Post on 27-May-2018
National Highways Authority of India (Ministry of Road Transport & Highways)
ANNUITY PROJECT - NH 45
TAMBARAM TO TINDIVANAM
(KM 28.000 TO KM 121.000)
INDEPENDENT ENGINEER
M/S. CDM SMITH INDIA PVT. LTD.
307,Thamarabarani Square, Periyar Nagar,
Villupuram-626501.
Submitted by
CONCESSIONAIRE
GMR Tambaram -Tindivanam Expressways Private Limited
No.1 C/B First Floor, R.V. Street,
Opposite: Govt. Arts College
Chengalpattu – 603 001.
MONTHLY O&M REPORT
SEP-2015
2015
National Highways Authority of India (Ministry of Road Transport & Highways)
ANNUITY PROJECT - NH 45
TAMBARAM TO TINDIVANAM
(Km 28.000 to Km 121.000)
MONTHLY O&M REPORT
SEP- 2015
CONCESSIONAIRE
GMR TAMBARAM – TINDIVANAM EXPRESSWAYS PRIVATE LIMITED
NO.1 C/B, FIRST FLOOR, RV STREET, CHENGALPATTU-603001
INDEPENDENT ENGINEER
CDM Smith India Pvt Ltd.
Villupuram
Executive Summary- SEP 2015
Activities Executed along with Regular O&M
1. 10th year Periodic maintenance works comprising BC overlay & Road marking
works has been completed for 80 km in length. BC works with HIP process has
been completed for 8km in length during the month of April’2014
2. All accidental repair works like RCC Handrails, PGR, Sign boards, MBCB &
Electrical pole are completed up to date, to enhance safety.
3. Illumination level is well maintained on highway for the purpose of safety. The
maintenance of the same is in progress on daily basis.
4. Removal of encroachments like private advertisement boards, petty shops &
platform vendors are removed then and there on daily basis.
5. The painting of PGR, Crash barriers, culvert parapet wall, TLB kerb & RCC
Handrails painting works at all faded locations in between km 28-121 are in
progress under periodic maintenance
6. Over shooting Tree branches have been removed from median & Avenue to
improve safety.
7. Damaged PGR, Culvert parapet wall & Kerb on Service road, MCW are
rectified to improve safety. Hazard marker, Delineator and Guard post fixed
and being done regularly at all required locations in between km 28-121.
8. TLB & Rest place Maintenance works are in progress at all TLB’s km 70, 72, 113
& 119.
9. Sign post painting, Gantry board painting, Boundary stone fixing & shoulder
rectification at all required locations are in progress.
10. As a part of CSR Activities, Road safety, Pollution Awareness programmes
and First AID programs are being conducted for road users at our TLBs,
Junctions & Bus stops and for the Institution and School students near to the
highway for the goodwill of Road user and public in our GMR Tambaram
Tindivanam NH-45 Section.
11. For safety improvement fixing of Diamond cluster (BIG size), Tyre with reflective
sticker and painting of Kerb with Yellow and black colour are in progress at all
Median openings and junctions.
12. Laying of Balance PQC Works for ETC Implementation in 53 & 103 Toll plaza have
been completed
13. Laying of kerb for ETC Implementation in 53 & 103 Toll plaza have been completed.
14. Plantation for Avenue & median for this monsoon have been scheduled as
such 20,000 No’s of plants procured and 14500 plants planted on median in
between km 60-121.
15. BC surface patch laying works are completed.
Need support from client for future works:
1. Even though our continuous effort with concern local authorities, we are
unable to control the disposal of garbage on service road rendering the
same not being utilised fully at singaperumal koil, Guduvancherry &
Urappakkam. We request your intervention with district level panchayath
administration on this issue to maintain service roads clean and tidy at all
times and free flow of traffic too.
2. The construction of RCC Drain in place of panchayath brick drain is to be
considered under COS to solve flooding of drain overflow water during rainy
season on service road. The proposals along with IE recommendations are
pending at your end.
3. As part of safety improvement the kidney island at some junctions are on the
MCW are to be rectified under COS to avoid two wheelers fatal accident. The
issue still under pending at your end for the approval of the same.
4. The Regularising of unauthorised median openings as suggested by Then
CGM & as recommended by “Then independent Engineer under COS “still
pending for approval from Authority.
