1

No. 01a 4x8x4’ Platform

1. Attach #4 2x4x 3’ 11 1/4" legs 2. Attach #2 2x8x 3’ 11 1/4" legs

2

No. 01b 4x8x4’ Platform-cont. (dungeon door)

1. Attach 2 bottom framing pieces first 2. Make dungeon frame then attach it to leg/supports and the 2 bottom framing pieces

3

No. 01c 4x8x4’ Platform-cont. (framing-back)

1. Attach #2 2x4x 4’ braces 2. Attach #1 2x4x 7 1/4" brace

4

No. 02a 4x8x5’ Platform

1. Attach #4 2x4x 4’ 11 1/4" legs 2. Attach #2 2x8x 4’ 11 1/4" legs

5

No. 02b 4x8x5’ Platform-cont. (bracing)

1. Attach #2 2x4x 3’ 9” braces 2. Attach #1 2x4x 8’ brace

6

No. 03a 4x4x1’ Platform (bracing)

1. Create a 2x4x 4’ by 2x4x 3’ 9” frame

7

No. 03b 4x4x1’ Platform-cont. (bracing)

1. 2x4x 3’ 6” can be secured by attaching screws through the vertical 2x4x 3’ 9”s and

Then attaching the 2x4x 3’ 6” braces down into the 2x4x8 platform w/ 2” screws

8

No. 03c 4x4x1’ Platform-legs

1. Attach the 2x4x 11 1/4" legs to the 4x4 platform before securing onto the 4x8 platform-this picture Is created to show how the legs of the 4x4 platform fit onto the 4x8 platform

9

No. 03d 4x4x1’ Platform

10

No. 03e 4x4x1’ & 4x6x5’ Platforms (walls & railings)

11

Cont.

12

No. 04a SL Stairs (runners)

1. 2 of each length of 2x10 runners

13

No. 04b SL Stairs (runners-brace)

1. #2 2x4x 3’ 10 1/4" brace across the bottom (2nd board for upstage braces)

2. #2 2x4x 3’ brace across the runners (2nd board for upstage braces)

14

No. 04c SL Stairs

15

No. 05a 4x6x4’ platform (framing)

1. 2# 2x4x 3’ 9”

2. 2# 2x4x 6’

16

No. 05b 4x6x4’ platform w/ legs

6# 2x4x 3/ 11 1/4" legs

17

No. 05c 4x6x4’ railing

1. #2 2x4x 2’ boards 2. #1 2x4x 6’ board

18

No. 06a 4x4 Main Door (platform)

NOTE: the 4x4 platform is placed 2’ UP STAGE from the DS corner of the SR platform

(4x4 is on casters)

19

No. 06b 4x4 Main Door (pillars)

1. 2x6x 8” base, screwed to the posts and then to the 4x4 platform

2. #4 2x6x 8’ boards screwed to each other to create a pillar (door post) 3. Repeat on other side

20

No. 06c 4x4 Main Door (both pillars)

21

No. 07a Fireplace Wall

1. #2 2x4x 8’ boards

2. #2 2x4x 5’ 10” boards

22

No. 07b Fireplace (frame)

1. #2 2x6x 3’ sides

2. Supported on the right by a 2x4x 2’ 10 1/2" board 3. 2x8x 3’ 5 1/2” mantle

23

No. 07c Fireplace (interior)

1. #2 2x4x 3’

2. #2 2x4x 1’ 3 1/2" 3. #2 2x4x 1’

4. (both sides)

24

No. 07d Fireplace (interior-cont.)

#2 2x4x 3’ 9 1/2" cross boards

25

No. 07e Fireplace (interior-cont. w/ lauan and cross support)

1. #1 2x4x 5’ 10” cross board

2. 4x8 sheet of lauan

26

No. 08a 2x8 library platform

1. x6 2x4 x2’ 6 1/2" legs 2. platform is to be placed 10” down stage from the corner of the 2x4 fireplace wall frame

27

No. 08b library platform back wall (frame)

1. #1 2x4x 8’ (top)

2. #3 2x4x 7’ 10 1/2” (sides/middle) 3. #2 2x4x 3’ 9 3/4" (bottom)

28

No. 08c library platform book wall

1. #2 2x4x 7’ 9"

2. #2 2x4x 7’ 10 1/2" 3. #3 2x4x 2’

4. #1 2x4x 1’ 9”

29

No. 08d Library platform book wall complete

30

No. 09a 4x8 Library reading platform

#1 6# 2x4 1’ 11 1/4" legs

31

N0. 09b 4x8 reading platform steps

(same as bottom 2 steps on stage right)

32

Set in frames

33

Set filled in