applicant shall comply with all the prevalent regulations and norms of competent authority in
order to execute the defined scope of work during the contract period.
13. Proformas
All the applicants should submit their bids in the attached formats only.
13.1 Proforma 1: Cover Letter
[On the Letterhead of the Applicant]
To,
The Chief Executive Officer (CEO),
Pimpri Chinchwad Smart City Limited (PCSCL),
Pimpri Chinchwad Municipal Corporation Main Building, Mumbai-Pune Road,
Pimpri, Pune, Maharashtra - 411018
Subject:
Dear Sir,
Having examined the EoI Document, the receipt of which is hereby duly acknowledged, we, the
undersigned, offer to this EOI and to meet such requirements & provide such services as are set
out in the EoI.
We hereby attach the response as per the requirements of the EoI document.
We undertake, if our response to EoI is accepted, to adhere to the requirements put forward in
the EoI or such adjusted requirements as may subsequently be mutually agreed between us and
PCSCL or its appointed representatives. If our EoI is accepted, we will participate in the
succeeding stages as per the requirement set out in the EoI document.
Pimpri Chinchwad Smart City Limited Expression of Interest
29 | P a g e
We agree that you are not bound to accept the lowest or any Bid Response you may receive. We
also agree that you reserve the right in absolute sense to reject all or any of the products/ services
specified in the Bid Response or any/all bids without assigning any reason whatsoever.
It is hereby confirmed that I/We are entitled to act on behalf of our corporation/company
/firm/organization and empowered to sign this document as well as such other documents which
may be required in this connection.
We also certify that the period of validity of bids is 180 days from the last date of submission of proposal.
Dated this …………………………. Day of …………………..2018
(Signature) (In the capacity of)
Duly authorized to sign the Bid Response for and on behalf of:
……………………………………… ……………………………………………….
(Name and address of the Applicant) Seal/Stamp of Applicant
13.2 Proforma 2: Firm Details
[On the Letterhead of the Applicant]
i. Details of the Firm/ Applicant
Name of Firm/ Applicant: _____________ __________________________
Address: ___________________________________________________
Tel No. (with code): ________________________________________
Contact person: ____________________________________________
Name and Designation: _____________________________________
Address, Telephone No. and Email address: ____________________
ii. Type of Company (Public Limited/ Private Limited) : [with supporting]
iii. Date of incorporation with documentary evidence (or equivalent certificate):
iv. Registration detail of firm with documentary evidence (or equivalent certificate):
v. Service tax registration number and copy of the last return filed (or equivalent certificate):
[with supporting]
vi. Brief description of the firm and organization structure and business.
On Behalf of (Name of the Applicant)
Pimpri Chinchwad Smart City Limited Expression of Interest
30 | P a g e
________________________________
Signature of the Authorized Person
Name:
Designation:
Pimpri Chinchwad Smart City Limited Expression of Interest
31 | P a g e
13.3 Proforma 3: Detailed experience format
Project Experience References
[Formats to be filled for each reference experience / project individually along with
verifiable documentary proof]
Please add as many as required to show case the required work experience along with the order
values to add up to the requirements
Name of the Work & Location
Client's Name and Complete
Address
Scope of work carried out by
the Applicant
Contract Value for the
Applicant (in INR)
Contract value of whole
project (in INR)
Date of Start
Date of Completion
Note:
In support of having completed above works attach self-attested copies of the completion
certificate from client indicating the name of work, the description of work done by the Applicant,
date of start, date of completion (contractual & actual), value of contract as awarded and as
executed by the Applicant and value of material supplied free by the client and escalation amount.
If a work carried out as a Partner in the Joint Venture is included in this Proforma, details of
Contract Value should be furnished including information on the extent of Financial participation
by the Partner in that work. The proportionate share of the Partner will only be taken into account
for assessment of work experience on similar works.
Pimpri Chinchwad Smart City Limited Expression of Interest
32 | P a g e
13.4 Proforma 4: Self Declaration by Applicant
[On the Letterhead of the Applicant]
To,
{Procuring entity},
In response to the EoI Ref. No. _____________________________ dated ___________ for
{Project Title}, as an Authorized Signatory of ____________________________________, I/ We
hereby declare that presently our Company/ firm _________________, at the time of bidding,: -
a) possess the necessary professional, technical, financial and managerial resources and
competence required by the Bidding Document issued by the Procuring Entity;
b) is having unblemished record and is not declared ineligible for corrupt & fraudulent
practices either indefinitely or for a particular period of time by any State/ Central
government/ PSU/ UT.
c) does not have any debarment by any other procuring entity
d) is not insolvent in receivership, bankrupt or being wound up, not have its affairs
administered by a court or a judicial officer, not have its business activities suspended
and is not the subject of legal proceedings for any of the foregoing reasons;
e) does not have, and our directors and officers not have been convicted of any criminal
offence related to their professional conduct or the making of false statements or
misrepresentations as to their qualifications to enter into a procurement contract within
a period of three years preceding the commencement of the procurement process, or
not have been otherwise disqualified pursuant to debarment proceedings;
f) will comply with the code of integrity and all the prevalent regulations and norms of the
competent authority in order to execute the defined scope of work during the contract
period.
