Physical Installation Symmetra LX 2.1 Physical ...

Post on 08-Jan-2022

11 views 0 download

Transcript of Physical Installation Symmetra LX 2.1 Physical ...

Symmetra LXTower UPS

Remove the door.

Grab onto the door at the tabs , gently pull forward torelease the top of the door from the UPS frame, lift andremove.

Remove the bolts and shipping brackets securing the unit tothe pallet.

Retain the bolts and shipping brackets if reusing them to boltthe unit to the floor (see Step 3).

Unpack Equipment

Remove Door and Shipping Brackets

1

2

Remove the straps and open the cardboard box.

Remove the foam partition and ramps .

Remove the cardboard box from the pallet.

Read, understand and follow ALL safety instructionscontained in the

Failure to follow safetyinstructions and warnings could result in equipment damage,serious injury, or death.

Symmetra LX Safety Instructions andGeneral Information Guide.

®

Electrical

Hazard

The use of a cart or forklift may aid in transporting thepallet to the installation site.

Note

!

1.1

1.2

1.3

2.1

2.2

Symmetra LXPhysical Installation Guide

Tower UPS

®

For use with Symmetra LX UPS Models:

200 V, 4 16 kVA208/240 V, 4 16 kVA

220/230/240 V, 4 16 kVA

200 V, 4 8 kVA208/240 V, 4 8 kVA

220/230/240 V, 4 8 kVA

Important Safety and Installation Instructions

Symmetra LX is a scalable, redundant UPS for data centers and highavailability applications. Install the UPS as shown in this guide.

Your configuration may include the optional Symmetra LX Extended RunCabinet.

See and retain the product documentation shipped with your system forother important installation, operation, and maintenance instructions.

Illustrations are representative. Your Symmetra LX configuration, includingcomponents and optional APC equipment, may be different from the modelsshown in this guide.

Entire contents copyright 2005 by American Power Conversion Corporation.All rights reserved. Reproduction in whole or in part without permission isprohibited.

APC, the APC logo, PowerChute, InfraStruXure, Smart-UPS and Symmetraare registered trademarks of American Power Conversion Corporation. Allother trademarks are the property of their respective owners.

990-1545A-001, 05/2005

Physical Installation

!Remove the equipment from the pallet.

Ensure that the mounting stabilizers are in the upposition.

Attach the ramp to the pallet. Secure the ramp metal

brackets in the cutouts on the pallet.

With two people, one on either side of the unit, firmly holdthe front and rear of the unit. Carefully push the unit ontothe ramp, and to the floor.

Move equipment to the installation site.

Lower the mounting stabilizers to the floor to secure the unit.

Optional Seismic Anchoring: The unit may be anchored by

reattaching the four shipping brackets and bolting these tothe floor.

Install Battery Modules, If Applicable5

Install battery modules in the lowest emptyapplicable bays for your configuration. Installremaining modules from the bottom upward.

Note

4Transport the UPS to the Installation Site3

Caution Caution

Two people are required to move the UPS due to itsweight.

The mounting stabilizers should remain up until theUPS is off of the ramps.

Battery modules are heavy. Two people are requiredto handle a battery module due to its weight.

Install power modules in the appropriate bay locations for yourconfiguration.

Slide the module into the frame until the front of the

module is fully seated behind the safety catch .

Slide the latch up and tighten the captive screw .

Install Power Modules, If Applicable

3.1

3.23.3

4.1

4.2

!Note

� UBC calculations require a 3/8” diameter Truboltwedge anchor, embedded 3” into a concrete slab.

Refer to appropriate codes for specific requirementsthat would apply to this particular installation.�

3.4

P

B

B

2

2

B

B

2

2

B

B

2

2

B 2 B 2 B 2

B

B

1

1

B

B

1

1

Determine battery orientation. Each battery module will be

Installed in one of two orientations, B or B . Refer to

below.

For B1 orientation, position battery module with handles

on the top and right side of the module .

For B2 orientation, position the battery module with

handles on the top and left side of the module .

Slide the battery into the battery bay until the front of the

battery is behind the safety catch .

Check that each battery module is in the connectedposition. Use a coin to turn the battery switch

counterclockwise to the ON position .

1 2

5.1

5.2

5.3

P

P

P

P