5. Unauthorised/illegal parking at Melmaruvathur km 91-96 BHS by devotees of
Temple & Km 72-76 BHS by sand quarry Gov. of TN, request your support to
stop this parking on the interest of road safety on NH-45.
6. Encroachment like private approaches & Commercial establishments are
developing in TT NH 45 on daily basis, we put our effort to stop & remove the same
but in vain. Need your intervention for the same to avoid such unlawful events in
future.
7. COS proposals have been submitted for the construction of Balance PQC for the ETC
Implementation and Construction of Medical, Traffic Aid post and Washroom
facilities at 53 & 103 Toll plazas for Approval.
Project Details
NH-45 (popularly known as GST Road) is one of the important National Highways, which connects Chennai,
the Capital City of Tamilnadu with the southern districts of the State, including major towns such as Trichy,
Madurai, etc. This National Highway has been entrusted to National Highways Authority of India (NHAI) for
development and maintenance. NHAI has taken up the project road from Km 28/0 (starting from
Tambaram at the outskirts of Chennai city) to Km 121/0 (Tindivanam junction) for development under the
Annuity Scheme. Total length of the project road is 93 Kms.
The project has been awarded to the Concessionaire, M/s GMR Tambaram-Tindivanam
Expressways Pvt. Ltd. As per the Concession Agreement signed between NHAI and the Concessionaire on 9th
October 2001. Under the provision of the Concession Agreement, the Concessionaire is awarded a
Concession to Design, Finance, Construct, Operate and Maintain the Project Highway
for a Concession Period of 17.5 years out of which the project has to be constructed within the first 30
months.
For supervision of the project works, the role of Independent Engineer has been envisaged in the
Concession Agreement and, accordingly, DORSCH Consultant has been appointed as the Independent
Engineer. The Concessionaire has appointed M/s UE Development India Pvt. Ltd., Bangalore as their EPC /
O&M Contractor for the execution / Operation & Maintenance of the project.
Salient dates are:
S.N
o
Description Date
1 Date of signing of Concession
Agreement
9 October 2001
2 Commencement date of Concession 9 May 2002
3 Schedule Commencement date of
O&M
8 Nov 2004
4 Actual Commencement date of O&M 11 Oct 2004
5 Scheduled End of Concession 8 Nov 2019
The Project details are as follows:
Sr. Description Details
1 Scope of
Construction
Four laning of the entire Project highway of length 93
kms - from Km.28/000 to Km.121/000
2 Project
Length
93 kms (Urban - 31.3 kms ; Rural - 61.7 kms)
3 Pavement 4 lane divided carriageway with raised median
Service road of 5.5/7 m – 20.265/3.750 km
4 Bridges Minor - 15 no.
Major - 2 no.
5 ROB’s 52/000 ; 55/400 & 101/118 – 3 no.
6 Trumpet One at Km.80/655
7 Culverts Pipe culverts – 96
Slab culverts - 93
8 Toll Plaza 12 laned at Km.52/820
10 laned at Km.103/250
9 Underpasses 91/461 ; 91/907 ; 92/072 ; 95/575 ; 100/975 – 5 no.
10 Fly over 56/1 & 61/1
11 Wayside
amenities
On RHS carriageway at km.72/208
On LHS carriageway at km.119/138
12 Other
facilities
Truck laybys-2 x 2
LHS - KM.69/900 to 70/400
RHS - KM.70/425 to 70/925
LHS & RHS – KM.113/700 to 114/200
The address and telephone Numbers of the Concessionaire, Independent Engineer are as
below: Concessionaire:
Independent Engineer:
Dedication to Nation
The road was dedicated to Nation on 19th March 2005.
Toll collection
Toll collection was started on 01st April 2005.
Registered Office:
M/s GMR Tambaram Tindivanam
Expressways Pvt.Ltd.
Skip House
25/1, Museum Road
Bangalore – 560 025
Tel: 080-2570100 Fax: 080-2075044
Managing Director: Mr. O.B.Raju
Mobile: 98450 – 10060
Site Office:
M/s GMR Tambaram Tindivanam
Expressways Pvt.Ltd.
No. 1 C/B, First Floor
Rajeswari Vedhachalam Road
Chengalpattu – 603 001
Tel: 044-27431162/27430960
Project Manager: Mr.R.Barathi.
