New Morehead State Bowling Facility

Post on 08-Feb-2016

39 views 0 download

Tags:

description

New Morehead State Bowling Facility. IET 499C, Fall 2012 Stephen Glossner. Why the need for a new bowling facility?. The current bowling facility is Too small No restrooms Outdated Font desk area is cramped No space for maintenance/repairs. Site Work. Site location Site survey - PowerPoint PPT Presentation

Transcript of New Morehead State Bowling Facility

New Morehead State Bowling Facility

IET 499C, Fall 2012

Stephen Glossner

Why the need for a new bowling facility?The current bowling facility is

Too small No restrooms Outdated Font desk area is cramped No space for maintenance/repairs

Site WorkSite locationSite surveyCut and fill analysis

Site location

Site Pictures Photo of site location 1 of 2

Photo of site location 2 of 2

Design General floor planPlumbing/ HVAC/ ElectricalFinished floor plan3D rendering

Current Floor Plan

96’

68’

36’

28’

8’

15’

13’

23’

Total square feet = 3,640 sq./ft.

4’

Dimensions = 96’ X 36’

151’ 6”

106’ 9”

20’

10’ 7”

New Floor Plan

15’

33’

Total square feet = 16,172 sq./ft.

Dimensions = 151’ 6” X 106’ 9”

Comparison Current Floor Plan New Floor Plan

Total square feet =

3,640 sq./ft.Available standing room =

468 sq./ft. Area behind front desk =

184 sq./ft.Maintenance area =

144 sq./ft.

Total square feet =

16,172 sq./ft.Available standing room =

5618 sq./ft.Area behind front desk =

380 sq./ft.

Maintenance area =

1121 sq./ft.

Plumbing Plan Men’s restroom -handicapped stall -three urinals -double sink

Woman’s restroom -handicapped stall -two additional stalls -double sink

HVAC Plan•Forced centralized air system with outside unit mounted on the roof•Fourteen, ceiling hung, air vents

Electrical PlanElectrical Key

Electrical outlet

Recessed can light

Fluorescent tube light

Single switch

Finished Floor Plan

Current BowlingFacility Pictures

Area behind front desk

Area behind pin-setters

New Bowling Facility Design

Cost/ Schedule Material and Labor estimateCost analysis Project schedule

Turn-Key Estimate Sample

Exterior walls 2X4X10 390 boards $6 a board $2,340.00

Treated Bottom Plate 45 boards $7 a board $315.00

2x4x12 Top Plate 45 boards $6 a board $270.00

2x4x16 Second Top Plate 35 boards $8 a board $280.00

7/16 OSB Sheets 200 $13 a sheet $2,600.00

Tyvek Wrap 4 $150 a roll $600.00

Vinyl Siding 520 squares $150 a square $78,000.00

Dry Wall 84 $40 a sheet $3,360.00

Roof Steel Joist 152 $300 per joist $45,600.00

Plywood Sheeting Roof16800 sq./ft. $2 sq./ft. $33,600.00

Insulation Board/Membrane16800 sq./ft. $6 sq./ft. $100,800.00

Overview of Estimate Lot/Site Work $750,000.00

Foundation $102,875.00

Exterior $133,365.00 Material/Labor Cost $2,080,992

Roof $134,400.00 Slippage 5%

Interior $347,682.00 Overhead 15%

Plumbing $8,575.00 Profit 10%

HVAC $51,830.00 Total project cost $2,705,289.60Electrical $58,800.00

Bowling Equipment $464,600.00

Other Equipment $28,865.00

Cost Analysis Expected annual income for new bowling facility =

$157,800

It would take just over 17 years to cover the initial cost of the project.

Section of Project Schedule

May/1/2012 December/7/2012 June/18/202

Start Date Half Way Date End Date

Project Schedule: 296 working days

Conclusion A new bowling facility would benefit the university, the bowling team and the city of MoreheadThe university

Increased revenuegreater appeal for potential students

The bowling teamBigger, better facilityMore members can joinUpdated machines/equipment

The city of Morehead Something new and exciting New place to take family

Questions ?