Post on 26-Jul-2020
North East Coastal Group 15th February 2019
Next Generation Supplier Arrangement (NGSA)
• Through NGSA, we are transforming the way we work with
suppliers and modernising our approach
• Current WEM framework is coming to a close
• New Collaborative Delivery Framework (schemes £250k to
£50m) and specialist frameworks
• 6 Collaborative delivery teams nationally, each team
will include Environment Agency and delivery partner
staff
• There will be a separately appointed consultant and
contractor in each team
• Tender process is being finalised and the outcome is
due in March 2019
• RMA’s will be able to use the Framework – if
required – separate details to be issued
Combined model
Lower value projects
Substantial programme of medium value
projects
Larger or more complex projects
Generally, above
£50 million in
value
Usually less than
£0.25 million,
through other
operational
framework
arrangements
Through 6
geographic hubs
via a
Collaborative
Delivery
Framework (CDF)
4
Client support:
• Technical client support • Technical review of higher risk project proposals
• Client safety support
• Other specialist engineering and environmental
• Cost and carbon management
Mapping and modelling • Delivery of national and local modelling and mapping requirements,
primarily relating to non-capital asset management or non houses
protected projects
Marine and coastal • Specialist marine and coastal civil engineering works (80% of work below
High Water Mark)
Specialist national frameworks
Client support, mapping and modelling, marine and coastal
Programme Refresh…
North East Coastal Update
Simon Wilson
FCRM Senior Advisor,
North East Area
Coastal Schemes Current Programme 2015/16 to 2020/21
£8.4m £2.8m £10.8m £8.4m £2.7m £0.1m
£30.4m complete – 92%
Total Programme Expenditure
£33.2m
Properties protected
1,124
27% of North
East Investment
Programme
18% of North
East Homes
Better Protected
Coastal Schemes – Indicative Pipeline Programme 2021/22 to 2026/27
£9.7m £12m £11.1m £6.3m £2.2m £0.3m
Forecast
Total Programme Expenditure
£41.6m
Forecast
Properties protected
689
435 less than
current
programme
Environment Agency Port Clarence and Greatham South
• Overall costs c£15m – approx. £1.7m under the original contract value.
• Protects 350 residential properties and major infrastructure, includes 36ha
of intertidal habitat with 12ha of freshwater habitat
• 0.5%AEP standard of protection, including 50yrs of Climate Change
• Officially opened November 2018
Risk Management Authorities
Hartlepool – Headland Walls and Blocksands
• Scheme substantially complete – promenade open to public and compound has been removed
• Minor snagging and sealant works remaining
• 197 Homes Better Protected
South Tyneside – Marsden Bay
• Following discussions at the last
meeting STC are commissioning a
Risk Management and Emergency
Response Plan
Risk Management Authorities
North Tyneside – Southern Promenade
• OBC Approval Q4 2018/19
• TPE £600k
• Better protection to 93 homes
• Scheme to commence in Spring
Northumberland County Council – Little Shore
• Main works (Seawall Capital Maintenance) and emergency repairs (Southern Breakwater)
• 54 Properties Better Protected
Yorkshire Area Coastal Update
Ed Hinton
Senior Advisor, Yorkshire Area
Yorkshire Coastal investment
• Total 2015-21 Programme = £44.4m
• FCRM Grant-in-Aid = £27.2m
• Contributions = £17.2m
• Homes better protected (OM2 & 3) = 1,613
Pipeline (2021-27)
• Total 2021-27 Programme = £37.0m
• Homes better protected (OM2 & 3) = 1,876
• Significant work required to develop projects and identify funding sources
Yorkshire area overview
14
Staithes & Cowbar
Runswick Bay
Whitby Piers
Robin Hoods Bay
Boggle Hole
Withernsea groynes
Scarborough Spa
Whitby Church St.
Flat Cliffs
Seathorne revetment
Whitby Piers
• Voiding, undermining
• Sheet piles, grouting
• 362 OM3s, 14 OM2s
• Cost - £9,001k – funding secure • FDGiA - £4,812k
• ESIF - £2,700k
• LEP - £500k
• NYCC – 489k
• SBC - £500k
• Currently demobilised from site for the winter period – remobilise again in March.
• Works continuing whilst offsite include: • Final elements of design being completed
• Planning methods & temporary works design
• Permitting & planning activities
Whitby Church St. • Elevated water levels in River Esk due to
tides & storm surges pose flooding risk along Church St.
• 54 residential & 8 commercial properties
• Designed to 1 in 100 S.O.P.
• Planning approved. SBC Cabinet approval 12.02.19.
• Cost - £2,094k – funding providers: • LEP - £1,100k
• GiA - £672k
• Local Levy – 246k
• SBC - £61k
• NYCC - £15k
• Construction start March 2019, end October 2019.
Scarborough Spa
• Cliff Instability
• 380 properties- coastal erosion
• Piling, soil nailing, drainage, regrading
• Cost - £15,909k • FDGiA - £ 11,619k
• SBC/NYCC - £2,290k
• Risk - £2,000k
• Started on site mid-May, completion end 2019.