Mobile No: 95666 99194
Registered Office:
Site Office:
M/s Wilbur Smith Associates Pvt ltd,
307, Thamirabarani Square,
Periyar nagar,
VILLUPURAM-626501
Team Leader: Mr.Rajasekhar,
Mobile No: 94435 89187
Maintenance Activity during “August-2015”
Highway Patrol
Highway patrolling is carried out regularly with two teams round the clock. The patrol team
monitors the traffic flow and encroachments into NH property, emergency action in case
of accidents like first aid, calling ambulance, information to all concerned, clearing
vehicles from road way to ensure smooth traffic flow. The various other activities carried
out like removal of parked vehicles, safety arrangement to breakdown vehicles, removal
of private approaches, timely assistance to road users in emergency & keep utmost
vigilant for road safety to road users and road assets.
Turf Maintenance
Turf maintenance is being carried out using the grass-cutting machine @ Km 50+000 to
60+000, Km 80+000 to 90+000 & Km 110+000 to 121+000 as per monthly task.
Sl.No Week Chainage Remarks
1 I Km 50+000 – Km 52+000,Km 80+00 – Km
82+000,Km 110+00 – Km 112+000
2 II Km 52+000 – Km 54+000, Km 82+000
– Km 85+000, Km 112+000 – Km
115+000
3 III Km 54+000 – Km 57+000, Km
85+000 – Km 87+000, Km 115+000 –
Km 118+000
4 IV Km 57+000 – Km 60+000, Km
87+000 – Km90+000, Km 118+000 –
Km121+000
Land Scalping
Watering to the plants was carried out as and when required. Basin formation and
blowing of soil to the plants were carried out. Removing the unwanted plants was carried
out. Replacing of dead/missed plants is in progress.
ROW Clearance
Removal of Undesirable growth and vegetation in areas within the ROW is being carried
out regularly using the manpower. Watering is carried out as and when required for the
ROW trees. The clearance work carried out between Km 40+000 to 60+000, Km 80+000 to
90+000 & Km 110+000 to 121+000.
Avenue plantation
Replacing of Dead/missed avenue plants has been carried out during this month from Km
28-121
Cleaning of MCW & SR
Cleaning of MCW & SR is being carried out using power Broomers and man power to the
entire project based on observation on daily basis.
Debris / Road Obstruction
Our patrol team & maintenance team removed debris on the carriage way regularly by
using men & machinery.
Culverts
The total no of culverts is 186. As per the schedule the cleaning of culverts are to be done
once at 6 months frequency. The cleaning of culverts between KM 55 to KM 60 - 14 nos.,
KM 84 to KM 90 – 9 nos. & KM 120 to KM 121– 6 nos. is completed during this month.
Drainage
The total length of concrete drain is 21625m. As per the schedule the Clearing of concrete
drains are to be done at 4 months frequency. The clearing work carried out between Km
33.650-34.700R (1050), Km 35.700-37.700L (200), Km76.340-76.850R (510), Km 92.00-92.240R
(240), Km 100.305-100.455L (150), Km 100.305-100.525R ( 220)
Building Maintenance
Building maintenance such as Toll plazas @ 103+000 & 53+000, Rest areas @ 72+000 RHS,
119+000 LHS & Truck lay bye @ 113+000 LHS & RHS, 70+000 LHS & RHS are done regularly.
Shoulder Maintenance
Shoulder maintenance is maintained by using the approved borrow gravel with
compaction using the Roller is in progress and grader is used for removal of excess soil and
for levelling the shoulder on weekly/daily Basis at required locations.
Electrical
Street lighting, High mast, Feeder Pillar and Building lighting are being maintained
regularly. Rectification of Damaged electrical poles, fused bulbs & other electrical faults
are progressed and in progress on daily basis with our electrical team.
Encroachment removal
Encroachments were cleared from Km 28+000 to Km 121+000 on both LHS & RHS on daily
basis with our detected team. Periodic Removal at service roads and ROW areas will also
be taken up as scheduled.
Painting works
Painting of faded locations like Median kerb, Pedestrian fencing & Road marking have
been carried out during this month in-between km 60-121.
Safety improvement plan
All median openings, Important deep curves has been highlighted with median markers
and Lane visibility Studs and All Important Junctions has been highlighted by red Rumbled
studs strips on both sides as goodwill to the project safety. This activity has been
completed in between km 28-121.
All median openings and junctions have been facilitated with Diamond (big cluster), Tyre
with reflective stickers, kerb with yellow and black paint to improve visibility during Day &
night, this work is in progress on regular basis.
