MSU/MCTC Law Enforcement and Criminal Justice Center March 10, 2010.

Post on 11-Jan-2016

216 views 0 download

Tags:

Transcript of MSU/MCTC Law Enforcement and Criminal Justice Center March 10, 2010.

MSU/MCTC Law Enforcement and Criminal Justice Center

March 10, 2010

Agenda- Schedule- Quality- Financial-Literary Quotations-Monument Sign-Spandrel Panel Issue-Additional Contracts- Progress Photos

Activity Date

Start Construction May 7, 2009

Substantial Completion June 19, 2010*

Inspections/Punchlist Work June 20 – July 20, 2010

FF&E Installation June 20 – July 20, 2010

Move-in July 20 – August 9, 2010

Fall Semester Begins August 21, 2010

Master Schedule Milestone Dates

* Excludes pending request for time extension

Activity Scheduled Completion % Done/anticipated completion

Curtainwall March 12 75%/March 19

Ceramic Tile March 26 65%/March 26

Plumbing Fixtures March 23 5%/March 23

Architectural Casework March 15 5%/March 15

Ceiling Grid Installation May 11 20%/May 11

Contractor’s Schedule – Activity Comparison Dates:

UPCOMING WORK-Complete Curtain wall Installation- Mechanical and Electrical Equipment - Soffit Framing- Painting- Ceiling Grid/Light Fixtures/Diffusers- Ceramic Tile- Firing Range Equipment

QUALITY Material TestingWindow TestingRoof Inspections/TestingWaterproofing InspectionGeneral ConformanceCommissioning

Literary Quotations

Monument Sign

Option A

Option B

Spandrel Panel Thermal Barrier

Additional Contracts

• Elert & Associates- $8,250 – Commissioning of technology systems

• Midwave- $34,750 – Design of the building’s LAN

• Intereum – Furniture plan and installation coordinator- $14,100

Acoustic Separation of Private Offices

Overview

South Curtain Wall

Casework Delivered

Ceiling Grid Installation

Main Street Corridor

2nd Floor Mechanical Room

Overlooking Main Street

1st Floor Restroom