Outline• Introduction

– History– Office & Staff

• Registration/Deregistration– Submittal Process– New/Updated Registrations– Backlogged Registrations– Deregistrations

• Compliance Monitoring– Compliance Determination– Inspection Zones– Field Approach

• Providing Compliance Assistance– Registered Facilities– Unregistered Facilities– Common Compliance Issues

• Current Status and Path Forward

• Contact Information

August 27, 2008

Introduction

August 27, 2008

History

Before January 2006– Department had 600+ MAQP applications from

oil or gas well facilities– Majority of facilities already

constructed/operating without MAQP– Not feasible to utilize existing Department staff

to issue the MAQPs within statutory time frames

J F M A M J J A S O N D

2006J F M A M J J A S O N D

2007J F M A M J J A S O N D

2008

August 27, 2008

History

January 2006• ARM Title 17, Chapter 8, Subchapter 16

– Oil or gas well facilities can construct/operate prior to issuance of MAQP

– Must comply with requirements of Subchapter 16

– Must have submitted application prior to January 3, 2006, or within 60 days after well completion date (whichever was later)

J F M A M J J A S O N D

2006J F M A M J J A S O N D

2007J F M A M J J A S O N D

2008

Jan 06 – Subchapter 16

August 27, 2008

History

April 2006• ARM Title 17, Chapter 8, Subchapter 17

– Allow oil or gas well facilities to register with the Department in lieu of obtaining MAQP

• Supply requested registration information• Follow fee, operating, emission control, inspection and

repair, and recordkeeping and reporting requirements

J F M A M J J A S O N D

2006J F M A M J J A S O N D

2007J F M A M J J A S O N D

2008

Jan 06 – Subchapter 16

Apr 06 – Subchapter 17

August 27, 2008

History

October 2007• Air Quality Registration Section

– Office established and staffed– Began acknowledging backlog– Acknowledge new registration/deregistration

requests– Identify/contact facilities that may be required

to be either permitted or registered but have not submitted an application

J F M A M J J A S O N D

2006J F M A M J J A S O N D

2007J F M A M J J A S O N D

2008

Jan 06 – Subchapter 16

Apr 06 – Subchapter 17

Oct 07 – Registration Section

August 27, 2008

History

June 2008• Initial Field Inspections and Verifications

– Compliance inspections on Registered facilities– Verify status of unregistered facilities that may

require MAQP or registration– Provide compliance assistance

J F M A M J J A S O N D

2006J F M A M J J A S O N D

2007J F M A M J J A S O N D

2008

Jan 06 – Subchapter 16

Apr 06 – Subchapter 17

Oct 07 – Registration Section

June 08 – Field Insp/Verif

August 27, 2008

History

Present Day• Ongoing Work

– Inspection reports– Contact companies with unregistered facilities– New registration/deregistration requests– Backlog– Evaluate/improve process

• Subchapter 17 rule change

J F M A M J J A S O N D

2006J F M A M J J A S O N D

2007J F M A M J J A S O N D

2008

Jan 06 – Subchapter 16

Apr 06 – Subchapter 17

Oct 07 – Registration Section

June 07 – Initial Facility Inspections

WE ARE HERE

August 27, 2008

Purpose of Registration• Provide oil or gas well facilities with an

alternative to MAQP– More operational flexibility

• Register 60-days after well completion• Notify within 15-days after change

– Reduced administrative burden• No application• No public notice• No BACT analysis• No notification prior to change

August 27, 2008

Reg. Section Office & Staff• Office - Butte, Montana• Staff

– 1 Supervisor• Dave Aquirre

– 3 Full-Time Staff• Mark Peterson• Eileen Steilman• Mark Ewanic

– 2 Student Interns• Karen Gillespie• Whitney Walsh

August 27, 2008

Registration&

DeregistrationProcesses

August 27, 2008

Registration Submittal Process

• Facility Eligibility

• Registration Form– Inventory of emitters– Quantify emissions

• Registration & Operation Fees

August 27, 2008

Oil or Gas Well Facility Eligibility

• Meets definition of oil or gas well facility– 75-2-103(13), MCA

• Subject to requirements of ARM 17.8.743– PTE > 25-tpy any airborne

pollutant– Modified after 11/23/68

and PTE increase >25-tpy

• NOT subject to ARM Title 17, Chapter 8, Subchapter 12 (Title V Source)

August 27, 2008

Registration Form

• Available online– (http://deq.mt.gov/AirQuality/airForms.asp)

• Owner & Facility Information– Contact– Location– Emitting Units– Emission Controls– Uncontrolled/Controlled Emissions

• Electronic or hard copies

August 27, 2008

Registration & Operation Fee

• Registration Fee– $500 per newly

registered facility– Registration request is

incomplete until fee is paid

• No fee when submitting facility update

• Annual Operation Fee– $600 per registered

facility

August 27, 2008

Registration Acknowledgement

• Completeness Review

• Compliance Review Desk Audit

• Acknowledgment Letter

August 27, 2008

Completeness Review

• Facility is eligible for registration?