Over shooting tree branches on median have been removed for road user safety in
between km 28-60 & 90-95 and remaining in progress.
Hazard markers and delineator at all Crash barriers/parapet wall has been provided in
between km 28-60 and is in progress in between km 60-121
Road safety awareness programme at schools, colleges and at all important junctions, toll
plaza and TLB locations conducted.
Periodic maintenance activities
To improve Raiding Quality 80 Km BC Inlay work have been completed in the month of
March-2014 as 10th year periodic maintenance.
BC Surface patches laying work is in progress
Median plantation:
14500 No’s so far planted and 20,000 No’s of Median plants procured for this monsoon.
Works Done Under COS 1. Laying of Balance PQC Works for ETC Implementation in 53 & 103 Toll plaza have been
completed
2. Laying of kerb for ETC Implementation in 53 & 103 Toll plaza have been completed.
Status of Damaged Project Facilities
Month: Sep 2015 (As of 30.09.15)
Sl. No
Date of incident
Location Side Description Remark /
compliance
1 02.01.15 57+900 RHS
Hand rails verticals -7nos, Hand rails horizontal - 21nos , Foundation - 7 nos
Completed
2 27.01.15 76+500 LHS
single arm pole-1nos, PGR 02 nos Completed
3 16.02.15 47+350 LHS
Pedestrian fencing- 05 Nos Completed
4 27.02.15 37+200 Median
Double arm pole Completed
5 28.02.15 41+850 LHS
Pedestrian fencing- 07 Nos Completed
6 04.03.15 42+400 Median
Double arm pole Completed
7 08.03.15 92+200 RHS
Pedestrian fencing- 06 Nos Completed
8 24.04.15 58+550 RHS Hand rails verticals -7nos, Hand rails horizontal - 21nos , Foundation - 7 nos
Completed
9 27.04.15 45+980 LHS single arm pole-1nos Completed
10 30.04.15 76+550 Median 1. Double Arm Electrical pole & fittings -01 nos+ Diamond cluster-01Nos
Completed
11 5.5.15 88+900 LHS LHS Metallic Beam cross barrier – 18 meters Completed
12 8.5.15 82+750 LHS LHS Metallic Beam cross barrier – 15 meters Completed
13 12.5.15 30+100 Median
Median 1. Double Arm Electrical pole & fittings -01 nos Completed
14 16.5.15 105+800 LHS LHS Metallic Beam cross barrier – 45 meters Completed
15 19.5.15 76+850 LHS LHS Pedestrian fencing- 07 Nos Completed
16 23.5.15 95+800 LHS LHS single arm pole-1nos, PGR 09 nos Completed
17 8.6.15 81+000 LHS Metallic Beam cross barrier – 45 meters, PGR -02 nos
Completed
18 19.6.15 39+750 Median Double Arm Electrical pole & fittings -01 nos
Completed
19 29.6.15 94+975 Median Double Arm Electrical pole & fittings -01 nos
Completed
20 9.7.15 58+500 RHS Hand rails verticals -10 nos, Hand rails horizontal -30 nos , Foundation - 10 nos
Completed
21 11.7.15 36+550 RHS single arm pole-1nos, PGR 08 nos
Completed
22 13.7.15 37+500 LHS Pedestrian fencing- 06 Nos
Completed
23 16.7.15 37+350 RHS Pedestrian fencing 5 Nos,Single arm pole & A pedestrian crossing board
Completed
24 22.7.15 80+600 LHS Metallic Beam cross barrier – 20 meters Completed
25 12.8.15 94+400 Median Double Arm Electrical pole & fittings -01 nos
Completed
26 15.8.15 88+700 RHS 1. Brick parapet wall damaged 11m*0.5m*0.6m. 2. Hazard Marker sign Board-01 nos.