• 94% of soil nails & 25% of piles installed so far
• Over £2.1m of efficiencies accepted in Q3
Lincolnshire Coastal Update
Mark Adams
FCRM Senior Advisor,
Lincolnshire and Northamptonshire Area
Lincolnshire Coastal investment (2015-21) (2015-21 Investment Programme indicative allocation - Jan 2019 – see programme)
• Total 2015-21 Programme = £73.4m
• FCRM Grant-in-Aid = £58.4m
• Local contributions = £15.0m (Port of Immingham, South Ferriby)
• PF contributions pursued = £ 1.0m (South Ferriby – to further offset FCRM GiA)
*Above figures to be consented by EA Board (Feb 2019)
Outcomes :
• Households better protected = 26,800
• Intertidal habitat = 106 ha
SOUTH FERRIBY Flood Alleviation Scheme
• Full BC assured. FSoD expected Feb 2019 - £11.8m Capital
• Includes defence realignment – future sustainability
• Planning Application – determination by 22 March by NLC
• Enabling works winter 2018/19. Works Spring 2019
• £5.9m contributions reduce need for GiA from £8m to £5.9m
• Further funding bids being pursued to reduce GiA further –
£0.6m HE, £0.25m Lottery Fund, £0.25m AWS & LEP LGF?
• Strong partnership with CEMEX: 60,000 tonnes clay
stockpiled so far.
Lessons Learnt: • Surrender your commercial
advantage to single source
supplier, thro’ PDU?
• Who carries out env. surveys?
Local or national supplier?
• How do you manage risk from local
archaeology? Time/cost impact.
• Partnership - can/can’t do.
• Legal advice and non-dedicated
resource affect programmes.
Saltfleet to Gibraltar Point Strategy Review
• Feb 2018 - public consultation: • Preferred option – Beach with control structures • Reduces long-term sand volume and frequency
• PFCalc > 100% FCRM GiA…. but: • Affordability implications • Programme delivery challenges
• Spring 2019: Draft Strategy consultation
• 2020/2021: LPRG approval
• 2021 and beyond – delivery of on site works
• Up to 2021 – Lincolnshire Beach
Management 3 year contract to continue
(annual sand re-nourishment)
• 2019 campaign from May (Brexit permitting)
2021+ Pipeline programme Initial Assessments: • Continuing programme to inform 2019 programme refresh (May-June 2019)
• More certainty ahead of CSR20 negotiations with Defra/HMT
• Priority projects – risk based approach, greatest outcomes, spend and contributions
Current outline 2021+ pipeline programme (to 2027?) • Driven by emerging outputs of Humber and Lincs Coastal Strategy Reviews
• Pipeline programme needs more delivery certainty through 2019/20 & 2020/21
• South Humber pipeline estimated at £43.1M (5x large projects)
• Lincolnshire coastal works >£100M - affordability and delivery challenges
• Very significant contributions/funding still to be identified
• Strategic outcome apportionment to optimise FCERM GiA with other RMAs underway
• Separate tidal and ‘rainfall’ economic justification – asset led approach
South Humber bank – 2021+ pipeline projects
Immingham - Freshney (£6.5M) • Along 7.0km - >5000 prop’s & >£1Bn industry
• Asset strengthening and refurbishment
• Considering 4 MR and IDB outfalls
Barton to New Holland & Barton ‘west’ (£15-20M) • Combined appraisal – joint benefits/outcomes 1500+ properties
• Habitat and recreation challenges and opportunities
• Barrow Haven outfall – highest risk but low BCR on own
Cleethorpes - Humberston (£4.0M+) • >1700 properties and economic benefits
• With NELC to reduce risk to tourism amenities
• Various strategic options being considered
• Private caravan and chalet parks = contributions?
Halton Marshes phase 2 (£4.0M+) • Realigned defence at existing Ro-Ro port complex
• With NLC to enable growth and development
• Significant contributions likely to be needed
Bulldog Bank
Jason Fife
Partnerships & Strategic Overview Officer,
Lincolnshire and Northamptonshire Area
Background
• Change to SMP Policy Unit P
- current – hold the line
- acceleration of policy in Epoch 3
• Tidal Surge of December 2013
- 400m cross bank breached in 5 locations
- tidal surge in excess of 0.5% design tide
- no properties were flooded
Tidal inundation
Dec 2013
Partnership working
• Natural England & Lincs Wildlife Trust
- located in Gibraltar Point SSSI/SPA/Ramsar/SAC
- Gibraltar Point Coastal Wetland Adaptation Study
- 2014 repaired low spots in dune system
- under Natural England licence
- continued protection to Aylmer Avenue
• Consultation with SMP partners
- Lincolnshire County Council
Current Situation
• Low spots to back bank filled in 2014 - repaired to design tidal defence standard
• Modelling highlighted no risk to properties - overtopping migrates into tidal floodplain
- local area can accommodate flows
• Options considered (a) repair (Est. £70,000)
(b) replace (Est. £300,000)
(c) move defence line to Western dune
(d) move defence line / revise flood warning thresholds
• Promoted approach - option (c) is preferred with (d) instigated short term
Benefits • Restoration of brackish habitat
• May reduce the future SMP risks of coastal squeeze
Future outlook
• Agreement from NECG
• Approach RFCC – April 2019
Questions?
Redwell Steps, Marsden Bay
Redwell Steps
1 – Canoe Store
2 – Lower section of steps
3 – Lifeguard Station
Recommended work
• Urgent: Prevent access to canoe store
roof and improve signage
• Future:
- Demolition of structures as soon as
practicably feasible
- Construction of new access steps
Environmental Designations / EIA
Access Steps
Advice
• Funding
• Access closure
• Health and safety