If this declaration is found to be incorrect then without prejudice to any other action that may be
taken as per the provisions of the applicable Act and Rules thereto prescribed by GoM, my/ our
bid, to the extent accepted, may be cancelled.
Thanking you,
Name of the Applicant: -
Authorised Signatory: -
Seal of the Organization: -
Date:
Place:
Pimpri Chinchwad Smart City Limited Expression of Interest
33 | P a g e
13.5 Proforma 5: Power of Attorney
FORMAT FOR POWER OF ATTORNEY TO AUTHORIZE SIGNATORY
POWER OF ATTORNEY
[To be executed on non-judicial stamp paper of the appropriate value in accordance with relevant
Stamp Act. The stamp paper to be in the name of the company who is issuing the power of
attorney.]
We, M/s.______ (name of the firm/company with address of the registered office) hereby
constitute, appoint and authorise Mr./Ms.______ (Name and residential address) who is presently
employed with us and holding the position of ______, as our Attorney to do in our name and our
behalf all or any of the acts, deeds or things necessary or incidental to our EoI for the Project
_____ (name of the Project), including signing and submission of the EoI, participating in the
meetings, responding to queries, submission of information/ documents and generally to
represent us in all the dealings with Client or any other Government Agency or any person, in
connection with the works until culmination of the process of bidding till the Project Agreement is
entered into with ____________ (Client) and thereafter till the expiry of the Project Agreement.
We hereby agree to ratify all acts, deeds and things lawfully done by our said Attorney pursuant
to this power of attorney and that all acts, deeds and things done by our aforesaid Attorney shall
and shall always be deemed to have been done by us.
(Signature and Name of authorized signatory)
___________
(Signature and Name in block letters of all the remaining partners of the firm Signatory for the
Company)
Seal of firm Company
Witness 1: Witness 2:
Notes:
To be executed by all the members individually.
The Mode of execution of the power of attorney should be in accordance with the procedure, if
any laid down by the applicable law and the charter documents of the executant(s) and when it is
so required the same should be under common seal affixed in accordance with the required
procedure.
Pimpri Chinchwad Smart City Limited Expression of Interest
34 | P a g e
13.6 Proforma 6: Suggestions from Applicant
Name of Applicant: _______________________________________________________
Category: _______________________________ Date: __________________
Project 1:
13.6.1 What would be most suitable Network Topology based on your understanding of
the Project 1 requirements?
13.6.2 What are the suggested/recommended Partnership Models (revenue sharing) for
the implementation of Project 1
13.6.3 What are the probable Monetization Opportunities with respect to Solution
Components of Project 1
Pimpri Chinchwad Smart City Limited Expression of Interest
35 | P a g e
Project 2:
13.6.4 Please furnish below mentioned details and any other details which shall be critical
in estimating the requirement of IT & non IT Infra & System requirement at Smart
Pole
Applicant is required to furnish details on the below mentioned points:
No. of locations for Smart Pole:
Types of location for Smart Pole deployment:
Types and size of Pole Infra:
Fibre core capacity (no. of cores, ribbon size, type of fibre, type of duct etc.) required at
Smart Pole for operationalization:
Type of services that can be hosted at the Smart Pole:
Internet/intranet bandwidth requirement at Smart Pole:
Any other details:
13.6.5 What are the suggested/recommended Partnership Models (revenue sharing) for
the implementation of Project 2
13.6.6 What are the probable Monetization Opportunities with respect to Solution
Components of Project 2
Pimpri Chinchwad Smart City Limited Expression of Interest
36 | P a g e
13.7 Proforma 7: Applicant’s Experience & Learnings highlighting key issues &
challenges encountered
13.7.1 Project 1
13.7.2 Project 2
Pimpri Chinchwad Smart City Limited Expression of Interest
37 | P a g e
13.8 Proforma 8: Applicant’s Suggestions & Recommendations
13.8.1 Project 1
13.8.2 Project 2
Pimpri Chinchwad Smart City Limited Expression of Interest
38 | P a g e
13.9 Proforma 9: Pre Bid Queries Format
Name of Person(s) Representing the Company/ Firm:
Name of Person Designation Email-ID(s) Tel. Nos. & Fax Nos.
S. No EOI Document Reference (s)
(Page Number and Section
Number)
Content of EOI
Requiring Clarification
Points of
Clarification
1.
2.
3.
4.
5.