Completed
27 19.8.15 77+600 Median 1. Double Arm Electrical pole & fittings -01 nos+ Diamond cluster-01Nos
Completed
28 27.8.15 76+450 Median 1. Double Arm Electrical pole & fittings -01 nos+ PGR-02 nos
Completed
29 6.9.15 54+790 RHS Hand rails verticals -8 nos, Hand rails horizontal -24 nos , Foundation - 8 nos
Completed
30 20.9.15 47+250 LHS Pedestrian fencing- 09 Nos In progress
Rectificationof Assets & Other Periodic Works completed During this month Month: Sep-15
Sl. No Date of
Rectification
Location Side
Item Description
Units QTY Remark /
compliance From To
1 60000 62000 BHS
Kerb Painting
RM
4000
2 64650 66300 BHS 3300
3 66500 74200 BHS 15400
4 75500 77600 BHS 4200
5 79350 82800 BHS 6900
6 107000 108300 BHS 2600
7 99200 101000 BHS 3600
8 90+600 91+200 LHS
rectification damaged
Drain Cover Nos
5
9 90+600 91+200 RHS 1
10 94+200 94+740 LHS 4
11 94+350 95+600 RHS 10
12 69+150 69+250 LHS 2
13 96+200 96+800 LHS 5
14 96+500 96+750 RHS 2
15 97+580 97+750 RHS 4
16 94+500 95+650 LHS rectification damaged Manhole
Cover
Nos
18
17 94+700 95+400 RHS 8
18 76+400 76+800 LHS 8
19 76+550 76+700 RHS 4
20 88+800 RHS Culvert Parapet
Wall Nos
1
21 74+200 RHS 1
22 82+720 LHS 2
23 60+000 121+000 BHS HM Stones Nos 90
24 60+000 121+000 BHS KM Stones Nos 10
Details of Replacement of Plants in Median From Km28-121 in 2015-2016
S.No Date Location
No of plants Remarks From To
1
13.07.15
66.400 67.000 51
2 67.000 68.000 131
3 68.000 69.000 148
4 69.000 70.000 96
5 70.000 71.000 74
6
14.07.15
71.000 72.000 151
7 72.000 73.000 170
8 73.000 74.000 167
9 74.000 75.000 158
10
15.07.15
75.000 76.000 185
11 76.000 77.000 163
12 77.000 78.000 101
13 78.000 79.000 205
14 91.800 93.000 180
15 93.000 94.400 220
16
16.07.15
79.000 80.000 292
17 80.000 81.000 332
18 94.400 95.000 50
19 95.000 96.000 230
20 96.000 97.100 170
21
17.07.15
82.000 83.000 254
22 83.000 84.000 296
23 84.000 84.800 250
24 97.100 98.000 178
25 98.000 99.000 270
26 99.000 99.400 152
27
18.07.15
84.800 85.000 53
28 85.000 86.000 197
29 86.000 87.000 250
30 87.000 88.000 204
31 88.000 88.200 46
32 90.000 90.600 81
33 99.400 100.000 203
34 100.000 101.000 125
35 101.000 101.400 141
36
20.07.15
101.400 102.000 140
37 102.000 103.000 160
38 103.000 104.000 122
39 104.000 105.000 131
40 105.000 105.400 47
41
21.07.15
105.400 106.000 80
42 106.000 107.000 175
43 107.000 108.000 160
44 108.000 109.000 185
45
24.07.15
109+000 110+000 192
46 110+000 111+000 307
47 111+000 112+000 227
48 112+000 112+400 74
49
01.08.15
112+600 113+600 150
50 113+600 114+600 180
51 114+600 115+600 170
52 02.08.15 115+600 116+600 220
53 116+600 117+600 280
54
03.08.15
60+000 61+400 700
55 117+600 118+000 130
56 118+000 119+000 370
57 04.08.15
88+400 89+400 300
58 119+000 120+000 500
59 19.09.15 58.000 60.000 500
60 20.09.15 56.000 58.000 340
61 22.09.15 54.000 56.000 325
62 23.09.15 49.000 54.000 750
63 24.09.15 36.000 38.000 287
64 27.09.15 41.000 43.000 320
65 29.09.15 43.000 47.000 360
66 30.09.15 32.000 36.000
720
38.000 41.000
TOTAL in Nos 14576 Balance in progress
GMR Tambaram-Tindivanam Road Project(NH-45)
Patch works done from KM28 to 121-TT
S.NO Date Location Side Quantity in SQM Remarks
