Neighborhood Meeting No.2Golden Gate Bridge, Highway and Transportation District’sSan Francisco Mid-Day Bus Parking Facility

Contract No. 2013-BT-1 • March 20, 2013

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

March 20th Presentation

1. Project Status 2. Update: Traffic Signal3. Update: Sound Wall Design Concepts 4. Update: Modular Units and Security Fencing5. Update: Landscaping Planting Concepts6. Next Steps

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Proposed Site Plan

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Bus Ingress at Perry and 4th Streets

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Bus Egress at Perry and 3rd Streets

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

New Traffic Signal and Pavement Delineation at Perry and 3rd Streets

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Existing Midblock Crosswalk Downtown San Francisco

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

UpdatedSound Wall Elevations and Sections

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Selected OptionSound Wall Option 1 – “Diagonal Pattern”

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Variation on Selected OptionAlt. Sound Wall Option 2 – “Stripe Pattern”

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Sound Wall Steel Closure Plates – “Diagonal Pattern”

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Sound Wall Steel Closure Plates – “Stripe Pattern”

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Modular Units/Security FencingOriginal Concept

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Modular Units/Security FencingUpdated Concept

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Landscape Planting

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Landscape Planting

Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility

Project Schedule

• Comments: April 1, 2013• Complete Design Documents – estimated May 2013• Award Construction Contract – estimated July 2013• Complete Construction – estimated January 2014• Start Bus Parking – February 2014

Q&A