• Registration Process and Information is complete?

• Registration Fee has been received?

• Department requests additional information if necessary

August 27, 2008

Compliance Review Desk Audit

• Completed prior to registration acknowledgement

• Does not delay registration– Potential compliance issues

identified– Provides compliance

assistance

August 27, 2008

Acknowledgement Letter

• New facilities – Within 30-days of receiving completed Registration Form

• Backlog - 25% each calendar year beginning in 2008

August 27, 2008

Deregistration Request• Letter to Department

– Justification for deregistration• Department may request additional

information– Quantify all emissions (e.g., fugitives)– Emission calculations using more appropriate

software– Source specific inputs

• Updated production• Separator temperature and pressure• Site specific oil and/or gas analytical data

• Plan Ahead– Submit in time to deregister by March 1– Be aware of issues that my delay

acknowledgement

August 27, 2008

Deregistration Acknowledgement

• Review similar to compliance review desk audit

• Respond to deregistration requests within 30-days of receiving completed request

August 27, 2008

ComplianceMonitoring

August 27, 2008

Compliance Determination• Initial compliance review desk audit

– Completed when Registration is acknowledged

• Field inspection– Standardized field observations sheet– Compliance review desk audit upon

return to office

• Documentation– Standardized inspection reports– Supplemental CD

• Digital photos• Video from IR camera

August 27, 2008

Inspection Zones

• Divided counties with oil or gas well facilities

• Full-time staff members assigned zones– Complete field inspections – Registered– Complete field verifications –

Unregistered

August 27, 2008

Inspection Zones - Inspectors

August 27, 2008

Inspection Zones - Facilities

August 27, 2008

Inspection Zones – Richland County

August 27, 2008

Current Field Approach• Focusing on

companies/facilities that did not comply with the ARM– Focus on unregistered

facilities potentially needing to be registered

– Conduct compliance field inspections on registered sources in same area

August 27, 2008

ProvidingComplianceAssistance

August 27, 2008

Registered FacilitiesField

Comp. Insp.

Comp. Desk Audit

Issue Insp. Rpt.

30-Days

In Compliance

No Further Action

YES

NO

Phone Call Followed By

Report

Warning or Violation

Letter

Possible Enforceme

nt

Company Responds

YES

NO

Resolution, More

Time, etc.

60-Days

August 27, 2008

Unregistered Facilities

Review DNRC Data

???PTE >25-tpy

???

Phone Call Followed By

Letter

No Further Action

Company Responds

Site Verificatio

n

NO

YES

60-Days

NO YES

Possible Enforceme

nt

Request Add. Time

Submit Registration

Submit Info. For Not

Registering

Review Submittal

August 27, 2008

Common Compliance Issues• Controlling emissions

– Tank emissions not controlled• Flare, VRU, etc.

– Flare not working properly (i.e., combusting produced gas and/or tank gas)

– Leaks detected

• H2S detected– Strong odor but no air quality analysis– Must comply with ARM 17.8.210

• Notification of change(s) to registration information– Addition of emitter– Change to emission controls

August 27, 2008

ThermCAMTM GasFindIR Camera

• Detect hydrocarbon emissions– Cost savings to industry

• Leaks in produced gas line• Leaks in vapor recovery unit

– Assistance with site maintenance

• Leaking thief hatches (faulty seal)

• Flares not operating

• Repair leaking VOC equipment (ARM 17.8.1712)

August 27, 2008

Current Statusand

Path Forward

August 27, 2008

Registration Activity (8/26/08)Total Registrations Submitted: 727

Total Registered Facilities: 621

Reg. Facilities Acknowledged: 135/67 (Backlog/New)

Reg. Updates Acknowledged:145

August 27, 2008

Inspection/Verification Activity

Facility Inspections:75

Facility Verifications: 130

August 27, 2008

• Emission Inventory– Send out in December– Report actual 2008 emissions– Return to Department by February

Upcoming Activity• Rule Changes – Subchapter 17

– Addition of BACT requirements for larger internal combustion engines

– Emission control requirements of Subchapter 16 match Subchapter 17

– Notification requirements

• Registration Form Format– Working on ExcelTM version– Link calculation sheets

August 27, 2008

Things To Remember• Not required to register in

lieu of MAQP• No fee for submitting an

update• Registering by facility

versus by well• PTE should reflect

maximum potential production

• March 1 deadline for deregistration

And when in doubt...

August 27, 2008

ContactInformation

August 27, 2008

DEQ ARMB Registration Section

Butte, Montana Office49 N Main, Suite BButte MT 59701

Tel: (406) 782-2689Fax: (406) 782-2701Web: http://deq.mt.gov/