1
9/4/2015
110+520 LHS 24.07
Main carriage way
2 27.72
3
118+450 to 118+570 LHS
29.5
4 135.8
5 469
6
9/5/2015
100+430 to 100+620 RHS 1099
7 100+700 to 100+760 RHS 350
8 90+760 to 90+880 LHS 721
9 91+150 to 91+180 LHS 69 Service Road
11
9/9/2015
91+020:Including BM & SDBC
LHS 126 Service Road Junction
12 90+985:including BM &
SDBC LHS 50 Service Road Junction
13 90+985 LHS 93.5 Service Road Junction
14 90+920 RHS 95.76 Service Road Junction
15
9/10/2015
78+820to 78+940 RHS 1456 Main carriage way
16 78+930: only BM RHS 30.8 Main carriage way
17 76+550 LHS 117.8 MCW & Service junction
18 9/11/2015 62+000 to 62+250 LHS 468 Palar bridge
19
9/23/2015
103+050 Median
73.5 Toll plaza on ETC lane at trichy
Side
20 73.5 Toll plaza on ETC lane on RHS at
trichy Side
21 9.5 Speed breakers on Toll plaza near
by ETC lane at trichy Side
22
102+950 Median
91 Toll plaza on ETC lane at Chennai
Side(including BM & SDBC)
23 29.75 Toll plaza on ETC lane at Chennai
Side
24 110.39 Toll plaza on ETC lane on LHS at
Chennai Side
25 16.8 Toll plaza on ETC lane on LHS at
Chennai Side
26 11.7 Speed breakers on Toll plaza near
by ETC lane at Chennai Side
27 9/24/2015 100+650 MCW-RHS 672 ROB top on RHS
28
100+360 to 100+540 Service Road-
BHS
28.8
Service Road-BHS(9number of spots)
29 4.14
30 3.6
31 2.24
32 3.25
33 15.5
34 7.56
35 2.25
36 1.8
37 61+950 MCW-RHS 108.8 MCW-Fast lane only(Kerb side)
38 9/25/2015 60+750 MCW-LHS 165.92
MCW 105.27
39 11.9.15 52+000-52+050 RHS 170 MCW
40
12.9.15
28+400 SR LHS 280.5 SR
41 28+500 Patch LHS 33.9 SR
42 28+530 Patch LHS 22.62 SR
43 28+600 SR LHS 440 SR
44 28+600 SR ramp LHS 40 SR
45 28+700 SR Ramp LHS 56 SR
46
16.9.15
32+200-32+280 RHS 560 MCW
47 32+380 JN LHS
52.48 SR/JN
48 31.32 SR/JN
49
23.9.15 Guduvancherry RHS
37+000-37+500 RHS
43.2
SR Patch work
50 6
51 12.45
52 12.96
53 19.5
54 13.3
55 17.2
56 16.72
57 55.08
58 19.2
59 15.04
60 7.2
61 5.5
62 3
63 20.16
64 12.96
65 9.4
66
23.9.15 Guduvancherry RHS
36+200-37+000 RHS
13.92
SR Patch work
67 10.8
68 9.12
69 21.6
70 6.24
71 24.9
72 58.9
73 21.84
74 7.26
75 7.8
76 7
77 21.06
78 18.24
79 57.6
80 17.43
81 26.7
82 6
83 35.65
84 3.84
85 2.52
86 1.5
87 0.5
88 2.09
89 24.9.16 Guduvancherry LHS 36+200-37+000
LHS 5.5
SR Patch work
90 0.5
91 22.44
92 3.12
93 16
94 1.44
95 2.34
96 3.01
97 2.56
98 14.72
99 7.35
100 14.64
101 72.5
102 12.16
103 4.18
104 4
105 7.68
106 14.03
107 7.92
108 19.53
109 9.86
110 1.2
111 9.18
112 51.45
113
24.9.15 31+700 Vandalur
Bridge
RHS
21.9
MCW
114 6.9
115 4.56
116 6.27
117 4.25
118 3.68
119 4.44
120 2.16
121
LHS
4.9
122 1.2
123 32.55
124
29.09.15
29+100 RHS 2
SR Patch work
125 28+850 RHS 1
126 30+450 LHS 10.08
127 30+820 LHS 1.4
128 30+910 LHS 9
129 31+030 LHS 6.3
130 31+800 LHS 16.28
131 33+600 LHS 1
132 33+650 LHS 1
133 33+800 LHS 8.4
134 33+900 LHS 8
135 34+200 LHS 1
136 34+120 MCW LHS 4
137
34+700 JN LHS
10.4
138 63
139 22
140 39+100 LHS 4
141 39+630 LHS 1
142 39+800 LHS 2.25
143 42+050 LHS 4
144 42+100 LHS 25
145
29.09.15 Tollplaza
LHS
27
Speed breakers rectification
146 18
147 12
148
RHS
27
149 18
150 12
O&M Performed Task for the month of SEP-2015 as per the Yearly Planner
Sl. No.
Description/Item Planed Locations for
this month as per O&M plan
Unit
Planed Qty for this month as per O&M
plan
Km 28-60
Km 60-121
Remark
1 Maintenance in ROW
a
Bushes cutting, Toe drain, slope, scatter papers removal & Avenue plantation
KM50-60, 80-90, 110-121
Km(B/S) 62 20 42 Completed
2 Median maintenance
a Grass cutting KM50-60, 80-90, 110-121
Km 31 10 21 Completed
b weeds removal Km 49-60,80-90,110-121
Km 40 20 20 Completed
c Basin work KM50-60, 80-90, 110-121
km 31 13.6 17.4 Completed
d Median plants/trees trimming
KM50-60, 80-90, 110-121
km 31 10 21 Completed
e Median drain/slot drain cleaning
KM50-60, 80-90, 110-121
Km 31 10 21 Completed
f Drain cleaning in divided kerb locations
KM50-60, 80-90, 110-121
Km 9.43 4.04 5.39 Completed
g Watering to the plantations
KM50-60, 80-90, 110-121
km 93 Is in progress on daily basis
h Monsoon Plantation Km28-121 km 61 3500 11000 Completed
3 Cleaning of Debris/Litter/ Garbage
a MCW 28-121 km 93 Repeated rounds of cleaning done in first 20 km with men & mechinery- List enclosed
As per site condition,
where ever required
weekly once
b Service road 28-121 km 22.37
c Junctions 28-121 No.s 44
d Bus bays & Bus shelters
28-121 No.s 49
e Garbage removal 28-121 Locations 10 10 Monthly Twice
4 Cleaning of C/D works
a Culverts Km 55-60(14) ,Km 84-90(9),Km 120-121(6)
No.s 29 14 15 Monsoon maintenance Completed
b Bridges Km 55-60 ,Km 84-90,Km 120-121
No.s 1 1 0
5 Cleaning of Drainage
33.650-34.700R, 35.700-37.700L, 76.340-76.850R,
92.00-92.240R(240), 100.305-
100.455L(150), 100.305-
100.525R(220)
Km 4170 3050 1120
Monsoon maintenance Completed
6 Cleaning of Road furniture
a Sign boards,Delinators,KM & HM stones
Km 28-39,60-70,90-100
KM 32 11 21 Completed
7 Building Maintenance
a Toilets 16 Daily No's 16 16
On daily basis b
Truck lay bys 2 Daily No's 2 2
c Public amenities 2 Daily No's 2 2
8 Electrical Maintenance
a Street lighting 28-121 Km 19.75 12.5 7.25 Maintenance on daily basis
with our electricians &
Team
b High mast 28-121 No's 47 12 35
c Building lighting 28-121 No's 2 1 1
d Bus lay byes 28-121 No's 20 15 5
9 Encroachment removal-Daily activities
Km 28-121 Nos 295 221 74
Daily - Road side vendors, Political board ,Huts & shop projections
10 Shoulder maintenance
KM 29-33BHS, 44-46 BHS, 52-54 BHS, 63-66 BHS, 84-85 BHS,
90-94 BHS.
Km 32 22 10 Monthly once
due to frequent damages
11 Repair Works
a PGR KM 28-121 RM
Accidental Damaged locations during the month of 15th May and up to 15th June-
15
48 18
Based on site observation
and damages
b RCC Handrails KM 28-121 RM 20
a MBCB KM 28-121 RM 20
d Kerb KM 28-121 RM
e Electrical poles KM 28-121 Nos 2
f KM/Hm Stones KM 28-121 Nos 60 120
g Pavement Defects KM 28-121 Sqm 3200 7000
h Potholes KM 28-121 Sqm
i Drainage Slabs KM 28-121 Nos
j Sign boards KM 28-121 Nos 10 25
12 Painting works:
a Kerb (Median)
28-121 Km Completed In progress
b RCC Hand rails 28-121 RM Completed
c PGR Painting 28-121 RM Completed 1900
d Road marking 28-121 Sqm Completed
Completed along with periodic
maintenance in march-2014
e Guard post 28-121 Nos Completed
f Head walls 28-121 Nos Completed
13 ERP Km 28-121 Km(B/S) 93 Patrolling 365*24 with Two patrol
teams in progress